This amendment provides changes to solicitation N00421-18-R-0017 for Lifetime Support Engineering supporting AD-4.11.3. Key details include an extension of the response date to June 4, 2019 at 12:00 PM to allow consideration of the changes. Offerors must acknowledge receipt and consideration of amendments. The scope of work involves electronic warfare systems technical support. The incumbent contractor is BAE Systems with subcontractors including AV3, Delphinus Enterprises, KITCO Fiber Optics, MERCOM, SERCO, and Tecnico Corporation.
N00421-18-R-0017 Amendment 0001 Modification
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0042118R0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been added by full text:
AMENDMENT 0001
Changes made to Solicitation N00421-18-R-0017 and responses to questions from industry via Amendment 0001 are outlined below. The proposal due date and time has not changed; all submissions shall be in accordance with Block 9 of the Solicitation cover page.
1. Question 1): “Section C, paragraph 3.1.5.1.1 lists numerous CONUS locations where work may be performed during the contract period of performance, yet only WD 15-4279 (Rev 5) for St. Mary’s County, MD is included with the RFP. If an offeror intends to propose SCA staff at several of the locations listed in paragraph 3.1.5.1.1 should they use the included WD for St. Mary’s County for bid pricing, or select the appropriate WD for that area and notify the government of that selection in the offeror’s cost volume.”
Answer 1): The offeror shall use the WD for St. Mary’s County and consider other locations as potential travel locations. (See Question 4)
2. Question 2): “The DoD 2018 Small Business Subcontracting goals (statutory goals) are 5% WOSB, 5% SDB, and 3% SDVOSB based on total subcontract value (TSV). The Solicitation lists the same percentage goals for each socio-economic category, but states they are based on total contract value (TCV). We request that the overarching small business participation goal remain based on TCV with the socio-economic goals based on TSV.”
Answer 2): Language in Section L, Part B, paragraph 1.3.3.1 has been changed from “total contract value” to “total subcontract value.”
3. Question 3): “The RFP states ‘Graphs and tables shall be presented in no smaller than a Times New Roman 12 pt Normal font and should contain a grid, which allows values to be read directly from the graph. Graphic resolution, including such data as tables or charts, shall be no smaller than 10 pt font and should be consistent with the purpose of the data presented.’ Will the government please clarify whether 10 pt or 12 pt font should be used when presenting tables?”
Answer 3): Section L, Part A, paragraph 2.1 has been corrected to say “Graphs and tables shall be presented in no smaller than a Times New Roman 10 pt Normal font……”
4. Question 4): “The RFP includes Department of Labor Wage Determination 15-4279 Rev 05 Dated 1/10/2018 for ST. INIGOES, MD (ST. MARY’S COUNTY). This is not the most recent wage determination scale for this locale. Wage Determination 15-4279 Rev 06 was issued on 7/18/2018. Please confirm that offerors should use WD 15-4279 Rev 5 for this solicitation.”
Answer 4): Offerors shall use WD 15-4279 Rev 6 dated 7/18/2018. Attachment 6 has been updated to the correct reference.
5. Question 5): “Instructions for Attachment P6 and P7 direct the offeror not to type in any colored areas. Some areas such as Column A (Labor Categories) on each of the Term Year pages in the workbooks need to be edited in order to be clear and provide needed information. Will the government allow the offeror to edit colored cells if necessary to show required information or will the government modify the colored cells within the spreadsheets?”
Answer 5): Attachments P6 and P7 have been modified to remove colors in some cells in Column A.
6. Question 6): “The Instructions for P6 and P7 direct the offeror not to change the government inserted formulas. These formulas may not be consistent with the offeror's disclosed practices. Will the government allow modifications to the formulas in order for the offeror to remain in compliance with their disclosure statement?”
Answer 6): Offerors may modify the formulas, if necessary, in order to remain in compliance with their disclosure statement. (See Section L, Part B, paragraph 3.3.1.)
7. Question 7): “The instructions for P4, Cell C3, direct the offeror to include fully rates ‘but should not include Fully Burdened Other Direct Costs (ODCs) such as Materials, Travel, and Cost of Money costs’. Is it the government's direction not to include any Cost of Money on the fully burdened labor rate?”
Answer 7): The intent is that the offeror not include ODCs with the fully burdened labor rates. COM, as applicable to the labor rate, may be included in the fully burdened labor rate. COM, as applicable to ODCs, should not be included in the fully burdened labor rate.
8. Question 8): We request an extension of at least 10 days to the due date to allow offerors to update their pricing models in response to the directions above, once received from the government.
Answer 8): No extensions will be granted at this time.
9. Question 9): On page 116 of the RFP the total Government estimates for Travel and Material are $13,088,377.79 and $13,088,377.79 respectively. On P6 the ODC worksheet, the total Government estimates for Travel and Material are $2,094,140 and $19,632,567 respectively. Would the Government please clarify what amounts are to be proposed for the Travel and Material?
Answer 9): Attachment P6 has been updated to reflect the correct ODC amounts.
