ELINS BASE YEAR
| Supplies/Services | Est Qty | Unit of Issue | Unit | ||||
| Price | EST Total | ||||||
| 0001 | Tow Barges | ||||||
| 0001AA | Tow (one way, up to 60 miles), YR, YRBM, YRBM(L) Class | 8 | EA | $0.00 | |||
| 0001AB | Tow (one way, up to 60 miles), APL Class | 2 | EA | $0.00 | |||
| 0001AC | Tow (one-way, up to 700 miles, Ocean tow) YRBM, YRBM(L) Class | 2 | EA | $0.00 | |||
| 0001AD | Tow (one-way, up to 700 miles, Ocean tow) APL Class | 2 | EA | $0.00 | |||
| 0001AE | DELETED | ||||||
| 0001AF | DELETED | ||||||
| 2 | Temporary Services | ||||||
| 0002AA | Cast off and tie up berthing barge (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 0002AB | Install and remove sewage, potable water, steam, shore power, telephone, fire main, gangways and cable television connections (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 0002AC | Provide and install all services required to accomplish the requirements of the Task Order to include gangways, oil booms, safety nets, shore power, sewage, steam, firemain, telephone, potable water and cable television (within 60 mile radius of Mayport Naval Station, at contractor facility) | 180 | DAY | $0.00 | |||
| 0002AD | Provide and install 2 inch diameter mooring lines (100 ft. in length). One end with a 6' loop and other end finished. | 10 | EA | $0.00 | |||
| X | 0002AE | Provide and maintain one 300KW diesel powered generator | 4 | Day | $0.00 | ||
| X | 0002AF | Provide and maintain one 500 GPM diesel powered fire pump | 4 | Day | $0.00 | ||
| X | 0002AG | Provide and maintain one compressor 200 CFM, 125 PSI | 4 | Day | $0.00 | ||
| 3 | Cleaning and Sanitizing | $0.00 | |||||
| 0003AA | Deep clean and sanitize the entire Craft (YRBM Class) | 2 | EA | $0.00 | |||
| 0003AB | Deep clean and sanitize the entire Craft (YRBM-L Class) | 8 | EA | $0.00 | |||
| 0003AC | Deep clean and sanitize the entire Craft (APL Class) | 2 | EA | $0.00 | |||
| 0003AD | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM Class | 2 | EA | $0.00 | |||
| 0003AE | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM(L) Class | 8 | EA | $0.00 | |||
| 0003AF | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - APL Class | 2 | EA | $0.00 | |||
| 0003AG | Chemically clean entire CHT system | 2 | EA | $0.00 | |||
| 0003AH | Chemically clean water heater (in place) | 2 | EA | $0.00 | |||
| 0003AJ | Chemically clean water heater (in shop) | 2 | EA | $0.00 | |||
| 0003AK | Chemically clean heat exchanger (in place) | 1 | EA | $0.00 | |||
| 0003AL | Chemically clean heat exchanger (in shop) | 1 | EA | $0.00 | |||
| 4 | Test and Inspections | $0.00 | |||||
| 0004AA | Accomplish a preliminary and final visual and operational inspection of all systems and equipment utilizing barge systems and equipment check off list (Planning Memorandum No. 601-005). Submit a detailed report of all discrepancies. | 7 | EA | $0.00 | |||
| 0004AB | Clean, gas free safe for entry and hot work, inspect and test CHT system, replacing 4 floats per system | 4 | SY | $0.00 | |||
| 0004AC | Clean, gas free safe for entry and hot work and air test tanks and voids | 10 | EA | $0.00 | |||
| 0004AD | Test alarm system | 2 | EA | $0.00 | |||
| 0005 | Fire Fighting Equipment: Replace, Repair and Maintenance | $0.00 | |||||
| 0005AA | Replace, stencil, and hydrostatically test fire hose (100 feet in length with couplings) | 2 | EA | $0.00 | |||
| 0005AB | Re-charge existing fire extinguishers, 20 lbs. or less | 60 | EA | $0.00 | |||
| 0005AC | Install new dry chemical fire extinguishers, 20 lbs. | 25 | EA | $0.00 | |||
| 0005AD | Install new fire station spanner wrenches | 20 | EA | $0.00 | |||
| 0005AE | Install new fire hose nozzles | 10 | EA | $0.00 | |||
| 0005AF | Replace, stencil, and hydrostatically test fire hose (50 feet in length with couplings) | 25 | EA | $0.00 | |||
| 0005AG | Hydrostatically test fire hose (50 feet in length) | 25 | EA | $0.00 | |||
| 0005AH | Certify portable fire extinguisher | 75 | EA | $0.00 | |||
| 0006 | Repair Galley/Messing Equipment and Fixtures | $0.00 | |||||
| 0006AA | Provide commercial type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 0006AB | Provide household type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 0006AC | Repair and certify Gaylord Hood and Range Guard | 6 | EA | $0.00 | |||
| 0006AD | Replace disposable filters (industrial fire retardant) for galley systems | 50 | EA | $0.00 | |||
| 0006AE | Steam clean permanent filter sets | 10 | EA | $0.00 | |||
| 0006AF | Replace permanent filter sets | 10 | EA | $0.00 | |||
| 0007 | Laundry Equipment, Replace | $0.00 | |||||
| 0007AA | Remove existing, provide and install new single function clothes washer, commercial style, accomplish operational test | 5 | EA | $0.00 | |||
| 0007AB | Remove existing, provide and install new single function clothes dryer, commerical style, accomplish operational test | 5 | EA | $0.00 | |||
| 0008 | Habitability Repairs | $0.00 | |||||
| 0008AA | Replace urinals | 4 | EA | $0.00 | |||
| 0008AB | Replace toilets | 4 | EA | $0.00 | |||
| 0008AC | Replace sinks | 4 | EA | $0.00 | |||
| 0008AD | Replace shower heads | 15 | EA | $0.00 | |||
| 0008AE | Replace shower mixing valves | 10 | EA | $0.00 | |||
| 0008AF | Replace flushometer | 8 | EA | $0.00 | |||
| 0008AG | Replace sink mixing valves | 10 | EA | $0.00 | |||
| 0008AH | Deck Drains - Clean free of obstructions, including associated piping | 25 | EA | $0.00 | |||
| 0008AJ | Replace composition ceiling panels (2 ft. x 4 ft.) vinyl coated | 400 | EA | $0.00 | |||
| 0008AK | Replace ceiling tile T-Rail | 240 | LF | $0.00 | |||
| 0008AL | Replace towel racks | 10 | EA | $0.00 | |||
| 0008AM | Replace soap dishes | 10 | EA | $0.00 | |||
| 0008AN | Replace shower curtains including hooks | 30 | EA | $0.00 | |||
| 0008AP | Replace shower mats | 30 | EA | $0.00 | |||
| 0008AQ | Replace toilet paper holder (frame and spool) | 20 | EA | $0.00 | |||
| 0008AR | Replace water fountains | 7 | EA | $0.00 | |||
| 0008AS | Replace mini blinds | 25 | EA | $0.00 | |||
| 0008AT | Replace flushometer hoses | 10 | EA | $0.00 | |||
| 0008AU | Fabricate replacement keys as per sample | 100 | EA | $0.00 | |||
| 0008AV | Open and reset pin type lock sets to include 2 replacement keys | 20 | EA | $0.00 | |||
| 0008AW | Provide and install new lock sets | 10 | EA | $0.00 | |||
| 0008AX | Open and reset combination on high security/classified locks on doors and/or safes | 10 | EA | $0.00 | |||
| 0008AY | Open and install new lock sets and reset combinations on high security/classified locks on doors and/or safes | 10 | EA | $0.00 | |||
| 0008AZ | Replace automatic door closures | 5 | EA | $0.00 | |||
| 0008BA | Replace bulkhead insulation (2" thick) | 800 | SF | $0.00 | |||
| 0008BB | Replace bulkhead insulation (1" thick) | 250 | SF | $0.00 | |||
| 0008BC | Replace deck drains up to 4" to include one foot of piping | 3 | EA | $0.00 | |||
| 0009 | Electrical Repairs | $0.00 | |||||
| 0009AA | Replace fluorescent tubes in closed fixtures: 12 inch | 100 | EA | $0.00 | |||
| 0009AB | Replace fluorescent tubes in closed fixtures: 24 inch | 250 | EA | $0.00 | |||
| 0009AC | Replace fluorescent tubes in closed fixtures: 48 inch | 400 | EA | $0.00 | |||
| 0009AD | Replace bulbs in closed incandescent fixtures | 75 | EA | $0.00 | |||
| 0009AE | Replace bulbs in spotlight fixtures | 30 | EA | $0.00 | |||
| 0009AF | Replace starters | 40 | EA | $0.00 | |||
| 0009AG | Replace bulb and battery in emergency light fixtures | 75 | EA | $0.00 | |||
| 0009AH | Install new nickel cadmium rechargeable emergency light fixtures | 25 | EA | $0.00 | |||
| 0009AJ | Replace fuses | 20 | EA | $0.00 | |||
| 0009AK | Install new exit light fixtures | 20 | EA | $0.00 | |||
| 0009AL | Replace light switches | 20 | EA | $0.00 | |||
| 0009AM | Replace light switch/receptacle covers | 25 | EA | $0.00 | |||
| 0009AN | Replace force protection halogen light bulbs | 5 | EA | $0.00 | |||
| 0009AP | Replace force protection light photo cells | 3 | EA | $0.00 | |||
| 0010 | Piping Replacement | $0.00 | |||||
| 0010AA | Replace valves up to 2 inches in diameter (WOG) | 20 | EA | $0.00 | |||
| 0010AB | Replace valves up to 2 inches in diameter (Steam) | 2 | EA | $0.00 | |||
| 0010AC | Replace valves 2 inches to 4 inches in diameter (WOG) | 10 | EA | $0.00 | |||
