Questions & Answers #35 ‐ #36, 11/28/2018
Question 35: Can an interested party bid on just some of the CLINs, or must Offeror’s bid on all of the CLINs?
Response to Question 35: To be considered technically acceptable, Offerors must be able to submit a quote to fulfill, at a minimum, 100% of the quantity required under any one or more
Contract Line Item(s) (CLINs)/SubCLINs.
Question 36: The Long Term Lodging Specifications, Rev1, Spec Item # 3.8.1.5. requires one (1) stove, with self‐cleaning oven, with a minimum of four (4) burners). The requirements are asking for housekeeping to be conducted on a weekly basis. The housekeeping team will be cleaning the ovens on a week basis already. How important is a self‐cleaning oven?
Response to Question 36: Long Term Lodging Specifications, Rev1, Spec Item # 3.10.1.1.5.
requires one (1) time weekly kitchen cleaning which shall be inclusive of Sub Spec Item #
3.10.1.1.5.1. Kitchen appliances. The government will accept one (1) time weekly cleaning of the kitchen appliances (including the oven) in lieu of a Item # 3.8.1.5.