P495_Revised_Price_Proposal_Form_080718.pdf

PDF 396 KB Posted

Attached to
DB CHAMBERS FIELD MAGAZINE CONSTRUCTION, PHASE I, NAVAL STATION NORFOLK, VA
Solicitation number
N4008517R0332
Issued by

About this file

P495_Revised_Price_Proposal_Form_080718.pdf

View the file

Other files

File Type Posted
NAVADMIN_026_18_Checklist_MAY-2018_-_Form_P-495_Chambers_Field_Magazines....pdf PDF
AMENDMENT_0016.pdf PDF
Amendment_0015.pdf PDF
Revised_Price_Proposal_Form_051018.pdf PDF
AMENDMENT_0014.pdf PDF
AMENDMENT_13.pdf PDF
ATTACHMENT_G_Price_Proposal_Form_P495_030818.pdf PDF
AMENDMENT_12.pdf PDF
AMENDMENT_0011.pdf PDF
P-495_Amendment_Drawings_1-26-18_Electrical_Site_Plans.pdf PDF
AMENDMENT_0010.pdf PDF
AMENDMENT_0009.pdf PDF
P-495_Amendment_Attachments.pdf PDF
AMENDMENT_0008.pdf PDF
AMENDMENT_0007.pdf PDF
AMENDMENT_0006.pdf PDF
AMENDMENT_0005.pdf PDF
Amendment_0004.pdf PDF
P495_SITE_VISIT_LOG.pdf PDF
Amendment_0003.pdf PDF
ATTACHMENT_H_Site_Visit_COMPOUND_ACCESS.docx DOCX document
N4008517R0332-0002.pdf PDF
ATTACHMENT_G_Price_Proposal_Form_P495.docx DOCX document
Attachment_C_-_Construction_Experience_Project_Data_Sheet.docx DOCX document
N4008517R0332_SOLICIT.pdf PDF
Attachment_A_-_Pre-Proposal_Inquiry_Form.xlsx XLSX spreadsheet
Attachment_B_-_Past_Performance_Questionnaire.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE PROPOSAL FORM

MCON P495, Chambers Field Magazine Recap PH 1

080718

Contractor price shall include the necessary labor, materials, equipment, management, supervision, and administration to accomplish the following:

ITEM 0001 – Price includes the following:

Price for providing all work, complete, in accordance with the drawings and specifications, but excluding Items 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, 0013, 0014, 0015, 0016, 0017, 0018, 0019, 0020, 0021, 0022, 0023, 0024, 0025, 0026.

TOTAL PRICE FOR ITEM 0001 $_______________

ITEM 0002 – Option 1 - Price for abatement and disposal of all asbestos containing sealants and caulking which are above and beyond what is indicated in the Hazardous Material Building Inspection

Report by GeoEnvironmental Resources, Inc. dated August 29, 2017. Cost shall include staging and scaffolding.

Item Unit Unit Unit Price No. Units Extension

Asbestos Sealant

Caulking Abatement 1 LF $______ 500 $__________________

ITEM 0003 – Option 2 - Price for abatement and disposal of all asbestos containing pipe insulation which are above and beyond what is indicated in the Hazardous Material Building Inspection Report by GeoEnvironmental Resources, Inc. dated August 29, 2017. Cost shall include staging and scaffolding.

Item Unit Unit Unit Price No. Units Extension

Asbestos Insulation

Abatement 1 LF $_______ 350 $__________________

ITEM 0004 – Option 3 - Price for abatement and disposal of Lead Paint which are above and beyond what is indicated in the Hazardous Material Building Inspection Report by GeoEnvironmental

Resources, Inc. dated August 29, 2017.

Item Unit Unit Unit Price No. Units Extension

Lead Paint

Abatement 5 SF $_______ 40 $__________________

ITEM 0005 – Option 4 - Price for abatement and disposal of Ballast containing PCB’s which are above and beyond what is indicated in the Hazardous Material Building Inspection Report by

GeoEnvironmental Resources, Inc. dated August 29, 2017.

Item Unit Unit Unit Price No. Units Extension

PCB

Abatement 1 Ballast $_______ 10 $__________________

ITEM 0006 – Option 5 – Price for Removal and Replacement of Buried Abandoned Debris and

Unsuitable Soil which are above and beyond what is indicated in the Geotechnical Data Report by

GeoEnvironmental Resources, Inc. dated May 22, 2017 and the Hazardous Material Building

Inspection Report by GeoEnvironmental Resources, Inc. dated August 29, 2017. Furnish all labor, material, equipment and supervision in connection with the removal, disposal and replacement of debris and unsuitable subgrade soil from site.

Item Unit Unit Unit Price No. Units Extension

Buried Abandoned Debris Cubic Yards $_______ 1000 $__________________ and Unsuitable Soil

ITEM 0007 – Option 6 – Price for providing all work, complete, in accordance with the drawings and specifications for Trailer Parking as shown on CS104.

TOTAL PRICE FOR ITEM 0007 $_______________

ITEM 0008 – Option 7 – Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM23.