| 0010AD | Replace valves 2 inches to 4 inches in diameter (Steam) | 2 | EA | $0.00 | |||
| 0010AE | Replace piping up to 2 inches in diameter (CUNI) | 200 | LF | $0.00 | |||
| 0010AF | Replace piping up to 2 inches in diameter (Steel) | 40 | LF | $0.00 | |||
| 0010AG | Replace piping 2 inches to 4 inches in diameter (CUNI) | 200 | LF | $0.00 | |||
| 0010AH | Replace piping 2 inches to 4 inches in diameter (Steel) | 20 | LF | $0.00 | |||
| 0010AJ | Replace flange up to 2 inches in diameter (WOG) | 6 | EA | $0.00 | |||
| 0010AK | Replace pipe fitting up to 2 inches in diameter (WOG) | 20 | EA | $0.00 | |||
| 0010AL | Replace flange up to 2 inches in diameter (Steam) | 6 | EA | $0.00 | |||
| 0010AM | Replace pipe fitting up to 2 inches in diameter (Steam) | 20 | EA | $0.00 | |||
| 0010AN | Replace flange 2 inches to 4 inches in diameter (WOG) | 4 | EA | $0.00 | |||
| 0010AP | Replace pipe fitting 2 inches to 4 inches in diameter (WOG) | 20 | $0.00 | ||||
| 0010AQ | Replace flange 2 inches to 4 inches in diameter (Steam) | 10 | EA | $0.00 | |||
| 0010AR | Replace pipe fitting 2 inches to 4 inches in diameter (Steam) | 20 | $0.00 | ||||
| 0010AS | Replace and preserve paint pipe lagging up to 2 inches in diameter | 100 | LF | $0.00 | |||
| 0010AT | Replace and preserve paint pipe lagging up to 2-4 inches in diameter | 100 | LF | $0.00 | |||
| 0010AU | Replace and preserve lagging pads up to 2 inch | 60 | SF | $0.00 | |||
| 0010AV | Replace and preserve lagging pads 2-4 inch | 60 | SF | $0.00 | |||
| 0010AW | Install in-line potable water filters | 3 | EA | $0.00 | |||
| 0010AX | Replace in-line potable water filters | 3 | EA | $0.00 | |||
| 0010AY | Temporary Pipe Soft Patch Repair (for piping 2" in Diameter or less) | 10 | EA | $0.00 | |||
| 0010AZ | Temporary Pipe Soft Patch Repair (for piping 2 - 4 inch in Diameter) | 10 | EA | $0.00 | |||
| 0011 | Heating Ventilation and Air Conditioning Repairs | $0.00 | |||||
| 0011AA | Accomplish repairs to A/C and refrigeration equipment | 500 | HR | $0.00 | |||
| 0011AB | Material (in support of ELIN 0011) to accomplish repairs to A/C and refrigeration equipment (for bidding purposes only) | 25,000 | EA | $0.00 | |||
| 0011AC | Material G&A/Handling (in support of ELIN 0011) (Contractor to submit a percentage) | 25,000 | X | $0.00 | |||
| In negotiating the fixed price for materials, the contractor shall submit quotes or invoices for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN. | $0.00 | ||||||
| 0011AD | Replace ventilation duct, Round, 6 inch diameter and below with CRES Type 316L | 20 | LF | $0.00 | |||
| 0011AE | Replace ventilation duct, Round, 6 - 12 inch diameter, with CRES Type 316L | 30 | LF | $0.00 | |||
| 0011AF | Replace ventilation duct, Rectangular, 48 inch perimeter and below, with CRES Type 316L | 20 | LF | $0.00 | |||
| 0011AG | Replace ventilation duct, Rectangular, 49-84 inch perimeter, with CRES Type 316L | 20 | LF | $0.00 | |||
| 0011AH | Replace ventilation duct, Rectangular, 85-100 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 0011AJ | Replace ventilation duct, Rectangular, 101-120 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 0011AK | Replace ventilation duct, Rectangular, 121-150 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 0011AL | Replace ventilation duct diffusers (12 in. x 12 in.) | 5 | EA | $0.00 | |||
| 0011AM | Replace ventilation and duct inspection covers | 5 | EA | $0.00 | |||
| 0011AN | Replace thermostats | 10 | EA | $0.00 | |||
| 0011AP | Clean the entire ventilation duct work system: YRBM Class | 1 | EA | $0.00 | |||
| 0011AQ | Clean the entire ventilation duct work system: YRBM(L) Class | 2 | EA | $0.00 | |||
| 0011AR | Clean the entire ventilation duct work system: APL Class | 1 | EA | $0.00 | |||
| 0011AS | Replace disposable filters (20 in. x 25 in.), 1 inch thick | 25 | EA | $0.00 | |||
| 0011AT | Replace disposable filters (20 in. x 25 in.), 2 inches thick | 50 | EA | $0.00 | |||
| 0011AU | Replace disposable filters (20 in. x 25 in.), 4 inches thick | 10 | EA | $0.00 | |||
| 0011AV | Fabricate and install vent screens | 40 | SF | $0.00 | |||
| 0011AW | Steam clean permanent filter sets | 3 | EA | $0.00 | |||
| 0011AX | Replace permanent filter sets | 3 | EA | $0.00 | |||
| 0011AY | Insulate and preserve vent duct with 1" closed cell foam | 250 | SF | $0.00 | |||
| 0012 | Miscellaneous Repairs | $0.00 | |||||
| 0012AA | Replace decking or bulkhead plating (15.3# O.S.) | 160 | SF | $0.00 | |||
| 0012AB | Replace hull plating (20.4# O.S.) | 80 | SF | $0.00 | |||
| 0012AC | Replace support structure (6" x 4" x 1/4" tee bar, O.S.) | 40 | LF | $0.00 | |||
| 0012AD | Replace hand rail | 120 | LF | $0.00 | |||
| 0012AE | Replace stanchion | 20 | EA | $0.00 | |||
| 0012AF | Sand and reseal Cosmetic Polymeric Type II, Class II (PRC) | 9,000 | SF | $0.00 | |||
| 0012AG | Resurface Cosmetic Polymeric Type II, Class II (PRC) decking | 1,800 | SF | $0.00 | |||
| 0012AH | Replace Cosmetic Polymeric Type II, Class II (PRC), including underlayment | 2,500 | SF | $0.00 | |||
| 0012AJ | Sand and reseal Cosmetic Polymeric Type I, Class I (Broadcast Quartz) decking | 2,500 | SF | $0.00 | |||
| 0012AK | Resurface Cosmetic Polymeric Type I, Class I (Broadcast Quartz) | 120 | SF | $0.00 | |||
| 0012AL | Replace Cosmetic Polymeric Type I, Class I (Broadcast Quartz) decking | 600 | SF | $0.00 | |||
| 0012AM | Replace vinyl tile, including underlayment | 160 | SF | $0.00 | |||
| 0012AN | Replace vinyl tile to underlayment | 80 | SF | $0.00 | |||
| 0012AP | Replace nonskid | 1,000 | SF | $0.00 | |||
| 0012AR | Replace nonskid with peel and stick nonskid | 200 | SF | $0.00 | |||
| 0012AS | Replace ladder treads, 6 in. x 12 in. aluminum | 25 | EA | $0.00 | |||
| 0013 | Preservation in accordance with 009-32 | $0.00 | |||||
| 0013AA | Exterior preservation up to 1,000 sq. ft. In accordance with 009-32, Table 2, Line One, Columns B and G (for overcoat) | 800 | SF | $0.00 | |||
| 0013AB | Exterior preservation greater than 1,000 sq. ft. In accordance with 009-32, Table 2, Line One, Columns B and G (for overcoat) | 8,000 | SF | $0.00 | |||
| 0013AC | Exterior preservation up to 1,000 sq. ft. In accordance with 009-32, Table 2, Line One. | 800 | SF | $0.00 | |||
| 0013AD | Exterior preservation greater than 1,000 sq. ft. In accordance with 009-32, Table 2, Line One | 8,000 | SF | $0.00 | |||
| 0013AE | Interior preservation (Overcoat in accordance with 009-32, Table 3, Line 2) | 4,000 | SF | $0.00 | |||
| 0013AF | Interior preservation (Overcoat Wet Spaces in accordance with 009-32, Table 3, Line 4, Columns B, D, F and G.) | 1,000 | SF | $0.00 | |||
| 0013AG | Interior preservation (In accordance with 009-32, Table 3, Line 8) | 4,000 | SF | $0.00 | |||
| 0013AH | Interior preservation (Wet Spaces inaccordance with 009-32, Table 3, Line 4, 5, 6, or 7) | 1,000 | SF | $0.00 | |||
| 0014 | Maintenance - Maintenance support to the ship's crew occupying the craft | EA | $0.00 | ||||
| 0015 | Undisclosed Work | EA | $0.00 | ||||
| 0016 | RESERVED (This CLIN will never be used) | ||||||
| 0017 | LWT 077-002, Hazardous Waste Produced on Naval Vessels; control | ||||||
| 0017AA | LWT 077-002, Hazardous Waste Produced on Naval Vessels; control (for bidding purposes only) | 5,000 | U.S. GALLONS | $0.00 | |||
| 0018 | Contract Data Requirements (DD Form 1423) | ||||||
| In negotiating the fixed price for materials, the contractor shall submit quotes or invoices for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN. |
Total Estimate for Base Year $0.00
NOTE 1: Proposed prices for each line item are to be fully burdened to include the potential of escalating fuel costs, all direct and indirect costs, labor, material (with the exception of the provision for material in Undisclosed Work (Correct Discrepancies), Undisclosed Work (Statement of Work), and Maintenance - Maintenance support to the ship's crew occupying the craft), equipment rental, services, overhead, profit, and to include work and costs to implement Cat I and II NAVSEA Standard Items (NSIs), Local Standard Items (LSI) Local Work Templates (LWTs), Standard Work Templates (SWTs), and CDRLs. Additionally, any overtime cost required to complete these tasks must be included in the ELIN prices.