Additional Changes made by the Government
Paragraph 4.0 has been added to Section M, Part B for the Evaluation of Options.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Exhibit A |
| Contract Data Requirements List |
| 49 |
| 10-MAY-2018 |
| Attachment 01 |
| Contract Surveillance Plan |
| 13 |
| 10-MAY-2018 |
| Attachment 02 |
| DD 254 - Draft for Bidding Purposes Only |
| 2 |
| 10-MAY-2018 |
| Attachment 03 |
| Data Item Transmittal Acceptance Rejection Form |
| 1 |
| 10-MAY-2018 |
| Attachment 04 |
| OCI List |
| 1 |
| 10-MAY-2018 |
| Attachment 05 |
| Approved Subcontractors |
| 1 |
| 10-MAY-2018 |
| Attachment 06 |
| Wage Determination |
| 1 |
| 10-MAY-2018 |
| Attachment 07 |
| Approved Key Personnel |
| 1 |
| 10-MAY-2018 |
| Attachment 08 |
| COR Appointment Letter |
| 1 |
| 10-MAY-2018 |
| Attachment P1 |
| Past Performance Information Form |
| 2 |
| 20-SEP-2018 |
| Attachment P2 |
| Contractor Performance Assessment Questionnaire |
| 15 |
| 10-MAY-2018 |
| Attachment P4 |
| Streamline Rates for Order Pricing |
| 4 |
| 10-MAY-2018 |
| Attachment P5 |
| Fully Burdened Labor Rate_Hours_Annual Salary Form |
| 2 |
| 10-MAY-2018 |
| Attachment P6 |
| Cost Spreadsheet (Prime Contractor) |
| 22 |
| 10-MAY-2018 |
| Attachment P7 |
| Cost Spreadsheet (Subcontractor) |
| 8 |
| 10-MAY-2018 |
| Attachment P8 |
| Labor Hours |
| 2 |
| 10-MAY-2018 |
to:
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Exhibit A |
| Contract Data Requirements List |
| 49 |
| 10-MAY-2018 |
| Attachment 01 |
| Contract Surveillance Plan |
| 13 |
| 10-MAY-2018 |
| Attachment 02 |
| DD 254 - Draft for Bidding Purposes Only |
| 2 |
| 10-MAY-2018 |
| Attachment 03 |
| Data Item Transmittal Acceptance Rejection Form |
| 1 |
| 10-MAY-2018 |
| Attachment 04 |
| OCI List |
| 1 |
| 10-MAY-2018 |
| Attachment 05 |
| Approved Subcontractors |
| 1 |
| 10-MAY-2018 |
| Attachment 06 |
| Wage Determination |
| 1 |
| 16-OCT-2018 |
| Attachment 07 |
| Approved Key Personnel |
| 1 |
| 10-MAY-2018 |
| Attachment 08 |
| COR Appointment Letter |
| 1 |
| 10-MAY-2018 |
| Attachment P1 |
| Past Performance Information Form |
| 2 |
| 20-SEP-2018 |
| Attachment P2 |
| Contractor Performance Assessment Questionnaire |
| 15 |
| 10-MAY-2018 |
| Attachment P4 |
| Streamline Rates for Order Pricing |
| 4 |
| 10-MAY-2018 |
| Attachment P5 |
| Fully Burdened Labor Rate_Hours_Annual Salary Form |
| 2 |
| 10-MAY-2018 |
| Attachment P6 |
| Cost Spreadsheet (Prime Contractor) |
| 9 |
| 18-OCT-2018 |
| Attachment P7 |
| Cost Spreadsheet (Subcontractor) |
| 8 |
| 17-OCT-2018 |
| Attachment P8 |
| Labor Hours |
| 2 |
| 10-MAY-2018 |
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
SECTION L
L – 1 CONTENT OF PROPOSALS (SERVICES)
PART A GENERAL INSTRUCTIONS
1.0 GENERAL
1.1 The Offeror must respond to all requirements of the solicitation and not alter or rearrange the solicitation. The Offeror is advised that the Government may incorporate any portions of the Offeror’s proposal into the resulting contract.
1.2 In presenting material in the proposal, the Offeror is advised that quality of information is more important than quantity. Clarity, brevity, and logical organization shall be emphasized during proposal preparation. Statements that the prospective Offeror understands, can comply with, or will comply with, the specifications, and paraphrasing the requirements or parts thereof without supporting information are considered inadequate by the Government, and may result in assessing weaknesses and/or deficiencies.
1.3 The Offeror must include any data that illustrates the adequacy of the various assumptions, approaches, and solutions to problems. Failure to address a specific factor or sub factor clearly may be considered a deficiency. Unnecessarily elaborate brochures or other presentation materials beyond that sufficient to present a complete and effective proposal is neither necessary nor desired.
1.4 The Government advises the Offeror that taking exception or deviating from any term or condition of the RFP may result in the assessment of a deficiency to the proposal.
1.5 Throughout these instructions, a “principal subcontractor” is defined as a subcontractor who provides at least 20% of the proposed total price/cost (excluding the Offeror’s profit/fee), for the contract or provides one or more Key Personnel. “JV Team member” is defined as one of the entities that make up a joint venture (JV) formed for the purpose of responding to this solicitation.
1.6 Questions: Offerors may submit questions requesting clarification of solicitation requirements by emailing Kara Marie Ridgell, Contract Specialist at kara.ridgell1@navy.mil and Amy G. Davis, Contracting Officer, at amy.g.davis@navy.mil. It is required that all questions be received within 10 calendar days of the date this solicitation is issued. Questions received after 10 calendar days may not be answered prior to the proposal due date.
2.0 PROPOSAL FORMAT
2.1 Written proposals must be formatted using a Times New Roman 12 pt. Normal font (no reduction permitted), single-spaced with 1-inch margins all around, and formatted for standard 8.5 x 11 inch paper. Offeror's proposal shall not utilize compressed or condensed spacing between lines or characters in order to circumvent the provided page limits; any proposal that utilizes compressed or condensed spacing will be deemed non-compliant, will not be evaluated, and will be ineligible for award. All pages should be numbered with section and page numbers. When foldout pages are used they must not exceed 11 x 17 inches and will be counted as 1 page. Drawings may be provided separately and may be any size but should be folded to approximately 8.5 x 11 inch standard size and will count as 1 page. Graphs and tables shall be presented in no smaller than a Times New Roman 10 pt. Normal font and should contain a grid, which allows values to be read directly from the graph. Graphic resolution, including such data as tables or charts, shall be no smaller than 10 pt. font and should be consistent with the purpose of the data presented.
