Atch (5) 1624524-SPEC Rev-Amend 0003 (2 pages).pdf
PDF 63 KB Posted
- Solicitation number
- N4008421B6500
About this file
This document contains two amendments to a Navy specification for maintenance dredging of India Basin at the U.S. Fleet Activities in Sasebo, Japan. Amendment 0002 revises the commencement and completion dates from 540 to 630 days and removes a sentence from shipyard regulations. Amendment 0003 changes the referenced FAR clause from 52.212-11 to 52.211-18 and adds as-built drawings of repaired seawalls as references.
The related federal contract opportunity is a solicitation from the Naval Facilities Engineering Command for maintenance dredging of India Basin at the U.S. Fleet Activities in Sasebo, Japan, under solicitation number N4008421B6500. The dredging project addresses India Basin and has an estimated completion date of 630 days from commencement. The Navy is the contracting agency managing this project.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
eProject No. 1624524
AMENDMENT NO. 0002 (1/1)
NAVFAC
SPECIFICATION NO.
AMENDMENT NO. 0002
DATE: 8 JULY 2021
MAINTENANCE DREDGING PH-2, INDIA BASIN
At the
U.S. FLEET ACTIVITIES, SASEBO, JAPAN
The purpose of this amendment is to delete one sentence of Shipyard Regulations items; to change a number of days in Commencement and Completion of Work.
SECTION 01 11 00.00 33 SUMMARY OF WORK
PARA. 1.4.1 Commencement, and Completion of Work:
LINE 2. Change “540” to “630”.
SECTION 01 14 00.00 33 WORK RESTRICTIONS
PARA. 1.3.2 Shipyard Regulations
g. Overnight Stay:
LINE 3, and 4. Delete the Sentence “Berthing(first word) --- time(last word”.
AMENDMENT NO. 0003 (1/1)
NAVFAC
SPECIFICATION NO.
AMENDMENT NO. 0003
DATE: 21 JULY 2021
MAINTENANCE DREDGING PH-2, INDIA BASIN
At the
U.S. FLEET ACTIVITIES, SASEBO, JAPAN
The purpose of this amendment is to revise of FAR number; to add reference drawings.
SECTION 35 20 23.00 33 DREDGING
PARA. 1.8 QUANTITY OF MATERIAL:
LINE 3, and 4. Change “FAR 52.212-11” to “FAR 52.211-18”.
PARA. 3.4.2 Safety of Structures:
LINE 6. After the period, add: “As-build drawings of repair the seawalls for Berth No. 0 and Berth No. 10 (12 sheets) are attached at end of this section for reference.”.