NOTE 2: ELINS are to be fully burdened to include any required subcontractors. Subcontract effort shall not be priced as material or considered as part of the material pools.
NOTE 3: Overtime is not authorized under the terms and conditions of this contract and thus will not be paid as a reimbursable expense or cost related to travel or any other category of incurred cost or expense unless otherwise expressly specified in a written task order or written modification to a task order.
NOTE 4: ELINS are to be fully burdened to include any required rental equipment.
Sheet1
| APL | YRB | ||||||||||||
| Class | Hull | Length | width | draft | Officer | Crew | |||||||
| 2 | 2 | 261 | 48 | 10 | 7 | 720 | 30 | 30 | 261 | 48 | 9 | 2 | 15 |
| 2 | 4 | 261 | 48 | 10 | 6 | 624 | 33 | 33 | 153 | 36 | 6 | 1 | 40 |
| 2 | 5 | 261 | 48 | 10 | 6 | 792 | YR26 | 34 | 153 | 36 | 6 | 1 | 40 |
| 2 | 15 | 261 | 48 | 10 | 6 | 624 | 36 | 36 | 153 | 36 | 6 | 1 | 40 |
| 17 | 18 | 261 | 48 | 10 | 4 | 314 | YRBM | ||||||
| 17 | 29 | 261 | 48 | 10 | 4 | 123 | Class | Hull | Length | width | draft | Officer | Crew |
| 17 | 32 | 261 | 49 | 10 | 6 | 588 | 7 | 8 | 112 | 36 | 4 | 10 | 90 |
| 35 | 39 | 328 | 50 | 14 | 39 | 1300 | 7 | 9 | 110 | 34 | 3 | 10 | 90 |
| 35 | 40 | 328 | 50 | 14 | 39 | 1295 | 13 | 13 | 110 | 34 | 4 | 5 | 90 |
| 41 | 42 | 261 | 48 | 10 | 4 | 105 | 13 | 14 | 110 | 34 | 4 | 10 | 90 |
| 41 | 45 | 261 | 49 | 11 | 12 | 664 | 13 | 15 | 110 | 34 | 4 | 10 | 90 |
| 41 | 50 | 261 | 48 | 10 | 7 | 716 | 20 | 20 | 261 | 48 | 9 | 2 | 15 |
| 53 | 58 | 261 | 48 | 11 | 6 | 83 | 23 | 23 | 147 | 46 | 7 | 26 | 201 |
| 61 | 61 | 360 | 90 | 6 | 30 | 575 | 23 | 24 | 147 | 47 | 7 | 26 | 231 |
| 61 | 62 | 360 | 90 | 6 | 30 | 575 | 23 | 25 | 147 | 47 | 8 | 26 | 231 |
| 23 | 26 | 147 | 46 | 8 | 26 | 231 | |||||||
| YR | 23 | 27 | 147 | 46 | 4 | 26 | 231 | ||||||
| Class | Hull | Length | width | draft | Officer | Crew | 23 | 28 | 147 | 46 | 7 | 21 | 231 |
| 24 | 29 | 150 | 36 | 6 | 5 | 44 | 23 | 29 | 147 | 47 | 8 | 26 | 231 |
| 44 | 63 | 153 | 36 | 6 | 1 | 40 | 23 | 30 | 146 | 46 | 4 | 26 | 231 |
| 26 | 68 | 153 | 36 | 6 | 1 | 40 | 31 | 31 | 146 | 46 | 4 | 26 | 231 |
| 26 | 78 | 153 | 36 | 6 | 1 | 40 | 31 | 32 | 146 | 46 | 4 | 26 | 231 |
| 83 | 83 | 111 | 30 | 3 | 1 | 46 | 31 | 33 | 146 | 46 | 4 | 26 | 231 |
| 84 | 85 | 210 | 41 | 4 | 40 | 31 | 34 | 146 | 46 | 4 | 26 | 231 | |
| 24 | 90 | 150 | 36 | 6 | 1 | 46 | 31 | 35 | 146 | 46 | 4 | 26 | 231 |
| 93 | 93 | 261 | 48 | 9 | 1 | 28 | 31 | 36 | 146 | 46 | 4 | 26 | 231 |
| 94 | 94 | 261 | 48 | 9 | 15 | 71 | 31 | 37 | 146 | 46 | 4 | 26 | 231 |
| 95 | 97 | 153 | 36 | 6 | 1 | 40 | 31 | 38 | 147 | 46 | 4 | 26 | 231 |
| 31 | 39 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 40 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 41 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 42 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 43 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 44 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 45 | 146 | 46 | 4 | 26 | 231 | |||||||
| 31 | 46 | 146 | 46 | 4 | 26 | 231 | |||||||
| 47 | 47 | 261 | 48 | 9 | 1 | 286 | |||||||
| 48 | 48 | 150 | 36 | 6 | 1 | 40 | |||||||
| 49 | 49 | 150 | 36 | 6 | 1 | 40 | |||||||
| 50 | 50 | 150 | 43 | 7 | 1 | 40 | |||||||
| 51 | 51 | 153 | 36 | 6 | 1 | 40 | |||||||
| 52 | 52 | 153 | 36 | 6 | 1 | 40 | |||||||
| 53 | 53 | ||||||||||||
| 54 | 54 | 150 | 36 | 6 | 3 | 62 | |||||||
| 55 | 55 | 153 | 36 | 6 | 1 | 40 | |||||||
| YFN 161 | 56 | 261 | 48 | 10 |
1ST OPT YR
| Supplies/Services | Est Qty | Unit of Issue | Unit | ||||
| Price | EST Total | ||||||
| 1001 | Tow Barges | ||||||
| 1001AA | Tow (one way, up to 60 miles), YR, YRBM, YRBM(L) Class | 8 | EA | $0.00 | |||
| 1001AB | Tow (one way, up to 60 miles), APL Class | 2 | EA | $0.00 | |||
| 0001AC | Tow (one-way, up to 700 miles, Ocean tow) YRBM, YRBM(L) Class | 2 | EA | $0.00 | |||
| 0001AD | Tow (one-way, up to 700 miles, Ocean tow) APL Class | 2 | EA | $0.00 | |||
| 1001AE | DELETED | ||||||
| 0001AF | DELETED | ||||||
| 1002 | Temporary Services | ||||||
| 1002AA | Cast off and tie up berthing barge (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 1002AB | Install and remove sewage, potable water, steam, shore power, telephone, fire main, gangways and cable television connections (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 1002AC | Provide and install all services required to accomplish the requirements of the Task Order to include gangways, oil booms, safety nets, shore power, sewage, steam, firemain, telephone, potable water and cable television (within 60 mile radius of Mayport Naval Station, at contractor facility) | 180 | DAY | $0.00 | |||
| 1002AD | Provide and install 2 inch diameter mooring lines (100 ft. in length). One end with a 6' loop and other end finished. | 10 | EA | $0.00 | |||
| X | 1002AE | Provide and maintain one 300KW diesel powered generator | 4 | Day | $0.00 | ||
| X | 1002AF | Provide and maintain one 500 GPM diesel powered fire pump | 4 | Day | $0.00 | ||
| X | 1002AG | Provide and maintain one compressor 200 CFM, 125 PSI | 4 | Day | $0.00 | ||
| 1003 | Cleaning and Sanitizing | ||||||
| 1003AA | Deep clean and sanitize the entire Craft (YRBM Class) | 2 | EA | $0.00 | |||
| 1003AB | Deep clean and sanitize the entire Craft (YRBM-L Class) | 8 | EA | $0.00 | |||
| 1003AC | Deep clean and sanitize the entire Craft (APL Class) | 2 | EA | $0.00 | |||
| 1003AD | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM Class | 2 | EA | $0.00 | |||
| 1003AE | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM(L) Class | 8 | EA | $0.00 | |||
| 1003AF | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - APL Class | 2 | EA | $0.00 | |||
| 1003AG | Chemically clean entire CHT system | 2 | EA | $0.00 | |||
| 1003AH | Chemically clean water heater (in place) | 2 | EA | $0.00 | |||
| 1003AJ | Chemically clean water heater (in shop) | 2 | EA | $0.00 | |||
| 1003AK | Chemically clean heat exchanger (in place) | 1 | EA | $0.00 | |||
| 1003AL | Chemically clean heat exchanger (in shop) | 1 | EA | $0.00 | |||
| 1004 | Test and Inspections | ||||||
| 1004AA | Accomplish a preliminary and final visual and operational inspection of all systems and equipment utilizing barge systems and equipment check off list (Planning Memorandum No. 601-005). Submit a detailed report of all discrepancies. | 7 | EA | $0.00 | |||
| 1004AB | Clean, gas free safe for entry and hot work, inspect and test CHT system, replacing 4 floats per system | 4 | SY | $0.00 | |||
| 1004AC | Clean, gas free safe for entry and hot work and air test tanks and voids | 10 | EA | $0.00 | |||
| 1004AD | Test alarm system | 2 | EA | $0.00 | |||
