N32205-17-R-4011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION F - DELIVERY AND PERFORMANCE
The following have been modified:
F-1 SHIP AVAILABILITY PERIOD
It is anticipated that ship will arrive at Contractor’s yard on or about 25 January 2017. All work shall be completed in no more than 42 calendar days from actual start date designated by the Government at time of contract award.
(End of Summary of Changes) image1.wmf