N0016720R0009 Amendment 2 Final.pdf

PDF 220 KB Posted

Attached to
Propulsor Demonstration Hardware
Solicitation number
N0016720R0009
Issued by

About this file

This is a request for proposal for propulsor demonstration hardware engineering and fabrication services. The Naval Surface Warfare Center Carderock Division is seeking proposals to provide manufacturing design drawings, engineering, fabrication, inspection, and assembly of prototype propulsors, shafting and bearing components, mechanical design specifications, and manufacturing plans to support submarine programs. The solicitation requests proposals for a cost plus fixed fee completion contract with a five year ordering period. Offerors must propose costs for the first delivery order and sample task 3, and evaluations will be based on best value. The deadline for proposals is February 10, 2020.

View the file

Other files

File Type Posted
N0016720R0009 0004.pdf PDF
Attachment 7 - Past Performance Reference (Rev 1).docx DOCX document
S9245-A4-TSM-010_REV00 30_DEC_2018-Part(2).pdf PDF
Attachment 13 - Questions and Answers 20R0009 Round 2.pdf PDF
Attachment 14 - Questions and Answers 20R0009 Round 3.pdf PDF
N0016720R0009 0001.pdf PDF
Attachment 4 - Sample 3_Rev A.pdf PDF
Attachment 12 - Questions and Answers 20R0009 Final.pdf PDF
CDRL A013_Meeting Minutes.pdf PDF
CDRL A001_TDP-Worksheet.pdf PDF
Attachment 2 -Sample 1_Requirement.pdf PDF
Attachment 10 - QASP.pdf PDF
CDRL A003_Test Plan_S.pdf PDF
Attachment 6 - Sub Plan Coversheet 19R0009.docx DOCX document
Attachment 9 - DD254.pdf PDF
Attachment 3 - Sample 2_Requirement.pdf PDF
CDRL A004_MSR_S.pdf PDF
N0016720R0009 Final.pdf PDF
CDRL A005_Engr Change Proposal_S.pdf PDF
CDRL A006_TestInspecton Report_S.pdf PDF
CDRL A002_Technical Report_S.pdf PDF
CDRL A011_Program Review Agenda Revised.pdf PDF
Responses to Synopsis Questions.pdf PDF
Attachment 1 DO1_Requirement.pdf PDF
CDRL A001_TDP_S.pdf PDF
Attachment 11 - GFP Template.xlsx XLSX spreadsheet
CDRL A008_Quality Status Report_R.pdf PDF
CDRL A007_Material Certification_S.pdf PDF
Attachment 4 - Sample 3_Requirements.pdf PDF
CDRL A012_Program Review Docs.pdf PDF
Attachment 8 - Past Performance Questionnaire.docx DOCX document
CDRL A010_Project Planning Chart.pdf PDF
Attachment 5 - Key Personnel Qualifications.pdf PDF
CDRL A014_GFP Inventory Revised.pdf PDF
CDRL A009_MER_S.pdf PDF
Attachment 7 - Past Performance Reference.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 2 is being provided to answ er further questions received from industry and to revise Sections C 5.3.1 and Section L.2.3.5.

1. CONTRACT ID CODE PAGE OF PAGES

U 1 23

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jan-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0016720R0009

X 9B. DATED (SEE ITEM 11)

11-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jan-2020

CODE

NAVAL SURFACE WARFARE CENTER CARDEROCK

LINA NGUYEN

301-227-1620, LINA.K.NGUYEN@NAVY.MIL

9500 MACARTHUR BLVD.

WEST BETHESDA MD 20817-5700

N00167 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0016720R0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

SOW

STATEMENT OF WORK

Statement of Work (SOW) for Engineering and Fabrication Services for Propulsor Demonstration Hardware, Naval Surface Warfare Center, Carderock Division.

1. BACKGROUND. The Advanced Propulsor Management Office (Code 808) in the Naval Architecture and Engineering Department (Department 80) of the Naval Surface Warfare Center, Carderock Division (NSWCCD) is responsible for managing the Research and Development (R&D), design, testing, and delivery of US Navy submarine propulsors. The APMO requires the design and development for prototype propulsors, shafting and bearing components, mechanical design specification, and manufacturing plans to support the COLUMBIA Class Submarine Program Office (PMS 397), the VIRGINIA Class Submarine Program Office (PMS 450), and future R&D activities towards the next generation of propulsor and shafting systems.

2. SCOPE. The objective of this procurement is to provide manufacturing design drawings, engineering, fabrication, inspection, and assembly of prototype propulsor, shafting and bearing components as well as the equipment needed to support propulsor Research & Development, testing and evaluation (RDT&E) for Department 80. These manufactured articles include scaled and full scale hardware, as well as hardware suitable for at-sea demonstration. Additionally, this contract maybe used to support vendor qualification of fleet hardware.

The following applicable Product Service Codes (PSC) for this requirement are: 2010 Ship and Boat Propulsion Components, AC22 R&D – Defense System: Ships (Applied Research/Exploratory Development), AC34 R&D

– Defense Systems: Ship (Engineering Development), AC35 R&D – Defense System: Ship (Operations Systems Development), AD22 R&D – Defense Other: Services (Applied Research/Exploratory Development), AD24 R&D – Defense Other: Services (Engineering Development), H230 Equipment and Material Testing – Mechanical Power Transmission Equipment, H320 Inspection – Ship and Marine Equipment and J020 Maintenance, Repair, and Rebuilding of Equipment, Ship and Marine Equipment. The PSC will be defined at the order level.

