Attachment 1 Specification.pdf
PDF 4 MB Posted
- Solicitation number
- N33191-25-R-0010
About this file
This document is a comprehensive Request for Proposal (RFP) for a design-build construction contract for repairs at the Grindavik Naval Radio Transmitter Facility (NRTF) in Iceland. The project, solicited by Naval Facilities Engineering Systems Command (NAVFAC) Europe, Africa, Central, involves four primary contract line items (CLINs): installing new automatic access gates, installing two independent electrical heating units, replacing septic tanks and installing a leach field, and replacing the roof of Building 2606. The contract is limited to Icelandic and American companies under a specific bilateral agreement, with a NAICS code of 236220 and a small business size standard of $45 million.
The total contract period is 365 calendar days, with a final revision date of 11FEB2025. The work is necessitated by recent volcanic eruptions and earthquakes that have damaged infrastructure at the NRTF base, including utility lines, roads, and facility structures. Key technical requirements include installing a new main gate with communications infrastructure, electrical heating systems connected to base generators, a new septic system serving two main buildings, and a complete roof replacement for Building 2606. The project requires comprehensive design, safety planning, environmental controls, and documentation, with strict adherence to sustainability and safety guidelines.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 2 - Attachment nr. 2 - road blue line.png | PNG image | |
| Amendment 0002.pdf | ||
| Amend 2 - Attachment nr. 1 asbestos.pdf | ||
| Amend 2 - Goverment Response to PPI.pdf | ||
| Amendment 01.pdf | ||
| Attachment 2 PPI Form.xlsx | XLSX spreadsheet | |
| Attachment 4 Price Schedule.docx | DOCX document | |
| Attachment 3 PPQ.doc | DOC document | |
| Solicitation N3319125F0010.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO. 1850668
N62995-GR Grindavik Eruption Repairs
Grindavik NRTF, Iceland
SUBMITTED BY:
NAVFAC EURAFCENT
NAS Sigonella PWD
FEAD – PDC 4
Sigonella, IT
PREPARED BY:
Electrical: Michele Cali’, Electrical Engineer Civil: Giovanni Paratore, Civil Engineer/Planner Architectural: Courtney Livingston, Architect
APPROVED BY:
For Commander, NAVFAC EURAFCENT:
Date:
N62995-GR Grindavik Eruption Repairs eProject Number 1850668 Grindavik NRTF, Iceland Final Rev. – 11FEB2025
1.0 Table of Contents (RFP Parts 2-6)
1. PART 2 – GENERAL REQUIREMENTS
00 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00.05 20 WORK RESTRICTIONS
01 20 00.05 20 PRICE AND PAYMENT PROCEDURES
01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS
01 31 19.05 20 POST AWARD MEETINGS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT
CONTRACT MANAGEMENT SYSTEM
01 32 16.05 20 SMALL PROJECT DESIGN AND CONSTRUCTION SCHEDULE
01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS
01 45 00.05 20 QUALITY CONTROL
01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19.05 20 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT FOR
DESIGN-BUILD
2. PART 3 – PROJECT PROGRAM
CHAPTER 1 & 2. PROJECT DESCRIPTION AND PROJECT OBJECTIVES
CHAPTER 3. SITE ANALYSIS
CHAPTER 4. BUILDING REQUIREMENTS – NOT USED
CHAPTER 5. ROOM REQUIREMENTS – NOT USED
CHAPTER 6. ENGINEERING SYSTEMS REQUIREMENTS
3. PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS
A10 FOUNDATIONS
A20 BASEMENT CONSTRUCTION
B10 SUPERSTRUCTURE
B20 EXTERIOR ENCLOSURE
B30 ROOFING
C10 INTERIOR CONSTRUCTION
C20 STAIRS
C30 INTERIOR FINISHES
D10 CONVEYING
D20 PLUMBING
D30 HVAC
D40 FIRE PROTECTION
D50 ELECTRICAL
E10 EQUIPMENT
E20 FURNISHINGS
F10 SPECIAL CONSTRUCTION
F20 SELECT BLDG DEMOLITION
G10 SITE PREPARATIONS
G20 SITE IMPROVEMENTS
G30 SITE CIVIL/MECHANICAL UTILITIES
G40 SITE ELECTRICAL UTILITIES
4. PART 5 – PRESCRIPTIVE SPECIFICATIONS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT
CONTRACTMANAGEMENT SYSTEM
01 32 16.05 20 SMALL PROJECT DESIGN AND CONSTRUCTION SCHEDULES
01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD
01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN-BUILD
5. PART 6 – ATTACHMENTS
Concept Floor Plan – For Reference Only
Management Notice
SMALL PROJECT TEMPLATE - PART 1 PROPOSAL FORMS AND DOCUMENTS - Page 1
Part 1 Proposal Forms and Documents
PART 2 GENERAL REQUIREMENTS - Page 1
Part 2 General Requirements
PART 2
GENERAL REQUIREMENTS
TABLE OF CONTENTS
2/18
• 00 00 00 GENERAL REQUIREMENTS
• 01 11 00 SUMMARY OF WORK
• 01 14 00.05 20 WORK RESTRICTIONS
• 01 20 00.05 20 PRICE AND PAYMENT PROCEDURES
• 01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS
• 01 31 19.05 20 POST AWARD MEETINGS
• 01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
• 01 32 16.05 20 SMALL PROJECT DESIGN AND CONSTRUCTION SCHEDULE
• 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
• 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
• 01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS
• 01 45 00.05 20 QUALITY CONTROL
• 01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS
• 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
• 01 74 19.05 20 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT FOR
PART 2 GENERAL REQUIREMENTS - Page 2
00 00 00 GENERAL REQUIREMENTS
1.1 Definitions
As used throughout the contract, the following terms have the meaning set forth below:
Contracting Officer (KO): The individual designated to administer the contract. Throughout this contract this individual will be responsible and possess the authority to act on behalf of the Government with respect to the specific contract.