| 1005 | Fire Fighting Equipment: Replace, Repair and Maintenance | ||||||
| 1005AA | Replace, stencil, and hydrostatically test fire hose (100 feet in length with couplings) | 2 | EA | $0.00 | |||
| 1005AB | Re-charge existing fire extinguishers, 20 lbs. or less | 60 | EA | $0.00 | |||
| 1005AC | Install new dry chemical fire extinguishers, 20 lbs. | 25 | EA | $0.00 | |||
| 1005AD | Install new fire station spanner wrenches | 20 | EA | $0.00 | |||
| 1005AE | Install new fire hose nozzles | 10 | EA | $0.00 | |||
| 1005AF | Replace, stencil, and hydrostatically test fire hose (50 feet in length with couplings) | 25 | EA | $0.00 | |||
| 1005AG | Hydrostatically test fire hose (50 feet in length) | 25 | EA | $0.00 | |||
| 1005AH | Certify portable fire extinguisher | 75 | EA | $0.00 | |||
| 1006 | Repair Galley/Messing Equipment and Fixtures | ||||||
| 1006AA | Provide commercial type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 1006AB | Provide household type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 1006AC | Repair and certify Gaylord Hood and Range Guard | 6 | EA | $0.00 | |||
| 1006AD | Replace disposable filters (industrial fire retardant) for galley systems | 50 | EA | $0.00 | |||
| 1006AE | Steam clean permanent filter sets | 10 | EA | $0.00 | |||
| 1006AF | Replace permanent filter sets | 10 | EA | $0.00 | |||
| 1007 | Laundry Equipment, Replace | ||||||
| 1007AA | Remove existing, provide and install new single function clothes washer, commercial style, accomplish operational test | 5 | EA | $0.00 | |||
| 1007AB | Remove existing, provide and install new single function clothes dryer, commerical style, accomplish operational test | 5 | EA | $0.00 | |||
| 1008 | Habitability Repairs | ||||||
| 1008AA | Replace urinals | 4 | EA | $0.00 | |||
| 1008AB | Replace toilets | 4 | EA | $0.00 | |||
| 1008AC | Replace sinks | 4 | EA | $0.00 | |||
| 1008AD | Replace shower heads | 15 | EA | $0.00 | |||
| 1008AE | Replace shower mixing valves | 10 | EA | $0.00 | |||
| 1008AF | Replace flushometer | 8 | EA | $0.00 | |||
| 1008AG | Replace sink mixing valves | 10 | EA | $0.00 | |||
| 1008AH | Deck Drains - Clean free of obstructions, including associated piping | 25 | EA | $0.00 | |||
| 1008AJ | Replace composition ceiling panels (2 ft. x 4 ft.) vinyl coated | 400 | EA | $0.00 | |||
| 1008AK | Replace ceiling tile T-Rail | 240 | LF | $0.00 | |||
| 1008AL | Replace towel racks | 10 | EA | $0.00 | |||
| 1008AM | Replace soap dishes | 10 | EA | $0.00 | |||
| 1008AN | Replace shower curtains including hooks | 30 | EA | $0.00 | |||
| 1008AP | Replace shower mats | 30 | EA | $0.00 | |||
| 1008AQ | Replace toilet paper holder (frame and spool) | 20 | EA | $0.00 | |||
| 1008AR | Replace water fountains | 7 | EA | $0.00 | |||
| 1008AS | Replace mini blinds | 25 | EA | $0.00 | |||
| 1008AT | Replace flushometer hoses | 10 | EA | $0.00 | |||
| 1008AU | Fabricate replacement keys as per sample | 100 | EA | $0.00 | |||
| 1008AV | Open and reset pin type lock sets to include 2 replacement keys | 20 | EA | $0.00 | |||
| 1008AW | Provide and install new lock sets | 10 | EA | $0.00 | |||
| 1008AX | Open and reset combination on high security/classified locks on doors and/or safes | 10 | EA | $0.00 | |||
| 1008AY | Open and install new lock sets and reset combinations on high security/classified locks on doors and/or safes | 10 | EA | $0.00 | |||
| 1008AZ | Replace automatic door closures | 5 | EA | $0.00 | |||
| 1008BA | Replace bulkhead insulation (2" thick) | 800 | SF | $0.00 | |||
| 1008BB | Replace bulkhead insulation (1" thick) | 250 | SF | $0.00 | |||
| 1008BC | Replace deck drains up to 4" to include one foot of piping | 3 | EA | $0.00 | |||
| 1009 | Electrical Repairs | ||||||
| 1009AA | Replace fluorescent tubes in closed fixtures: 12 inch | 100 | EA | $0.00 | |||
| 1009AB | Replace fluorescent tubes in closed fixtures: 24 inch | 250 | EA | $0.00 | |||
| 1009AC | Replace fluorescent tubes in closed fixtures: 48 inch | 400 | EA | $0.00 | |||
| 1009AD | Replace bulbs in closed incandescent fixtures | 75 | EA | $0.00 | |||
| 1009AE | Replace bulbs in spotlight fixtures | 30 | EA | $0.00 | |||
| 1009AF | Replace starters | 40 | EA | $0.00 | |||
| 1009AG | Replace bulb and battery in emergency light fixtures | 75 | EA | $0.00 | |||
| 1009AH | Install new nickel cadmium rechargeable emergency light fixtures | 25 | EA | $0.00 | |||
| 1009AJ | Replace fuses | 20 | EA | $0.00 | |||
| 1009AK | Install new exit light fixtures | 20 | EA | $0.00 | |||
| 1009AL | Replace light switches | 20 | EA | $0.00 | |||
| 1009AM | Replace light switch/receptacle covers | 25 | EA | $0.00 | |||
| 1009AN | Replace force protection halogen light bulbs | 5 | EA | $0.00 | |||
| 1009AP | Replace force protection light photo cells | 3 | EA | $0.00 | |||
| 1010 | Piping Replacement | ||||||
| 1010AA | Replace valves up to 2 inches in diameter (WOG) | 20 | EA | $0.00 | |||
| 1010AB | Replace valves up to 2 inches in diameter (Steam) | 2 | EA | $0.00 | |||
| 1010AC | Replace valves 2 inches to 4 inches in diameter (WOG) | 10 | EA | $0.00 | |||
| 1010AD | Replace valves 2 inches to 4 inches in diameter (Steam) | 2 | EA | $0.00 | |||
| 1010AE | Replace piping up to 2 inches in diameter (CUNI) | 200 | LF | $0.00 | |||
| 1010AF | Replace piping up to 2 inches in diameter (Steel) | 40 | LF | $0.00 | |||
| 1010AG | Replace piping 2 inches to 4 inches in diameter (CUNI) | 200 | LF | $0.00 | |||
| 1010AH | Replace piping 2 inches to 4 inches in diameter (Steel) | 20 | LF | $0.00 | |||
| 1010AJ | Replace flange up to 2 inches in diameter (WOG) | 6 | EA | $0.00 | |||
| 1010AK | Replace pipe fitting up to 2 inches in diameter (WOG) | 20 | EA | $0.00 | |||
| 1010AL | Replace flange up to 2 inches in diameter (Steam) | 6 | EA | $0.00 | |||
| 1010AM | Replace pipe fitting up to 2 inches in diameter (Steam) | 20 | EA | $0.00 | |||
| 1010AN | Replace flange 2 inches to 4 inches in diameter (WOG) | 4 | EA | $0.00 | |||
| 1010AP | Replace pipe fitting 2 inches to 4 inches in diameter (WOG) | 20 | $0.00 | ||||
| 1010AQ | Replace flange 2 inches to 4 inches in diameter (Steam) | 10 | EA | $0.00 | |||
| 1010AR | Replace pipe fitting 2 inches to 4 inches in diameter (Steam) | 20 | $0.00 | ||||
| 1010AS | Replace and preserve paint pipe lagging up to 2 inches in diameter | 100 | LF | $0.00 | |||
| 1010AT | Replace and preserve paint pipe lagging up to 2-4 inches in diameter | 100 | LF | $0.00 | |||
| 1010AU | Replace and preserve lagging pads up to 2 inch | 60 | SF | $0.00 | |||
| 1010AV | Replace and preserve lagging pads 2-4 inch | 60 | SF | $0.00 | |||
| 1010AW | Install in-line potable water filters | 3 | EA | $0.00 | |||
