Question_6_answered.doc

DOC document 41 KB Posted

Attached to
MTA OF USNS YUKON (T-AO 202)
Solicitation number
N32205-17-R-4011
Issued by

About this file

answer to clarification question 6

View the file

Other files

File Type Posted
N32205-17-R-4011-0004.docx DOCX document
N32205-17-R-4011-0002.docx DOCX document
N32205-17-R-4011_AMENDMENT_0003.docx DOCX document
Motor_Drains_sketch_for_question_11.pdf PDF
Question_10_answered.doc DOC document
Question_11_answered.doc DOC document
Question_9_answered.doc DOC document
WSM_Technical_Spec.pdf PDF
LOP_Strucal_8496442.pdf PDF
Question_3_answered.doc DOC document
LOP_Pipe_8496443.pdf PDF
Installation_Drawings.pdf PDF
Question_4_answered.doc DOC document
LOP_Rep_Elec_320-8496441.pdf PDF
Question_8_answered.doc DOC document
Question_7_answered.doc DOC document
6580666_D.pdf PDF
Question_3.doc DOC document
J-8_Request_for_Spec_Clarification_-_0001.doc DOC document
N32205-17-R-4011-P00001.docx DOCX document
DD_Form_1423-1_SWI-004_13SEP16.pdf PDF
DD_Form_1423-1_SWI-011__13SEP16.pdf PDF
J-8_Request_for_Spec_Clarification.doc DOC document
DD_Form_1423-1_SWI-021_13SEP16.pdf PDF
J-2_Category_A_Items_.xlsx XLSX spreadsheet
J-14_NDA.docx DOCX document
JA__USNS_YUKON_Redacted.pdf PDF
DD_Form_1423-1_SWI-014_13SEP16.pdf PDF
J-4__GFM.doc DOC document
DD_Form_1423-1_SWI-012_13SEP16.pdf PDF
DD_Form_1423-1_SWI-025_13SEP16.pdf PDF
DD_Form_1423-1_SWI-020_13SEP16.pdf PDF
DD_Form_1423-1_SWI-023_13SEP16.pdf PDF
DD_Form_1423-1_SWI-003_13SEP16.pdf PDF
J-9_Disclosure_of_Lobbying_Activities_SF-LLL.pdf PDF
J-5_Subcontracting_Plan.docx DOCX document
J-3_CAT_B.xlsx XLSX spreadsheet
DD_Form_1423-1_SWI-015_13SEP16.pdf PDF
J-10_Interport_Differential.doc DOC document
DD_Form_1423-1_SWI-016_13SEP16.pdf PDF
DD_Form_1423-1_SWI-007_13SEP16.pdf PDF
DD_Form_1423-1_SWI-006_13SEP16.pdf PDF
J-13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
DD_Form_1423-1_SWI-001_13SEP16.pdf PDF
DD_Form_1423-1_SWI-019_13SEP16.pdf PDF
DD_Form_1423-1_SWI-018_13SEP16.pdf PDF
N32205-17-R-4011.docx DOCX document
DD_Form_1423-1_SWI-010_13SEP16.pdf PDF
J-12_Past_Performance_Data.docx DOCX document
J-7_MSC_Ship_Repair_Facility_Survey.doc DOC document
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS YUKON (T-AO 202) – N32205-17-R-4011

REQUEST FOR SPECIFICATION CLARIFICATION #06

SPECIFICATION ITEM NO.: 103

PARAGRAPH / SECTION NO: Paragraph 7.2

TITLE: CHAIN LOCKER SUMP PRESERVATION AND STEEL REPAIRS (VR016-018)

In review of paragraph 7.2 of WI# 103, this offeror finds:

7.2.1 Crop out and replace bottom half of 8 out of 10 frames, each frame 5' x 1'

3" w/ access hole, 6.25 sq. feet each for a total of 50 sq. feet. 9/16" A-32

ABS grade steel plate. (FR 18.25, 18.5, 18.75, 19, 19.25).

7.2.2 Crop out and replace 25 sq feet of 1/2" A-32 ABS grade plate on tank boundary frame 18 at the 32'-6" level. Note: this plate extends into the forepeak 5-0-0 and the #1 Deep tank 5-18-0. This will require staging in both tanks for access.

7.2.3 Clad weld approx. 6 sq. feet of isolated pitting

Performing blasting & painting after the structural repair will result in the complete paint system application without the need to re-enter the sump to perform touch up after the structural work is completed.

QUESTION:

Please clarify the prioritization of the preservation and structural work on this work item. Is the Government’s intent to perform surface preparation and preservation of the Chain Locker Sump prior to performing the specified structural repairs, or shall the surface preparation and preservation be performed after the structural repairs are completed?

ANSWER:

1. Due to the condition of the chain locker sump it is preferred the sump be blasted and one primer coat applied to allow ABS and MSC to inspect the tank prior to any steel removal. If the contractor can clean the tank sufficient enough to have ABS and MSC inspect the tank without blasting than blasting and preservation can be conducted after steel replacement has been completed.

ATTACHMENT J - 8