3. REFERENCES

3.1. MIL-STD-31000B: Technical Data Packages, dated 31 October 2018

3.2. S9074-AR-GIB-010/278: Requirements for Fabrication Welding and Inspection, and Casting Inspection and Repair for Machinery, Piping, and Pressure Vessels, dated 01 August 1995, including Change A, dated 14 February 2013

3.3. S9074-AQ-GIB-010/248: Requirements for Welding and Brazing Procedure and Performance Qualification, dated 01 August 1995

3.4. T9074-AS-GIB-010/271: Requirements for Non Destructive Testing Methods, dated 15 May 1995

3.5. MIL-STD-2035A SH: Non Destructive Testing Acceptance Criteria, dated 15 May 1995

3.6. DOD 5000.64: Accountability and Management of DoD Equipment and Other Accountable Property, dated 09 May 2011

3.7. SPEC EB-4941: QUALIFICATION OF GLASS REINFORCED PLASTIC COMPOSITE MATERIAL

SYSTEMS, dated 30 September 2011

3.8. SAE AS9100 Revision D: Quality Management Systems - Requirements for Aviation, Space and

Defense Organizations, dated 01 October 2016

3.9. ASME Y14.5-2018: Dimensioning and Tolerancing, dated 2018

3.10. ASME B30.20-2018: Below The Hook Lifting Devices, dated 2018

3.11. DD Form 1694: Request for Variance, dated April 2017

3.12. ISO 9001 (2015) /ISO 9002 (2016)

4. GENERAL REQUIREMENTS

4.1. Engineering and Design. The contractor shall develop conceptual designs, execute manufacturing engineering and production feasibility studies, and develop manufacturing design drawings and manufacturing plans.

4.2. Manufacturing. The contractor shall furnish all labor and material necessary to fabricate, assemble, inspect hardware and provide the necessary technical documentation in the performance of DOs, except for those materials, equipment, and information to be provided by the Government as specified in individual DOs.

4.3. Facilities, Equipment, and Materials Requirements

4.3.1. Email Encryption. The contractor shall maintain equipment to receive and send encrypted emails compatible with Department of Defense (DoD) Navy Marine Corps Intranet (NMCI) encryption via public key infrastructure (PKI).

4.3.2. Fabrication Facilities. The contractor shall maintain fabrication facilities and equipment, such as Computer Numerically Controlled (CNC) machines, weld assembly facilities, manual machine tools, hand tools, inspection capabilities, lifting facilities, and paint shop (for surface preparation and coding).

4.3.3. Metallic Fabrication. The contractor shall maintain facilities to fabricate metal components from materials such as Aluminum, Nickel Aluminum Bronze (NAB), Inconel, Monel, Stainless Steel, and Steel. Fabrication shall include: CNC contour machining of sculpted surfaces, precision turning, milling, thread tapping/thread milling, welding, inspection, painting, and assembly of components.

4.3.4. Composite Fabrication. The contractor shall maintain facilities to perform fabrication of composite and multi-material (metallic/composite hybrid) components. Fabrication shall include:

CNC contour machining of sculpted surfaces, precision turning, milling, thread tapping/thread milling, bonding, inspection, painting, and assembly of components. Composite manufacturing shall be in accordance with reference 3.8 and include glass reinforced plastic (GRP) and carbon fiber reinforced plastic (CFRP) composite structures.

4.3.5. Component Handling. The contractor shall maintain a manufacturing facility capable of accepting, handling, storing, and manufacturing components procured under individual delivery orders. The following information for handling requirements serves only as a guidance:: orders may require handling of components up to 75 tons and approximate maximum dimensions of 240 in x 240 in x 102 in.

4.3.6. Material Requirements. The contractor shall provide the raw materials necessary to fabricate the propulsor and components.

5. TECHNICAL REQUIREMENTS

5.1. ENGINEERING SERVICES FOR MANUFACTURING

5.1.1. Design Engineering Deliverables/Lists. The contractor shall produce a Technical Data Package (TDP) to include Computer-Aided Design (CAD) manufacturing drawings, 2D/3D Models, and associated textual information for the development and fabrication of propulsor systems (e.g.

mounts, bearings, test stands, and lifting fixtures), propulsor test components, and assembly systems (CDRL A001).

5.1.2. Manufacturing Engineering and Manufacturing Feasibility Studies. The contractor shall execute manufacturing engineering and conduct manufacturing feasibility studies to assess the manufacturability of propulsors, bearings, shafts and associated hardware. To support the execution of these efforts, the contractor shall review and assess concept designs and/or manufacturing drawings and models, identify design and/or production process issues, design and execute manufacturing feasibility demonstrations, and recommend design and/or production process changes to improve manufacturability (CDRL A002).

5.1.3. Test Plans and Validation Reports. The contractor shall produce and deliver test plans (CDRL A003) and corresponding reports validating that the manufactured products comply with the requirements of the drawings.

5.1.4. Manufacturing Services. The contractor shall provide on-site engineering services at manufacturing facilities. The contractor will perform in-process inspection and verification of technical characteristics, manufacturing oversight and troubleshooting, provide field manufacturing capability and modify engineering plans when needed (CDRL A004).

5.1.5. Engineering Change Proposals (ECP). The contractor shall prepare and submit ECPs based on the Manufacturing Engineering and Manufacturing Feasibility Studies (paragraph 5.1.2), Manufacturing Services (paragraph 5.1.4), and Inspections and Test Services (paragraph 5.2.6). The contractor shall prepare and submit Notices of Revision (NOR) to request changes to drawings/documentation and Rough and Final Machining (paragraph 5.2.1). All contractor ECPs shall be submitted in accordance with reference 3.12 (CDRLs A005).