Contracting Officer Representative (COR): The individual designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature.
Contract: Contract or task order.
Contractor: The term Contractor refers to both the prime Contractor and all subcontractors, whether in contract with the Prime Contractor or other subcontractors at any tier, including the Designer of Record.
Designer of Record (DOR): Licensed architect/engineer working as subcontractor to or partner with prime Contractor who provides design for this contract.
Quality Control (QC): Contractor's system to control the quality of design, material, equipment and construction.
Quality Assurance (QA) Program: Government's program to evaluate the effectiveness of the Contractor's quality control. The Government's QA Program is not a substitute for the Contractor's QC Program.
Holidays: See attached holiday schedule in Part 6.
1.2 Accessibility
Provide barrier-free design in accordance with UFC 1-200-01, DoD Building Code.
1.3 Changes
No oral statement by any person other than the Contracting Officer, as provided in the Federal Acquisition Regulation (FAR) clause 52.243-5 entitled, "CHANGES AND CHANGED CONDITIONS," will in any manner or degree modify or otherwise affect the terms of this contract.
1.4 No Waiver by the Government
The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred is not to be construed as a wavier or relinquishment to any extent of the right to assert or rely upon such terms or options on any future occasion.
1.5 Equitable Adjustments
a. Whenever the Contractor submits a claim for equitable adjustment under a clause which
PART 2 GENERAL REQUIREMENTS - Page 3 provides for equitable adjustment of the contract, such claim must include all types of adjustments in the total amounts to which the clause entitles the Contractor, including, but not limited to, adjustment arising out of delays or disruptions.
b. Except as the parties may otherwise expressly agree, the Contractor must be deemed to have waived: (1) any adjustments to which he otherwise might be entitled under the clause where such claim fails to request such adjustments; and (2) any increase in the amount of equitable adjustments additional to those requested in its claim.
c. If required by the Contracting Officer, the Contractor agrees to execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental agreement setting forth the aforesaid equitable adjustment. The Contractor further agrees that such release will discharge the Government, including its officers, agents, and employees, from any further claims, including, but not limited to, further claims arising out of delays or disruptions caused by the aforesaid change.
1.6 Warranty
Warrant all materials and work for not less than one year after final acceptance of the work, except as otherwise indicated in this RFP. If required to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair. For warranted items, furnish the manufacturer’s original written warranty accompanied by a copy of the supplier's receipt showing place of purchase, telephone number of supplier, address, delivery order number if applicable, and ticket number.
01 11 00 SUMMARY OF WORK
1.0 Protection of Government Property
Take special care to protect Government property. Return areas damaged as a result of construction under this contract to their original condition. In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, perform the following:
a. Remove or alter existing work or facilities in such a manner as to prevent injury or damage to any portion of the existing work or facilities that remain.
b. Repair or replace portions of existing work altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
c. Preserve the natural resources in accordance with the approved environmental protection plan prepared in accordance with UFGS 01 57 19 Temporary Environmental Controls.
1.1 Government Furnished Material and Equipment
PART 2 GENERAL REQUIREMENTS - Page 4
If applicable, the Government will furnish the materials and equipment for installation by the Contractor pursuant to contract clause FAR 52.245-2, Government Property (Fixed Price Contracts). Notify the Contracting Officer in writing at least 15 calendar days before the materials and equipment are required. Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage at the prevailing rate. The Contracting Officer will specify the location of materials and equipment and the delivery location.
01 14 00.05 20 WORK RESTRICTIONS
1.1 Existing Underground Utilities
Verify on-site utilities and have them marked out by a third party utility locator service prior to the start of construction. Determine the elevations of existing utilities and underground obstructions indicated as existing to remain in locations to be traversed by new utilities and other work provided herein before new work is laid closer than the nearest manhole or other structure at which an adjustment in grade could be made. Where dig permits are required, obtain permits and notify the Contracting Officer 30 calendar days prior to any excavation.
Maintain all utility markings for the duration of the contract.
1.2 Work Hours, Access and Passes
All Contractor employees, including subcontractors, subcontractors' employees, suppliers, and suppliers' employees are required to comply with the Installation Security Requirements regarding personnel, vehicle, and equipment security passes and access the jobsite. Nothing in the contract is to be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard thestation.
