N3220519R6005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
The following have been modified:
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Category "A" Work Items (WIs)
FFP
Prepare for and accomplish the ROH/DD Availability the United States Navy Ship of the USNS WALLY SCHIRRA T-AKE 8) Total Category "A" WIs $_____________
Proposed unit price per KWh $_____ in accordance with (IAW) WI 011, 7.1.1.4
Proposed unit price per gallon of potable water $______ IAW WI 011, 7.1.3.2
Proposed unit price per gallon of distilled water $______ IAW WI 011, 7.1.4.2
Proposed unit price per gallon of bilge water removal $______ IAW WI 011, 7.1.20.3
Proposed unit price per crane usage $______ IAW WI 11, 7.9.1
Proposed Hazardous Waste handling fee rate IAW WI 023, 7.4.1 ______%
FOB: Destination
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
AGR and ODC
AGR
(10,000) man-hours @ $________ per man-hour = $_____________
ODC
Base $1,000,000.00
Proposed G&A Rate _______________% Subtotal: $_____________
Proposed Profit Rate _______________% Subtotal: $_____________
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Category "B" WI 0025
WI 0025 - Physical Security at Private Contractor's Facility in FPCON Bravo - Delta
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Category "B" WI 0030
WI 0030 - Continuation of Services
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
ADDITIONAL CAT "B" WORK ITEMS
101-BALLAST TANKZINC INSPECTION
166-MECHANICALLY CLEAN AND PRESERVE TANKS
202-MDG NO 1 2 3 4 COOLER CASING LEAK REPAIR
307-CELL PHONE DISTRIBUTION
561-BRINE AND DEFROST PUMP AND MOTOR OVERHAULS
517-CSW LTFW ISOLATION VALVE MANUAL GEAR OPERATOR REPAIRS
541-LTFW SW COOLER 20 AND 10 INCH VALVE REPLACEMENT
546-INCINERATOR INSPECTION AND AMINTENANCE
548-INSTALL ADDITIONAL ALARM COLUMNS (T-ALT 396)
555-MMR AFFF SYSTEM PIPINGREPLACEMENT REV 1
553-CHILL WATERS PUMP AND MOTOR OVERHAUL
555-MMR AFFF FOAM SYSTEM PIPING REPLACE(T-ALT 394)
902-DRY DOCKING AND UNDOCKING VESSEL -7.1 CONTINUE ALL SERVICES IN WORK ITEM 901
914-BILGE KEEL REPAIRS
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AA
Category "B" WI 101
WI 101- BALLAST TANK ZINC INSPECTION
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AB
Category "B" WI 166
WI 166- MECHANICALLY CLEAN AND PRESERVE TANKS
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AC
Category "B" WI 202
202-MDG NO 1 2 3 4 COOLER CASING LEAK REPAIR
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AD
Category "B" WI 307
307-CELL PHONE DISTRIBUTION
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AE
Category "B" WI 516
561-BRINE AND DEFROST PUMP AND MOTOR OVERHAULS
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AF
Category "B" WI 517
517-CSW LTFW ISOLATION VALVE MANUAL GEAR OPERATOR REPAIRS
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AG
Category "B" WI 541
541-LTFW SW COOLER 20 AND 10 INCH VALVE REPLACEMENT
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AH
Category "B" WI 546
546-INCINERATOR INSPECTION AND AMINTENANCE
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AJ
Category "B" WI 548
548-INSTALL ADDITIONAL ALARM COLUMNS (T-ALT 396)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AK
Category "B" WI 553
553-CHILL WATERS PUMP AND MOTOR OVERHAUL
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AO
Category "B" WI 555
555-MMR AFFF SYSTEM PIPING REPLACEMENT REV 1
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AL
Category "B" WI 902
902-DRY DOCKING AND UNDOCKING VESSEL -7.1 CONTINUE ALL SERVICES IN WORK ITEM 901
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0005AM
Category "B" WI 914
914-BILGE KEEL REPAIRS
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
TOTAL PROPOSED PRICE
TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0005 $______________
The contractor shall enter the total proposed price of all CLINs.
CLAUSES INCORPORATED BY FULL TEXT
PART I - THE SCHEDULE
Section B, Price Schedule, detailed information
CLIN 0001 –Attachment J-2 – Category “A” WIs provides a WI breakdown of CLIN 0001 pricing.