5.1.6. Lifting Equipment. The contractor shall design specialized lifting and handling equipment for large propulsors in accordance with reference 3.11 and with all applicable regulations (CDRL A001 and TDP Option Selection Worksheet).

5.2. MACHINING, ASSEMBLY, AND INSPECTION SERVICES

5.2.1. Machining. The contractor shall perform rough and final CNC machining and manufacturing services associated with the fabrication of the propulsor components as prescribed in the DOs’ Government Furnished Information (GFI) Conceptual Designs and in accordance with both the facilities requirements (paragraph 4.3) and the standards set forth in this section.

Typical multi‐axis surface profile milling and turning tolerances are:

Nominal Part Size

Tolerance (in, +/-) Diameter (in)

Height (in)

Weight (lbs)

0-24 6 500 0.003 24-48 12 3000 0.005

48-180 24 30000 0.008 180-240 60 70000 0.01

5.2.2. Instrumentation. The contractor shall install hardware and sensors in support of model test measurement systems (e.g. accelerometers, hydrophones, and other embedded instrumentation).

5.2.3. Assembly.. The contractor shall perform weld assembly of NAB, Inconel, Monel, Stainless Steel, and Steel components. The contractor shall perform Gas Tungsten Arc (GTA) and Gas Metal Arc (GMA) welding in accordance with references 3.2, 3.3, and 3.4.

5.2.4. Surface Preparation and Painting. The contractor shall perform surface preparation and painting as specified under the individual DOs.

5.2.5. Manufacturing Drawings. The contractor shall develop and deliver CAD-generated manufacturing/engineering drawings in accordance with ASME Y14.5 (reference 3.10). The contractor shall provide applicable CAD models suitable to be used directly with CAM software for manufacturing (CDRL A001 and TDP Option Selection Worksheet).

5.2.6. Inspection and Test Services

5.2.6.1. The contractor shall perform Non-Destructive Testing (NDT) to include Ultrasonic, Dye Penetrant, and Magnetic Particle Testing in accordance with references 3.2, 3.4, 3.5, and 3.6 (CDRLs A006).

5.2.6.2. The contractor shall perform geometry inspections utilizing Laser Tracker systems (CDRLs A006).

5.2.6.3. The contractor shall perform Geometry metrology inspections using a Coordinate Measuring Meaching (CMM) (CDRLs A006).

5.2.6.4. The contractor shall design, build, and use hard gauging in accordance with reference

3.10 (ASME Y14.5) and reference (ASME Y14.43) (CDRLs A001).

5.2.6.5. The contractor shall develop and provide Inspection Reports in accordance with engineering drawings and manufacturing plans, highlighting all non-conformances

(CDRL A006).

5.2.6.6. The contractor shall develop or provide Material Certifications for materials identified in the drawings (CDRL A007).

5.3. CONTRACTOR MANAGEMENT AND QUALITY CONTROL

5.3.1. Quality Control (QC) Program. The contractor shall conduct all work in accordance with reference 3.8 or reference 3.12, applicable to all types and phases of engineering and machining

(CDRL A008).

5.3.2. Monthly Report. The contractor shall provide monthly progress reports containing a list of work in progress, work completed, deliverables, and expenditures; and Progress Planning Charts (CDRLs A004, A009, and A010).

5.3.3. Meetings. The contractor shall host meetings at manufacturing facilities. The contractor shall provide agendas and meeting minutes (CDRLs A011 and A013).

5.4. PROGRAM MANAGEMENT AND PLANNING

5.4.1. General Services. The contractor shall provide the project management necessary for the efficient and effective administration and control of work performed under the individual DOs. The contractor shall manage deliveries to meet cost, schedule, and performance of each DO. These DOs will include standard, urgent, or complex situations in fulfillment of the customer’s needs. The contractor shall provide scheduling, tracking, reviewing, and estimating of projects assigned. The contractor shall resource material, facilities, personnel, and services for assigned projects. The contractor shall schedule, prioritize and track all projects, and report any discrepancies or conflicts to the designated Government representative for resolution.

5.4.2. Program Management Review (PMR)

5.4.2.1. Program Management Reviews. The contractor shall plan, host, attend, and conduct meetings and formal reviews as specified in the individual DOs. The contractor shall prepare and submit a proposed conference agenda in accordance with (CDRL A011).

The contractor shall conduct PMRs at Government or Contractor facilities or by other means (e.g. teleconference) as agreed to by the COR. Reviews requiring demonstration and/or examination of equipment shall be conducted at the contractor’s facility. The Government reserves the right to schedule PMR during any DO PoP, modify the PMR, or cancel any PMR.

5.4.2.2. Program Review Documentation. The contractor shall prepare agendas and conference presentation materials and provide minutes and reports following each PMR in accordance with (CDRLs A012 and A013). The contractor shall address the following topics at each PMR:

5.4.2.2.1. Pertinent technical, schedule, and cost aspects of each authorized technical effort under individual DOs, including an overview of the work to be accomplished in the next month;

5.4.2.2.2. Current and anticipated technical and implementation risks;

5.4.2.2.3. Each subcontractor’s technical progress on all DOs;

5.4.2.2.4. Status of all Government Furnished Property (Received, In Custody, Shipped, Disposed Of);

5.4.2.2.5. Substantiation of assumptions made and methodologies used in arriving at recommendations or conclusions; and

5.4.2.2.6. Documentation of action items; assignment of responsibility for completion and due dates shall be determined prior to adjournment of all PMRs.

