AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N40085-18-R-8717, Design-Build (DB) RM17-0145, CNIC Base Support Consolidation, Bldg. H1, Portsmouth Naval Shipyard, Kittery, ME
The purpose of this amendment is to provide an updated solicitation.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Jul-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008518R8717
X 9B. DATED (SEE ITEM 11)
27-Jun-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Jul-2018
CODE
NAVFAC MID ATLANTIC
9324 VIRGINIA AVENUE
BLDG Z-144
NORFOLK VA 23511
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008518R8717
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The description of performance FAR 52.211-10 has been added.
CLIN 0001
The CLIN extended description has changed from:
CLIN 0001 shall be the total amount for items 0001a through 0001hh, complete and in accordance with the drawings and specifications.
To:
CLIN 0001 shall be the total amount for items 0001a through 0001hh, complete and in accordance with the drawings and specifications. The performance period for the base work required by CLIN 0001 - Base Price shall be 1,200 calendar days from date of award (this date includes 15 calendar days for submission and approval of required bonds and insurance).
CLIN 0002
CLIN 0002 shall be the total amount for Water Line Relocation, Replacement, and Extension, complete and in accordance with the drawings and specifications.
CLIN 0002 shall be the total amount for Water Line Relocation, Replacement, and Extension, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise option(s).
CLIN 0003
CLIN 0003 shall be the total amount for Locate Chillers Near Building H-10, complete and in accordance with the
CLIN 0003 shall be the total amount for Locate Chillers Near Building H-10, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise option(s).
CLIN 0004
CLIN 0004 shall be the total amount for Locate Emergency Generator Near Building H-10, complete and in
CLIN 0004 shall be the total amount for Locate Emergency Generator Near Building H-10, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR
CLIN 0005
CLIN 0005 shall be the total amount for Solar Hot Water System, complete and in accordance with the drawings and specifications.
CLIN 0005 shall be the total amount for Solar Hot Water System, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise option(s).
CLIN 0006
CLIN 0006 shall be the total amount for Photovoltaic System, complete and in accordance with the drawings and specifications.
CLIN 0006 shall be the total amount for Photovoltaic System, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise option(s).
CLIN 0007
CLIN 0007 shall be the total amount for Passenger Elevator Upgrades, complete and in accordance with the
CLIN 0007 shall be the total amount for Passenger Elevator Upgrades, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise option(s).
CLIN 0008
CLIN 0008 shall be the total amount for Relocate Integrated Power Center at Building 241, complete and in
CLIN 0008 shall be the total amount for Relocate Integrated Power Center at Building 241, complete and in accordance with the drawings and specifications. This option is capable of being exercised at the discretion of the Government within 120 days from date of award. All work can be performed concurrently (i.e. work on the base and any option exercised is expected to be performed at the same time) due to the extended period of performance provided within the base price. No provision is made for economic price adjustment. In accordance with FAR
SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS
The following have been added by reference:
52.228-15
The following were previously included by reference and are now included by full text:
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by reference:
252.201-7000
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1200 calendar days. If any or all option CLIN(s) are exercised, the contract completion date remains the same as that of the base price (CLIN 0001), as the work required by these options can be performed concurrent to the base work. The time stated for completion shall include final cleanup of the premises.
(End of clause)
The following were previously included by reference and are now included by full text:
52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
(End of clause)
52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010)
(a) Definitions. As used in this clause--
Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, 3700 East West Highway, Room 6F01, Hyattsville, MD 20782. Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
252.201-7000 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 1991)
(a) "Definition. Contracting officer's representative" means an individual designated in accordance with subsection 201.602-2 of the Defense Federal Acquisition Regulation Supplement and authorized in writing by the contracting officer to perform specific technical or administrative functions.
(b) If the Contracting Officer designates a contracting officer's representative (COR), the Contractor will receive a copy of the written designation. It will specify the extent of the COR's authority to act on behalf of the contracting officer. The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.
(End of Summary of Changes)