This document contains a solicitation for repair and painting services at a U.S. Naval facility in Japan. The Navy seeks a contractor to perform roof repair by installing a new sheet waterproofing system on an existing folded metal roof. Exterior wall painting services are also required, which include removing damaged existing paint, preparing surfaces, and painting exterior walls. Material sampling for asbestos and lead, as well as asbestos and lead removal work, are included in the scope of services. Bidders must provide both a base price for general construction work and an optional price for additional asbestos abatement should sampling confirm the presence of asbestos in exterior walls. The solicitation identifies license requirements for contractors to operate in Japan and notes that official U.S. contractor status or civilian component certification under the U.S.-Japan Status of Forces Agreement will not be provided under this contract. Award is estimated between 50-100 million yen.

View the file

Other files

File Type Posted
N4008422B8001-A4.pdf PDF
Attachment9_Amend-0003_Summary.pdf PDF
N4008422B8001-A3.pdf PDF
Attachment9a_S01_11_0000_33_SummaryofWork.pdf PDF
N4008422B8001-A2.pdf PDF
N4008422B8001-A1.pdf PDF
Attachment8_ReferencePhoto.pdf PDF
Attachment4_InformationSecurity.pdf PDF
N4008422B8001.pdf PDF
Attachment6_SiteVisitRequestForm.xlsx XLSX spreadsheet
Attachment7_PreBidInquiryForm.xlsx XLSX spreadsheet
Attachment3_SupplementaryInstructions(eP1635281).pdf PDF
Attachment5_OPSECGuidance.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B983 Repair Roofing and Paint Exterior Wall, U.S. Naval Air Facility, Atsugi, Japan eProject No. 1635281

CUI//FEDCON[when filled in]

Source Selection Information--See FAR 2.101 and 3.104 [when filled in]

CUI//FEDCON[when filled in] Source Selection Information--See FAR 2.101 and 3.104 [when filled in]

SECTION 00 22 13.00 33 Page 1 (Rev. A, 6 July 2022)

DOCUMENT 00 22 13.00 33

SUPPLEMENTARY INSTRUCTIONS TO OFFERORS

06/21

PART 1 GENERAL

1.1 LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide lump sum price for each of the following line items:

Base Bid: Price includes the following:

Provide Base Item price for the work at Bldg. No. 983 in accordance with the contract drawings and the specification.

LINE ITEM DESCRIPTION

TOTAL PRICE FOR

Base Item

Base Item All Construction Work except Option Item. The work includes following items:

a. Abatement of asbestos containing material (ACM) and lead based paint (LBP) at existing and assumed locations

b. Sampling and analysis for ACM existence at exterior wall paint including putty and mortar

• Additional Notes for Base Item:

a. A cost for removal of exterior wall paint which will accrue whether or not ACM existence is confirmed as the result of the work item “b,” must be included in Base Item.

Option Bid: Price includes the following:

Provide Option Item price for the work at Bldg. No. 983 in accordance with the contract drawings and the specification. Option Item is only applicable if an existence of ACM is confirmed as the result of the work item “b” in Base Item.

LINE ITEM DESCRIPTION

TOTAL PRICE FOR

Option Item

Option Item Abatement of ACM at exterior wall paint including putty and mortar

B983 Repair Roofing and Paint Exterior Wall, U.S. Naval Air Facility, Atsugi, Japan eProject No. 1635281

CUI//FEDCON[when filled in]

Source Selection Information--See FAR 2.101 and 3.104 [when filled in]

CUI//FEDCON[when filled in] Source Selection Information--See FAR 2.101 and 3.104 [when filled in]

SECTION 00 22 13.00 33 Page 2 (Rev. A, 6 July 2022)

• Additional Note for Option Item:

a. A price for Option Item must consist of cost items particular for

Option Item, and must not include any cost required for general ACM abatement work which must be estimated in Base Item.

b. Option Item must not include the cost that must have been estimated for removal of exterior wall paint in Base Item but only include additional cost accruing from abatement work of ACM for exterior wall paint including putty and mortar in case that an ACM existence is confirmed as the result of the work item “b” in Base Item.

1.2 GENERAL BID NOTES

a. Awards will be made for Base Item and Option Item. Enter Base Price and Option Price in designated spaces provided.

b. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

c. The Government reserves the right to award or not award the Option Item pending availability of additional funds in excess of the original Government reserved fund equal to the Independent Government Estimate (IGE). If additional fund is made available, the Government will award the Option Item within and not exceed 27090 calendar days after award of the Base Item.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

PART 1 GENERAL
1.1 LINE ITEMS
1.2 GENERAL BID NOTES
PART 2 PRODUCTS
PART 3 EXECUTION

File details come from the government source that posted it. Updated .