5.5. LOGISTICS

5.5.1. Packing, Handling, Storage, and Transportation (PHS&T)

5.5.1.1. The contractor shall complete all required delivery documentation, prepare materials/assembly for delivery, and deliver equipment to destinations which can include: CONUS and OCONUS.

5.5.1.2. The contractor shall be able to receive and store CONFIDENTIAL documents, CONFIDENTIAL computer files, and CONFIDENTIAL hardware for each order, as identified. Stored material shall be tagged with a specific job and the part numbers associated with installation drawings and shall be stored separately from delivery materials not associated with this contract.

5.5.1.3. For unique materials with non-standard lifting requirements, the contractor shall manufacture, rent, or otherwise procure lifting equipment in accordance with reference

3.11 and all local and state regulations to load/unload, move, and lift the materials.

5.5.1.4. The contractor shall prepare, maintain, and provide records of DD Form 1149 shipping documentation for all Contractor-Acquired Material (CAM) or Contractor-Acquired Property (CAP) transferred to the Government, and GFP transferred to the Contractor by the Government. The contractor shall ensure that signed DD Form 1149s are obtained from the receiving activity and kept for record. All DD Form 1149s shall include contract number and CLIN/SLIN number, and be made available for inspection by the Government upon demand. The contractor shall follow In Transit Guidance outlined in accordance with reference 3.7 (DOD 5000.64).

5.5.2. Government Furnished Property (GFP)

5.5.2.1. General. The Government will provide GFP required by the contractor for performance of this contract as defined in individual DOs. The contractor shall provide a quarterly inventory of GFP (CDRL A014). All GFP shall be returned to the Government as specified in the individual DO.

5.5.2.2. Government Furnished Information (GFI). At the completion of the contract all GFI and any unclassified\classified data derived from GFI shall be returned to the Government within 60 days.

5.5.3. Contractor Acquired Material (CAM). The contractor shall identify items required by the contractor for the performance of this contract and not identified in an existing DO to the COR promptly. The requirement will be assessed by the COR on a case by case basis, and any changes in the requirement will be provided via a contract/DO modification.

5.5.4. Disposition of Materials. Upon completion of the PoP of each DO, all material associated with this contract that is purchased by the contractor, billed to the Government, and not depleted during the performance of the contract shall become the property of the Federal Government. The contractor shall transfer all materials not depleted to the COR, as specified within the individual DOs, by way of a Material Inspection and Receiving Report (DD Form 250) and a DD Form 1149.

Disposition shall follow instructions outlined in Section I, FAR 52.245-1 Alt I, GFP clause, unless otherwise directed via contract/DO modification or at the direction of the PCO.

6. SECURITY REQUIREMENTS

6.1. Personnel Security Clearance. All key and non-key personnel shall hold a CONFIDENTIAL clearance.

6.2. Facility Security Clearance. The contractor shall have the capability to handle and store information, models, and data up to the CONFIDENTIAL level. As the manufactured parts will largely be CONFIDENTIAL, the computer systems used to program the CNC machines, the CNC machine computers, and any computer systems used for geometric inspections shall be certified and approved for CONFIDENTIAL use by the security authority identified in the DD Form 254.

6.3. System Security Plan and Plans of Action and Milestones (SSP/POAM) Reviews

6.3.1. Within thirty (30) days of contract award, the Contractor shall make its System Security Plan(s) (SSP(s)) for its covered contractor information system(s) available for review by the Government at the contractor’s facility. The SSP(s) shall implement the security requirements in Defense Federal Acquisition Regulation Supplement (DFARS) clause 252.204-7012, which is included in this contract. The Contractor shall fully cooperate in the Government’s review of the SSPs at the Contractor’s facility.

6.3.2. If the Government determines that the SSP(s) does not adequately implement the requirements of DFARS clause 252.204-7012 then the Government shall notify the Contractor of each identified deficiency. The Contractor shall correct any identified deficiencies within thirty (30) days of notification by the Government. The contracting officer may provide for a correction period longer than thirty (30) days and, in such a case, may require the Contractor to submit a plan of action and milestones (POAM) for the correction of the identified deficiencies. The Contractor shall immediately notify the contracting officer of any failure or anticipated failure to meet a milestone in such a POAM.

6.3.3. Upon the conclusion of the correction period, the Government may conduct a follow-on review of the SSP(s) at the Contractor’s facilities. The Government may continue to conduct follow-on reviews until the Government determines that the Contractor has corrected all identified deficiencies in the SSP(s).

6.3.4. The Government may, in its sole discretion, conduct subsequent reviews at the Contractor’s site to verify the information in the SSP(s). The Government will conduct such reviews at least every three

(3) years (measured from the date of contract award) and may conduct such reviews at any time upon thirty (30) days’ notice to the Contractor.

6.4. Compliance to NIST 800-171

6.4.1. The Contractor shall fully implement the CUI Security Requirements (Requirements) and associated Relevant Security Controls (Controls) in NIST Special Publication 800-171 (Rev. 1) (NIST SP 800- 171), or establish a SSP(s) and POA&Ms that varies from NIST 800-171 only in accordance with DFARS clause 252.204-7012(b)(2), for all covered contractor information systems affecting this contract.

