WI 509_RevA_Tnk Dck Drain Piping Replace.docx

DOCX document 2 MB Posted

Attached to
USNS JOHN LENTHALL (T-AO 189) FY 21 MTA
Solicitation number
N3220520R4009
Issued by

About this file

This document outlines the requirements for a mid-term availability contract to replace drain piping aboard the USNS John Lenthall. The contractor will remove approximately 282 linear feet of existing 4-inch steel piping and install new piping, fittings, valves, and hangers to replace drain lines from several station tubs on the starboard side of the main deck to the tank deck sludge collection tank. The contractor must submit sketches of piping to be removed for approval, fabricate and install the new piping per specifications, conduct pressure testing and inspection, and paint all new and disturbed surfaces to match existing. The solicitation was issued by the Department of the Navy Military Sealift Command under number N3220520R4009 to support maintenance work aboard the USNS John Lenthall during its FY21 mid-term availability period.

View the file

Other files

File Type Posted
J-1 Work Item Index RevC.docx DOCX document
0108_A_Double Bottom Tank Top Steel Replacement.doc DOC document
WI 0090_A_Daily COVID-19 Prevention and Control Services Rev M.doc DOC document
0202_REV B_Port Main_Reduction_Gear_Annual_Inspection.docx DOCX document
J-3 CAT B Items-RevC.xlsx XLSX spreadsheet
J-2 Cat A Items-RevC .xlsx XLSX spreadsheet
J-3 RevB Category B Items.xlsx XLSX spreadsheet
Amendmnet 0008.docx DOCX document
Amendment 0007.docx DOCX document
Amendment 0006.docx DOCX document
Amendment 0005.docx DOCX document
Work Item Index-RevB 23OCT20.pdf PDF
J-2 Cat A Items-RevB .xlsx XLSX spreadsheet
J-1 RevA WI Index 15OCT20.pdf PDF
Amendment 0004.docx DOCX document
J-2 RevA Cat A Items.xlsx XLSX spreadsheet
New WI 403_ECDIS RADAR REPLACEMENT_13OCT20.docx DOCX document
408 REVA_Antenna Coupler Maint.pdf PDF
Amendment 0003.docx DOCX document
0105_A_Tank Hatch Preservation_RevA.doc DOC document
Amend 0002 20R4009-Update WI.docx DOCX document
0102_A_Degaussing Cable and Conduit Removal_RevA.doc DOC document
Amend 0001 20R4009-Extend.pdf PDF
J-12 Past Performance Data.pdf PDF
J-13 Past Performance Questionnaire.pdf PDF
J-7 MSC Ship Repair Facility Survey.pdf PDF
J-8 Request for Clarification.docx DOCX document
J-10 Interport Differential.pdf PDF
J-4 Gov Furnished Material.pdf PDF
J-14 Technical Non-Disclosure Agreement (NDA).pdf PDF
JA 20R4009_Redacted.pdf PDF
J-1 Work Item Index 08SEP20.pdf PDF
J-2 Category A Items.xlsx XLSX spreadsheet
J-3 Category B Items.xlsx XLSX spreadsheet
J-9 Disclosure Lobbying Activities (SF-LLL).pdf PDF
Solicitatioin 20R4009 - LENTHALL.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS LENTHALL

( TAO 189 )

AUXILIARY MACHINERY
CONTRACT NO. N32205-20-R-4009
ITEM NO. 0509
CATEGORY "A"
2020-10-19
Tank Deck Drain Piping Replacement_REVA
Coleman Ray

1.0 ABSTRACT

1.1 Remove and replace starboard side station tub drain piping for Stations 1, 1A, 3, 5A, 7 and 7A to the tank deck sludge collection tank.

2.0 REFERENCES/ENCLOSURES

2.1 References:

2.1.1 NAVSEA 500-6580660, Piping Material Schedule

2.1.2 ASI DWG. No PS -06-WJ-01, ASI Standard Joint Prep and Weld Details.

2.2 Enclosures:

2.2.1 Picture of Drains from Station Tubs.

3.0 ITEM LOCATION/DESCRIPTION/QUANTITY

3.1 Location/Quantity:

3.1.1 Location: Tank Deck (Main Deck) Kingpost Sumps draining from the 01 level down to the main deck Starboard Side.

3.1.2 Quantity/Description:

3.1.2.1 Approximately Two hundred eighty two (282) linier feet of existing 4" schedule 40 steel piping. (staging required)

3.1.2.2 Approximately Sixty (60) linear feet of 1 1/2” sch 80 steel piping.

3.1.2.3 Forty six (46) 4” eight bolt socket weld flanges.

3.1.2.4 Forty (40) existing piping hangers with stainless steel hardware and channel rubber.

3.1.2.5 Sixteen (16) 4” Welded Couplings

3.1.2.6 Twelve (12) 4” 45 degree elbows

3.1.2.7 Twelve (12) 4” 90 degree elbows.

3.1.2.8 Fifteen (15) 1 ½” 90 degree elbows.

3.1.2.9 Eight (8) 4” ball Valves.

3.1.2.10 Five (5) 1 ½” ball valves.

3.1.2.11 Three (3) linear feet of 6” sch 40 piping

3.1.2.12 Five (5) square feet of ½” plate.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES

4.1 None.

5.0 NOTES

5.1 None

6.0 QUALITY ASSURANCE REQUIREMENTS

6.1 All work shall be performed to the satisfaction of the ABS, USCG, MSC Port Engineer and the Chief Engineer.

6.2 All piping and flanges shall be installed in accordance with applicable rules and regulations of ABS and USCG.

7.0 STATEMENT OF WORK REQUIRED

7.1 Prior to making any removal, Contractor shall submit to MSCREP a sketch of piping to be removed to include pipe sizes and lengths of pipe to be renewed for approval

7.2 Remove existing drain piping lines and hangers identified in 3.1.2.

7.3 Crop and renew drain bowl in each station tub drain on the stbd side (5 stations)

7.4 All hangers shall be mechanically cleaned/ground smooth to ensure proper feathering of paint.

7.5 Fabricate new piping using existing as a template and utilizing 45 degree and 90 degree elbows and welded couplings where previously installed. Install new piping in place of piping removed. Install new hangers and brackets with new channel rubber complete 360 degrees around the pipe where hanger installed.

7.6 Install new butterfly valves where removed.

7.7 Provide and weld all piping and fittings identified in paragraph 3.1.2 in accordance with ABS and USCG rules and regulations.

7.7.1 Hydro test all welds to 100 psi and dye penetrate test all welds.

7.7.2 Ensure all piping is targeted correctly.

7.8 Utilizing an inflatable pipe plug perform a static drain test to ensure piping is not leaking.

7.9 All fasteners shall be coated with "Anti-Seize" compound prior to installation.

7.10 Modify existing pipe hangers brackets to properly support new piping.

7.11 All dirt and debris shall be removed from the ship on a daily basis and the area left clean and in good order.

7.12 Mechanically clean, prime, and paint all new and disturbed areas to match adjacent surfaces. All newly installed piping, brackets and couplings shall be painted to match existing.

8.0 GENERAL REQUIREMENTS

8.1 None.

Enclosure 2.2.1 Picture of Drains from Station Tubs.