CUXS Draft RFP_QA.pdf
PDF 436 KB Posted
- Attached to
- Counter Uncrewed Systems Support Services
- Solicitation number
- N00421-24-RFPREQ-4K0000T-1255
About this file
This document is a set of draft Request for Proposal (RFP) questions and answers for the Counter Uncrewed Systems Support Services contract (N00421-24-RFPREQ-4K0000T-1255) issued by the Department of the Navy Naval Air Systems Command. The document contains eight specific questions from potential bidders addressing topics such as Organizational Conflict of Interest (OCI) list, facility clearance requirements, transition-in plan duration, labor categories, missing attachments, and wage determination updates.
The government's responses indicate several key modifications to the draft RFP: the OCI list has been updated per command direction, the facility clearance level is confirmed as TOP SECRET, the transition-in plan is standardized to 30 days, Attachment 8 will be added to Sam.gov, the Wage Determination (WD 2015-4279) has been updated to Revision 28, and an Administrative Assistant labor category will not be included in the Statement of Work. The document suggests this is a pre-solicitation draft intended for contractor review and comment, with questions due by 1400 on 20 MAY 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CIIDS CSWF Attachment 08.xlsx | XLSX spreadsheet | |
| Attachment 3 Locator Form.pdf | ||
| Attachment P3 - SBPCD.docx | DOCX document | |
| 10. CUXS_OCI List V2.docx | DOCX document | |
| 12. CUXS_CSP V7.1 (1).docx | DOCX document | |
| Professional Engineering Positions_0800_Attachment 07.pdf | ||
| 8. CUXS_DD Form 254_June 2025 Expiration_Bidding_.pdf | ||
| 7. CUXS_CDRL_rev5.docx | DOCX document | |
| Attachment P2 - Annual Fully Burdened Rates.xlsx | XLSX spreadsheet | |
| Attachment P1 - Cost Summary Spreadsheet.xlsx | XLSX spreadsheet | |
| WD 2015-4279_Rev 27.pdf | ||
| Attachment 5 Data Item Transmittal Form.docx | DOCX document | |
| DRAFT_N0042125R0025.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUXS Draft RFP Questions
Question: RFP Reference: Topic: Question:
1 CUXS_OCI List V2 document OCI List DRAFT RFP included an attachment identifying SAIC on the OCI list
2 Page 2 Conflicting Information
Throughout the RFP, several labor categories require a TOP SECRET clearance. Would the Government revise, page 2 of 124, General Information; 6 to state: “The contractor will be required to have a TOP SECRET facility clearance for personnel identified in Section C SOW paragraph 3.2.2…”
3 Pages 14 and 109 Transition
Page 14 of 124, Paragraph 3.1.8.1 states: Transition-In services shall begin on the effective date of the award and shall be complete 30 calendar days after the effective date, at which time the contractor shall assume full responsibility for tasking. While page 109 of 124, 1.3 Transition-In Plan, first paragraph states: The offeror is required to submit a written narrative explaining a transition-in plan based on a 45-day transition that ensures…Please clarify if a 30-day or 45-day transition-in plan is required?
4 Page 18 Labor Categories
Under the existing contract, there is an Administrative Assistant Labor Category (SCA 01020) for the various deliverables and travel requirements.
The solicitation does not have an Administrative Assistant Labor Category listed on page 18 of 124, Labor Category Table. Would the Government consider Including an Administrative Assistant Labor Category (SCA 01020) for the administrative tasking in the SOW including CSDRL deliverable, travel requirements, etc.?
5 Attachment 8 CSWF
The Draft RFP is missing Attachment 8 (CI&IDS CSWF). Can the Government please provide?
6 WD 2015-4279_Rev27 WD Schedule
A newer revision of the prevailing Wage Determination for St Mary’s, Maryland has been issued (Rev. 28 dated 4/25/25). Will the Government issue the updated WD with the Final RFP release?
7 Attachment 7 CDRL List
Attachment 7 appears to be corrupt and will not open. Would the Government provide an updated attachment?
8 Section C, Para. 3.3.8 CUSX Operation Support
Under Paragraph 3.3.8 in Section C, the sub-paragraphs are incorrectly numbered. Would the Government please change 3.3.7.9 to 3.3.8.1 and
3.3.7.10 to 3.3.8.2?
Answer:
OCI List has been updated per Command direction.
Per the bidding DD254 the facility clearance level is TOP SECRET. RFP has been updated.
All references to the Transition-In Plan have been updated to a 30-day transition-in plan.
An Administrative Assistant will not be included in this
SOW.
Attachment 8 was available in PIEE. Attachment 8 added to Sam.gov. Final RFP and Attachments will be posted in PIEE. Let us know if you have any issues at that time.
Yes, WD 2015-4279 has been updated to Rev 28
Government has no issue opening Attachment 7, please attempt in PIEE.The Final RFP and Attachments will be posted in PIEE. Let us know if you have any issue at that time.
Corrected.