6.4.2. Notwithstanding the allowance for such variation, the contractor shall identify in any SSP and POA&M their plans to implement the following, at a minimum:

6.4.2.1. Implement Control 3.5.3 (Multi-factor authentication). This means that multi-factor authentication is required for all users, privileged and unprivileged accounts that log into a network. In other words, any system that is not standalone should be required to utilize acceptable multi-factor authentication. For legacy systems and systems that cannot support this requirement, such as CNC equipment, etc., a combination of physical and logical protections acceptable to the Government may be substituted;

6.4.2.2. Implement Control 3.1.5 (least privilege) and associated Controls, and identify practices that the contractor implements to restrict the unnecessary sharing with, or flow of, covered defense information to its subcontractors, suppliers, or vendors based on need-to-know principles;

6.4.2.3. Implement Control 3.1.12 (monitoring and control remote access sessions) - Require monitoring and controlling of remote access sessions and include mechanisms to audit the sessions and methods.

6.4.2.4. Audit user privileges on at least an annual basis;

6.4.2.4.1. Implement:

6.4.2.4.1.1. Control 3.13.11 (FIPS 140-2 validated cryptology or implementation of NSA or NIST approved algorithms (i.e. FIPS 140-2 Annex A: AES or Triple DES) or compensating controls as documented in a SSP and POAM); and,

6.4.2.4.1.2. NIST Cryptographic Algorithm Validation Program (CAVP) (see https://csrc.nist.gov/projects/cryptographic-algorithm-validation-program);

6.4.2.4.2. Implement Control 3.13.16 (Protect the confidentiality of CUI at rest) or provide a POAM for implementation which shall be evaluated by the Navy for risk acceptance.

6.4.2.4.3. Implement Control 3.1.19 (encrypt CUI on mobile devices) or provide a plan of action for implementation which can be evaluated by the Government Program Manager for risk to the program.

6.5. Cyber Incident Response:

6.5.1. The Contractor shall, within fifteen (15) days of discovering the cyber incident (inclusive of the 72-hour reporting period), deliver all data used in performance of the contract that the Contractor determines is impacted by the incident and begin assessment of potential warfighter/program impact.

6.5.2. Incident data shall be delivered in accordance with the Department of Defense Cyber Crimes Center (DC3) Instructions for Submitting Media available at http://www.acq.osd.mil/dpap/dars/pgi/docs/Instructions_for_Submitting_Media.docx. In delivery of the incident data, the Contractor shall, to the extent practical, remove contractor-owned information from Government covered defense information.

6.5.3. If the Contractor subsequently identifies any such data not previously delivered to DC3, then the Contractor shall immediately notify the contracting officer in writing and shall deliver the incident data within ten (10) days of identification. In such a case, the Contractor may request a delivery date later than ten (10) days after identification. The contracting officer will approve or disapprove the request after coordination with DC3.

6.6. Naval Criminal Investigative Service (NCIS) Outreach

The Contractor shall engage with NCIS industry outreach efforts and consider recommendations for hardening of covered contractor information systems affecting DON programs and technologies.

6.7. NCIS/Industry Monitoring

6.7.1. In the event of a cyber incident or at any time the Government has indication of a vulnerability or potential vulnerability, the Contractor shall cooperate with the Naval Criminal Investigative Service (NCIS), which may include cooperation related to: threat indicators; pre-determined incident information derived from the Contractor's infrastructure systems; and the continuous provision of all Contractor, subcontractor or vendor logs that show network activity, including any additional logs the contractor, subcontractor or vendor agrees to initiate as a result of the cyber incident or notice of actual or potential vulnerability.

https://csrc.nist.gov/projects/cryptographic-algorithm-validation-program

6.7.2. If the Government determines that the collection of all logs does not adequately protect its interests, the Contractor and NCIS will work together to implement additional measures, which may include allowing the installation of an appropriate network device that is owned and maintained by NCIS, on the Contractor's information systems or information technology assets. The specific details (e.g., type of device, type of data gathered, monitoring period) regarding the installation of an NCIS network device shall be the subject of a separate agreement negotiated between NCIS and the Contractor. In the alternative, the Contractor may install network sensor capabilities or a network monitoring service, either of which must be reviewed for acceptability by NCIS. Use of this alternative approach shall also be the subject of a separate agreement negotiated between NCIS and the Contractor.

6.7.3. In all cases, the collection or provision of data and any activities associated with this statement of work shall be in accordance with federal, state, and non-US law.

7. CONTRACTOR MANPOWER REPORTING APPLICATION

7.1.1. Refer to C-237-H001 Enterprise-Wide Contractor Manpower Reporting Application

8. TRAVEL. Both CONUS and OCONUS travel will be required and will be identified at the order level.

9. PERSONNEL. If the PCO questions the qualifications of any person performing under the contract, the burden of proof that the person is qualified as prescribed herein shall be upon the contractor. The contractor shall respond to questions raised by the PCO in the time requested by the PCO, and remove the person from the contract, if the PCO determines that the person does not meet the contractual qualifications.

10. eCRAFT

10.1 Refer to C-237-W001 Electronic Cost Reporting and Financial Tracking (e-Craft) System Reporting

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J - LIST OF ATTACHMENT

Exhibit A – CDRLs A001-A014 Attachment 1 – DO1 Requirement Attachment 2 – Sample Task 1 Attachment 3 – Sample Task 2 Attachment 4 – Sample Task 3 Rev A Attachment 5 – Key Personnel Qualifications Attachment 6 – Subcontracting Plan Cover Sheet Attachment 7 – Past Performance Reference Attachment 8 – Past Performance Questionnaire Attachment 9 – DD254 Attachment 10 – Quality Assurance Surveillance Plan Attachment 11 – GFP Template Attachment 12 – Questions and Answers 20R0009 Attachment 13 – Questions and Answers 20R0009 Round 2 Attachment 14 – Questions and Answers 20R0009 Round 3

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

INSTRUCTIONS TO OFFERORS

L.1.0. SECTION L - INSTRUCTIONS TO OFFERORS

L.1.1 Eligibility

This solicitation is unrestricted. The offeror, other than Small Businesses, is required to submit a Small Business Subcontracting Plan in accordance with FAR 52.219-9. If a Subcontracting Plan is required, the offeror shall complete the Subcontracting Plan (Attachment 6) and provide it with their proposal.