| 1010AX | Replace in-line potable water filters | 3 | EA | $0.00 | |||
| 1010AY | Temporary Pipe Soft Patch Repair (for piping 2" in Diameter or less) | 10 | EA | $0.00 | |||
| 1010AZ | Temporary Pipe Soft Patch Repair (for piping 2 - 4 inch in Diameter) | 10 | EA | $0.00 | |||
| 1011 | Heating Ventilation and Air Conditioning Repairs | ||||||
| 1011AA | Accomplish repairs to A/C and refrigeration equipment | 500 | HR | $0.00 | |||
| 1011AB | Material (in support of ELIN 0011) to accomplish repairs to A/C and refrigeration equipment (for bidding purposes only) | 25,000 | EA | $0.00 | |||
| 1011AC | Material G&A/Handling (in support of ELIN 0011) (Contractor to submit a percentage) | 25,000 | X | $0.00 | |||
| In negotiating the fixed price for materials, the contractor shall submit quotes or invoices for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN. | $0.00 | ||||||
| 1011AD | Replace ventilation duct, Round, 6 inch diameter and below with CRES Type 316L | 20 | LF | $0.00 | |||
| 1011AE | Replace ventilation duct, Round, 6 - 12 inch diameter, with CRES Type 316L | 30 | LF | $0.00 | |||
| 1011AF | Replace ventilation duct, Rectangular, 48 inch perimeter and below, with CRES Type 316L | 20 | LF | $0.00 | |||
| 1011AG | Replace ventilation duct, Rectangular, 49-84 inch perimeter, with CRES Type 316L | 20 | LF | $0.00 | |||
| 1011AH | Replace ventilation duct, Rectangular, 85-100 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 1011AJ | Replace ventilation duct, Rectangular, 101-120 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 1011AK | Replace ventilation duct, Rectangular, 121-150 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 1011AL | Replace ventilation duct diffusers (12 in. x 12 in.) | 5 | EA | $0.00 | |||
| 1011AM | Replace ventilation and duct inspection covers | 5 | EA | $0.00 | |||
| 1011AN | Replace thermostats | 10 | EA | $0.00 | |||
| 1011AP | Clean the entire ventilation duct work system: YRBM Class | 1 | EA | $0.00 | |||
| 1011AQ | Clean the entire ventilation duct work system: YRBM(L) Class | 2 | EA | $0.00 | |||
| 1011AR | Clean the entire ventilation duct work system: APL Class | 1 | EA | $0.00 | |||
| 1011AS | Replace disposable filters (20 in. x 25 in.), 1 inch thick | 25 | EA | $0.00 | |||
| 1011AT | Replace disposable filters (20 in. x 25 in.), 2 inches thick | 50 | EA | $0.00 | |||
| 1011AU | Replace disposable filters (20 in. x 25 in.), 4 inches thick | 10 | EA | $0.00 | |||
| 1011AV | Fabricate and install vent screens | 40 | SF | $0.00 | |||
| 1011AW | Steam clean permanent filter sets | 3 | EA | $0.00 | |||
| 1011AX | Replace permanent filter sets | 3 | EA | $0.00 | |||
| 1011AY | Insulate and preserve vent duct with 1" closed cell foam | 250 | SF | $0.00 | |||
| 1012 | Miscellaneous Repairs | ||||||
| 1012AA | Replace decking or bulkhead plating (15.3# O.S.) | 160 | SF | $0.00 | |||
| 1012AB | Replace hull plating (20.4# O.S.) | 80 | SF | $0.00 | |||
| 1012AC | Replace support structure (6" x 4" x 1/4" tee bar, O.S.) | 40 | LF | $0.00 | |||
| 1012AD | Replace hand rail | 120 | LF | $0.00 | |||
| 1012AE | Replace stanchion | 20 | EA | $0.00 | |||
| 1012AF | Sand and reseal Cosmetic Polymeric Type II, Class II (PRC) | 9,000 | SF | $0.00 | |||
| 1012AG | Resurface Cosmetic Polymeric Type II, Class II (PRC) decking | 1,800 | SF | $0.00 | |||
| 1012AH | Replace Cosmetic Polymeric Type II, Class II (PRC), including underlayment | 2,500 | SF | $0.00 | |||
| 1012AJ | Sand and reseal Cosmetic Polymeric Type I, Class I (Broadcast Quartz) decking | 2,500 | SF | $0.00 | |||
| 1012AK | Resurface Cosmetic Polymeric Type I, Class I (Broadcast Quartz) | 120 | SF | $0.00 | |||
| 1012AL | Replace Cosmetic Polymeric Type I, Class I (Broadcast Quartz) decking | 600 | SF | $0.00 | |||
| 1012AM | Replace vinyl tile, including underlayment | 160 | SF | $0.00 | |||
| 1012AN | Replace vinyl tile to underlayment | 80 | SF | $0.00 | |||
| 1012AP | Replace nonskid | 1,000 | SF | $0.00 | |||
| 1012AR | Replace nonskid with peel and stick nonskid | 200 | SF | $0.00 | |||
| 1012AS | Replace ladder treads, 6 in. x 12 in. aluminum | 25 | EA | $0.00 | |||
| 1013 | Preservation in accordance with 009-32 | ||||||
| 1013AA | Exterior preservation up to 1,000 sq. ft. In accordance with 009-32, Table 2, Line One, Columns B and G (for overcoat) | 800 | SF | $0.00 | |||
| 1013AB | Exterior preservation greater than 1,000 sq. ft. In accordance with 009-32, Table 2, Line One, Columns B and G (for overcoat) | 8,000 | SF | $0.00 | |||
| 1013AC | Exterior preservation up to 1,000 sq. ft. In accordance with 009-32, Table 2, Line One. | 800 | SF | $0.00 | |||
| 1013AD | Exterior preservation greater than 1,000 sq. ft. In accordance with 009-32, Table 2, Line One | 8,000 | SF | $0.00 | |||
| 1013AE | Interior preservation (Overcoat in accordance with 009-32, Table 3, Line 2) | 4,000 | SF | $0.00 | |||
| 1013AF | Interior preservation (Overcoat Wet Spaces in accordance with 009-32, Table 3, Line 4, Columns B, D, F and G.) | 1,000 | SF | $0.00 | |||
| 1013AG | Interior preservation (In accordance with 009-32, Table 3, Line 8) | 4,000 | SF | $0.00 | |||
| 1013AH | Interior preservation (Wet Spaces inaccordance with 009-32, Table 3, Line 4, 5, 6, or 7) | 1,000 | SF | $0.00 | |||
| 1014 | Maintenance - Maintenance support to the ship's crew occupying the craft | EA | $0.00 | ||||
| 1015 | Undisclosed Work | EA | $0.00 | ||||
| 1016 | RESERVED (This CLIN will never be used) | ||||||
| 1017 | LWT 077-002, Hazardous Waste Produced on Naval Vessels; control | ||||||
| 1017AA | LWT 077-002, Hazardous Waste Produced on Naval Vessels; control (for bidding purposes only) | 5,000 | U.S. GALLONS | $0.00 | |||
| Total Estimate for 1st Option Year | $0.00 |
2ND OPT YR
| Supplies/Services | Est Qty | Unit of Issue | Unit | ||||
| Price | EST Total | ||||||
| 2001 | Tow Barges | ||||||
| 2001AA | Tow (one way, up to 60 miles), YR, YRBM, YRBM(L) Class | 8 | EA | $0.00 | |||
| 2001AB | Tow (one way, up to 60 miles), APL Class | 2 | EA | $0.00 | |||
| 0001AC | Tow (one-way, up to 700 miles, Ocean tow) YRBM, YRBM(L) Class | 2 | EA | $0.00 | |||
| 0001AD | Tow (one-way, up to 700 miles, Ocean tow) APL Class | 2 | EA | $0.00 | |||
| 2001AE | DELETED | ||||||
| 2001AF | DELETED | ||||||
| 2002 | Temporary Services | ||||||
| 2002AA | Cast off and tie up berthing barge (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 2002AB | Install and remove sewage, potable water, steam, shore power, telephone, fire main, gangways and cable television connections (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 2002AC | Provide and install all services required to accomplish the requirements of the Task Order to include gangways, oil booms, safety nets, shore power, sewage, steam, firemain, telephone, potable water and cable television (within 60 mile radius of Mayport Naval Station, at contractor facility) | 180 | DAY | $0.00 | |||