CLIN 0002: This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated under the H-3 Clause - AGR and H-4 Clause ODC, for the duration of the contract. Changes are inherent to vessel repair contracts and should be expected by the Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:
| Abrasive cleaning/blasting | Tank cleaning | ||
| Welding | Machinists (inside and outside) | ||
| Burning | Brazing | ||
| Carpentry | Electrical work | ||
| Electronic work | Shipfitting | ||
| Lagging | Painting | ||
| Boilermaking | Pipefitting | ||
| Sheetmetal work | Engineering | ||
| Rigging | Staging/scaffolding | ||
| General labor | Fire Watch |
Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:
| Testing | Quality Assurance | ||
| Planning | Cleaning (except tank cleaning) | ||
| Material handling & warehousing | Security | ||
| Surveying | Administration | ||
| Transportation | Purchasing staff | ||
| Lofting | Other indirect support | ||
| Supervision |
Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's fully loaded manhour rate and not separately priced.
The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The KO will apply these rates to the ODCs for each CCO when it is negotiated and settled.
The base cost, stated in this CLIN does not include the profit or G&A rates.
NOTE: This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.
CLINs 0003 through 0005 –Attachment J-3 – Category “B” WIs provides a WI breakdown of CLIN 0003 through 0005 pricing.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
C – 2 List of Standard WIs included for this solicitation:
SECTION 0000 GENERAL REQUIREMENTS
NOT SEPARATELY PRICED (NSP) REQUIREMENTS
| 0001 | Intent, Scope, General Requirements and Definitions |
| 0002 | Technical and Manufacturer’s Representatives |
| 0003 | Approach, Berth, and Mooring Requirements |
| 0004 | Testing and Quality Assurance |
| 0005 | Electrical Safety Procedure Requirements |
| 0006 | Heavy Weather Plan |
| 0007 | Cold Weather Plan |
| 0024 | NSP Physical Security at Private Contractor’s |
| Facility |
CATEGORY “A” WORK ITEMS
| 0010 | Furnish Office for Overhaul Management Team(OMT) |
| 0011 | Furnish General Services |
| 0012 | Telephone Services |
| 0013 | Project Planning and Production Status |
| Monitoring Reports | |
| 0014 | Preparation of Weight and Moment Report |
| 0015 | Integrated Logistics and GFM Support |
Requirements
| 0016 | Fire Protection and Ship’s Safety Program |
| 0017 | Handling Ship’s Stores |
| 0018 | Delivery and Redelivery of the Vessel |
| 0019 | Shipboard Access and Security |
| 0020 | Gas Free Certificates |
| 0021 | Clean and Gas Free Tanks, Voids, |
| Cofferdams and Spaces | |
| 0022 | Dock Trials and Sea Trial |
| 0023 | Hazardous Waste Disposal |
CATEGORY “B” WORK ITEMS
0025 Physical Security at Private Contractor’s Facility 0030 Continuation of Services
SECTION 0100 HULL STRUCTURE
CATEGORY “A” WORK ITEMS
0105 Misc. Weld Repairs Rev 1 0108 Tank Boundary Testing and Structural Survey(ABS) 0111 Hull Survey Support (Special Survey 2) 0126 Cargo Hold No 2 Drain Piping & Valve Replacement 0169 Hazmat Containers Replacement
CATEGORY “B” WORK ITEMS
0101 Ballast Tank Zinc Inspection 0166 Mechanically Clean and Preserve Tanks
SECTION 0200 Machinery, Propulsion
CATEGORY “A” WORK ITEMS
0201 Propulsion Motor and Cooler Cleaning, Inspection and Maintenance 0202B Main Engine Flexible Connection Replacement (10-Year) 0204 MDE Control Safety Inspection and Test 0205 Annual Automation and Propulsion Control Inspection and Testing 0206 Vulkan Couplings Annual Inspection 0207 Propulsion Motor Pedestal Bearing Inspection 0251 Main Diesel Engine Start Air System Flush 0252 MDG 1 2 3 & 4 Start Air System Component Ovhl.
CATEGORY “B” WORK ITEMS
0202 MDG NO 1, 2 ,3, & 4 Cooler Casing Leak Repair
SECTION 0300 ELECTRICAL
CATEGORY “A” WORK ITEMS
0301 Cleaning Main Generators and Propulsion Control System (10-Year) 0302 High Voltage Cable Crimp Connector Inspection 0303 HV-SS-E Switchboard Inspection and Cleaning 0305 SO2 Detection System Install (T-ALT 404) 0306 SO2 Sensor Calibration Commissioning Certif.