L.1.2 Questions

It is the offeror's responsibility to bring to the attention of the PCO at the earliest possible time, but prior to the solicitation closing date, any ambiguities, discrepancies, inconsistencies, or conflicts between the SOW and other solicitation documents attached hereto or incorporated by reference. All questions shall be submitted via e-mail to the contract specialist and PCO at lina.k.nguyen@navy.mil and abeer.ameer@navy.mil within 10 calendar days after issuance of the solicitation. Questions received after this date may be answered at the discretion of the Government.

L.1.3 Estimated Contract Start Date

NSWCCD’s intent is to make awards for this solicitation on 05 June 2020. For cost/pricing propulsor purposes in response to Section L and Cost Proposal Instructions, assume a start date of June 5, 2020. This date is only an estimate of the anticipated contract start date and will be used for the purpose of proposal evaluation only. The definitive start date will be stated in the contract award document.

L.2.0 INSTRUCTIONS FOR SUBMISSION OF OFFERS

THE GOVERNMENT RESERVES THE RIGHT TO REJECT ANY PROPOSAL THAT DOES NOT COMPLY

WITH THESE PROPOSAL PREPARATION/SUBMISSION INSTRUCTIONS. NOTE: INFORMATION

REQUESTED AND SUBMITTED IN ONE VOLUME WILL NOT BE CONSIDERED FOR PURPOSES OF

EVALUATION OF INFORMATION CONTAINED IN ANOTHER VOLUME. COST PROPOSAL

SUBMISSIONS MUST REFLECT WHAT IS SUBMITTED IN THE TECHNICAL VOLUME. PROPOSALS

FOR WHICH THE COST ELEMENTS (E.G. NUMBER OF HOURS, LABOR CATEGORIES,

SUBCONTRACTORS) IN THE COST VOLUME DO NOT MATCH THOSE IDENTIFIED IN THE

TECHNICAL VOLUME MAY BE DEEMED UNAWARDABLE.

L.2.1 General Instructions

Proposals shall be submitted by e-mail to the contract specialist and PCO identified in section L.1.1. Proposals shall be received by the solicitation closing date and time specified on the cover page of this solicitation, block (9).

Offerors are encouraged to submit their proposal early enough to verify that their proposal was received prior to the closing date and time of the solicitation. Offerors shall comply with the instructions for the format and content of the proposal; proposals that fail to comply may be ineligible for award.

(a) Definitions. As used in this solicitation –

• “In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

• Proposal modification is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

mailto:abeer.ameer@navy.mil

• Proposal revision is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a PCO.

• Day is defined as a calendar day unless otherwise specified. If the last day of a specified period falls on a Saturday, Sunday, or Federal Holiday, the period shall be deemed to end on the next Federal work day.

• Major Subcontractor is defined as a subcontractor performing 30% or more of total proposed burdened labor costs.

(b) Amendments to the solicitation. If this solicitation is amended, terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Proposal submissions, modifications, revisions, and withdrawals shall be e-mailed to the contract specialist and PCO at the above e-mail addresses referenced in paragraph L.1.1.

• Offerors may submit modifications to their proposals at any time before the solicitation closing date and time. Proposal modifications after the solicitation close date and time are not allowed.

• After the solicitation closing date and time, the offeror may submit revised proposals only if requested or allowed by the PCO.

• Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the PCO.

L.2.2 Electronic Submission

The offeror’s proposal shall be received via e-mail or DOD-SAFE at https://safe.apps.mil by the contract specialist and PCO by the solicitation’s closing date/time of 12:00PM ET 10 February 2020 in order to be eligible for award.

If the proposal is not received by solicitation closing date, it will be deemed ineligible for award. In the event that the offeror experiences technical difficulties, the offeror shall immediately notify the PCO via e-mail or telephone prior to the solicitation closing date and time. Failure to submit a complete proposal prior to the solicitation closing date and time will in almost all circumstances render the proposal late and unacceptable.

Proposals may be withdrawn by written notice to the PCO provided such notice is received prior to contract award.

L.2.3 Proposal Format Instructions

All offerors are required to submit proposals in accordance with the format and content specified herein. The requirements below apply equally to subcontractors. Proposals that do not meet the below requirements may be deemed unacceptable and may not be eligible for award. The offeror shall include in its proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes.

The electronic submission for Volumes I, II, III, and IV:

• Contain one copy of the respective proposal volume in Microsoft Word or Adobe Acrobat portable document format (i.e. “.doc,.docx, .xls, .xlsx, or .pdf”). Note, instructions regarding use of certain electronic products (e.g. Microsoft Office, Excel, Adobe) listed herein shall not be construed as Government endorsement of specified product.

• Each volume submitted, as a separate electronic file, shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date, and solicitation number in either the headers or footers.

• Hyperlinks to locations outside a document is not permitted, however, certain hyperlinks to places within a document, such as table of contents numbers, section headings, and table or figure cross references are acceptable.