Coordinate with the Contracting Officer for specific security and access requirements.
a. Access to Buildings/ Occupied Buildings: The Contractor may work in or around existing occupied buildings. The Contractor is responsible, via the Contracting Officer, to obtain access to building and facilities and arrange for them to be opened and closed. Do not enter the building(s) without prior approval of the Contracting Officer. Keep the existing buildings and their contents secure at all times. Provide temporary closures as required to maintain security. Contract personnel will not be permitted in security-regulated buildings or areas unless cleared by the Security Officer.
b. Passes/Badges/Access: Contractor employees and representatives performing work under this contract are required to be either United States citizens or documented legal residents (status verified by prime contractor). All Contractor employees must obtain the required employee and vehicle passes. Follow guidance for bases that participate in the Navy Commercial Access Control System (NCACS). Failure to obtain security and base access passes must not be a cause for contract performance time extension. The Contractor is required to immediately turn in all terminated employee's badges to the issuing office. i
PART 2 GENERAL REQUIREMENTS - Page 5
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS) or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office will be furnished without charge. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
a) NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON). Information on costs and requirements to participate and enroll in NCACS is available at http://www.rapidgate.com/vendors or by calling 1-877-727-4342. Contractors should be aware that the costs incurred to obtain NCACS credentials, or costs related to any means of access to a Navy Installation, are not reimbursable. Any time invested, or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.
b) One-Day Passes: Participation in the NCACS is not mandatory, and if the Contractor chooses not to participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
c) Contractor Vehicles: All vehicles must display a valid state license plate and safety inspection sticker, if applicable, and must be maintained in good repair. The company name must be displayed in a clearly visible manner and size on each Contractor vehicle used in the course of work. Registration, proof of insurance and driver's licenses are required to obtain a station vehicle pass.
d) Work Hours: Unless otherwise indicated, work will be located on a Government compound, military installation, or station. Contractor work hours are between 0700 and 1530 Monday through Friday. Obtain advance approval from the Contracting Officer for Contractor personnel to remain on site beyond normal working hours. Notify the Contracting Officer at least 48 hours in advance to obtain approval for access to the jobsite or work outside of normal working hours or on Saturday, Sunday, and Federal Holidays.
e) Contractor Personnel: Provide the Contracting Officer the name(s) of the supervisory person(s) authorized to act for the Contractor. Provide, and update as required, a list of the key personnel for the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency.
http://www.uscis.gov/portal/site/uscis http://www.rapidgate.com/vendors
PART 2 GENERAL REQUIREMENTS - Page 6
f) Contractor employees must conduct themselves in a proper, efficient, courteous and businesslike manner. Remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of National Security.
1.3 Security Requirements
All security requirements apply to all subcontractors and suppliers associated with this contract.
Comply with the following:
a. Do not publicly disclose any information concerning any aspect of the materials or services relating to this contract, without prior written approval of the Contracting Officer.
b. Do not disclose or cause to be disseminated any information concerning the operations of the activity's security or interrupt the continuity of its operations.
c. Do not disclose any information to any person not entitled to receive it. Failure to safeguard any classified information that may come to the Contractor or any person under his control, may subject the Contractor, his agents or employees to criminal liability under 18 U.S.C., Sections 793 and 798.
d. Direct to the Contracting Officer and or Installation Security Officer for resolution all inquiries, comments or complaints arising from any matter observed, experienced, or learned as a result of or in connection with the performance of this contract, the resolution of which may require the dissemination of official information.
e. Coordinate photography requirements with the Contracting Officer. Some areas restrict or prohibit photographing Government property.
Deviations from or violations of any of the provisions of this paragraph, will, in addition to all other criminal and civil remedies provided by law, subject the Contractor to immediate termination for default and withdrawal of the Government's acceptance and approval of employment of the individuals involved.
01 20 00.05 20 PRICE AND PAYMENT PROCEDURES
1.1 Schedule of Prices
Submit a schedule of prices for approval on forms furnished by the Government. The initial schedule of prices may be preliminary for construction activities until the design is developed.
Include a detailed breakdown of the contract price with quantities and unit prices for each work activity or definable feature of work. Include general conditions, profit, and overhead costs within the unit prices. Break down into design and construction is required. The Contractor may invoice for bonds once the Government has approved the bonds, however, no other requests for payment will be processed without an approved schedule of prices and baseline schedule.
PART 2 GENERAL REQUIREMENTS - Page 7
1.2 Contractor Invoices
Contractor requests for payment must conform and will be processed in accordance with the requirements of FAR 52.232-5 and FAR 52.232-27.
a. Content of Invoice: Requests for payment in accordance with the terms of the contract must consist of the following: (If NFAS Clause 5252.232-9301 is present in the contract, documents must be provided as attachments in Wide Area Workflow (WAWF). The maximum size limit per attachment is less than 2 megabytes, but there are no limits on the number of attachments. If a document cannot be attached to WAWF due to system or size restrictions it must be provided as instructed by the contracting officer). If NFAS Clause 5252.232.9301 is not present in the contract, follow the invoicing instructions provided in the contract.
1. Contractor's Invoice on NAVFAC Form 7300/30, must show, in summary form, the basis for arriving at the amount of the invoice.
2. Contractor's Estimate for Voucher/ Contract Performance Statement on NAVFAC
Form 7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC LANT Form 4-330/110 (New 7/84) on NAVFAC Atlantic contracts when a Monthly Estimate for Voucher is required.