| 2002AD | Provide and install 2 inch diameter mooring lines (100 ft. in length). One end with a 6' loop and other end finished. | 10 | EA | $0.00 | |||
| X | 2002AE | Provide and maintain one 300KW diesel powered generator | 4 | Day | $0.00 | ||
| X | 2002AF | Provide and maintain one 500 GPM diesel powered fire pump | 4 | Day | $0.00 | ||
| X | 2002AG | Provide and maintain one compressor 200 CFM, 125 PSI | 4 | Day | $0.00 | ||
| 2003 | Cleaning and Sanitizing | ||||||
| 2003AA | Deep clean and sanitize the entire Craft (YRBM Class) | 2 | EA | $0.00 | |||
| 2003AB | Deep clean and sanitize the entire Craft (YRBM-L Class) | 8 | EA | $0.00 | |||
| 2003AC | Deep clean and sanitize the entire Craft (APL Class) | 2 | EA | $0.00 | |||
| 2003AD | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM Class | 2 | EA | $0.00 | |||
| 2003AE | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM(L) Class | 8 | EA | $0.00 | |||
| 2003AF | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - APL Class | 2 | EA | $0.00 | |||
| 2003AG | Chemically clean entire CHT system | 2 | EA | $0.00 | |||
| 2003AH | Chemically clean water heater (in place) | 2 | EA | $0.00 | |||
| 2003AJ | Chemically clean water heater (in shop) | 2 | EA | $0.00 | |||
| 2003AK | Chemically clean heat exchanger (in place) | 1 | EA | $0.00 | |||
| 2003AL | Chemically clean heat exchanger (in shop) | 1 | EA | $0.00 | |||
| 2004 | Test and Inspections | ||||||
| 2004AA | Accomplish a preliminary and final visual and operational inspection of all systems and equipment utilizing barge systems and equipment check off list (Planning Memorandum No. 601-005). Submit a detailed report of all discrepancies. | 7 | EA | $0.00 | |||
| 2004AB | Clean, gas free safe for entry and hot work, inspect and test CHT system, replacing 4 floats per system | 4 | SY | $0.00 | |||
| 2004AC | Clean, gas free safe for entry and hot work and air test tanks and voids | 10 | EA | $0.00 | |||
| 2004AD | Test alarm system | 2 | EA | $0.00 | |||
| 2005 | Fire Fighting Equipment: Replace, Repair and Maintenance | ||||||
| 2005AA | Replace, stencil, and hydrostatically test fire hose (100 feet in length with couplings) | 2 | EA | $0.00 | |||
| 2005AB | Re-charge existing fire extinguishers, 20 lbs. or less | 60 | EA | $0.00 | |||
| 2005AC | Install new dry chemical fire extinguishers, 20 lbs. | 25 | EA | $0.00 | |||
| 2005AD | Install new fire station spanner wrenches | 20 | EA | $0.00 | |||
| 2005AE | Install new fire hose nozzles | 10 | EA | $0.00 | |||
| 2005AF | Replace, stencil, and hydrostatically test fire hose (50 feet in length with couplings) | 25 | EA | $0.00 | |||
| 2005AG | Hydrostatically test fire hose (50 feet in length) | 25 | EA | $0.00 | |||
| 2005AH | Certify portable fire extinguisher | 75 | EA | $0.00 | |||
| 2006 | Repair Galley/Messing Equipment and Fixtures | ||||||
| 2006AA | Provide commercial type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 2006AB | Provide household type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 2006AC | Repair and certify Gaylord Hood and Range Guard | 6 | EA | $0.00 | |||
| 2006AD | Replace disposable filters (industrial fire retardant) for galley systems | 50 | EA | $0.00 | |||
| 2006AE | Steam clean permanent filter sets | 10 | EA | $0.00 | |||
| 2006AF | Replace permanent filter sets | 10 | EA | $0.00 | |||
| 2007 | Laundry Equipment, Replace | ||||||
| 2007AA | Remove existing, provide and install new single function clothes washer, commercial style, accomplish operational test | 5 | EA | $0.00 | |||
| 2007AB | Remove existing, provide and install new single function clothes dryer, commerical style, accomplish operational test | 5 | EA | $0.00 | |||
| 2008 | Habitability Repairs | ||||||
| 2008AA | Replace urinals | 4 | EA | $0.00 | |||
| 2008AB | Replace toilets | 4 | EA | $0.00 | |||
| 2008AC | Replace sinks | 4 | EA | $0.00 | |||
| 2008AD | Replace shower heads | 15 | EA | $0.00 | |||
| 2008AE | Replace shower mixing valves | 10 | EA | $0.00 | |||
| 2008AF | Replace flushometer | 8 | EA | $0.00 | |||
| 2008AG | Replace sink mixing valves | 10 | EA | $0.00 | |||
| 2008AH | Deck Drains - Clean free of obstructions, including associated piping | 25 | EA | $0.00 | |||
| 2008AJ | Replace composition ceiling panels (2 ft. x 4 ft.) vinyl coated | 400 | EA | $0.00 | |||
| 2008AK | Replace ceiling tile T-Rail | 240 | LF | $0.00 | |||
| 2008AL | Replace towel racks | 10 | EA | $0.00 | |||
| 2008AM | Replace soap dishes | 10 | EA | $0.00 | |||
| 2008AN | Replace shower curtains including hooks | 30 | EA | $0.00 | |||
| 2008AP | Replace shower mats | 30 | EA | $0.00 | |||
| 2008AQ | Replace toilet paper holder (frame and spool) | 20 | EA | $0.00 | |||
| 2008AR | Replace water fountains | 7 | EA | $0.00 | |||
| 2008AS | Replace mini blinds | 25 | EA | $0.00 | |||
| 2008AT | Replace flushometer hoses | 10 | EA | $0.00 | |||
| 2008AU | Fabricate replacement keys as per sample | 100 | EA | $0.00 | |||
| 2008AV | Open and reset pin type lock sets to include 2 replacement keys | 20 | EA | $0.00 | |||
| 2008AW | Provide and install new lock sets | 10 | EA | $0.00 | |||
| 2008AX | Open and reset combination on high security/classified locks on doors and/or safes | 10 | EA | $0.00 | |||
| 2008AY | Open and install new lock sets and reset combinations on high security/classified locks on doors and/or safes | 10 | EA | $0.00 | |||
| 2008AZ | Replace automatic door closures | 5 | EA | $0.00 | |||
| 2008BA | Replace bulkhead insulation (2" thick) | 800 | SF | $0.00 | |||
| 2008BB | Replace bulkhead insulation (1" thick) | 250 | SF | $0.00 | |||
| 2008BC | Replace deck drains up to 4" to include one foot of piping | 3 | EA | $0.00 | |||
| 2009 | Electrical Repairs | ||||||
| 2009AA | Replace fluorescent tubes in closed fixtures: 12 inch | 100 | EA | $0.00 | |||
| 2009AB | Replace fluorescent tubes in closed fixtures: 24 inch | 250 | EA | $0.00 | |||
| 2009AC | Replace fluorescent tubes in closed fixtures: 48 inch | 400 | EA | $0.00 | |||
| 2009AD | Replace bulbs in closed incandescent fixtures | 75 | EA | $0.00 | |||
| 2009AE | Replace bulbs in spotlight fixtures | 30 | EA | $0.00 | |||
| 2009AF | Replace starters | 40 | EA | $0.00 | |||
| 2009AG | Replace bulb and battery in emergency light fixtures | 75 | EA | $0.00 | |||
| 2009AH | Install new nickel cadmium rechargeable emergency light fixtures | 25 | EA | $0.00 | |||
| 2009AJ | Replace fuses | 20 | EA | $0.00 | |||