2.2 The Offeror shall provide one complete copy of the proposal to the Procuring Contracting Officer (PCO) as electronic files fully compatible with Microsoft 2010 and for information not supported by MS Office products, with the latest Adobe Acrobat reader on a CD-ROM. The Offeror will ensure that the Price/Cost Volume is provided on a separate CD-ROM. Each CD-ROM is to be labeled with Offeror’s name and include “For Official Use Only” and “Source Selection Information – See FAR 2.101 and 3.104.” If a discrepancy exists between the original paper copy of the proposal and the disk copy, the paper copy will take precedence.
3.0 PROPOSAL CONTENT AND VOLUMES
3.1 The Offeror must present proposal information in a manner that facilitates a one-to-one comparison between the information presented and this Proposal Instruction. Proposal information must be structured such that its Volume and paragraph number matches the Proposal Instructions Volume and paragraph number provided in section “Part B Specific Instructions” to which it is responding, although the Offeror may add lower tier subparagraphs. The Offeror must provide any reason(s) it will not provide information for a particular paragraph. The proposal information instructions are structured by paragraph numbers where first, second, third, and fourth parts correspond to the volume, section, and element, etc., in the Offeror’s proposal.
3.2 Each volume of the proposal shall be submitted as one original paper copy and additional copies as specified in the table below. The table below supersedes the copies requested in Block 9 of the Standard Form (SF) 33. All volumes of the original proposal shall be delivered to the address provided in Section 4.0 prior to the closing date/time stated in this solicitation. Page limitations for each volume, if any, are also specified in the table below; title pages and table of contents pages do not count towards the page limit. Any pages submitted exceeding the page limit will be disregarded and will NOT be evaluated.
3.3 Information submitted as an Annex to the proposal includes manuals, specifications, plans, procedures, and policies that exist as an official document of the company or facility, as well as other information requested in Part B Specific Instructions. Page limitations for Annexes, if any, are specified below. The authorized Annexes are summarized in the table below.
| Volume |
| Section |
| Title |
| Page Limitations |
| Copies Required |
| 1.0 |
| Technical Proposal |
1 Original;
3 Paper Copies;
1 Electronic Copy
| 1.1.1 |
| Understanding of the Work - Statement of Work Approach |
| 20 pages |
| 1 Original; |
| 1.2 |
| Key Personnel Resumes/Personnel Qualifications |
| 2 pages per resume |
| 1 Original; |
| 1.3 |
| Management Approach |
| 20 pages |
| 1 Original; |
3 Paper Copies;
1 Electronic Copy
| 2 |
| 2.0 |
| Past Performance |
| No page limit |
| 1 Original; |
2 Paper Copies;
1 Electronic Copy
| 3 |
| 3.0 |
| Price/Cost Proposal |
| No page limit |
| 1 Original; |
2 Paper Copies;
1 Electronic Copy
Annex 1
| Small Business Utilization Strategy |
| No page limit |
1 Original;
2 Paper Copies;
1 Electronic Copy
Annex 2
| Past Performance Supporting Documents |
| No page limit |
| 1 Original; |
1 Paper Copy;
1 Electronic Copy
Annex 3
Past Performance Cross Reference Matrix (CRM)
| 1 page per past performance contract reference |
| 1 Original; |
1 Paper Copy;
1 Electronic Copy
Annex 4
| Small Business Subcontracting Plan |
| No page limit |
| 1 Original; |
1 Paper Copy;
3.4 Each proposal volume shall contain the following information:
| a. Cover and title page |
| b. Title of proposal and proposal number as applicable |
| c. Offeror’s name, address, and POC |
| d. RFP number |
| e. Proposal volume/book number |
| f. Copy number |
| g. Table of Contents (The table of contents must provide sufficient detail to enable easy location of important elements) |
| h. Use tabs and dividers |
3.5 The Offeror shall submit a Cross Reference Matrix (CRM) for the Technical Volume, similar to the example below, to help ensure that all solicitation requirements are addressed and to facilitate the evaluators’ review of the Offeror’s proposal. The CRM should be a single integrated matrix and cross-reference the proposal volumes and paragraphs to specific RFP requirements, as well as other parts of the proposal that contain relevant information. The Offeror’s CRM may be identical to the example below or revised such as to add columns to indicate the page number on which information may be found, identify where other relevant information in the proposal is located, or provide other comments. The CRM does not count against any of the proposal page limitations.
EXAMPLE OF A CROSS REFERENCE MATRIX (CRM)
| Section L – Proposal Instructions |
| Government SOW/PWS |
| Section M – Evaluation Factor |
| Offeror’s Proposal Reference |
| CLIN Reference |
Volume 1 Technical Example: Para 3.1 Note: This column shall address all paragraphs in Sections xx and xy of the SOW/PWS.
| 3A |
| Provide reference to Offeror’s Proposal Volume I – Technical. Example: Refer to appropriate page number in Offeror’s written proposal |
Volume 1 Technical
Volume 1 Technical
4.0 PROPOSAL SUBMISSION:
4.1 Offeror shall clearly mark all packages with the solicitation number. All proposals shall be received at the address below no later than the date and time specified in Block 9 of the SF 33 of the RFP.
4.2 Offeror shall hand carry or submit proposals via United States Postal Service or through a commercial carrier using the address provided below.
4.2.1 Hand carried proposals and commercial carried proposals (e.g. FEDEX, UPS, etc.) shall be delivered, attention to: Kara Marie Ridgell and/or Amy G. Davis to the below address. When submitting hand carried proposals, contact either Kara Marie Ridgell at (301) 757-0841 or Amy G. Davis at (301)757-9773 to coordinate access into the building at time of proposal delivery.