3. Affidavit to accompany invoice (LANTDIV NORVA Form 4-4235/4 (Rev. 5/81)).
4. Updated copy of submittal register.
5. Updated copy of progress schedule. Furnish as specified in "FAR 52.236-15, Schedules for Construction Contracts."
6. Contractor Safety Self Evaluation Checklist (original)
7. Final release (for final payment only). Final invoice must be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release.
b. Payment:
1. Payment will be made on Contractor's submission of itemized requests and will be subject to reduction for overpayments or increased for underpayments from previous payments. The Government may withhold payment or reduce payments for the following:
a. Defects in material or workmanship.
b. Claims the Government may have against the Contractor under or in connection with this contract.
c. Contractor's failure to submit an updated schedule.
d. Payroll violations.
e. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.
2. Payments may be made for materials, stored off construction sites, under the following conditions:
a. Materials to be considered for progress payment prior to installation must be located and stored within 20 miles by streets and roads of the construction site.
b. Materials adequately insured and protected from theft and exposure.
Payment requests for offsite materials must include the consent of surety.
c. Materials not susceptible to deterioration or physical damage in storage or in transit to the job site are acceptable for progress payments. Items such as steel, machinery, pipe and fittings and electrical cable are
PART 2 GENERAL REQUIREMENTS - Page 8 acceptable, but items such as gypsum board; glass, insulation and wall covering are not.
d. Materials in transit to the job or storage site are not acceptable for payment.
e. Conditions specified in FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
1.3 Budget Management
The Contractor must be responsible for budget management throughout the entire project. It is the intent of the Government to partner with the Contractor to maximize project value while strictly controlling contract modifications and maintaining overall fiscal control. When required, develop a Budget Management System for each phase of the design.
01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS
1.1 Supervision
The Contractor must have a superintendent fluent in English and host nation language on the job site during working hours.
The Superintendent must have a minimum of 5 years of experience as a Superintendent on previous projects of similar size and complexity. The Superintendent may serve as the Site Safety and Health Officer. Provide a Superintendent Resume for the proposed on-site Project Superintendent describing experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.2 Required Insurance
Within 15 calendar days after award, furnish the Contracting Officer a Certificate of Insurance as evidence of the following insurance coverage amounts not less than the amount specified below in accordance with FAR Clause 52.228-5, Insurance Work On A Government Installation:
a. Comprehensive General Liability: $500,000 per occurrence.
b. Automobile Liability: $200,000 per person, $500,000 per occurrence for bodily injury;
$20,000 per occurrence for property damage.
c. Worker's Compensation: As required by Federal and State Worker's compensation and occupational disease and other laws.
d. Employer's Liability Coverage: $100,000, except in states where worker's compensation may not be written by private carriers.
e. Others as required by state law.
f. Above insurance coverages are to extend to Contractor personnel operating Government owned equipment and vehicles.
PART 2 GENERAL REQUIREMENTS - Page 9
g. The Certificate of Insurance must provide for 30 calendar days written notice to the
Contracting Officer by the insurance company prior to cancellation or material change in policy coverage.
For projects which require removal of asbestos containing materials the Asbestos Contractor or Subcontractor, as the case may be is required to provide occurrence-based liability insurance with asbestos coverages in an amount not less than $1,000,000 and must name the Government and PQP as additional insureds.
01 31 19.05 20 POST AWARD MEETINGS
1.1 Post Award Kick-off Meeting (PAK)
Prior to commencement of design, and within 21 calendar days of award, meet with representatives of the Contracting Officer, installation and client to present the concept design for discussion and acceptance. The project team will develop a mutual understanding relative to the approved proposal, safety program, environmental permits and requirements, quality control procedures, and design and construction schedule. During the meeting, Contractor must propose and gain acceptance for any critical path work activities requiring advance submittal and approval.
If the contract includes work on any fire protection system, including fire alarm and mass notification systems, the Contractor and the appropriate fire protection DOR must meet with the NAVFAC Fire Protection Engineer (FPE) to establish clear expectations of fire protection requirements of the project.
The Contractor's key personnel must attend including the Project Manager, Superintendent, Site Safety and Health officer, CQ Manager, DQC Manager, DOR, and major subcontractors.
1.2 Partnering
The Contracting Officer will organize initial and follow-up informal partnering sessions with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session may be a part of the PAK Meeting. The initial partnering session will be conducted and facilitated using electronic media provided by the Contracting Officer. Follow-on partnering sessions will be conducted every 6 months or less frequent as determined by the Contracting Officer.
1.3 Pre-Construction Conference
Prior to construction or demolition, meet with representatives of the Contracting Officer to discuss and develop mutual understanding relative to administration of the safety programs, environmental issues, safety of building occupants and surrounding area, hazardous materials, waste disposal, construction QC procedures, construction schedule, labor provisions and other construction phase contract procedures.
1.4 NAVFAC Red Zone Meeting (NRZ)
Participate in NAVFAC Red Zone (NRZ) meetings with the Contracting Officer to identify strategies to ensure the project is carried to expeditious closure and turnover to the client. The Contracting Officer will provide a template to the Contractor to use to develop a NRZ Checklist.
