0105_A_Tank Hatch Preservation_RevA.doc

DOC document 4 MB Posted

Attached to
USNS JOHN LENTHALL (T-AO 189) FY 21 MTA
Solicitation number
N3220520R4009
Issued by

About this file

This document outlines requirements for preservation work on thirteen cargo and ballast tank hatches aboard the USNS Lenthall. The contractor will be required to remove, blast, paint, and reinstall the tank hatches according to specifications provided. Hatch gaskets and nameplates will need to be manufactured to complete the work. Amercoat 240 products will be provided by the government for the paint scheme. The contractor must comply with general technical requirements and review all other related work items. Surface preparation, coating application, and quality assurance requirements are defined. This preservation work is likely being conducted as part of the Mid-Term Availability solicited by the Navy's Military Sealift Command under solicitation number N3220520R4009 for the USNS John Lenthall.

View the file

Other files

File Type Posted
J-1 Work Item Index RevC.docx DOCX document
0108_A_Double Bottom Tank Top Steel Replacement.doc DOC document
WI 0090_A_Daily COVID-19 Prevention and Control Services Rev M.doc DOC document
0202_REV B_Port Main_Reduction_Gear_Annual_Inspection.docx DOCX document
J-3 CAT B Items-RevC.xlsx XLSX spreadsheet
J-2 Cat A Items-RevC .xlsx XLSX spreadsheet
J-3 RevB Category B Items.xlsx XLSX spreadsheet
Amendmnet 0008.docx DOCX document
Amendment 0007.docx DOCX document
Amendment 0006.docx DOCX document
WI 509_RevA_Tnk Dck Drain Piping Replace.docx DOCX document
Amendment 0005.docx DOCX document
Work Item Index-RevB 23OCT20.pdf PDF
J-2 Cat A Items-RevB .xlsx XLSX spreadsheet
J-1 RevA WI Index 15OCT20.pdf PDF
Amendment 0004.docx DOCX document
J-2 RevA Cat A Items.xlsx XLSX spreadsheet
New WI 403_ECDIS RADAR REPLACEMENT_13OCT20.docx DOCX document
408 REVA_Antenna Coupler Maint.pdf PDF
Amendment 0003.docx DOCX document
Amend 0002 20R4009-Update WI.docx DOCX document
0102_A_Degaussing Cable and Conduit Removal_RevA.doc DOC document
Amend 0001 20R4009-Extend.pdf PDF
J-12 Past Performance Data.pdf PDF
J-13 Past Performance Questionnaire.pdf PDF
J-7 MSC Ship Repair Facility Survey.pdf PDF
J-8 Request for Clarification.docx DOCX document
J-10 Interport Differential.pdf PDF
J-4 Gov Furnished Material.pdf PDF
J-14 Technical Non-Disclosure Agreement (NDA).pdf PDF
JA 20R4009_Redacted.pdf PDF
J-1 Work Item Index 08SEP20.pdf PDF
J-2 Category A Items.xlsx XLSX spreadsheet
J-3 Category B Items.xlsx XLSX spreadsheet
J-9 Disclosure Lobbying Activities (SF-LLL).pdf PDF
Solicitatioin 20R4009 - LENTHALL.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS Lenthall

( TAO 189 )

HULL AND STRUCTURAL
CONTRACT NO. N32205-21-R-4006
ITEM NO. 0105
CATEGORY "A"
2020-06-25
Tank Hatch Preservation
Coleman Ray

1.0 ABSTRACT

1.1 This item describes the requirement to preserve thirteen (13) Tank hatches located on the tank deck.

2.0 REFERENCES/ENCLOSURES

2.1 References

2.1.1 MSC Drawings, 167-6580087, “Hatch, Scuttle, AVHC & Tank Cleaning Openings.”

2.2 Enclosure

2.2.1 Cross Section of Gasket Material (2 Pictures)

2.2.2 Sample Chalk Test (1 Picture)

2.2.3 Hatch Opening Components (1 Picture)

2.2.4 Enclosure 2.2.4 – Tank Names and Locations

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location/Quantity

3.1.1 Location: Main Deck, FR 18-57

3.1.2 Quantity: Thirteen (13) total Cargo and Ballast Tank hatches to be designated upon arrival of the vessel by the Chief Engineer.

3.2 Gasket Description

3.2.1 Hatch Gasket -Semi-Hard Rubber Gasket Material 40 mm x 40 mm x 3750 mm. See Enclosure 2.2.1 for photographs of gasket cross section.

3.3 Paint Scheme

AREA
COAT
PRODUCT
SOLVENT
DFT
Hatch Cover and Coaming Area (2600 sq. ft.)
1st Coat
Amercoat 240 Buff
Amercoat T-10
5-6 mils
2nd Coat
Amercoat 240 Off-White
Amercoat T-10
5-6 mils
3rd Coat
Amercoat 240 Light Gray
Amercoat T-10
5-6 mils

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES

PRODUCT
Solvent
QTY
Amercoat 240 Buff
Amercoat T-10
13 Gals
Amercoat 240 Off-White
Amercoat T-10
13 Gals
Amercoat 240 Light Gray
Amercoat T-10
13 Gals
Amercoat 240 Yellow
Amercoat T-10
1 Gal
Amercoat 240 Purple
Amercoat T-10
1 Gal
Amercoat 240 Green
Amercoat T-10
1 Gal

Amercoat T-10 Solvent

8 Gal

5.0 NOTES

5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s including but not limited to GTR’s 1-7, and 25.