NAVAL AIR SYSTEMS COMMAND
CODE: AIR-2.5.1.3.12. (KARA MARIE RIDGELL)
47060 LILJENCRANTZ ROAD, BLDG 433
PATUXENT RIVER, MD 20670
Solicitation Number: N00421-18-R-0017
4.2.2 United States Postal Service proposal delivery shall be delivered, attention to Kara Marie Ridgell at the following address:
DEPARTMENT OF THE NAVY
AIRCRAFT SUPPORT CONTRACTS DIVISION
ATTN (KARA MARIE RIDGELL) CODE (AIR-2.5.1.3.12)
21983 BUNDY ROAD BLDG 441
PATUXENT RIVER, MD 20670-1127
Solicitation Number: N00421-18-R-0017
4.2.3 Offeror shall not submit proposals by facsimile or electronically via email.
5.0 PROPOSAL PACKAGING:
5.1 The Offeror shall package the proposal volumes in cartons or equivalent packaging containers in the most efficient manner possible grouping like volumes to the maximum extent possible. Each container shall be single person portable. One container shall include all Original Proposal volumes including the original/signed documents submitted as part of Volume 3 Price/Cost.
5.2 Each box should include a packing slip detailing the contents to include the volume number, title, and copy number. Also, each box should be stamped or marked “For Official Use Only” and “Source Selection Information – See FAR 2.101 and 3.104.”
6.0 CLASSIFIED DATA
All proposals must be UNCLASSIFIED.
7.0 SOLICITATION CHANGES
For notice of any changes and additional information provided by the Government for the solicitation, please go to www.FedBizOpps.gov.
PART B SPECIFIC INSTRUCTIONS
Cost or pricing information shall only appear in the Price/Cost volume.
1.0 VOLUME 1: TECHNICAL
1.1. Understanding of the Work
1.1.1 Understanding of the Work Statement of Work Approach
1.1.1.1 Offer shall provide a written narratives of proposed understanding and capability to perform the requirements of 3.3.1.9 EW Systems.
1.1.1.1.1 Provide Description of approach, including a detailed step-by-step procedures and methodology which would be used in accomplishing the SOW.
1.1.1.1.2 Identify any areas that may impact successful performance and potential mitigation steps.
1.1.1.1.3 Provide a description of possible areas to be investigated in researching task area.
1.1.1.2 Offer shall provide a written narratives of proposed understanding and capability to perform the requirements of 3.3.2 Technical Support.
1.1.1.2.1 Provide Description of approach, including a detailed step-by-step procedures and methodology which would be used in accomplishing the SOW.
1.1.1.2.2 Identify any areas that may impact successful performance and potential mitigation steps.
1.1.1.2.3 Provide a description of possible areas to be investigated in researching task area.
1.1.1.3 Describe the Offeror’s strategy to meet requirements of SOW 3.1.2.3.
1.2 Key Personnel
The following definitions apply: A “contingent hire” is an individual who has committed, under a signed letter of intent (LOI), to being employed by the offeror with a stated salary, if the offeror is awarded the contract. A “prospective hire” is an individual that the offeror has committed to hiring if the offeror is awarded the contract whose identity may not be known until after award.
Key Personnel Resumes/Personnel Qualifications For Key Personnel, offeror shall provide a resume of the work assignments, training, etc. that demonstrates the experience and specialized qualifications of each key person proposed. Resumes shall contain, at a minimum, the following information:
· Employee name
· Years of employment experience in chronological order including narrative description of duties and responsibilities
· Current position, title and employer
· Educational history
· Institution name, degree (type and field of study) or certification earned, and year for all degrees or certifications earned
· Specialized training or certifications as it relates to the labor category qualifications and the year training was completed or certification was achieved
· Current level of security clearance and status (i.e. final, interim, pending submission, or n/a)
Offeror shall only submit resumes for the number of key personnel listed in Section C, Paragraph 3.0, Sub-paragraph 3.4, Part 3.4.2.
If the qualification (i.e. education, experience) does not readily or easily compare to the minimum qualification stated in the SOW, the offeror has the burden of proof to show how proposed qualifications meet the minimum qualifications.
1.2.1.1 Only current or contingent personnel may be proposed as Key Personnel. No prospective hire may be proposed as Key Personnel.
1.2.1.2 The Government may check backgrounds to verify experience, education and certifications received.
1.3 Management Approach
1.3.1 Overall Management Approach: Offerors shall address in sufficient detail the following:
1.3.1.1 Proposed management approach to recruiting and retaining personnel to support this specific contract. The approach shall address the ability to meet security clearance level and any Cyber IT/CSWF certifications requirements as defined in Section C, Paragraph 3.0, Sub-paragraph 3.2, Paragraph 3.2.2.1.
1.3.1.2 Proposed lines of responsibility, authority, and communication through which the tasks will be managed.
1.3.1.3 Procedures to be taken to ensure quality, security, deliverable compliance and cost control
1.3.1.4 Processes for managing the contract and Task Orders from start to finish, including the role and authority of the offeror’s Program Manager in comparison to the role played by the offeror’s indirect or corporate office.
1.3.1.5 Identification of potential performance risks and proposed risk mitigation strategies.
1.3.2 Usage of Teaming, Personnel, and Subcontractors: Offerors shall present in sufficient detail the following:
1.3.2.1 Subcontract Management Approach. Prime Contractor shall detail how the team members and/or subcontractors will be managed to ensure cohesive integration into the overall management approach.
1.3.2.2 How the offeror will leverage their strengths to increase value to the customer through technical leadership, quality assurance, and process improvement.
1.3.2.3 How and why selected subcontractor(s) were chosen, which knowledge and skills the offeror will be acquiring through each subcontract, the level of subcontract effort expected
1.3.2.4 How the offeror will maintain control during the performance of work and how the offeror will ensure subcontractors are tasked consistent with their overall and task order proposals.
1.3.2.5 Offerors shall provide all information in its proposal to clearly demonstrate that its proposal meets the solicitation's minimum requirements, to include compliance with DoD Directive 8140.01 and SECNAV M-5239.2.
