AMENDMENT_0005_WALLY_SCHIRRA.docx

DOCX document 43 KB Posted

Attached to
Extended: USNS WALLY SCHIRRA (T-AKE 8) Regular Overhaul and Dry Docking
Solicitation number
N3220519R6005
Issued by

About this file

AMENDMENT 0005 WALLY SCHIRRA

View the file

Other files

File Type Posted
AMENDMENT_0006_USNS_WALLY_SCHIRRA.docx DOCX document
0902_B_Drydocking_and_Undocking_Vessel_Rev.doc DOC document
J_-_3_Category_B_Items.xls XLS spreadsheet
0169_A_Hazmat_Containers_Replacement.doc DOC document
J_-_2_Category_A_Items.xls XLS spreadsheet
J_-_3_Category_B_Items.xls XLS spreadsheet
0555_B_MMR_AFFF_System_Piping_Replaceme_Revision_I.doc DOC document
USNS_WALLY_SCHIRRA_CONTRACT_SOLICITATION_AMEND_0004_N32205-19-R-6005.docx DOCX document
USNS_WALLY_SCHIRRA_2019_ROH_DD_-_WI_Index,_5_JUN-18_AUG_19_Rev_C.doc DOC document
N32205-19-R-6005_QUESTIONS_&_ANSWERS___3.docx DOCX document
0105_A_Misc._Weld_Repairs_Revision_I.doc DOC document
CONTRACT_SOLICITATION_AMENDMENT_P00003_FOR_USNS_WALLY_SCHIRRA_N32205-19-R-6005.docx DOCX document
0918_A_Freeboard_Cleaning_Painting_(Spot)_Rev_I.doc DOC document
N32205-19-R-6005_QUESTIONS_&_ANSWERS___2.docx DOCX document
0406_A_NAVMACS_II_Upgrade_(T-ALT-16_454)_NEW.doc DOC document
0522_A__Steering_Gear_Scheduled_Maintenance_10_Year_Rev_I.doc DOC document
N32205-19-R-6005_QUESTIONS_&_ANSWERS___1.docx DOCX document
USNS_WALLY_SCHIRRA_SOLICITATION_AMENDMENT_N32205-19-R-6005-0002.docx DOCX document
0903_A_Propeller_Shaft_and_Stern_Tube_Inspection_Rev._I.doc DOC document
01004_A_NSTR_Upgrade_Station_6_Rev_P4.docx DOCX document
J_-_2_Category_A_Items_2_Jan.xls XLS spreadsheet
8289300_Rev_X1_NSTR_Interface.pdf PDF
0606_A_Flght_Deck_non-skid_Renewal_REV_A.docx DOCX document
N3220519R6005.docx DOCX document
J-4_GFM.xlsx XLSX spreadsheet
CONTRACT_SOLICITATION_FOR_USNS_WALLY_SCHIRRA_N32205-19-R-6005.docx DOCX document
J-6_CDRL_Zip.zip ZIP file
USNS_WALLY_SCHIRRA_J-_ATTACHMENTS.zip ZIP file
J-14_Technical_NDA.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220519R6005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been modified:

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "A" Work Items (WIs)

FFP

Prepare for and accomplish the ROH/DD Availability the United States Navy Ship of the USNS WALLY SCHIRRA T-AKE 8) Total Category "A" WIs $_____________

Proposed unit price per KWh $_____ in accordance with (IAW) WI 011, 7.1.1.4

Proposed unit price per gallon of potable water $______ IAW WI 011, 7.1.3.2

Proposed unit price per gallon of distilled water $______ IAW WI 011, 7.1.4.2

Proposed unit price per gallon of bilge water removal $______ IAW WI 011, 7.1.20.3

Proposed unit price per crane usage $______ IAW WI 11, 7.9.1

Proposed Hazardous Waste handling fee rate IAW WI 023, 7.4.1 ______%

FOB: Destination

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

AGR and ODC

AGR

(10,000) man-hours @ $________ per man-hour = $_____________

ODC

Base $1,000,000.00

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0025

WI 0025 - Physical Security at Private Contractor's Facility in FPCON Bravo - Delta

