This amendment provides responses to questions from offerors on the solicitation for a Design-Build/Design-Bid-Build Indefinite Delivery Indefinite Quantity Multiple Award Construction Contract to support facilities at the Public Works Department Crane, Indiana. The contract allows for a wide range of construction projects including new builds, demolitions, repairs, renovations, and infrastructure work. It is a 100% small business set-aside for North American Industry Classification System code 236210, with a business size standard of $36.5 million. The amendment maintains the original proposal due date of April 24, 2018 and clarifies that only evaluation Factors 1 through 4 need be included in Phase I submissions.

AMENDMENT_0001.pdf

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

DESIGN-BUILD (DB)/DESIGN-BID-BUILD (DBB), INDEFINITE DELIVERY/INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) FOR FACILITIES LOCATED WITHIN THE AREA OF RESPONSIBILITY (AOR) OF NAVFAC MIDLANT, PUBLIC WORKS

DEPARTMENT (PWD) CRANE, INDIANA

The purpose of this amendment is to provide responses to Pre-Proposal Inquiries (PPIs). See attached pages.

The proposal due date remains 24 April 2018.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Apr-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008518R8706

X 9B. DATED (SEE ITEM 11)

21-Mar-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Apr-2018

CODE

NAVFAC MID ATLANTIC

NORTH IPT

9324 VIRGINIA AVENUE

BLDG Z-144

NORFOLK VA 23511

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008518R8706

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The Issued By organization has changed from

NAVFAC MID ATLANTIC

IPT NORTH

9324 VIRGINIA AVENUE

BLDG Z-140

NORFOLK VA 23511

to

NAVFAC MID ATLANTIC

NORTH IPT

9324 VIRGINIA AVENUE

BLDG Z-144

NORFOLK VA 23511

(End of Summary of Changes)

SOLICITATION NO. N40085‐18‐R‐8706

PROJECT TITLE/LOCATION: Crane MACC NSA Crane,IL

Page Section Para.

1 4/10/2018 11 RFP 1 The RFP states "The attached Construction & Design

Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information. If the same project is being used to demonstrate construction and design experience, submit separate Project Data Sheets for construction and design. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double‐ sided page (or two (2) single‐sided pages). " To clarify, in our documents received the Attachment is A is not in an expandable file. Would you forward the expandable file or is the 4 page document in RFP acceptable?

The Construction & Design Experience Project Data Sheet has been reformatted into a two page document. The updated form has been uploaded to NECO and is labeled "Attachment C ‐ Construction & Design Experience Data Sheet_rev1"

2 4/10/2018 13 RFP 1 Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other solicitations. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Are past PPQ's be acceptable for submission?

Yes PPQ's from previously submitted can be submitted again. This lanaguage is simply stating that referencing previous projects is not sufficient. You have to submit the PPQ in your Phase I proposal.

3 4/10/2018 17 5.2 First paragraph states: in response to this RFP, the completed proposal shall include both the Price Proposal and the Non‐Cost/Price Factors Proposal. But in BOLD below states for Phase I only a technical binder with Factors 1‐4 will be required. I assume we are only submitting on the Phase I which will only be Factors 1‐ 4, correct??

Only Factors 1‐4 will be submitted for Phase I.

4 4/10/2018 11 1st paragraph

The Experience Project Data Sheet (EPDS Attachment C) is MANDATORY. Should be Attachment A, correct??

Yes. 1

5 12

2nd Paragraph

The EPDS same as above states at the bottom of the paragraph that the EPDS cannot exceed (1) doubled sided or (2) single sided pages but the EPDS in attachment A is 4 pages??

The Construction & Design Experience Project Data Sheet has been reformatted into a two page document. The updated form has been uploaded to NECO and is labeled "Attachment C ‐ Construction & Design Experience Data Sheet_rev1"

1st parapraph

In this paragraph it staes the PPQs are attachment D.

We assume that should be attachment B, correct??

Yes.

REFERENCE

Question No. QUESTION GOVERNMENT RESPONSEDate Received

Posted on Amend No.

AMENDMENT 0001
Copy of N4008518R8706Attachment_C_-_PPI_Form Question 1