1.3.3 Small Business Utilization Strategy. As part of the Management Approach, Offerors shall present the following in Annex 1:
1.3.3.1 Small Business (SB) Utilization Strategy: All Offerors shall describe their strategies for utilizing SB Concerns in the performance of this contract, whether as a JV teaming arrangement to achieve a Government established Small Business Participation Goal of no less than 23% of the total subcontract value, inclusive of options and include the following minimum goals: SDB 5%, WOSB 5%, and SDVOSB 3%. Small business offerors should include themselves in addressing their strategies. All goals shall be presented in percentages in relation to total contract value. This strategy is separate from, but shall be consistent with, the SB Subcontracting Plan, if such a Plan is required.
1) Offerors shall specifically identify the small business subcontractors to be utilized in performance of this contract to the maximum extent practical. For each SB concern specifically identified in the proposal, provide the SB concern’s SB subcategory (e.g SDB, SDVOSB, WOSB, HUB Zone, etc.), provide the SB concern’s CAGE code (or, if not registered in System for Award Management (SAM), provide evidence of self-certification in accordance with FAR 19.703(b) as a SB concern), and the NAICS code for the work to be performed by the SB subcontractor.
2) Offerors shall describe the complexity and variety of the work small firms are to perform. For each SB subcontractor specifically identified, the offeror shall identify if the planned subcontract effort is considered to be of low, medium, or high complexity along with a brief rationale.
1.3.4 Transition Plan: The services under this solicitation are vital to the Government and must be continued without interruption. The offeror is required to submit a written narrative delineating a transition plan based on a 30 day period after award that ensures a smooth workplace changeover from an incumbent with no loss of service and minimal loss of corporate knowledge. The plan should take into consideration the following elements as well as any additional elements deemed necessary by the Offeror.
1.3.4.1 Work Turnover: The Offeror shall provide a plan of action to effectively transfer tasked work that is in process at the expiration of the current contract from the incumbent to the successor offeror.
1.3.4.2 Training – The offeror shall provide a plan of action to implement personnel training needed during the transition period to ensure continuity between the services provided by the incumbent and the successful offeror.
1.3.4.3 Risk Mitigation Strategies: The Offeror shall provide a plan of action to mitigate contract performance risks (quality and schedule) encountered during the transition period.
1.3.4.4 Security Requirements to include OPSEC, facility clearances and base access. The offeror shall provide a plan to implement the required security clearances and physical access requirements of the contract during the transition period so that service is not interrupted.
1.3.4.5 Data Transfer – The offeror shall provide a plan of action for the efficient inventory and transfer of program data from the incumbent to the successful offeror.
1.3.4.6 Timeline – The offeror shall provide proposed schedule of events during the transition period.
2.0 VOLUME 2: PAST PERFORMANCE
2.1 General
2.1.1 Sources of past performance evaluation information include information provided by the Offeror in response to the solicitation, information obtained from questionnaires, and any other sources available to the Government, to include, but not be limited to, the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information Systems, Electronic Subcontract Reporting System, or other databases; the Defense Contract Management Agency; and interviews with Program Managers, Contracting Officers, or Fee Determining Officials.
2.1.2 The Offeror shall complete the Past Performance Information Form, Attachment P1, for each past performance reference performed within five years of the solicitation release date. The Offeror shall submit no more than five Past Performance Information Forms as the Prime Contractor, no more than two forms for each principal subcontractor, and no more than two forms for each JV team member. The Offeror shall submit written consent from its principal subcontractor(s) and JV team member(s) that will allow the Government to coordinate any past performance issues directly with the Offeror. If the Offeror does not submit the written consent, the Government will address any past performance issues directly with the principal subcontractor or JV Team member and the Offeror will forfeit the opportunity to participate in any related communications. Consequently, for any principal subcontractor or JV team member that does not provide the written consent, the Offeror shall provide the name, job title, address, phone number, and email address for the subcontractor or JV team member POC with whom the Government may address any past performance issues.
2.1.3 The Offeror shall provide one electronic copy of the Statement of Work (SOW) for each contract reference as Annex 2 and cross reference how each provided contract aligns to the RFP SOW. If the work was performed by a subcontractor, the Offeror shall submit the subcontract’s SOW. The Offeror shall submit a Cross Reference Matrix (CRM), similar to example below. Past Performance CRMs shall be no more than one page per Past Performance reference contract.
| Contract Number (List Order Number, if Applicable) Identified in Attachment P1 |
| N000421-18-R-0017 SOW Paragraph |
| Attachment P1 Reference SOW Paragraph |
3.3.1.1
3.3.1.2
3.3.1.3
3.3.1.4
3.3.1.5
3.3.1.6
3.3.1.7
3.3.1.8
3.3.1.9
3.3.1.10
3.3.1.11
3.3.1.12
3.3.2.1
3.3.2.2
3.3.2.3
3.3.2.4
3.3.2.5
3.3.2.6
3.3.2.7
3.3.3.1
3.3.3.2
3.3.3.3
3.3.3.4
3.3.3.5
3.3.3.6
3.3.3.7
(a) Offerors may choose one of two options when submitting the Attachment P1 – Past Performance Information Form:
(i) Offerors may fill in the information in the Contract Effort Description box of the Attachment, if the response is concise enough to fit within the limitations of the form and the information is viable when the form is printed; OR,
(ii) Offerors may designate within the Contract Effort Description Box “See Continuation Page”, and then submit a second PDF or MS Word document in order to provide the required information for the Contract Description Box of the Attachment P1 – Past Performance Information Form.
2.1.4 The primary source of past performance information will be PPIRS. If a Contractor Performance Assessment Report (CPAR) exists for multiple years for the same contract/order, all periods of performance for that contract/order will be used for evaluation. In the event a CPAR does not exist for a past performance reference, the Offeror shall submit a Contractor Performance Assessment Questionnaire (CPAQ), Attachment P2, to the Program Manager who is the Assessing Official. The Offeror shall provide the instructions to the Program Manager within two weeks of solicitation release. This will allow the customer approximately two weeks to complete and provide their response via e-mail to Kara Marie Ridgell Contract Specialist, at kara.ridgell1@navy.mil AND Amy G. Davis, Contract Officer at amy.g.davis@navy.mil. All CPAQs should be received by the Government concurrently with the Offeror’s proposal submission.