| 2009AK | Install new exit light fixtures | 20 | EA | $0.00 | |||
| 2009AL | Replace light switches | 20 | EA | $0.00 | |||
| 2009AM | Replace light switch/receptacle covers | 25 | EA | $0.00 | |||
| 2009AN | Replace force protection halogen light bulbs | 5 | EA | $0.00 | |||
| 2009AP | Replace force protection light photo cells | 3 | EA | $0.00 | |||
| 2010 | Piping Replacement | ||||||
| 2010AA | Replace valves up to 2 inches in diameter (WOG) | 20 | EA | $0.00 | |||
| 2010AB | Replace valves up to 2 inches in diameter (Steam) | 2 | EA | $0.00 | |||
| 2010AC | Replace valves 2 inches to 4 inches in diameter (WOG) | 10 | EA | $0.00 | |||
| 2010AD | Replace valves 2 inches to 4 inches in diameter (Steam) | 2 | EA | $0.00 | |||
| 2010AE | Replace piping up to 2 inches in diameter (CUNI) | 200 | LF | $0.00 | |||
| 2010AF | Replace piping up to 2 inches in diameter (Steel) | 40 | LF | $0.00 | |||
| 2010AG | Replace piping 2 inches to 4 inches in diameter (CUNI) | 200 | LF | $0.00 | |||
| 2010AH | Replace piping 2 inches to 4 inches in diameter (Steel) | 20 | LF | $0.00 | |||
| 2010AJ | Replace flange up to 2 inches in diameter (WOG) | 6 | EA | $0.00 | |||
| 2010AK | Replace pipe fitting up to 2 inches in diameter (WOG) | 20 | EA | $0.00 | |||
| 2010AL | Replace flange up to 2 inches in diameter (Steam) | 6 | EA | $0.00 | |||
| 2010AM | Replace pipe fitting up to 2 inches in diameter (Steam) | 20 | EA | $0.00 | |||
| 2010AN | Replace flange 2 inches to 4 inches in diameter (WOG) | 4 | EA | $0.00 | |||
| 2010AP | Replace pipe fitting 2 inches to 4 inches in diameter (WOG) | 20 | $0.00 | ||||
| 2010AQ | Replace flange 2 inches to 4 inches in diameter (Steam) | 10 | EA | $0.00 | |||
| 2010AR | Replace pipe fitting 2 inches to 4 inches in diameter (Steam) | 20 | $0.00 | ||||
| 2010AS | Replace and preserve paint pipe lagging up to 2 inches in diameter | 100 | LF | $0.00 | |||
| 2010AT | Replace and preserve paint pipe lagging up to 2-4 inches in diameter | 100 | LF | $0.00 | |||
| 2010AU | Replace and preserve lagging pads up to 2 inch | 60 | SF | $0.00 | |||
| 2010AV | Replace and preserve lagging pads 2-4 inch | 60 | SF | $0.00 | |||
| 2010AW | Install in-line potable water filters | 3 | EA | $0.00 | |||
| 2010AX | Replace in-line potable water filters | 3 | EA | $0.00 | |||
| 2010AY | Temporary Pipe Soft Patch Repair (for piping 2" in Diameter or less) | 10 | EA | $0.00 | |||
| 2010AZ | Temporary Pipe Soft Patch Repair (for piping 2 - 4 inch in Diameter) | 10 | EA | $0.00 | |||
| 2011 | Heating Ventilation and Air Conditioning Repairs | ||||||
| 2011AA | Accomplish repairs to A/C and refrigeration equipment | 500 | HR | $0.00 | |||
| 2011AB | Material (in support of ELIN 0011) to accomplish repairs to A/C and refrigeration equipment (for bidding purposes only) | 25,000 | EA | $0.00 | |||
| 2011AC | Material G&A/Handling (in support of ELIN 0011) (Contractor to submit a percentage) | 25,000 | X | $0.00 | |||
| In negotiating the fixed price for materials, the contractor shall submit quotes or invoices for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN. | $0.00 | ||||||
| 2011AD | Replace ventilation duct, Round, 6 inch diameter and below with CRES Type 316L | 20 | LF | $0.00 | |||
| 2011AE | Replace ventilation duct, Round, 6 - 12 inch diameter, with CRES Type 316L | 30 | LF | $0.00 | |||
| 2011AF | Replace ventilation duct, Rectangular, 48 inch perimeter and below, with CRES Type 316L | 20 | LF | $0.00 | |||
| 2011AG | Replace ventilation duct, Rectangular, 49-84 inch perimeter, with CRES Type 316L | 20 | LF | $0.00 | |||
| 2011AH | Replace ventilation duct, Rectangular, 85-100 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 2011AJ | Replace ventilation duct, Rectangular, 101-120 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 2011AK | Replace ventilation duct, Rectangular, 121-150 inch perimeter, with CRES Type 316L | 10 | LF | $0.00 | |||
| 2011AL | Replace ventilation duct diffusers (12 in. x 12 in.) | 5 | EA | $0.00 | |||
| 2011AM | Replace ventilation and duct inspection covers | 5 | EA | $0.00 | |||
| 2011AN | Replace thermostats | 10 | EA | $0.00 | |||
| 2011AP | Clean the entire ventilation duct work system: YRBM Class | 1 | EA | $0.00 | |||
| 2011AQ | Clean the entire ventilation duct work system: YRBM(L) Class | 2 | EA | $0.00 | |||
| 2011AR | Clean the entire ventilation duct work system: APL Class | 1 | EA | $0.00 | |||
| 2011AS | Replace disposable filters (20 in. x 25 in.), 1 inch thick | 25 | EA | $0.00 | |||
| 2011AT | Replace disposable filters (20 in. x 25 in.), 2 inches thick | 50 | EA | $0.00 | |||
| 2011AU | Replace disposable filters (20 in. x 25 in.), 4 inches thick | 10 | EA | $0.00 | |||
| 2011AV | Fabricate and install vent screens | 40 | SF | $0.00 | |||
| 2011AW | Steam clean permanent filter sets | 3 | EA | $0.00 | |||
| 2011AX | Replace permanent filter sets | 3 | EA | $0.00 | |||
| 2011AY | Insulate and preserve vent duct with 1" closed cell foam | 250 | SF | $0.00 | |||
| 2012 | Miscellaneous Repairs | ||||||
| 2012AA | Replace decking or bulkhead plating (15.3# O.S.) | 160 | SF | $0.00 | |||
| 2012AB | Replace hull plating (20.4# O.S.) | 80 | SF | $0.00 | |||
| 2012AC | Replace support structure (6" x 4" x 1/4" tee bar, O.S.) | 40 | LF | $0.00 | |||
| 2012AD | Replace hand rail | 120 | LF | $0.00 | |||
| 2012AE | Replace stanchion | 20 | EA | $0.00 | |||
| 2012AF | Sand and reseal Cosmetic Polymeric Type II, Class II (PRC) | 9,000 | SF | $0.00 | |||
| 2012AG | Resurface Cosmetic Polymeric Type II, Class II (PRC) decking | 1,800 | SF | $0.00 | |||
| 2012AH | Replace Cosmetic Polymeric Type II, Class II (PRC), including underlayment | 2,500 | SF | $0.00 | |||
| 2012AJ | Sand and reseal Cosmetic Polymeric Type I, Class I (Broadcast Quartz) decking | 2,500 | SF | $0.00 | |||
| 2012AK | Resurface Cosmetic Polymeric Type I, Class I (Broadcast Quartz) | 120 | SF | $0.00 | |||
| 2012AL | Replace Cosmetic Polymeric Type I, Class I (Broadcast Quartz) decking | 600 | SF | $0.00 | |||
| 2012AM | Replace vinyl tile, including underlayment | 160 | SF | $0.00 | |||
| 2012AN | Replace vinyl tile to underlayment | 80 | SF | $0.00 | |||
| 2012AP | Replace nonskid | 1,000 | SF | $0.00 | |||
| 2012AR | Replace nonskid with peel and stick nonskid | 200 | SF | $0.00 | |||
| 2012AS | Replace ladder treads, 6 in. x 12 in. aluminum | 25 | EA | $0.00 | |||
| 2013 | Preservation in accordance with 009-32 | ||||||
| 2013AA | Exterior preservation up to 1,000 sq. ft. In accordance with 009-32, Table 2, Line One, Columns B and G (for overcoat) | 800 | SF | $0.00 | |||
| 2013AB | Exterior preservation greater than 1,000 sq. ft. In accordance with 009-32, Table 2, Line One, Columns B and G (for overcoat) | 8,000 | SF | $0.00 | |||