The electronic submission for Volume IV – Cost Proposal:

• Cost proposal shall be submitted in Microsoft Excel, spreadsheet files (workbooks) for all prime AND subcontractors.

https://safe.apps.mil/

• For each workbook, all rows, columns, cells, shall be visible. Spreadsheets shall include all calculations in the cells (e.g. show all formulas) as the Government MUST be able to determine how costs were calculated. The following formats are considered NOT acceptable when preparing the cost proposal:

o Worksheet cells formatted with the font color equal to the fill color o Print image files or pictures should not be used (e.g. a picture of an Excel spreadsheet embedded in a Word document) o Cell references to data or links to other Volumes

• All files named with the file extension .doc or .docx shall be Microsoft Word 2010 compatible; Prime /Subcontractor Cost Summaries shall be submitted using Microsoft Excel (2010 or compatible). Any other attached documents requested herein shall be compatible with Microsoft Office. Compression tools are limited to PKZip or WinZip.

• The offeror shall submit proposals in response to this solicitation in English and in U.S. dollars.

• Narratives related to the cost summary data may be provided in Microsoft Word and shall be submitted in accordance to format instructions for volume I, II, and III.

Additionally, the electronic proposal shall be prepared so that, if printed, the proposal meets the following requirements:

• Page setup parameters:

o Margins – Top, Bottom, Left, Right - 1”, o Gutter – 0”, Page Size, o Width – 8.5”, Page Size, Height – 11”

• Pages shall be single-spaced and each paragraph shall be separated by at least a 6-point spacing.

• The offeror will use a standard, Times New Roman 12-point minimum font. The Offeror may use a reduced legible font size, not less than 8 point in Times New Roman, Arial, Cambria, or Calibri font, and landscape orientation for Tables and Illustrations (i.e. graphs, tables, and charts).

L.2.3.1 Cover Page and Table of Contents

Each proposal volume, except for the Cost Volume, shall include a Cover Page and a Table of Contents. The Cover Page shall identify the solicitation number, amendment number (if any), proposal volume and title, and the offeror’s name, CAGE Code, and DUNS Number. Cover Pages, Tables of Contents, and the Proposal Cross-Reference Table will not count against page limitations.

L.2.3.2 Page Numbering System

The offeror shall use a standard page numbering system to facilitate proposal references. All pages shall be numbered. Consecutive pages will be numbered within sections. Charts, graphs, and other insert materials shall be page-numbered as part of the page numbering system.

L.2.3.3 Glossary of Abbreviations and Acronyms

The offeror may submit a glossary which includes abbreviations, acronyms, and their corresponding definitions.

Glossaries will not count against page limitations.

L.2.3.4 File Naming Convention

All files must be submitted in the following formats:

• Technical_Company Name_Document Name_Volume #

Example: Technical_Company X_Technical and Management_Volume I

• Past Performance_Company Name_Document Name/Attachment #_Volume # Example: Past Performance_Company X_Previous Contracting Efforts_Volume II

• Cost_Company Name_Document Name_Vol # (or Attachment Number) Example: Cost_Company X_Cost Narrative_Volume III

Example: Cost_Company X_Cost Summary_Attachment 1

L.2.3.5 Section L and Proposal Volume Cross-Reference Table

The table below represents a cross-reference of proposal content, volume in which the proposal content shall be submitted, and whether proposal content is included in page limitations defined in paragraph L.2.3.6.

Cross Reference Table Section L Paragraph

Required Documentation Volume Page Limitation

L.2.3.1 Cover Page N/A 1 page L.2.3.1 Table of Contents All No page limitation L.2.3.3 Glossaries All No page limitation L.4.1 Technical and Management

L.4.1.1 Technical Capabilities and Approach (Subfactor A) I 75 pages

L.4.1.2 Three Sample Tasks & First Delivery Order (Subfactor B) I L.4.1.3 Management Approach (Subfactor C)

Section I – Overall Management Approach Section II – Subcontract Management Plan Section III– Risk Management

I

L.4.1.4 Personnel Qualifications (Subfactor D) I L.4.2 Past Performance (Factor 2) II No page limitation L.4.3 Small Business Participation (Factor 3) III No page limitation L.4.4 Cost Proposal (Factor 4) IV No page limitation L4.5 Contract Fill-ins V No page limitation

N/A = The content shall be submitted at the front of the proposal rather than within any of the volumes.

L.2.3.6 Page Limitations

Page limitations are identified for each volume of the proposal as shown above and will be treated as maximums. Proposal Cross Reference Table and Glossaries referenced in paragraph L.2.3.1 and L.2.3.3 do not count against the page limitation. All other volumes do not have a page limit.

For purposes of page limitations, a page count consists of all pages within the respective proposal volume. If a volume exceeds the page limitation, the Government will evaluate it in chronological order starting with page “1”;

any pages in excess of the page limitations set forth above WILL NOT be read or considered in the proposal evaluation. When both sides of a sheet display printed material, it shall be counted as two pages.

L.3.0 WRITTEN PROPOSAL ORGANIZATION

L.3.1 Cover Letter

Offerors shall provide a cover letter with the following information:

• Solicitation number;

• The name, address, e-mail address, and telephone and facsimile numbers of the Offeror;

• A statement confirming agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all CLINs upon which prices are offered at the price set opposite each CLIN. If the offeror takes exception to any terms, conditions, or provisions, the exceptions shall be clearly stated in the cover letter;

• A statement that the proposal is valid through 180 calendar days from the date specified for receipt of proposals;

• Names, titles, telephone and facsimile numbers, and e-mail addresses of persons authorized to negotiate on the Offeror's behalf with the Government in connection with this solicitation;

• DCAA and DCMA office point of contact (POC), including branch location, contact name, telephone number, and e-mail address for both the Prime its Subcontractors;

• Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office; and

• Identify all enclosures being transmitted as part of the Offeror's proposal.

