About this file

This document is an amendment to a solicitation for mechanical, electrical, and plumbing multiple award construction contracts (MACC) services. The Naval Facilities Engineering Command is seeking these MACC services for projects located at Camp Lejeune. This amendment provides answers to contractor questions, changes the response date from October 10th to October 17th at 2:00 PM, and deletes and replaces the original Construction Experience Project Data Sheet. Contractors will compete for task orders after initial contract awards and a seed project, with lowest price being the determining factor. Offerors are not responsible for engineering design as part of the seed project and no alternate technical solutions beyond the provided scope will be considered.

Amendment 0005 - Answer Requests for Information

View the file

Other files for this federal contract opportunity

Other files attached to Mechanical, Electrical, & Plumbing MACC, newest first.
File Type Posted
Amend 0008 198057.pdf PDF
Boiler_Platform.pdf PDF
Amend_0007_198057.pdf PDF
Amend_0006_198057.pdf PDF
02_82_00_ASBESTOS_REMEDIATION.pdf PDF
NH100_Asbestos_Report.pdf PDF
Construction_Exp_Project_Data_Sheet_198057.docx DOCX document
198057_Amend_0004.pdf PDF
198057_Amend_0003.pdf PDF
Amend_0002_198057.pdf PDF
198057_Amend_0001.pdf PDF
Attach_2_DWGS_1_of_3_198057.pdf PDF
ATTACH_2(b)_DWGS_1_of_3_198057.pdf PDF
ATTACH_2(a)_DWGS_1_of_3_198057.pdf PDF
ATTACHMENT_6_PPQ.docx DOCX document
ATTACH_3_DWGS_2_of_3_198057.pdf PDF
RFP_N4008519R8057.pdf PDF
ATTACH_1_Spec_198057.pdf PDF
ATTACHMENT_5_Construction_Exp_Project_Data_Sheet.docx DOCX document
ATTACH_4_DWGS_3_of_3_198057.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MACC240M

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N40085-19-R-8057, Mechanical, Electrical and Plumbing MACC Amendment 0005, Answ er Requests for Information

The time and date for receipt of proposals is changed to 1400, 17 October 2019.

This amendment should be acknow ledged w hen your proposal is submitted. Failure to acknow ledge the amendment may constitute grounds for rejection of a proposal.

See Continuation Page(s)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Oct-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R8057

X 9B. DATED (SEE ITEM 11)

21-Aug-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Oct-2019

CODE

NAVFAC MID ATLANTIC

ROICC CAMP LEJEUNE

1005 MICHAEL ROAD

CAMP LEJEUNE NC 28547-2521

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R8057

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMEND 0005

1. QUESTION: Section 4.4 states: “Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non‐ price factors considered.” Please verify if this evaluation criteria for award is applicable to all task orders for this IDIQ MACC?

ANSWER: After award of the initial contracts and seed project, the successful IDIQ contractors will compete for task orders based on lowest price.

2. QUESTION: 2. Section 1.3.4 states: “After award of the initial contracts and seed project, the successful IDIQ contractors will compete for task orders based on lowest price.” Please verify if this evaluation criteria for award is applicable to all task orders for this IDIQ MACC?

ANSWER: This is applicable to task orders issued after the initial contracts and seed project task order are issued.

3. QUESTION: Section 5.5 references a Technical Proposal. Is a Technical Proposal required as part of this proposal?

ANSWER: Yes, refer to Section 4 and 5 of the solicitation.

4. QUESTION: Section 5.2 references "the above Basis of Evaluation". In what part of the Basis of Evaluation is the Technical Proposal included?

ANSWER: Refer to Section 4.5 of the solicitation.

5. QUESTION: Section 5.5 references a Technical Proposal. What components are required to be submitted as part of the Technical Proposal?

ANSWER: Refer to Section 4 and 5 of the solicitation.

6. QUESTION: Section 5.5 references a Technical Proposal. What is the page limit for the Technical Porposal?

ANSWER: Refer to Sections 4 and 5 of the Solicitation for proposal requirements.

7. QUESTION: Please confirm if alternate solutions to the provided design will be considered.

ANSWER: No alternate solutions will be considered.

8. QUESTION: Please confirm if the provided drawings are considered construction documents or if contractors are to provide final design/construction drawings.

ANSWER: No final design/construction drawings are to be provided by Offerors.

9. QUESTION: Confirm contractors are not responsible for engineering design as a part of the SEED project.

ANSWER: Offerors are not responsible for engineering design as part of the Seed project.

10. QUESTION: Please confirm which of the four (4) provided evaulation factors (Corporate Experience, Management Approach, Safety, and Past Performance) the technical proposal is to be included in.

ANSWER: Refer to Section 4 and 5 of the Solicitation for the non‐price factors proposal (technical proposal) requirements.

11. QUESTION: If the intent is to include the technical proposal in the information for Evaluation Factor 2 ‐ Management Approach, can and additional 5 double sided pages be included to allow adquate page count to provide a detailed technical propsoal?

12. QUESTION: Please provide the evaluation criteria for the technical propoal required in this section.

13. QUESTION: Reference: Page 13 of 68, “ADDITIONAL INFORMATION TO BE SUBMITTED WITH

PRICE PROPOSAL PACKAGE: RESPONSIBILITY DETERMINATION INFORMATION”; 1. ONE (1)

signed bank reference…

Please advise if the government has a form they would like us to utilize for the bank reference.

ANSWER: No standard form is available. Please provide the information requested in Section

4.5 of the Solicitation.

14. Please delete the original Construction Experience Project Data Sheet provided with the Solicitation and use the attached Construction Experience Project Data Sheet.

15. All other terms and conditions remain unchanged.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 10-Oct-2019 02:00 PM to 17-Oct-2019 02:00 PM.

(End of Summary of Changes)