5.2 The contractor and all subcontractors regardless of tier are advised to review all other work items in this specification to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional

7.0 STATEMENT OF WORK REQUIRED

7.1 Contractor to provide all labor, tools and equipment to remove tank hatch covers and all associated hardware, including but not limited to the yoke, hand wheel and ullage cover from their position and transport them to the blast shop.

7.1.1 While tank hatch covers are removed, set up safety precautions to prevent any unauthorized entry into the tank.

7.2 Surface Prep/Coating Application

7.2.1 SSPC-SP-10 “Near White Metal” blast all removed Cargo and Ballast Hatch Covers, yoke, hand wheel and associated hardware that listed in para 3.0.

7.2.2 SSPC-SP 3 “Power Tool Clean” all tank coaming of tanks listed in para 3.0 to include but not limited to:

7.2.2.1 Vent pipe from coaming to flange

7.2.2.2 Drop bolt pad

7.2.2.3 Locking pin pad

7.2.2.4 Pin pad

7.2.3 Conduct a surface preparation checkpoint in the presence of the MSC Paint Representative to verify proper surface preparation.

7.2.4 Upon approval of surface preparation and/or the application of the previous coat, install three (3) each coats of paint using paint scheme detailed in Paragraph 3.3.

7.2.5 Tank Cover

7.2.5.1 The hand wheel with have a top coat to match the ship’s color scheme for tank contents. DFM hand wheel is to have a Top Coat of Yellow, JP-5 DFM hand wheel is to have a Top Coat of Purple and Ballast DFM hand wheel is to have a Top Coat of Green.

7.2.5.2 After the top coat of light gray, manufacture new tank nameplates, using the following as an example:

No. 8 S SW Ballast

5- 47 -2

7.2.6 Tank Coaming

7.2.6.1 After the top coat of light gray, stencil the coaming with TANK ENTRY PROHIBITED WITH OUT PERMISSION FROM THE MASTER, using existing as template.

7.3 Contractor is to remove each of the Gaskets from the Cargo and Ballast Tanks Hatches before blasting. Using removed Gasket as a template manufacture Cargo Hatch Gaskets. Size and dimension of the Hatch Gasket is detailed in Paragraph 3.2.1 and photographs of the cross section can been viewed in Enclosure 2.2.1. Dimensions and details of the Hatch Covers are outlined in Reference 2.1.1.

7.3.1 Install the Hatch Gasket using contact cement. When installed gasket ends are make contact with each other to make the gasket air/fluid tight.

7.4 Reinstall the hatch cover and conduct an operation test of the removed Cargo Hatches to verify that the Hatches move freely and do not bind.

7.5 Manufacture seven (7) each new drop bolt and wing nut and install with new pins.

7.6 Conduct a chalk test of each Cargo Hatches to verify that the Hatch Cover is making contact with the lip of the Hatch Cover Upright. Verify that 100% contact is being made. Sample of acceptable 100% Chalk test is shown on Enclosure 2.2.2.

7.7 All dirt and debris resulting from this work item shall be removed from the ship daily and all areas left clean and in good order.

8.0 GENERAL REQUIREMENTS: None Additional

Enclosure 2.2.1-Cross Section of Gasket Material (2 Pictures)

Enclosure 2.2.2-Sample Chalk Test (1 Picture)

Enclosure 2.2.3 - Hatch Opening Components (1 Picture)

Enclosure 2.2.4 – Tank Names and Locations

No.
Location
Description

CARGO TANKS

1
5-22-1
No. 1S DFM Tank
2
5-22-2
No. 1P DFM Tank
3
5-26-0
No. 2C JP5 Tank
4
5-31-0
No. 3C DFM/JP5 Tank
5
5-31-1
No. 3S DFM Tank
6
5-31-2
No. 3P DFM Tank
7
5-37-1
No. 5S DFM Tank
8
5-37-2
No. 5P DFM Tank
9
5-43-0
No. 7C DFM/JP5 Tank
10
5-43-1
No. 7S DFM Tank
11
5-43-2
No. 7P DFM Tank
12
5-47-0
No. 8C DFM/JP5 Tank
13
5-51-0
No. 9C JP5 Tank
14
5-51-1
No. 9S DFM Tank
15
5-51-2
No. 9P DFM Tank
16
5-55-0
No. 10C JP5 Tank
17
5-55-1
No. 10S DFM Tank
18
5-55-2
No. 10P DFM Tank
19
3-33-0
JP-5 SETTLING Tank
20
3-40-0
DFM SETTLING Tank

SW BALLAST TANKS

21
5-18-0
No. 1 Deep SW Ballast Tank
22
5-28-1
No. 2S SW Ballast Tank
23
5-28-2
No. 2P SW Ballast Tank
24
5-35-1
No. 4S SW Ballast Tank
25
5-35-2
No. 4P SW Ballast Tank
26
5-39-1
No. 6S SW Ballast Tank
27
5-39-2
No. 6P SW Ballast Tank
28
5-47-1
No. 8S SW Ballast Tank
29
5-47-2
No. 8P SW Ballast Tank

0105 - 4