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0030

WI 0030 - Continuation of Services

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

ADDITIONAL CAT "B" WORK ITEMS

101-BALLAST TANKZINC INSPECTION

166-MECHANICALLY CLEAN AND PRESERVE TANKS

202-MDG NO 1 2 3 4 COOLER CASING LEAK REPAIR

307-CELL PHONE DISTRIBUTION

561-BRINE AND DEFROST PUMP AND MOTOR OVERHAULS

517-CSW LTFW ISOLATION VALVE MANUAL GEAR OPERATOR REPAIRS

541-LTFW SW COOLER 20 AND 10 INCH VALVE REPLACEMENT

546-INCINERATOR INSPECTION AND AMINTENANCE

548-INSTALL ADDITIONAL ALARM COLUMNS (T-ALT 396)

555-MMR AFFF SYSTEM PIPINGREPLACEMENT REV 1

553-CHILL WATERS PUMP AND MOTOR OVERHAUL

555-MMR AFFF FOAM SYSTEM PIPING REPLACE(T-ALT 394)

902-DRY DOCKING AND UNDOCKING VESSEL -7.1 CONTINUE ALL SERVICES IN WORK ITEM 901

914-BILGE KEEL REPAIRS

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AA

Category "B" WI 101

WI 101- BALLAST TANK ZINC INSPECTION

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AB

Category "B" WI 166

WI 166- MECHANICALLY CLEAN AND PRESERVE TANKS

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AC

Category "B" WI 202

202-MDG NO 1 2 3 4 COOLER CASING LEAK REPAIR

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AD

Category "B" WI 307

307-CELL PHONE DISTRIBUTION

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AE

Category "B" WI 516

561-BRINE AND DEFROST PUMP AND MOTOR OVERHAULS

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AF

Category "B" WI 517

517-CSW LTFW ISOLATION VALVE MANUAL GEAR OPERATOR REPAIRS

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AG

Category "B" WI 541

541-LTFW SW COOLER 20 AND 10 INCH VALVE REPLACEMENT

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AH

Category "B" WI 546

546-INCINERATOR INSPECTION AND AMINTENANCE

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AJ

Category "B" WI 548

548-INSTALL ADDITIONAL ALARM COLUMNS (T-ALT 396)

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AK

Category "B" WI 553

553-CHILL WATERS PUMP AND MOTOR OVERHAUL

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AO

Category "B" WI 555

555-MMR AFFF SYSTEM PIPING REPLACEMENT REV 1

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AL

Category "B" WI 902

902-DRY DOCKING AND UNDOCKING VESSEL -7.1 CONTINUE ALL SERVICES IN WORK ITEM 901

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0005AM

Category "B" WI 914

914-BILGE KEEL REPAIRS

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

TOTAL PROPOSED PRICE

TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0005 $______________

The contractor shall enter the total proposed price of all CLINs.

CLAUSES INCORPORATED BY FULL TEXT

PART I - THE SCHEDULE

Section B, Price Schedule, detailed information

CLIN 0001 –Attachment J-2 – Category “A” WIs provides a WI breakdown of CLIN 0001 pricing.

CLIN 0002: This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated under the H-3 Clause - AGR and H-4 Clause ODC, for the duration of the contract. Changes are inherent to vessel repair contracts and should be expected by the Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:

Abrasive cleaning/blastingTank cleaning
WeldingMachinists (inside and outside)
BurningBrazing
CarpentryElectrical work
Electronic workShipfitting
LaggingPainting
BoilermakingPipefitting
Sheetmetal workEngineering
RiggingStaging/scaffolding
General laborFire Watch

Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:

TestingQuality Assurance
PlanningCleaning (except tank cleaning)
Material handling & warehousingSecurity
SurveyingAdministration
TransportationPurchasing staff
LoftingOther indirect support
Supervision

Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's fully loaded manhour rate and not separately priced.

The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The KO will apply these rates to the ODCs for each CCO when it is negotiated and settled.

The base cost, stated in this CLIN does not include the profit or G&A rates.