Revise the template to include critical work activities and their planned completion dates based on
PART 2 GENERAL REQUIREMENTS - Page 10 the project scope of work and schedule. Discuss any progress changes with items listed on the NRZ Checklist during regularly scheduled NRZ Meetings beginning approximately at 75% stage of construction prior to project completion.
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
See UFGS Section 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System in Part 5 of this RFP for requirements for the use of eCMS.
01 32 16.05 20 SMALL PROJECT DESIGN AND CONSTRUCTION
SCHEDULES
Develop and implement a design and construction schedule in accordance with attached UFGS 01 32 16.05 20.
01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
1.1 Construction submittals are to be Contractor-approved, except those listed below:
DOR Approval required for:
1. Earthwork and Geotechnical submittals
2. All components of the roof and exterior wall.
3. HVAC Testing, Adjusting, and Balancing.
4. Telecommunications
b. Government Approval required for:
1. Government approved submittals as required by UFGS specification sections edited by the DOR.
2. Electronic Security Systems
3. Electrical Distribution: piping, wiring, panelboards, accessories
1.2 Submit the following construction submittals, approved by the DOR, to the Government for surveillance:
a. Submit fire protection related submittals pertaining to spray-applied fire proofing and fire stopping, exterior fire alarm reporting systems, interior fire alarm & detection systems, and fire suppression systems including fire pumps and standpipe systems.
b. Submit geotechnical related submittals pertaining to the soils investigations (reports and soils analysis), foundations (shallow and deep), pavements structure design, test pile and production pile testing and installation.
PART 2 GENERAL REQUIREMENTS - Page 11
c. Submit HVAC Testing, Adjusting, and Balancing required submittals.
d. Submit Performance Verification and Acceptance Testing required by IBC or this RFP.
e. Submit all Interim Special Inspection Reports on a bi-weekly basis until work requiring special inspections is complete. Submit all Structural Observation Reports and the Final Report of IBC Special Inspections.
f. Comply with sustainability submittals per UFGS section 01 33 29.05 20 Sustainability Reporting for Design-Build.
1.3 Construction Submittal Process
Provide to the Government submittals as listed. See Section 01 33 10.05 20 "Design Procedures" for specific design and construction submittal format and approval and surveillance requirements.
Design drawings may be prepared more like shop drawings to minimize construction submittals after final designs are approved. Therefore, the Contractor is encouraged to prepare and submit with the design drawings, appropriate connection, fabrication, layout, and product specific drawings.
a. QC Plan, prior to Design/Construction (may be phased).
b. Construction submittals, prior to construction, approved in accordance with QC Plan, the
DOR or QC Specialist is the approving authority for submittals unless otherwise indicated.
c. Sustainability Action Plan (and Sustainability Notebook when required) in accordance with 01 33 29.05 20 Sustainability Reporting for Design-Build.
d. DOR-approved construction submittals identifiedfor Government surveillance (typically
Fire Protection system and Life Safety submittals). Stamp the submittals "FOR SURVEILLANCE ONLY." Submit Surveillance submittals to the Governmentprior to starting work for that item. Submittals required for surveillance will be returned only if corrective actions are required.
e. Safety Data Sheets (SDS) as applicable.
f. Baseline Schedule: due prior to PAK.
g. Environmental Protection Plan, prior to start of the work.
h. Contractor Safety Self-Evaluation Checklist.
i. Accident Reports - submit if incidence occurs.
j. Accident Prevention Plan and Activity Hazard Analysis: Submit prior to construction.
PART 2 GENERAL REQUIREMENTS - Page 12
k. Schedule of Prices, initial due 21 calendar days after award and a detailed due prior to
l. Record Drawings, due at Beneficial Occupancy
m. Operation and Maintenance Information: Due prior to testing as applicable, no later than
30 calendar days before Beneficial Occupancy.
n. Licenses and Permits: Per this section and Part 4.
o. Completed High Performance and Sustainable Building (HPSB) compliance checklists in accordance with UFC 1-200-02, High Performance and Sustainable Building Requirements and UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build. Attach completed HPSB Checklist to Interim DD 1354.
p. DD Form 1354:
Prepare a Draft and Interim DD Form 1354, TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY, in accordance with UFC 1-300-08, available at http://www.wbdg.org/ccb/DOD/UFC/ufc_1_300_08.pdf. Coordinate the identification of appropriate asset construction categories with the Contracting Officer and the Real Property Accounting Officer.
1) Draft DD Form 1354. DOR must determine applicable real property assets broken out by construction categories and submit a "Draft DD Form 1354" for Government approval as a part of the Design Analysis included with the Prefinal Design submittal. "Draft DD Form 1354" must include all quantities and units of measure, but does not require cost breakdown. The Real Property Accountable Officer (RPAO)will provide the first draft of the DD1354 to the contractor with RPUIDs and CCNS on it.
2) Interim DD Form 1354. Contractor must coordinate with the DOR and update the Draft DD Form 1354 submission to include any additional assets, improvements, or alterations that occurred during construction. Use the Draft DD Form 1354 and the UFGS Section 01 20 00.05 20, Price and Payment Procedures to identify costs. The costs and quantities must align with the RPUID and unit of measures listed on the RPAO's draft 1354. Submit the final draft Interim DD Form 1354 to the Government for approval 30 days prior to the Beneficial Occupancy Date (BOD). If modifications to the Interim DD Form 1354 are required by the Government, the corrected version must be submitted prior to the BOD.