3.0 VOLUME 3: PRICE/COST PROPOSAL
If proposed, subcontractors and/or consultants shall provide the same information required for the prime contractor, unless otherwise noted below.
3.1 Volume Content:
3.1.1 This Volume shall contain the Contract Compliance information specified below as follows:
a. Offeror Summary Table: The Offeror shall complete the table below. The Offeror shall include all subcontractors and team members who will be involved with the performance or management of the contract and list all sites where the work will be performed. If a teaming or subcontracting arrangement is proposed, identify the work share, distribution elements, and ratios that each contractor will perform using the table below. Also provide a definition of the legal relationship between the entities if it is other than a Prime/subcontractor relationship. (Only required from Prime contractor.)
Contractor Name (Indicate Prime, Team Member, or Sub)
| CAGE Code |
| Place of Performance |
| DUNS # |
| % of Total Proposed Price |
| b. | Signed SF33 for basic solicitation and acknowledgment of each amendment, including completion of any RFP clause or provision that requires a fill-in or response. (Only required from Prime contractor). | |
| c. | Signed Representations, Certifications, and Acknowledgements and/or System for Award Management (SAM). | |
| d. | Guarantee the length of proposal validity (for at least 210 days after proposal submission). |
3.1.2 This Volume shall also contain a copy of Section B with the Contract Line Item Number (CLIN) and Sub-CLIN Unit Prices and, for evaluation purposes, the Total Prices filled in using the estimated quantities value in the solicitation and the instructions below. Section B prices shall be provided separately in one digital data copy in MS Office 2010 Excel format on CD-ROM media. (Only required from Prime contractor.) Within all Excel spreadsheets, the Offeror shall use formulas and functions to the maximum extent possible and avoid using output type “value only” cells. If links are utilized, supply those referenced files. Spreadsheets shall not be protected.
3.1.3 All price/cost and price/cost supporting information shall be contained in Section B and the price/cost proposal. No price or pricing information shall be included in any other proposal volume including cover letters. Offerors are responsible for submitting sufficient information to enable the Government to fully evaluate their price/cost proposal.
3.2 Ground Rules and Assumptions:
3.2.1 As this is a competitive acquisition with adequate price competition anticipated, certified cost or pricing data in accordance with FAR 15.403-1 is not required. However, in the event that adequate price competition does not exist after receipt of proposals, the Government reserves the right to request additional cost or pricing data as necessary from both the Offeror and subcontractors. Further, the Offeror may be required to provide a Certificate of Current Cost or Pricing Data prior to award, pursuant to FAR 15.406-2.
3.2.2 The Offeror shall provide sufficient information to support its price/cost as well as an explanation of all ground rules and assumptions that affect the price/cost estimates.
3.3 Price/Cost Information:
3.3.1 Offerors shall submit their fully completed price/cost proposal utilizing the Cost Summary Format (Attachments P6 and P7 for the Prime and Subcontractor respectively). The spreadsheet shall be formatted on letter size (8.5 X 11) paper and shall be unprotected and unlocked, with formulae intact to show mathematical operations. The Offeror shall use the CLIN Summary tab to breakout total proposed costs by CLIN.
3.3.2 RESERVED
3.3.3 To facilitate the establishment of streamlined task orders, the offeror shall complete Attachment P4, Streamlined Rates for Order Pricing.
3.3.3.1 Composite Fully Burdened Rates: Attachment P4 spreadsheet will consist of composite fully burdened rates for each of the key and non-key labor categories, inclusive of fee. Fully burdened rates are defined as direct labor rates plus all applicable burdens, to include indirect rates, fees, and subcontractor pass-through costs where applicable. These rates will be incorporated into Section B of the contract. The Government will utilize the rates when developing estimated labor ceilings for task orders by using the estimated hours per labor category multiplied by the composite rates found in Section B. (Only required from Prime contractor.)
3.3.3.2 Fixed Fee (Non-Performance Based/Level of Effort): Fixed Fee will be calculated based on fee per hour. The fee per hour is the total fee proposed for all ordering periods divided by the total number of hours for all ordering periods. The offeror shall identify the Fixed Fee in Attachment P4, Streamlined Rates for Order Pricing. The spreadsheet shall be formatted on letter size (8.5 X 11) paper and shall be unprotected and unlocked, with formulae intact to show mathematical operations. The rates will be incorporated into Section B of the contract. (Only required for Prime Contractor)
3.3.3.3 Labor Tripwire: Offerors shall complete Attachment P5 detailing the fully burdened labor rates per ordering period, hours to be performed per ordering period and total annual salary per ordering period for all prime contractors and their subcontractor personnel. This shall be provided for both on-site and offsite locations. Fully burdened labor rates are defined as direct labor rates plus all applicable burdens, to include indirect rates, fees and subcontractor pass-through costs where applicable. For subcontractor labor, the fully burdened labor rate shall be inclusive of any pass-through charges (e.g. subcontractor handling, fixed fee on subcontractor labor, etc.) applied by the prime contractor. The total annual salary is the total of the hours performed applied to the fully burdened labor rate. Proposed fully burdened labor costs may be subject to the NAVAIR labor tripwire in Section M. Offerors that propose a fully burdened per employee labor cost exceeding the labor tripwire shall provide rationale in their cost proposal narrative section that justifies the reasonableness of the tripwire costs for the applicable employee. If a proposed employee’s fully burdened labor rate exceeds the labor tripwire but the contractor chooses to apply a lower rate, then the contractor shall propose an H-clause to identify the unallowability of the employee’s fully burdened rate to exceed the labor tripwire to the contract.
3.3.4 The Government is not soliciting any investments. However, in order for the Government to properly assess a proposed price/cost that appears low due to a corporate decision to absorb costs, e.g., lower than usual burdens or rates, the Offeror shall fully identify and explain any such investments.