NOTE: This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.

CLINs 0003 through 0005 –Attachment J-3 – Category “B” WIs provides a WI breakdown of CLIN 0003 through 0005 pricing.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

C – 2 List of Standard WIs included for this solicitation:

SECTION 0000 GENERAL REQUIREMENTS

NOT SEPARATELY PRICED (NSP) REQUIREMENTS

0001Intent, Scope, General Requirements and Definitions
0002Technical and Manufacturer’s Representatives
0003Approach, Berth, and Mooring Requirements
0004Testing and Quality Assurance
0005Electrical Safety Procedure Requirements
0006Heavy Weather Plan
0007Cold Weather Plan
0024NSP Physical Security at Private Contractor’s
Facility

CATEGORY “A” WORK ITEMS

0010Furnish Office for Overhaul Management Team(OMT)
0011Furnish General Services
0012Telephone Services
0013Project Planning and Production Status
Monitoring Reports
0014Preparation of Weight and Moment Report
0015Integrated Logistics and GFM Support

Requirements

0016Fire Protection and Ship’s Safety Program
0017Handling Ship’s Stores
0018Delivery and Redelivery of the Vessel
0019Shipboard Access and Security
0020Gas Free Certificates
0021Clean and Gas Free Tanks, Voids,
Cofferdams and Spaces
0022Dock Trials and Sea Trial
0023Hazardous Waste Disposal

CATEGORY “B” WORK ITEMS

0025 Physical Security at Private Contractor’s Facility 0030 Continuation of Services

SECTION 0100 HULL STRUCTURE

CATEGORY “A” WORK ITEMS

0105 Misc. Weld Repairs Rev 1 0108 Tank Boundary Testing and Structural Survey(ABS) 0111 Hull Survey Support (Special Survey 2) 0126 Cargo Hold No 2 Drain Piping & Valve Replacement 0169 Hazmat Containers Replacement

CATEGORY “B” WORK ITEMS

0101 Ballast Tank Zinc Inspection 0166 Mechanically Clean and Preserve Tanks

SECTION 0200 Machinery, Propulsion

CATEGORY “A” WORK ITEMS

0201 Propulsion Motor and Cooler Cleaning, Inspection and Maintenance 0202B Main Engine Flexible Connection Replacement (10-Year) 0204 MDE Control Safety Inspection and Test 0205 Annual Automation and Propulsion Control Inspection and Testing 0206 Vulkan Couplings Annual Inspection 0207 Propulsion Motor Pedestal Bearing Inspection 0251 Main Diesel Engine Start Air System Flush 0252 MDG 1 2 3 & 4 Start Air System Component Ovhl.

CATEGORY “B” WORK ITEMS

0202 MDG NO 1, 2 ,3, & 4 Cooler Casing Leak Repair

SECTION 0300 ELECTRICAL

CATEGORY “A” WORK ITEMS

0301 Cleaning Main Generators and Propulsion Control System (10-Year) 0302 High Voltage Cable Crimp Connector Inspection 0303 HV-SS-E Switchboard Inspection and Cleaning 0305 SO2 Detection System Install (T-ALT 404) 0306 SO2 Sensor Calibration Commissioning Certif.

0323 E-Board EDG & Bus-Tie Breaker Replace (T-ALT 486) 0325 EDG LO Cooler Installation (T-ALT 359)

CATEGORY “B” WORK ITEMS

0307 Cell Phone Distribution

SECTION 0400 COMMUNICATION AND NAVIGATIONAL AIDS

CATEGORY “A” WORK ITEMS

0401 Bridge Equipment Annual Service 0402 Antenna Preventative Maintenance 0403 Communications System Annual Preventative Maintenance 0404 OE-570 WSC Antenna System Maintenance 0405 AIS Renewal 0406 NAVMACS II Upgrade (T-ALT-16-454) 0452 Echo Depth Sounder Preventative Maintenance