3) When documenting demolition work, the DD Form 1354 must list the quantitative data associated with this work as a negative value to show the cost should be deleted from the Navy asset data store. Coordinate with the Installation Real Property POC to assist in determining the negative value for demolition work. There are two ways to account for the demolition portion of the project and to document the reduction of real property: (1) attach an Authorization for Demolition form 18 (Service-specific) to the DD Form 1354 to document category codes and quantities of demolished real property. These should be listed separately from constructed/transferred item numbers; or, (2) indicate, as additional DD Form 1354 item numbers, all demolished real property facility numbers and category codes using negative numbers (shown in parenthesis) for units of measure, and in block 18 indicate N/A for costs. Disposal cost within the footprint of the project is added into total construction cost of new facility prompting the demolition.
http://www.wbdg.org/ccb/DOD/UFC/ufc_1_300_08.pdf
PART 2 GENERAL REQUIREMENTS - Page 13
q. Construction Submittals:
1) In addition to the design submittals noted in Section 01 33 10.05 20, construction submittals will be required. The list of required submittals will be generated from the Contractor-prepared specifications and indicated in the submittal register.
2) Shop drawing submissions will be governed by UFGS 01 33 00.05 20 Construction Submittal Procedures, available on the Whole Building Design website (www.wbdg.org ).
Contractor must assume a 15 day review period, and provide 3 hard copies of all submittals (in addition to electronic submittals) to be submitted to FEAD.
1.4 Operations and Maintenace Information (OMSI)
Deliverable FEAD FEC USER
1 Quality Control Plan
2 Material Safety Data Sheets
3 Design/Construction Schedule
4 Waste Management Plan
5 Safety and Health Plan
6 Schedule of Prices
7 Budget Management Summary
8 Record Drawings
9 Operation and Maintenance Information
10 Licenses and Permits
11 Badge Requests
12 Statement of Acknowledgement SF 1413
13 Demolition and Work Plan
14 Design Development Docs
15 Final Design Docs
16 Submittal Register
17 Waste Management Opportunity Assessment Form
18 Performance/Payment Bonds
19 Environmental Protection Plan
20 Certificates of Insurance
21 DD Form 1354
22 Sustainability Action Plan
23 Sustainability Notebook
24 NAVFAC Sustainability & Energy Data Record Card
1.5 Licenses and Permits
http://www.wbdg.org/
PART 2 GENERAL REQUIREMENTS - Page 14
Obtain all appointments, licenses, and permits required to perform work under this contract at no additional expense to the Government. See "Permits Record of Decision" (PROD) form for list of permits. Comply with all applicable federal, state, and local laws, and base regulations and procedures. Provide evidence of such permits and licenses to the Contracting Officer before work commences and at other times as requested by the Contracting Officer (see FAR 52.236-7, Permits and Responsibilities). Coordinate permit applications with Navy or local environmental office.
The contractor must submit a complete PROD form with the first design submittal package. A blank PROD form can be obtained from the NAVFAC Design-Build website at the following link http://www.wbdg.org/FFC/NAVFAC/NDBM/ST/PROD_Form.doc . Contractor must determine correct permit fees and pay said fees. Copies of all permits, permit applications, and the completed PROD form must be forwarded to the Government's Civil Reviewer and Environmental Reviewer.
Contractor is exclusively responsible for his full compliance with patent laws and must affirm that the company is licensed to use equipment and processes the company employs in this project.
1.6 Record Drawings
The as-built modifications must be accomplished by electronic drafting methods on the Contractor-originated DWG design drawings to create a complete set of record drawings. For each record drawing, provide CAD drawing identical to signed Contractor-originated PDF drawing that incorporate modifications to the as-built conditions. After all as-built conditions are recorded on the DWG files, produce a PDF file of each individual record drawing in conformance with FC 1-300-09N. Electronic signatures are not required on record drawings.
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
1.1 Summary
This section includes requirements for contractor-originated design documents and design submittals.
1.2 Reference Standards
This RFP references published standards, the titles of which can be found in the Unified Master Reference List (UMRL) on the Whole Building Design Guide at the Unified Facilities Guide Specification (UFGS) Website. The publications referenced form a part of this specification to the extent referenced.
The advisory provisions of all codes, requirements, and standards are mandatory; substitute words such as "must" or "required" for words such as "shall", "should", "may", or "recommended," wherever they appear. The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the "authority having jurisdiction" is interpreted to mean Contracting Officer or Contracting Officer Representative. Comply with the required and advisory portions of the current edition of the standard at the time of contract solicitation.
Provide work in compliance with the following design standards and codes, as a minimum.