| 2013AC | Exterior preservation up to 1,000 sq. ft. In accordance with 009-32, Table 2, Line One. | 800 | SF | $0.00 | |||
| 2013AD | Exterior preservation greater than 1,000 sq. ft. In accordance with 009-32, Table 2, Line One | 8,000 | SF | $0.00 | |||
| 2013AE | Interior preservation (Overcoat in accordance with 009-32, Table 3, Line 2) | 4,000 | SF | $0.00 | |||
| 2013AF | Interior preservation (Overcoat Wet Spaces in accordance with 009-32, Table 3, Line 4, Columns B, D, F and G.) | 1,000 | SF | $0.00 | |||
| 2013AG | Interior preservation (In accordance with 009-32, Table 3, Line 8) | 4,000 | SF | $0.00 | |||
| 2013AH | Interior preservation (Wet Spaces inaccordance with 009-32, Table 3, Line 4, 5, 6, or 7) | 1,000 | SF | $0.00 | |||
| 2014 | Maintenance - Maintenance support to the ship's crew occupying the craft | EA | $0.00 | ||||
| 2015 | Undisclosed Work | EA | $0.00 | ||||
| 2016 | RESERVED (This CLIN will never be used) | ||||||
| 2017 | LWT 077-002, Hazardous Waste Produced on Naval Vessels; control | ||||||
| 2017AA | LWT 077-002, Hazardous Waste Produced on Naval Vessels; control (for bidding purposes only) | 5,000 | U.S. GALLONS | $0.00 | |||
| Total Estimate for 2nd Option Year | Total | $0.00 |
3RD OPT YR
| Supplies/Services | Est Qty | Unit of Issue | Unit | ||||
| Price | EST Total | ||||||
| 3001 | Tow Barges | ||||||
| 3001AA | Tow (one way, up to 60 miles), YR, YRBM, YRBM(L) Class | 8 | EA | $0.00 | |||
| 3001AB | Tow (one way, up to 60 miles), APL Class | 2 | EA | $0.00 | |||
| 0001AC | Tow (one-way, up to 700 miles, Ocean tow) YRBM, YRBM(L) Class | 2 | EA | $0.00 | |||
| 0001AD | Tow (one-way, up to 700 miles, Ocean tow) APL Class | 2 | EA | $0.00 | |||
| 3001AE | DELETED | ||||||
| 3001AF | DELETED | ||||||
| 3002 | Temporary Services | ||||||
| 3002AA | Cast off and tie up berthing barge (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 3002AB | Install and remove sewage, potable water, steam, shore power, telephone, fire main, gangways and cable television connections (within 60 mile radius of Mayport Naval Station) | 12 | EA | $0.00 | |||
| 3002AC | Provide and install all services required to accomplish the requirements of the Task Order to include gangways, oil booms, safety nets, shore power, sewage, steam, firemain, telephone, potable water and cable television (within 60 mile radius of Mayport Naval Station, at contractor facility) | 180 | DAY | $0.00 | |||
| 3002AD | Provide and install 2 inch diameter mooring lines (100 ft. in length). One end with a 6' loop and other end finished. | 10 | EA | $0.00 | |||
| X | 3002AE | Provide and maintain one 300KW diesel powered generator | 4 | Day | $0.00 | ||
| X | 3002AF | Provide and maintain one 500 GPM diesel powered fire pump | 4 | Day | $0.00 | ||
| X | 3002AG | Provide and maintain one compressor 200 CFM, 125 PSI | 4 | Day | $0.00 | ||
| 3003 | Cleaning and Sanitizing | ||||||
| 3003AA | Deep clean and sanitize the entire Craft (YRBM Class) | 2 | EA | $0.00 | |||
| 3003AB | Deep clean and sanitize the entire Craft (YRBM-L Class) | 8 | EA | $0.00 | |||
| 3003AC | Deep clean and sanitize the entire Craft (APL Class) | 2 | EA | $0.00 | |||
| 3003AD | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM Class | 2 | EA | $0.00 | |||
| 3003AE | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - YRBM(L) Class | 8 | EA | $0.00 | |||
| 3003AF | Fumigate/Exterminate in accordance with the U.S. Navy Shipboard Pest Control Manual - APL Class | 2 | EA | $0.00 | |||
| 3003AG | Chemically clean entire CHT system | 2 | EA | $0.00 | |||
| 3003AH | Chemically clean water heater (in place) | 2 | EA | $0.00 | |||
| 3003AJ | Chemically clean water heater (in shop) | 2 | EA | $0.00 | |||
| 3003AK | Chemically clean heat exchanger (in place) | 1 | EA | $0.00 | |||
| 3003AL | Chemically clean heat exchanger (in shop) | 1 | EA | $0.00 | |||
| 3004 | Test and Inspections | ||||||
| 3004AA | Accomplish a preliminary and final visual and operational inspection of all systems and equipment utilizing barge systems and equipment check off list (Planning Memorandum No. 601-005). Submit a detailed report of all discrepancies. | 7 | EA | $0.00 | |||
| 3004AB | Clean, gas free safe for entry and hot work, inspect and test CHT system, replacing 4 floats per system | 4 | SY | $0.00 | |||
| 3004AC | Clean, gas free safe for entry and hot work and air test tanks and voids | 10 | EA | $0.00 | |||
| 3004AD | Test alarm system | 2 | EA | $0.00 | |||
| 3005 | Fire Fighting Equipment: Replace, Repair and Maintenance | ||||||
| 3005AA | Replace, stencil, and hydrostatically test fire hose (100 feet in length with couplings) | 2 | EA | $0.00 | |||
| 3005AB | Re-charge existing fire extinguishers, 20 lbs. or less | 60 | EA | $0.00 | |||
| 3005AC | Install new dry chemical fire extinguishers, 20 lbs. | 25 | EA | $0.00 | |||
| 3005AD | Install new fire station spanner wrenches | 20 | EA | $0.00 | |||
| 3005AE | Install new fire hose nozzles | 10 | EA | $0.00 | |||
| 3005AF | Replace, stencil, and hydrostatically test fire hose (50 feet in length with couplings) | 25 | EA | $0.00 | |||
| 3005AG | Hydrostatically test fire hose (50 feet in length) | 25 | EA | $0.00 | |||
| 3005AH | Certify portable fire extinguisher | 75 | EA | $0.00 | |||
| 3006 | Repair Galley/Messing Equipment and Fixtures | ||||||
| 3006AA | Provide commercial type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 3006AB | Provide household type garbage disposal, remove existing, replace and operational test | 2 | EA | $0.00 | |||
| 3006AC | Repair and certify Gaylord Hood and Range Guard | 6 | EA | $0.00 | |||
| 3006AD | Replace disposable filters (industrial fire retardant) for galley systems | 50 | EA | $0.00 | |||
| 3006AE | Steam clean permanent filter sets | 10 | EA | $0.00 | |||
| 3006AF | Replace permanent filter sets | 10 | EA | $0.00 | |||
| 3007 | Laundry Equipment, Replace | ||||||
| 3007AA | Remove existing, provide and install new single function clothes washer, commercial style, accomplish operational test | 5 | EA | $0.00 | |||
| 3007AB | Remove existing, provide and install new single function clothes dryer, commerical style, accomplish operational test | 5 | EA | $0.00 | |||
| 3008 | Habitability Repairs | ||||||
| 3008AA | Replace urinals | 4 | EA | $0.00 | |||
| 3008AB | Replace toilets | 4 | EA | $0.00 | |||
| 3008AC | Replace sinks | 4 | EA | $0.00 | |||
| 3008AD | Replace shower heads | 15 | EA | $0.00 | |||
| 3008AE | Replace shower mixing valves | 10 | EA | $0.00 | |||
| 3008AF | Replace flushometer | 8 | EA | $0.00 | |||
| 3008AG | Replace sink mixing valves | 10 | EA | $0.00 |