3.3.5 Direct/Indirect Rates: The Offeror shall submit Forward Pricing Rate Agreements (FPRAs), Collective Bargaining Agreements (CBAs), and Area Wage Determinations (AWDs) as applicable for all proposed personnel. The Offeror shall identify whether the labor rates proposed are FPRAs, CBAs, AWDs, ACO/DCAA recommended rates (FPRRs), or Offeror proposed rates (FPRPs). The Offeror shall propose in compliance with the current hourly rate set forth in the Department of Labor Wage Determination as applicable. The Offeror shall provide Defense Contract Audit Agency (DCAA) Information/Payroll Verification information as follows: A DCAA point of contact, with a current e-mail address, must be provided for the prime and each subcontractor. The Offeror and proposed subcontractors shall provide: the most current DCAA Provisional Billing Rate Approval Letter, DCAA Final Billing Rate Approval Letter, and/or DCAA Forward Pricing Rate Agreement recommendation; payroll verification for currently employed proposed personnel; and any other information necessary to substantiate the rates proposed. Payroll verification shall consist of a form containing the title, direct labor rate, and a signed certification by an authorized representative of the company that the information contained in the form is correct. For key personnel contingent hires, the offeror shall provide contingent offer letters outlining salary information for contingent hire employees. For any prospective hires for non-key labor categories, provide information to substantiate the rates proposed. All contingent hires shall have a letter of intent submitted under the Cost Volume. Any proposed consultants shall have a consultant agreement substantiating the rates proposed. If a composite rate or other pricing methodology (e.g. cost estimating relationships) is utilized, the Offeror shall demonstrate how those rates were developed. Subcontractors and team members shall provide this information either separately or included in the Offeror’s submission of this document.
3.3.5.1 If any of the rates utilized by the Offeror or any subcontractors differ from the DCAA information and/or payroll verification, a justification shall be provided for the difference. If DCAA has not reviewed the rate information for an Offeror or one of its subcontractors, the Offeror must submit a detailed justification of the proposed direct and indirect rates. Offerors and subcontractors shall provide the last three (3) years of actual indirect and escalation rates. The Government may compare a prospective Offeror’s labor category rate to the average labor rate from industry.
3.3.5.2 As this requirement contains cost type CLINs, the Offeror shall also provide documentation verifying that it has a DCAA approved Cost Accounting System or state that its Cost Accounting System has not been approved by DCAA, pursuant to the requirement at FAR 16.301-3(a)(3). It is the prime Contractor’s responsibility to ensure that each subcontractor with a proposed cost-reimbursement subcontract type has an adequate accounting system. If a subcontractor does not have an adequate accounting system, they should be priced on a Firm-Fixed-Price (FFP) or Time-and-Materials (T&M) basis. The prime Contractor shall provide a list of all subcontractors/consultants by name and shall specify the type of subcontract (i.e., CPFF, FFP, T&M, etc.). For those subcontractors who will be priced on a cost-type basis, documentation verifying possession of a DCAA approved Cost Accounting System shall be provided.
In addition, the Prime Offeror shall provide the following:
Contractor’s Estimating System: Date determined acceptable by ACO (DFARS 215.407-5);
Contractor’s Accounting System: Date determined adequate by CAO/DCAA (FAR 16.301-3);
Disclosure Statement: Date determined current, accurate and complete by ACO (FAR 42.302(a)(11);
Contractor Purchasing System: Date determined to be approved by the ACO (FAR 42.302(50), FAR 44.304);
Property System: Date reviewed for acceptability by ACO (FAR 45.105).
3.3.6 For all Cost type CLINS (e.g., CPFF, Cost – No Fee), under the solicitation, the Offeror shall fully disclose the buildup of price/cost of each CLIN.
3.3.7 When completing the Cost Summary Spreadsheets (Attachments P6 and P7), the Offeror shall not utilize any fully burdened hourly rates when pricing the labor of its employees.
3.3.8 Offeror’s labor classification should cross reference to Department of Labor (DOL) wage determination classifications as much as possible.
3.3.9 This solicitation contains some labor categories that are subject to the Service Contract Act of 1965, as amended, and to FAR clause 52.222-41, contained in Section I of this solicitation. Offerors shall propose employee’s wages for the labor categories marked SCA in accordance with the Wage Determination shown under Attachment 6. As part of the Price/Cost proposal, the Offeror shall furnish the names of the proposed labor categories and the corresponding labor categories from the attached Wage Determination as well as documentation of compliance with the minimum monetary wages and fringe benefits for service employees as specified in the Wage Determination (provided as an attachment in Section J of this solicitation). Offerors are required to submit a total compensation plan setting forth salaries and fringe benefits proposed for employees (including temporary and part time employees) who will work under the contract and are subject to the Act, and explain how the compensation plan complies with the Service Contract Act.
3.3.10 RESERVED
3.3.11 Offeror shall provide a narrative that addresses any assumptions made during the preparation of the Price/Cost proposal and discuss the basis for the cost elements listed below:
· Direct labor rates by category. The Offeror is required to submit labor rates for all proposed current, contingent, and prospective hire individuals. If composite or category averages are proposed, provide a breakdown of how rates are developed. If necessary provide a narrative to describe derivation of labor rates, use of uncompensated overtime, pools to which indirect rates are applied, historical /provisional billing rates for indirect rates for the last 3 years and description, and amount of proposed other direct costs. If the Offeror requires the use of consultants in performance of the effort, the consultant cost shall be captured under the appropriate labor CLIN not the ODCs CLIN.
· Escalation on labor. Offerors, including subcontractors, shall address escalation for all labor categories, and shall provide rationale for the specific escalation rate used. Offerors that do not include escalation, or an explanation as to why it is not included, may be considered unrealistically low and may have their proposals adjusted by the Government to include escalation.
· Historical indirect costs (e.g., Overhead, Fringe Benefits, General & Administrative (G&A), etc.) for the past three years.
· Information needed to explain the offeror’s estimating practices.