Government standards listed in this RFP take precedence over industry standards. The following list of codes and standards is not comprehensive and is augmented by other codes and standards http://www.wbdg.org/FFC/NAVFAC/NDBM/ST/PROD_Form.doc
PART 2 GENERAL REQUIREMENTS - Page 15 referenced and cross-referenced in the RFP. Refer to Parts 3 and 4 for specific requirements within other UFC's.
a. U.S. Department of Defense (DoD) Unified Facilities Criteria (UFC)
UFC 1-200-01 DoD Building Code (General Building
Requirements)
UFC 1-200-02 High Performance and Sustainable
Building Requirements
UFC 1-300-08 Criteria for Transfer and Acceptance of
DoD Real Property
FC 1-300-09N Navy and Marine Corps Design
Procedures
UFC 3-560-01 Electrical Safety, O&M
UFC 3-600-01 Fire Protection Engineering
UFC 3-810-01N Navy and Marine Corps Environmental
Engineering for Facility Construction
b. UFC 1-200-01
UFC 1-200-01, DoD Building Code is a hub document that provides general building requirements and references other critical UFCs. A reference to UFC 1-200-01 in the RFP document requires compliance with the Tri-Service Core UFCs. Refer to the UFC 1-200-01 for a complete list of all applicable Tri-Service Core UFCs at website location http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc . Contractor-originated design documents must provide a project design that complies with the Request For Proposal (RFP), FC 1-300-09N, UFC 1-200-01, UFC 3-810-01N, the Core UFCs, and other UFC's listed above.
1.3 Design Requirements
a. Provide design documents that include basis of design, design drawings and design specifications, reports and submittal register in accordance with FC 1-300-09N Navy and Marine Corps Design Procedures.
b. Design is the work necessary to ensure functionality, quality, and safety for critical facets of the project. Special coordination requirements such as for phone, LAN and cable, are included herein.
c. Part 3 contains the project description, functional and performance requirements, scope items, and expected quality levels that exceed Part 4. Part 4 identifies design criteria, http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
PART 2 GENERAL REQUIREMENTS - Page 16 verification requirements, and performance and quality requirements of products.
d. Provide professional registration and design signing and stamping requirements per requirements of FC 1-300-09N, Design Procedures. Interior Designers must be NCIDQ certified per UFC 3-120-10 Interior Design. The design effort must be overseen by a Design Quality Control (DQC) Manager who will ensure that the design meets the requirements of this RFP. The DQC Manager will prepare a DQC Plan describing how the design process will ensure conformance to the RFP.
e. Provide a Contractor-originated design specification that in conjunction with the drawings, demonstrates compliance with requirements of the RFP. The specified products, materials, systems, and equipment that are approved by the DOR; submitted to the Government by the Contractor; and reviewed by the Contracting Officer must be used to construct the project. Prescriptive specification sections contained in RFP Part 5 must become a part of the Contractor-originated specification without modification. The Contractor must prepare design specifications that include a UFGS specification for each product, material, or system on the project. Organize the specifications using Construction Specification Institute (CSI) MasterformatTM . Provide project specifications to include the following:
1. Provide the specification cover sheet with the professional seal and signature of the lead licensed architect or engineer of the project design team. Indicate the Contractor's company name and address on the specification coversheet.
2. Table of contents for entire specification.
3. Individual UFGS specification sections for each product, material, and system required by the RFP. Edit UFGS sections in accordance with RFP Part 3 and 4.
4. If proprietary information is provided or required, include a coversheets for the product, material, or system information that is being proprietarily specified. This information must comply with the related UFGS specification.
5. If proprietary information is provided or required, include highlighted and annotated Catalog Cuts, Manufacturer's Product Data, Tests, Certificates, Manufactures information and letters for each product, material, or system that is being proprietary specified.
6. Coordinated submittal register for all products, materials and systems with each design submittal. Provide a cumulative register that identifies the design and construction submittals required by each design package along with previous design submittals. The DOR must assist in developing the submittal register by determining which submittal items are required to be approved by the DOR.
Complete all fields in the final submittal register in order to obtain Government approval of the final design.
f. Identification of Manufacturer's Product Data Used as Specifications: Provide complete and legible catalog cut sheets, product data, installation instructions, operation and maintenance instructions, warranty, and certifications for products and equipment for which final material and equipment choices have been made. Indicate, by prominent notation, each product that is being submitted including optional manufacturer's features, and indicate where the product data shows compliance with the RFP. Attach this product data to the end of the applicable UFGS specification section that specifies the material.
g. Specification Software: Submit the final specification source files in either MS Word or
SpecsIntact with a Submittal Register generated in Excel or SpecsIntact.
h. Meet sustainability requirements per UFC 1-200-02 High Performance and Sustainable
Building requirements and UFGS Section 01 33 29.05 20 Sustainability Reporting for
PART 2 GENERAL REQUIREMENTS - Page 17
Design-Build. UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build must be included in Part 5 of all project RFPs.
i. Submit design drawings or sketches, calculations and manufacturer's data to demonstrate compliance with contract requirements. The Contractor is encouraged to prepare design drawings more like shop drawings to minimize construction submittals.
Provide the following Design Submittal packages. Provide comprehensive, multi-discipline design packages that include design documentation for project elements, fully developed to the design stage indicated, and in accordance with UFC 1-300-09N, except where specified otherwise.
