WI 503

View the file

Other files

File Type Posted
ROH_AMENDMENT_UNSN_CHAMBERS.docx DOCX document
0606_Flight_Deck_Non-Skid_Renewal_Rev_-_(CSI)_REV_2.doc DOC document
Chambers_ROH_Amendment_0006.docx DOCX document
0030_B_Continution_of_Services_REV_1.doc DOC document
0621_B_Replace_Deck_Covering_in_Various_Heads_(VR17-024)REV_1.doc DOC document
Chamber_ROH_Amendment_0005.docx DOCX document
Chambers_ROH_Amendment_0005.docx DOCX document
0606_Flight_Deck_Non-Skid_Renewal_Rev_-_(CSI)_REV_1.doc DOC document
0532_A_HTLT_Freshwater_System_Flush_REV_1.doc DOC document
J_-_2_Category_A_Items_CHAMBERS.xls XLS spreadsheet
BQ_-_0007_WI_802_GFS_scope_Response.doc DOC document
SAWS_INSTL_LIST_OF_CONNECTIONS_439-8394524.pdf PDF
8394521_-SaWS_Support_-_Mechanical_Dwg.pdf PDF
BQ_-_0006_WI_531_Dwgs_Response.doc DOC document
0214_8_Cylinder_Main_Diesel_Engine_24000_Hour_Scheduled_Maintenance_(CSI).doc DOC document
Questions_and_Answers.docx DOCX document
USNS_Chambers_ROH_Solicitation_0004.docx DOCX document
J_-_2_Category_A_Items_CHAMBERS_-_REV_1.xls XLS spreadsheet
0012_Information_Technology_Services_Rev_16July18.doc DOC document
USNS_Chambers_ROH_Solicitation_0004.docx DOCX document
0021__Clean_and_Gas_Free_Tanks_Voids_Cofferdams_and_Spaces.doc.doc DOC document
0010_Furnish_Office_for_Overhaul_Management_Team(OMT)_Rev16July18.doc DOC document
0916_Underwater_Hull_Blast_&_Paint_(Spot_Blast)-_REV_(1).docx DOCX document
0532_A_HTLT_Freshwater_System_Flush.doc DOC document
N3220518R4259_Amendment_0003.docx DOCX document
N3220518R4259_AMENDMENT_0002.docx DOCX document
USNS_CHAMBERS_ROH_AMENDMENT.docx DOCX document
USNS_CHAMBERS_ROH.docx DOCX document
CDRLS.zip ZIP file
USNS_WASHINGTON_CHAMBERS_ROH.docx DOCX document
J_&_A_N32205-18-Q-4259_Redacted.pdf PDF
J_Attachments_and_GFM.zip ZIP file
SYNOPSIS_N32205-18-R-4259.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS Chambers

( TAKE 11 )

AUXILIARY MACHINERY
CONTRACT NO. N32205-18-R-4259
ITEM NO. 0503
CATEGORY "A"
2018-08-28
Self Contained Breathing Apparatus (SCBA) Air Compressor and Re-Filling Station Inspection and Maintenance Rev - (CSI)
Escobar, Daniel

1.0 ABSTRACT:

1.1 This item describes the requirement to perform all required inspection and maintenance to the SCBA Air Compressor and Re-Filling Station.

2.0 REFERENCES:

2.1 Technical Manual T6220-CH-MMC-010; Compressor Unit, High Pressure Breathing Air, VERTICUS Model VT13

2.2 MAKO Model SCFS3-3HP; Instruction, Maintenance, and Operating Manual

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Location/Quantity:

3.1.1 Location:

a. SCBA Charging Room (1-69-1)

b. Cargo Handling Area 2 (1-58-1)

3.1.2 Quantity:

a. One (1) SCBA Air Compressor

b. One (1) SCBA Re-Filling Station

3.2 Item Description/Manufacturer’s Data:

3.2.1 SCBA Air Compressor

a. BAUER Compressor

b. VERTICUS Model VT13

3.2.2 SCBA Re-Filling Station

a. MAKO Model SCFS3-3HP

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.

5.0 NOTES:

5.1 The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs.

5.2 The contractor and all subcontractors regardless of tier are advised to review the other work items under this contract to determine their effect on the work required under this work item.

5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER AUTHORIZATION.

5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED AND PROVEN OTHERWISE. TEST ALL ELECTRICAL CABLES TO ENSURE THEY ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7.0 STATEMENT OF WORK REQUIRED:

7.1 Secure, Lock-out/Tag-out, and draine/bleed the SCBA Charging System.

7.2 Provide the services of an authorized/certified Original Equipment Manufacturer (OEM) repair facility to perform the required inspection and maintenance of the SCBA Air Compressor and Re-Filling Station using Ref. 2.1 and 2.2 as guidance.

7.2.1 If the Contractor requires any repair parts or if there are any changes that are not covered by this work item, then the Contractor shall submit a Condition Found Report.

7.3 Notify Ship’s Force upon completion to unlock and re-charge the system.

7.4 Conduct a leak test of the SCBA Charging System.

7.5 Preparation of Drawings/Documents:

7.5.1 Provide a Service Report documenting completion of work, describing all work accomplished, future recommendations, and results of any required testing performed. All documentation to be submitted to the MSCREP.

7.6 Inspection/Testing:

7.6.1 Perform operational check at system pressure and inspect for leakage. No leakage is allowed. MSCREP to witness testing.

7.7 Manufacturer's Representative:

7.7.1 Provide the services of an authorized/certified Original Equipment Manufacturer (OEM) Technical Representative to accomplish all required inspections and maintenance.

7.7.2 Recommended Source:

BAUER COMPRESSORS, INC.

Azalea Garden Road, Norfolk, VA Phone: (757) 855-6006

8.0 GENERAL REQUIREMENTS: None additional.