TOTAL PRICE FOR ITEM 0008 $_______________

ITEM 0009 – Option 8 – Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM4.

TOTAL PRICE FOR ITEM 0009 $_______________

ITEM 00010 – Option 9 – Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM80.

TOTAL PRICE FOR ITEM 0010 $_______________

ITEM 00011 – Option 10 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM7.

TOTAL PRICE FOR ITEM 0011 $_______________

ITEM 00012 – Option 11 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM9.

TOTAL PRICE FOR ITEM 0012 $_______________

ITEM 00013 – Option 12 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM27.

TOTAL PRICE FOR ITEM 0013 $_______________

ITEM 00014 – Option 13 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM25.

TOTAL PRICE FOR ITEM 0014 $_______________

ITEM 00015 – Option 14 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM176.

TOTAL PRICE FOR ITEM 0015 $_______________

ITEM 00016 – Option 15 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM45.

TOTAL PRICE FOR ITEM 0016 $_______________

ITEM 00017 – Option 16 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM17.

TOTAL PRICE FOR ITEM 0017 $_______________

ITEM 00018 – Option 17 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM14.

TOTAL PRICE FOR ITEM 0018 $_______________

ITEM 00019 – Option 18 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM13.

TOTAL PRICE FOR ITEM 0019 $_______________

ITEM 00020 – Option 19 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM11.

TOTAL PRICE FOR ITEM 0020 $_______________

ITEM 00021 – Option 20 - Price for providing all work, complete, in accordance with the drawings and specifications for the demolition of NM177.

TOTAL PRICE FOR ITEM 0021 $_______________

ITEM 00022 – Option 21 - Price for providing all work, complete, in accordance with the drawings and specifications for the Inert Storage Building.

TOTAL PRICE FOR ITEM 0022 $_______________

ITEM 00023 – Option 22 - Price for providing all work, complete, in accordance with the drawings and specifications for the Water Tower.

TOTAL PRICE FOR ITEM 0023 $_______________

TOTAL PRICE FOR ITEMS 0002 thru 0023 $_____________________

ITEM 0024 - PLANNED MODIFICATION - FURNITURE, FIXTURES & EQUIPMENT

(FF&E):

Price to procure and supervise installation, required for the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the plans and specifications and in accordance with the following schedule:

GOVERNMENT FF&E HAR TOTAL PRICE FOR

ITEM FF&E ESTIMATE AMT FF&E + HAR AMT

(NTE 5%)

Procurement, $277,000.00 $13,850.00 $ 290,850.00

Installation, Labor, Material, Equipment, Transportation, and Supervision Required for the (PSE)

ITEM 0025 –PLANNED MODIFICATION – PHYSICAL SECURITY EQUIPMENT:

Price for providing work in connection with the procurement and installation, all labor, material, equipment, transportation, and supervision required for the Physical Security Equipment (PSE) including all work indicated in the contract documents as Planned Modification Item 0025, in accordance with the following schedule:

ITEM

GOVERNMENT

PSE BUDGET

PSE HAR

AMT

(NTE 5%)

TOTAL PRICE

FOR PSE +

HAR AMT.

Procurement, Installation, Labor, Material, Equipment, Transportation, and

Supervision Required for the (PSE)

$150,000.00

$7,500.00

$157,500.00

ITEM 0026 –PLANNED MODIFICATION – AUDIO/VISUAL:

Price for providing work in connection with the procurement and installation, all labor, material, equipment, transportation, and supervision required for the Audio/Visual including all work indicated in the contract documents as Planned Modification Item 26, in accordance with the following schedule:

ITEM

TOTAL

A/V AMT.

Procurement, Installation, Labor, Material, Equipment, Transportation, and

Supervision Required for the (A/V)

$42,491.58

TOTAL PRICE FOR ITEMS 0001 thru 0026 $___________________

NOTES

General

1. Award will be made on the total sum of Item 0001. Offerors shall enter unit prices and/or extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended price and the total recomputed accordingly. If an offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

2. FAR 52.217-5, Evaluation of Options (Jul 1990) – Except when it is determined in accordance with FAR 17.206 (b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

3. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

4. In accordance with FAR 52.228-15, if an option is exercised after award and the contract price increases, an additional amount equal to 100 percent of the increase is required for the Performance and Payment Bonds. The Government has the unilateral right to exercise Options 1-5 within 360 days from award. The Government has the unilateral right to exercise Options 6 – 20 within 90 days from award.

5. Unit Prices: The unit prices provided will be the basis for the adjustment in accordance with FAR

52.211-18, Variation in Estimated Quantity.