SECTION 0500 MACHINERY, AUXILIARY SYSTEMS

CATEGORY “A” WORK ITEMS

0501B Firefighting Inspections and Testing(5-Year) 0502 SCBA Annual Inspection 0503 SCBA Air Compressor and Refilling Station Inspection and Maintenance 0504B Cargo Crane Maintenance and Retesting(10-Year) 0506 Emergency Diesel Generator(EDG) Annual 0510 Calibrate and Test Oily Water Separators 0513 Gage Calibration Rev 0514 Relief Valve Testing 0515 Open and Inspect Air Receivers and HP Air Flask 0522 Steering Gear Preventative Maintenance REV 0527 Brine System Flush 0528A Magazine Sprinkler Valve Overhaul (T-AKE 1-10) 0549 Sea Chest Grating (T-ALT 296) 0556 Flush HT LT Freshwater and Chill Water Systems

CATEGORY “B” WORK ITEMS

0516 Brine and Defrost Pump and Motor Overhauls 0517 CSW LTFW Isola. Valve Manual Gear Operator Rep.

0541 LTFW SW Cooler 20 and 10 Inch Valve Replacement 0553 Chill Water Pump and Motor Overhaul 0555 MMR AFFF System Piping Replacement Rev 1 0546 Incinerator Inspection and Maintenance 0548 Alarm Tower in Engine Workshop (T-ALT 396)

SECTION 0600 OUTFIT, FURNISHINGS and HABITABILITY

CATEGORY “A” WORK ITEMS

0601 LB, RHIB, Davits and Accom. Ladder Annual Inspections and Testing.

0602 Unrep Stations No 1 No 2 No 5 No 7 No 8 Winch Drum Preservation.

0603 Lifeboat Certification & Falls Renewal (5-Year) 0604 RHIB Boat Certification & Falls Renewal (5-Year) 0605 Life Raft Annual Certification 0606 Flght Deck non-skid Renewal REV I 0609 Immersion Suit Inspection and Testing 0610 Galley and MSO Equipment Calibration 0626 Flight Deck Hatch Wire Rope Repl. (T-ALT 450)

SECTION 0800 HEATING, VENTILATION and AIR CONDITIONING

CATEGORY “A” WORK ITEMS

0801 Galley and Laundry Exhaust Duct Cleaning 0822 Air Handlers and Fan Coil Units Cleaning 0823 Brine System Valve Replacement 0824 Cargo Refrigeration and AC Plant Expansion Joint Replacement

SECTION 0900 DRYDOCKING

CATEGORY “A” WORK ITEMS

0901 Dry Docking and Undocking Vessel 0903 Propeller Shaft and Stern Tube Inspection REV 1 0904 Stern Tube Seal Inspection (FW System) 0905B Bow Thruster Maintenance (5-Year) 0907 Polish Bow Thruster Propeller 0908 Renew Sea chest, Rope Guard and Bow Thruster Zincs 0909 Anchor and Anchor Chain Ranging 0910 Overhaul Sea Valves 0911 Inspect and Repair Cathodic Protection 0912 Shaft Grounding Maintenance 0913 Waster Pieces Renewal 0916 Underwater Hull Cleaning and Painting (SPOT) 0918 Freeboard Cleaning and Painting (SPOT) REV 1 0931 Rudder Stock Gland Seal and Lower Bearing Inspection Rev. II 0933 Bow Thruster Grating (T-ALT 448) 0934 Shaft Bulkhead Seal Overhaul

CATEGORY “B” WORK ITEMS

0902 Dry-Docking and Undocking 0914 Bilge Keel Repairs Rev- 0932 Valve MOV Groom

SECTION 1000 UNREP GEAR

CATEGORY “A” WORK ITEMS

1001 RAS Station Sliding Block Drive Chain Replace 1002 RAS Sliding Block and Transfer Head Refurbish 1003 RAM tensioner sway bracket install Mod

SECTION F - DELIVERY AND PERFORMANCE

F-1 SHIP AVAILABILITY PERIOD

It is anticipated the ship will arrive at contractor’s yard on or about 12 JUNE 2019. All work shall be completed in no more than 75 calendar days from actual start date designated by the Government at time of contract award.

(End of Summary of Changes) image1.wmf