This is a Technical Offer Worksheet that establishes the technical proposal requirements for offerors responding to solicitation N3220526R0005 for a clean, double hull tanker capable of carrying a minimum of 240,000 barrels of clean petroleum products (JP5, JP8, JAA, JA1, or F76). The worksheet outlines 13 technical requirements that offerors must address, including vessel certification and documentation standards. Key requirements include: vessel participation in the Ship Inspection Report (SIRE) System; submission of a current Q-88 inspection report dated no earlier than 60 days prior to offer submission; warranty that the vessel has not been rejected or refused by any charterer or refinery since joining SIRE; stowage plans for each cargo type; current Safety Management Certificate (SMC), International Ship Security Certificate (ISSC), and Certificate of Inspection (COI); specification of cargo tank heating coil types and pressure testing results (within 12 months of offer); cargo history for the previous six months; internal tank coating types (with coal tar explicitly prohibited); and compliance capability with Fuel Delivery Station requirements per Attachment (14). Special provisions address new construction vessels, which may warrant future compliance rather than provide existing documentation. For vessels exceeding 20 years of age during contract performance, additional compliance requirements outlined in PART II(o)(7) apply. The worksheet accommodates both existing vessels and new construction offerings, with modified documentation requirements for new builds that have not yet entered commercial service.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| TECHNICAL OFFER WORKSHEET | ||
| Technical Proposal | ||
| Requirement | Requirement Description | Offeror |
| Page # / Box # | COMMENTS | |
| Section 3.1 | Offeror shall warrant that vessel is a party to the Ship Inspection Report (SIRE) System. In the event that a new construction is offered, the Offeror shall warrant that vessel will be a party to the Ship Inspection Report (SIRE) System, and offerors must provide a copy of the current report as soon as possible post-award. | |
| Section 3.2 | Offerors must provide a copy of the current Q-88 with a date no earlier than 60 days prior to offer submission The Q-88 shall detail current acceptances and dates of inspection. In the event that a new construction is offered, and the vessel has not entered commercial service, only requirements in 1) are to be provided. | |
| Section 3.3 | Offeror shall warrant that the vessel has not been rejected or refused by any Charterer or refinery since becoming a party to the SIRE System. In the event that a new construction is offered, and the vessel has not entered commercial service, only requirements in 1) are to be provided. | |
| Section 3.4 | Offeror shall provide stowage plans for each cargo listed in Attachment(02), Paragraph (a). In the event that a new construction is offered, the Offeror warrants that the vessel will meet all cargo carrying requirements. | |
| Section 3.5 | Offeror shall provide a copy of vessel’s current Class Society issued Safety Management Certificate (SMC). In the event that a new construction is offered, the Offeror warrants the vessel will be issued a Safety Management Certificate and the Offeror will provide a copy after award immediately upon its issuance. | |
| Section 3.6 | Offeror shall provide a copy of vessel’s current Flag State issued International Ship Security Certificate (ISSC). In the event that a new construction is offered, the Offeror warrants the vessel will be issued an International Ship Security Certificate and the Offeror will provide a copy after award immediately upon its issuance. | |
| Section 3.7 | Offeror shall provide a copy of the vessel’s current flag state Certificate of Inspection (COI) or equivalent. In the event that a new construction is offered, the Offeror warrants the vessel will be issued a COI or equivalent and the Offeror will provide a copy after award immediately upon its issuance. | |
| Section 3.8 | Offeror shall provide, if vessel cargo tanks will have heating coils, the coil type or composition (such as stainless steel, copper, etc.). Vessels with coil types or compositions that are incompatible with the fuel to be carried will be rejected. In the event that a new construction is offered, the Offeror warrants that the vessel will have heating coils that are compatible with the fuel to be carried. | |
| Section 3.9 | If vessel cargo tanks have heating coils, offeror shall provide the date heating coils were last pressure tested and the results of the test (passed or failed). Date of last pressure test shall be within 12 months of the date of offer and, thereafter, cannot exceed 12 months for duration of this charter. Vessel tanks with copper or yellow metal compounds are not acceptable for Jet Fuel cargoes. In the event that a new construction is offered, pressure testing information is not required. However, please note that vessel tanks with copper or yellow metal compounds are not acceptable for Jet Fuel cargoes. | |
| Section 3.10 | Offeror shall provide a listing of all cargoes carried for the previous six months and the refineries these cargoes were loaded. In the event that a new construction is offered, this information is not required. | |
| Section 3.11 | Offeror shall provide, if vessel cargo tanks are or will be internally coated, the coating type (epoxy, inorganic zinc, etc.). Coal tar coating is not acceptable. If tanks are not or will not be coated then state “none”. Vessels with coatings that are incompatible with the fuel to be carried will be rejected. In the event that a new construction is offered, the Offeror shall provide information regarding the anticipated coating type. Vessels with coatings that are incompatible with the fuel to be carried will be rejected. | |
| Section 3.12 | Offeror shall warrant that the vessel will be capable of providing services required by the Fuel Delivery Station in accordance with Attachment (14). In the event that a new construction is offered, the Offeror warrants that the vessel will be capable of providing services required by the Fuel Delivery Station in accordance with Attachment (14). | |
| Section 3.13 | For proposed vessels that will exceed 20 years of age during the performance of the contract, offerors shall warrant it will comply with the requirements outlined in PART II(o)(7). |