FF&E – Procurement and Installation (ITEM 0024) - In this solicitation, for FF&E Procurement and Installation planned modification, the contractor will only propose and be evaluated on the HAR rate applied to the Government Estimated amount for FF&E. Upon Government approval of the preliminary design and best value analysis, a Best Value Determination (BVD) will be made and will be the rationale for selecting the FF&E vendor(s) for the project. Accordingly, the price(s) provided by the selected vendor(s), using predominately negotiated price schedules from BPA, GSA or other

Federal contracts, will be the basis for the actual cost of the Final FF&E Package. The actual total cost of the awarded planned modification will be the total of the accepted Final FF&E Package and the

HAR rate applied to the accepted Final FF&E Package. See PART 3, Section 6, ESR E20 and PART

4, PTS E20. Government Estimated Amount for Furniture Fixtures and Equipment (FF&E). The

Government estimated amount for FF&E, as shown above, includes the FF&E cost, freight and installation charges. The Government estimated amount for FF&E has been identified to provide offerors with the projected magnitude of effort for FF&E. The total estimated budget amount for the

FF&E includes the actual cost of the FF&E including freight and installation charges and Prime

Contractor’s proposed Handling and Administrative Rate (HAR). The Total FF&E Budget Amount

(Estimated) shall be entered by the Government. Prime Contractor FF&E Handling and Administration

Rate (HAR). Offerors may propose a fee, up to but not to exceed 5%, for the handling and administration of the FF&E. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontractors, profit and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E. No other charges, expenses, fee, mark-ups, etc., will be authorized. The prime contractor’s proposed HAR mark-up shall be applied to the Government estimated amount of FF&E to derive the price for Item 0022.The prime contractor’s FF&E HAR will be incorporated into the contract as proposed and will not be adjusted regardless of fluctuations from the Government budget amount of FF&E. The HAR is a fixed rate.

When the final FF&E package is priced, the contractor’s HAR, as incorporated into the contract, shall be applied to the FF&E supplier and vendor quotes to derive a total proposed price for final negotiation of the FF&E planned modification.

The design for the FF&E itself is performed under the Base Bid and shall be included in Item

0001. The Final FF&E shall be submitted no later than 9 months prior to building completion. The

Government is not obligated to award the planned modification line item(s). Should the Government choose to award the planned modification the line item will be awarded as a negotiated modification to the contract/task order. If exercised, the FF&E planned modification will be awarded at least six months prior to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E without impacting the overall completion date of the project.

The Contractor's schedule must assume the award of the FF&E as a modification. No schedule extensions will be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor demonstrates that an accepted Final FF&E package was submitted within the approved schedule deadlines and sufficient lead time for the FF&E is not available and the Government's award of the modification is in the last six months of the contract.

Bonding is not required for ITEM 0024 Planned Modification - FF&E.

PSE – Procurement and Installation (ITEM 0025) - Contractor shall be authorized by the

Contracting Officer to procure and install all physical security equipment as specified in the approved final design of Physical Security Equipment Systems Package (PSE) which includes Electronic

Security Systems (ESS). The amount of this item will be the actual cost of the Physical Security

Equipment (PSE) items, Electronic Security System (ESS) items and the respective cabling for each

Electronic Security System plus all labor, material, equipment, transportation and supervision required to install and test a complete operating turnkey system for all required security systems within the contract completion date. The Government is not obligated to award the PSE - Planned Modification –

ITEM 0025. Should the Government choose to award the PSE the line item will be awarded as a negotiated modification to the contract/task order. The PSE Modification shall be awarded at least six months prior to the contract completion date. A minimum of six months is required for the contractor to purchase, deliver and install the PSE without impacting the overall completion date of the project.

The contractor’s schedule should assume the award of the PSE as a modification. No schedule extensions shall be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the Physical Security Equipment

Modification with less than six months prior to the contract completion date, the contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the prime contractor demonstrates that an accepted

Final PSE Package was submitted within the approved schedule deadlines and sufficient lead time for the PSE is not available and the Government’s award of the modification is in the last six months of the contract. Note: All conduits, wire ways, junction boxes, pull stations, conduit support and wire way support systems listed with a pull wire for the above equipment are included in the ITEM

0001 (Base BID).

A/V – Procurement and Installation (ITEM 0026):

Contractor shall be authorized by the Contracting Officer to procure and install all audio/visual equipment as specified in the approved final design of Audio/Visual Package (A/V). The amount of this item will be the actual cost of the A/V items and the respective cabling for each plus all labor, material, equipment, transportation and supervision required to install and test a complete operating turnkey system within the contract completion date. The Government is not obligated to award the

A/V - Planned Modification – ITEM 0026. Should the Government choose to award the PSE the line item will be awarded as a negotiated modification to the contract/task order. The A/V Modification shall be awarded at least six months prior to the contract completion date. A minimum of six months is required for the contractor to purchase, deliver and install the A/V without impacting the overall completion date of the project. The contractor’s schedule should assume the award of the A/V as a modification. No schedule extensions shall be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the

A/V Modification with less than six months prior to the contract completion date, the contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the prime contractor demonstrates that an accepted Final A/V Package was submitted within the approved schedule deadlines and sufficient lead time for the A/V is not available and the Government’s award of the modification is in the last six months of the contract.

Note: All conduits, wire ways, junction boxes, pull stations, conduit support and wire way support systems listed with a pull wire for the above equipment are included in the ITEM 0001

(Base BID).

AMENDMENTS ACKNOWLEDGED

Amendment No. Date Amendment No. Date Amendment No. Date

Offeror:

Name:

Signed:

Date:

File details come from the government source that posted it.