0323 E-Board EDG & Bus-Tie Breaker Replace (T-ALT 486) 0325 EDG LO Cooler Installation (T-ALT 359)
CATEGORY “B” WORK ITEMS
0307 Cell Phone Distribution
SECTION 0400 COMMUNICATION AND NAVIGATIONAL AIDS
CATEGORY “A” WORK ITEMS
0401 Bridge Equipment Annual Service 0402 Antenna Preventative Maintenance 0403 Communications System Annual Preventative Maintenance 0404 OE-570 WSC Antenna System Maintenance 0405 AIS Renewal 0406 NAVMACS II Upgrade (T-ALT-16-454) 0452 Echo Depth Sounder Preventative Maintenance
SECTION 0500 MACHINERY, AUXILIARY SYSTEMS
CATEGORY “A” WORK ITEMS
0501B Firefighting Inspections and Testing(5-Year) 0502 SCBA Annual Inspection 0503 SCBA Air Compressor and Refilling Station Inspection and Maintenance 0504B Cargo Crane Maintenance and Retesting(10-Year) 0506 Emergency Diesel Generator(EDG) Annual 0510 Calibrate and Test Oily Water Separators 0513 Gage Calibration Rev 0514 Relief Valve Testing 0515 Open and Inspect Air Receivers and HP Air Flask 0522 Steering Gear Preventative Maintenance REV 0527 Brine System Flush 0528A Magazine Sprinkler Valve Overhaul (T-AKE 1-10) 0549 Sea Chest Grating (T-ALT 296) 0556 Flush HT LT Freshwater and Chill Water Systems
CATEGORY “B” WORK ITEMS
0516 Brine and Defrost Pump and Motor Overhauls 0517 CSW LTFW Isola. Valve Manual Gear Operator Rep.
0541 LTFW SW Cooler 20 and 10 Inch Valve Replacement 0553 Chill Water Pump and Motor Overhaul 0555 MMR AFFF System Piping Replacement Rev 1 0546 Incinerator Inspection and Maintenance 0548 Alarm Tower in Engine Workshop (T-ALT 396)
SECTION 0600 OUTFIT, FURNISHINGS and HABITABILITY
CATEGORY “A” WORK ITEMS
0601 LB, RHIB, Davits and Accom. Ladder Annual Inspections and Testing.
0602 Unrep Stations No 1 No 2 No 5 No 7 No 8 Winch Drum Preservation.
0603 Lifeboat Certification & Falls Renewal (5-Year) 0604 RHIB Boat Certification & Falls Renewal (5-Year) 0605 Life Raft Annual Certification 0606 Flght Deck non-skid Renewal REV I 0609 Immersion Suit Inspection and Testing 0610 Galley and MSO Equipment Calibration 0626 Flight Deck Hatch Wire Rope Repl. (T-ALT 450)
SECTION 0800 HEATING, VENTILATION and AIR CONDITIONING
CATEGORY “A” WORK ITEMS
0801 Galley and Laundry Exhaust Duct Cleaning 0822 Air Handlers and Fan Coil Units Cleaning 0823 Brine System Valve Replacement 0824 Cargo Refrigeration and AC Plant Expansion Joint Replacement
SECTION 0900 DRYDOCKING
CATEGORY “A” WORK ITEMS
0901 Dry Docking and Undocking Vessel 0903 Propeller Shaft and Stern Tube Inspection REV 1 0904 Stern Tube Seal Inspection (FW System) 0905B Bow Thruster Maintenance (5-Year) 0907 Polish Bow Thruster Propeller 0908 Renew Sea chest, Rope Guard and Bow Thruster Zincs 0909 Anchor and Anchor Chain Ranging 0910 Overhaul Sea Valves 0911 Inspect and Repair Cathodic Protection 0912 Shaft Grounding Maintenance 0913 Waster Pieces Renewal 0916 Underwater Hull Cleaning and Painting (SPOT) 0918 Freeboard Cleaning and Painting (SPOT) REV 1 0931 Rudder Stock Gland Seal and Lower Bearing Inspection Rev. II 0933 Bow Thruster Grating (T-ALT 448) 0934 Shaft Bulkhead Seal Overhaul
CATEGORY “B” WORK ITEMS
0902 Dry-Docking and Undocking 0914 Bilge Keel Repairs Rev- 0932 Valve MOV Groom
SECTION 1000 UNREP GEAR
CATEGORY “A” WORK ITEMS
1001 RAS Station Sliding Block Drive Chain Replace 1002 RAS Sliding Block and Transfer Head Refurbish 1003 RAM tensioner sway bracket install Mod
SECTION F - DELIVERY AND PERFORMANCE
F-1 SHIP AVAILABILITY PERIOD
It is anticipated the ship will arrive at contractor’s yard on or about 12 JUNE 2019. All work shall be completed in no more than 75 calendar days from actual start date designated by the Government at time of contract award.
(End of Summary of Changes) image1.wmf