L.3.2 Technical and Management (Volume I)

The offerors shall ensure that all Technical Capabilities and Approach, Three Sample Tasks & First Delivery Order (DO1), Management Approach, and Personnel Qualifications are contained within Volume I and that no cost/price information is included in this volume.

L.3.3 Past Performance (Volume II)

The offeror shall ensure that all Past Performance information is contained within Volume II and that no cost/price information concerning this requirement is included in this volume.

L.3.4 Small Business Participation (Volume III)

The offeror shall ensure that all Small Business Participation Plan information is contained in Volume III and that no cost/price information concerning this requirement is included in this volume.

L.3.5 Cost/Price Proposal (Volume IV)

The offeror shall ensure that all cost/price information is contained within Volume IV. The offeror shall ensure Section B pricing matches the Prime’s Cost Summary and the subcontractor’s Cost Summary submission.

L.4.0 PROPOSAL CONTENT

L.4.1 Factor I – Technical and Management (Volume I)

L.4.1.1 Subfactor A – Technical Capabilities and Approach

The offeror (including prime and subcontractors) shall describe the technical capabilities and/or approach to the following sections. This description shall include proposed subcontractors that will perform major or critical aspects of the requirement. The offeror shall provide evidence in its proposal that it possesses the facility security and safeguarding clearances listed in Section 6 of the SOW and Attachment 9 – DD254 to be eligible for award.

a. The offeror shall provide a list and a detailed description of its principal machine and fabrication equipment in accordance with SOW Section 4.3.2 Fabrication Facilities and 5.2.4 Surface Preparation. Additionally, the description shall include manufacturer model, install/retrofit data, machine type, controller, multi-axis, capabilities, machining envelope, and weight capacity. The offeror shall also demonstrate its personnel knowledge, skills, and qualifications to operate equipment listed by the offeror.

b. The offeror shall describe in detail its experience, capability and approach to performing fabrication of metal components from the following metals: aluminum, Nickel Aluminum Bronze (NAB), inconel, Monel, Steel and Stainless steel. The description shall include the offeror experience and/or approach with the fabrication methods listed in SOW Section 4.3.3 Metallic Fabrication.

c. The offeror shall describe in detail its experience, capability and approach to performing fabrication of composite and multi-material (metallic/composite hybrid) components. The description shall include the offeror experience and/or approach with the fabrication methods listed in SOW Section 4.3.4 Composite components.

d. The offeror shall provide a list and detailed description of its manufacturing facilities in accordance with SOW Section 4.3.5 Component Handling.

e. The offeror shall describe its experience, capability and approach to perform rough and final Computer Numerically Controlled (CNC) machining and manufacturing services as described in SOW Sections 5.1 and 5.2. This shall include its ability to meet the machining tolerances listed in SOW Section 5.2.1 Machining.

f. The offeror shall identify active and inactive welding qualification certifications. The offeror shall also demonstrate Gas Tungsten Arc (GTA) and Gas Metal Arc (GMA) welding capabilities in accordance with SOW Section 5.2.3 Assembly and References 3.2, 3.3, and 3.4.

g. The offeror shall have the capability to receive, modify, and generate 3D computer aided design (CAD) models and 2D drawings in accordance with SOW Section 5.2.5 Manufacturing Drawings. The offeror shall demonstrate its experience with the development and manipulation of 3D Models CAD and with the development of engineering drawings, including adherence to ASME Y14.5, SOW reference 3.10. The offeror shall also demonstrate its understanding and capability to develop Technical Data Packages for propulsor components and prototypes. This section shall also address the offeror’s understanding of the requirements listed in SOW Sections 5.1.2. Manufacturing Engineering and Manufacturing Feasibility Studies and 5.1.3. Test Plans and Validation Reports.

h. The offeror shall provide an explanation of its anticipated inspection approach for conducting inspections to ensure the part is in tolerance, including any uncertainty induced by the measurement technique itself.

The offeror shall provide a list of planned deliverables and material certifications that would be provided to the Government to ensure the part is in accordance with the design/drawing. The offeror shall also demonstrate its experience with conducting the various inspection and test services in accordance with SOW Section 5.2.6 Inspection and Test Services. The offeror shall address all subsections of 5.2.6.

i. The offeror shall provide a statement of compliance with the remaining portions of the SOW listed in section C of this solicitation.

L.4.1.2 Subfactor B –Three Sample Tasks & First Delivery Order

The offerors shall demonstrate their technical approach based on the requirements for the sample tasks and first delivery order. For the first delivery order, the offeror shall provide a manufacturing plan/approach that meets the requirement set out in Attachment 1. For the three sample tasks (Attachments 2,3, and 4), at a minimum, the offeror’s manufacturing plan/approach for each of the three sample tasks shall include the following, as applicable:

a. Overall Program Management Team Approach. The offeror shall describe its program management support to assist in project execution and improvements to quality control and planning activities such as quarterly meetings and monthly status reporting.

b. Material Sourcing Plan. The offeror shall list materials needed to meet the sample task requirements and shall provide its sourcing strategy to procure raw material and other components. The offeror shall also include its inspection process approach for materials/components that will be acquired.

c. Machining Capabilities. The offeror shall provide a draft machining strategy to include selection of machines/tools at various phases in the machining process, machining steps and fixturing, machine specifications, machine tool parameters, cutting speeds and feed rates, and offeror’s approach for developing and verifying the quality of CNC toolpaths.

d. Logistics Assessment. The offeror shall provide an assessment of the ability to lift and handle all parts (including the certifications and safety plans for doing so); an assessment of the logistical flow…

This is the start of the file's text. The full file is on GovTribe.