· Profit/Fee: Identify profit/fee rate and total amounts proposed and identify the various cost elements to which the profit/fee is being applied. Profit, Base, Award, and Incentive fee rates, as applicable in Section B, must be clearly distinguishable. Profit/Fee shall not be applied to ODCs.
· Other Direct Costs (ODCs) by specific cost element (e.g., Travel & Material). Reimbursement for Travel will be in accordance with the Joint Travel Regulations. If the Offeror proposes burdens on the Government provided ODC estimates, the Offeror shall provide a percentage breakdown of the Offeror’s indirect costs and burdens added to the Government estimates for any and all Cost Reimbursable CLINs in Section B.
· When the Offeror elects to claim Cost of Money (COM) as an allowable cost, the Offeror must submit a COM form and show the calculations of the proposed amount.
3.4 Total Professional Compensation Plan:
3.4.1 The Offeror shall provide a Total Compensation Plan in accordance with FAR 52.222-46 and FAR 22.1103 for each proposed professional employee. For evaluation purposes, see Section C, paragraph 3.4.7 for the labor categories deemed to be professional. The Plan shall include, but not limited to, the following items:
a. The proposed direct labor rate for each professional employee proposed;
b. The total cost of the proposed fringe benefits package for each professional employee proposed, including:
i. list and brief summary of the benefits that make up the fringe package (e.g. vacation time, sick leave, stock, incentive plans, family leave, life insurance, severance pay, bonus plans, health insurance, holidays, location allowance, retirement benefits); and
ii. an itemization of the benefits that require employee contributions, and the amount of that contribution as a percentage of the cost of the particular benefit; and
c. Data, such as recognized national and regional compensation surveys and studies of professional, public and private organizations, used by the Offeror in establishing the total compensation structure.
3.5 Government Furnished Information
3.5.1 ODCs
The Government’s estimates for ODCs for the prime and all subcontract efforts, unburdened are listed below:
ODCs associated with CPFF LOE and CPFF Completion – CLIN 0007
| CLIN 0013 |
| Travel |
| Material |
| Total |
| Year 1 |
| $2,500,000.00 |
| $2,500,000.00 |
| $5,000,000.00 |
| Year 2 |
| $2,557,500.00 |
| $2,557,500.00 |
| $5,115,000.00 |
| Year 3 |
| $2,616,322.50 |
| $2,616,322.50 |
| $5,232,645.00 |
| Year 4 |
| $2,676,497.92 |
| $2,676,497.92 |
| $5,352,995.84 |
| Year 5 |
| $2,738,057.37 |
| $2,738,057.37 |
| $5,476,114.74 |
| Total |
| $13,088,377.79 |
| $13,088,377.79 |
| $26,176,755.58 |
The offeror shall utilize the estimated amounts provided by the Government for ODCs and include all applicable burdens. If it is the contractor’s accounting practice to apply (and invoice for) burdens with regards to ODCs, then the contractor shall propose the ODC amount plus the addition of the applicable burdens. If the contractor chooses not to burden ODCs, then the contractor shall propose an H-clause to identify the unallowability of burden cost to the contract. The costs in the table above do not include cost for SOW 3.1.2.3 Industrial Support Services. NO FEE SHALL BE APPLIED TO ODCs.
3.5.2. CPFF Non-Performance Based/LOE
The Government estimate is 986,400 hours for the entire work effort, inclusive of options. A work-year is defined as 1920 hours exclusive of holidays and leave. For evaluation purposes, the Offeror shall propose the labor categories/hours as outlined in Attachment P8.
3.5.3 SB Subcontracting Plans: The Large Business Offeror shall provide its SB Subcontracting Plan conforming to the requirements of FAR 19.7 and DFARS 219.7 as Annex 3. The Subcontracting Plan of the successful Offeror(s) will be reviewed and approved by the PCO prior to contract award. See FAR 19.702(a) (1) Statutory Requirements, regarding failure of the apparent successful Offeror to negotiate and submit a Subcontracting Plan acceptable to the Contracting Officer. The successful Offeror’s approved Subcontracting Plan will be incorporated into the resultant contract.
3.5.4 Incumbent Information
The incumbent contractor is:
BAE Systems Technology Solutions & Services, Inc.
520 Gaither Road Rockville, MD 20850
The incumbent subcontractors are:
AV3, Inc.
Delphinus Enterprises KITCO Fiber Optics
MERCOM
SERCO
Tecnico Corporation Valkyrie Enterprises, LLC
3.5.5 Industrial Space
Historically, the industrial space utilized is approximately 15,000 square feet. The industrial space is used for storage, integration, and testing of electronic equipment and systems associated with assigned projects. Historically, the industrial space has been configured to provide distinct and securable areas for material receiving and inspection, equipment testing, storage awaiting buildup, buildup area (including foundation, cabinet, and cable buildup), machine shop for fabricating of pieces and parts, storage for equipment awaiting integration and testing, and storage of completed systems.
3.5.6 Quality Control Inspector
3.5.6.1 The Offeror shall propose the Quality Control Inspector Labor Category as required by Statement of Work paragraph 3.4.2 and Section L paragraph 3.5.2 above. The Quality Control Inspector shall be proposed as a Service Contract Act (SCA) labor category.
3.5.6.2 Quality Control Inspector is an allowable labor category per Department of Labor: SCA Directory of Occupation, Fifth Edition. However, Wage Determination 2015-4279, Revision 3, dated 25 July 2017 does not list this labor category.
3.5.6.3 The Offeror shall propose the Direct Labor for the Quality Control Inspector in accordance with 29 C.F.R §4.6(b).
SECTION M - EVALUATION FACTORS FOR AWARD
The following have been modified:
SECTION M
M - 1 EVALUATION FACTORS FOR AWARD (SERVICES) (10 April 2018)
PART A: GENERAL INFORMATION
1.0 GENERAL
The Government expects to select one Offeror…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .