644_A_COSAL_STOREROOM_VIDMAR_MOUNTING_-_AMENDED.doc

DOC document 55 KB Posted

Attached to
USNS MEDGAR EVERS: Regular Overhaul and Dry-Docking Federal contract opportunity
Solicitation number
N32205-16-R-4314
Issued by
Department of the Navy Military Sealift Command

About this file

Revised Work Item 644

View the file

Other files for this federal contract opportunity

Other files attached to USNS MEDGAR EVERS: Regular Overhaul and Dry-Docking, newest first.
File Type Posted
N32205-16-R-4314_Amendment_0007.doc DOC document
J_-_2_Category_A_Items.xls XLS spreadsheet
N32205-16-R-4314_Amendment_0006.doc DOC document
N104-16-R-4314_OEM_J&A.pdf PDF
J_-_2_Category_A_Items.xls XLS spreadsheet
144_A_SHELL_AND_DECK_STEEL_REPLACEMENT_-_AMENDED.doc DOC document
N32205-16-R-4314_Amendment_0006.doc DOC document
210_A_8_CYL_MDE_12K_HR_SKED_MAINT_REV_-_(AMENDED).docx DOCX document
WI_144.zip ZIP file
WI_644.zip ZIP file
565_A_CENTRAL_SEAWATER_SYSTEM_SPOOL_REPAIRS_(AMENDED).doc DOC document
N32205-16-R-4314_Amendment_0005.doc DOC document
Amendment_0005_reference_for_Work_items_.zip ZIP file
Q_AND_A_Responses_2.docx DOCX document
N32205-16-R-4314_Amendment_0004.docx DOCX document
FUEL_OIL_FLEX_CONN_FINAL_DRAFT.PDF PDF
0021_A_CLEAN_AND_GAS_FREE_TANKS _VOIDS_AND_COFFERDAMS _REV_FEB_14_Rev_A.doc DOC document
Q_AND_A_Responses_1.docx DOCX document
N32205-16-R-4314_Amendment_0002.docx DOCX document
J_-_3_Category_B_Items_Medgar_Evers_ROHDD_2017.xls XLS spreadsheet
J_-_2_Category_A_Items_Medgar_Evers_ROHDD_2017.xls XLS spreadsheet
N32205-16-R-4314.docx DOCX document
N32205-16-R-4314.docx DOCX document
J-4.pdf PDF
J-Attachments_2-14.zip ZIP file
J-6Zip.zip ZIP file
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS MEDGAR EVERS

(T-AKE 13)

HULL STRUCTURE

RFP NO. N32205-16-R-4314

09 December 2016

ITEM NO. 644

Category “A”

N756/MCB

COSAL STOREROOM VIDMAR CABINET MOUNTING - AMENDED

1.0 ABSTRACT:

1.1 This item describes the requirement to mount seven (7) Vidmar cabinets to the deck of the COSAL Storeroom.

2.0 REFERENCES

2.1 MSC Drawing No. 802-7488866; General Arrangement

2.2 Excel File “COSAL SHELVING”

2.3 JPG File “VIDMARS”

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location:

3.1.1 Location:

a. COSAL Storeroom (2-34-0)

b. Cargo F.O. Tank 3C (4-34-0)

c. Cargo F.O. Tank 3S (4-34-1)

3.1.2 Description:

a. Stud Weld 28 studs to deck of COSAL Storeroom to mount seven (7) Vidmar Cabinets.

b. Repair any damage caused to the tank coating of 3C and 3S Cargo F.O. Tank by stud welding of studs.

3.2 Item Description/Manufacturer’s Data: None.

3.3 Bill of Material (Contractor Furnish Material):

Description
Specification
QTY
Studs/Ferrules
¾”- 10 302 Stainless Steel 1.50” Length
100
Nuts
¾” – 10 Stainless Steel
100
Washers
¾” Stainless Steel
100

4.0 GOVERNMENT-FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Government Furnished Equipment: None.

4.2 Government Furnished Material:

4.2.1 PPG Paint As Required

4.2.2 7 EA Stanley Vidmar Cabinets

4.3 Government Furnished Services:

4.3.1 PPG Paint Representative

5.0 NOTES

5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s.

5.2 The contractor and all subcontractors, regardless of tier are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

5.3 COSAL Storeroom and 3C and 3S Cargo Fuel Oil Tanks require Gas Free certificates prior to entry and paint removal. The Contractor shall notify the Marine Chemist, Port Engineer and Chief Engineer prior to commencement of work for deck plate inspections.

5.4 Provide all staging and floating platforms necessary to perform work.

5.5 Provide all pumping/transportation/disposal of waste water and debris generated by this work item.

5.6 Cleaning and gas freeing shall be covered under Work Items 20 and 21. Closure of tank shall be covered under Work Items 20 and 21.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7.0 STATEMENT OF WORK REQUIRED:

7.1 The Contractor and Ships Force shall document “as-found” conditions. All deficiencies shall be submitted to the MSCREP for review.

7.1.1 Deficiencies noted during this inspection shall be corrected and the MSCREP shall be given the opportunity to inspect and approve the corrective measures before work begins.

7.2 Observe the location where Vidmar cabinets are to be mounted and mark the deck as to where securing studs will be welded.

7.3 Mechanically clean each spot on the deck where studs are to be welded.

7.4 Weld each of the 28 total studs to the deck.

7.5 Prime and paint around the disturbed areas of the welded stud.

7.5.1 Priming and painting will be in accordance with PPG Paint representative recommendation.

7.6 Mount each Vidmar Cabinet with contractor furnished hardware.

7.7 Inspect the overhead of Cargo Fuel Tank NO. 3C and 3S in the presence of an MSC Representative for damage caused by stud welding.

7.7.1 If damage is observed consult PPG Paint representative for guidance on repair.

7.7.2 Follow Note 5.4 for erecting scaffolding or staging to accomplish repair.

7.7.2 Repair damage using provided PPG Paint.

7.7.3 Inspect repair in the presence of and MSC Representative and PPG Paint representative.

8.0 GENERAL REQUIREMENTS: None additional.

644-1

File details come from the government source that posted it. Updated .