1. Concept Design (PAK Meeting)
2. Design Development (35%) - Government Progress QA. 14 calendar days Government review time.
3. Design Development (65%) - Government Progress QA. 14 calendar days Government review time.
4. Pre-Final Design (100%) - Government QA. 14 calendar days Government review time.
5. Final Design - Government QA. 14 calendar days Government review time.
Provide hard and electronic copies of design submittal package 2 weeks prior to the review meeting to the following address:
FEAD/ROICC
PWD FEAD Bldg 618 NAS 2 Sigonella SP 69/II snc 95100 Catania - Italy
Deliverables and recipients are as indicated in the below table:
Deliverable
Number of Submittals Schedule
FEAD/
ROICC
PW
ENV
DEPT
User Maximum Time Period*
Total Time from Award
Concept Design (for PAK Meeting) 20 20
Half-size Drawings or Sketches 3 1 1
PAK Meeting (Review Meeting)** 1 21
Design Development (35%) 30 51
Half-size Drawings or Sketches 3 1 1
Specifications and Manufacturer’s Cut Sheets
3 1 1
Design/Construction Schedule 2 1 1
Calculations 3 0 0
PROD Form (Permits) 2 0 0
PART 2 GENERAL REQUIREMENTS - Page 18
Electronic Media (CD or DVD) 2 0 0
Government Review and Comment 14 65
Review Meeting** 2 67
Design Development (65%) 50 117
Half-size Drawings or Sketches 3 1 1
Specifications and Manufacturer’s Cut Sheets
3 1 1
Design/Construction Schedule 2 1 1
Calculations 3 0 0
PROD Form (Permits) 2 0 0
Electronic Media (CD or DVD) 2 0 0
Government Review and Comment 14 131
Review Meeting** 3 134
Pre-Final Design Development (100%) 20 154
Half-size Drawings or Sketches 3 1 1
Specifications and Manufacturer’s Cut Sheets
3 1 1
Design/Construction Schedule 2 1 1
Calculations 3 0 0
Electronic Media (CD or DVD) 2 0 0
Government Review and Comment 14 168
Review Meeting** 3 171
Final Design 14 185
Half-size Drawings or Sketches 3 1 1
Specifications and Manufacturer’s Cut Sheets
3 1 1
Design/Construction Schedule 2 2 1
Calculations 3 1 0
Electronic Media (CD or DVD) 2 0 0
Government Review and Comment 14 199
Review Meeting** 1 200
Construction Time 165 365
*Design time period is maximum allowed and contractor can accelerate design period to allow for more construction time within the total period of performance.
**Design Review Meetings during which shall be discussed the comments and the replies provided by DOR, are mandatorily called within seven calendar days from when the DOR receives the Review
PART 2 GENERAL REQUIREMENTS - Page 19
Comments
j. Provide electronic copies of design submittal package to the following reviewers 21 calendar days to the in-progress review meeting.
Deliverable FEAD FEC USER Design Development
Basis of Design 1 1 1 Half-size Drawings or Sketches 1 1 1 Outline Specifications 1 1 1 Finish Documentation Color Board 1 1 1 Calculations 1 1 1 Final Design
Basis of Design 1 1 1 Half-size Drawings or Sketches 1 1 1 Specifications and Manufacturer's Cut Sheets 1 1 1 Finish Documentation Color Board 1 1 1 Quality Control Review - Drawings and Specifications 1 1 1 Completed Project Information Form (PIF) including Bid Schedule 1 1 1 Structural Interior Design (SID) 1 1 1 Preliminary FF&E 1 1 1 Calculations 1 1 1 Draft DD Form 1354 1 1 1 Facility Recognition Plaque - Design and Specification 1 1 1
k. The final design submittal must be professionally signed and sealed by the DOR and forwarded to the Contracting Officer prior to the start of construction. Separated final design packages will only be considered for Government review and approval during the Post Award Kick-off Meeting.
l. Submit Draft DD Form 1354. See section 01 33 00.05 20 for detailed requirements.
1.4 Order of Precedence
The contract consists of the solicitation, the approved proposal, and the final design. In the event of conflict or inconsistency between any of the below described portions of the conformed contract, precedence must be given in the following order:
a. Any portions of the proposal or final design that exceed the requirements of the
PART 2 GENERAL REQUIREMENTS - Page 20 solicitation.
1. Any portion of the proposal that exceeds the final design.
2. Any portion of the final design that exceeds the proposal.
3. Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
b. The requirements of the solicitation, in descending order of precedence:
1. Standard Form 1442, Price Schedule, and Davis Bacon Wage Rates.
2. Part 1 - Contract Clauses.
3. Part 2 - General Requirements.
4. Part 3 - Project Program Requirements.
5. Part 6 - Attachments (excluding Concept Drawings).
6. Part 5 - Prescriptive Specifications exclusive of performance specifications.
7. Part 4 - Performance Specifications exclusive of prescriptive specifications.
8. Part 6 - Attachments (Concept Drawings).
c. Within Part 3- Project Program Requirements Section 5.0 ROOM REQUIREMENTS provides detailed requirements on a room by room basis that further defines requirements that are in addition to the ENGINEERING SYSTEMS REQUIREMENTS
SECTION.
d. Government review or approval of any portion of the proposal or final design does not relieve the Contractor from responsibility for errors or omissions with respect thereto.
1.5 Fire Protection and Life Safety Requirements
The Contractor shall retain the services of a Registered Fire Protection Engineer (FPE). This FPE shall be an integral part of the Prime Contractor's Design and Quality Control Organization, and shall have no business relationships (owner, partner, operating officer,…