About this file

This document outlines 28 Contract Data Requirements Lists (CDRLs) required under Solicitation Number N00039-17-R-0043 for the PMW 750 C4I Testing, Integration, and Installation Follow-on contract. The CDRLs require the delivery of technical documentation including configuration management plans, drawings, reports, schedules and test plans to support testing, integration and installation of C4I systems. Key CDRLs include platform configuration baselines, technical interface drawings, various progress and status reports, integrated schedules and test plans. The solicitation is for the Department of the Navy and has an estimated contract award date of October 2019. All CDRLs are to be delivered electronically and marked with a distribution statement authorizing release to the DoD and DoD contractors.

View the file

Other files for this federal contract opportunity

Other files attached to PMW 750 C4I Testing, Integration, and Installation Follow-on, newest first.
File Type Posted
Draft_RFP_QA_N00039-17-R-0043_rev1.pdf PDF
Draft_RFP_QA_N00039-17-R-0043.pdf PDF
Draft_RFP_Att10-PEOC4I_POR_and_Non-POR_Systems_09JUL2018.pdf PDF
Draft_RFP_Att12-Past_Perf_Questionnaire_Survey_09JUL2018.pdf PDF
Draft_RFP_Att9-Hull_POR_Summary_09JUL2018.pdf PDF
Section J - List of Attachments-09JUL2018.docx DOCX document
Draft_RFP_Att11-Ship_Avail_Schedule_09JUL2018.pdf PDF
RFP QUESTIONNAIRE FORM.xlsx XLSX spreadsheet
Draft_RFP_Sections_L&M_07112018.pdf PDF
Draft_RFP_Att13-Small_Business_Participation_Data_09JUL2018.pdf PDF
Section B - CLIN Structure-11JUL2018.docx DOCX document
Draft_RFP_Att1-PWS_09JUL2018.pdf PDF
Draft_RFP_Att6-Relevant_Experience_Form_09JUL2018.pdf PDF
Draft_RFP_Att4-Labor_Table_09JUL2018.pdf PDF
Draft_RFP_Att7-Gate_Review_Matrix09JUL2018.pdf PDF
Draft_RFP_Att14-Prime_Ctr_and_Subctr_Cost_Sprshts_11JUL2018.xlsx XLSX spreadsheet
Draft_RFP_Att8-Relevant_PEOC4I_POR_and_Systems_09JUL2018.pdf PDF
Draft_RFP_Att5-QASP_09JUL2018.pdf PDF
Draft_RFP_Att13-Small_Business_Participation_Data_09JUL2018.pdf PDF
Draft_RFP_Att10-PEOC4I_POR_and_Non-POR_Systems_09JUL2018.pdf PDF
Draft_RFP_Att1-PWS_09JUL2018.pdf PDF
Draft_RFP_Att12-Past_Perf_Questionnaire_Survey_09JUL2018.pdf PDF
Draft_RFP_Att8-Relevant_PEOC4I_POR_and_Systems_09JUL2018.pdf PDF
Draft_RFP_Att6-Relevant_Experience_Form_09JUL2018.pdf PDF
Draft_RFP_Att5-QASP_09JUL2018.pdf PDF
Draft_RFP_Att4-Labor_Table_09JUL2018.pdf PDF
Section J - List of Attachments-09JUL2018.docx DOCX document
Draft_RFP_Att7-Gate_Review_Matrix09JUL2018.pdf PDF
RFP QUESTIONNAIRE FORM.xlsx XLSX spreadsheet
Draft_RFP_Att14-Prime_Ctr_and_Subctr_Cost_Sprshts_11JUL2018.xlsx XLSX spreadsheet
Draft_RFP_Sections_L&M_07112018.pdf PDF
Draft_RFP_Att9-Hull_POR_Summary_09JUL2018.pdf PDF
Draft_RFP_Att11-Ship_Avail_Schedule_09JUL2018.pdf PDF
Section B - CLIN Structure-11JUL2018.docx DOCX document
Draft_RFP_Att2-CDRLS_09JUL2018.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROGRAM EXECUTIVE OFFICE COMMAND,

CONTROL, COMMUNICATIONS, COMPUTERS

AND INTELLIGENCE (PEO C4I), CARRIER & AIR

INTEGRATION PROGRAM OFFICE,

PMW 750

C4I Testing, Integration, and Installation, (CTII) Follow-On Contract

(Attachment 2)

09 July 2018

Contract Date Requirements List (CDRLs)

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

Platform Configuration/Product Baseline

3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-82133

5. CONTRACT REFERENCE

PWS 3.1.1.4, 3.1.3.1, 3.1.3.2, 3.1.3.6

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

9. DIST

STATEMENT

D

10. FREQUENCY

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

Reg Repro

16. REMARKS

Submit electronically in native format as specified in each task order. Delivery should be via the Intelink tool unless the system has failed, in which case the contractor shall submit CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

IPM 1

PL 1

15. TOTAL --------- 0 3 0

G. PREPARED BY

Mike Murphy, PMW 750 COR

H. DATE

I. APPROVED BY

Steve Valvonis, PMW 750 PIPM

J. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 1 of 28 Pages

18. ESTIMATED

TOTAL PRICE

17. PRICE

GROUP

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A002

TIF and Shipboard Drawings

MIL-STD-23140D

5. CONTRACT REFERENCE

PWS 3.1.1.5, 3.1.2.7, 3.1.2.7.1, 3.1.2.7.2,

3.1.2.7.3, 3.1.2.7.5 3.2.7.5

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

Submit electronically in native format as specified in each task order. Delivery should be via the Intelink tool unless the system has failed, in which case the contractor shall submit CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

Drawings may include but are not limited to:

A) TIF Arrangement Drawing B) Installation Control Drawing (ICD) C) 3-D Drawing D) TIF Connectivity Design

E) Functional Interface Diagram (FID) F) Ship Installation Drawing (SID)

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 2 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A003

Technical Reports

DI-MISC-80508B, MIL-D-23140D

5. CONTRACT REFERENCE

SEE BLK 16

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

Submit electronically as specified in each task order. Delivery should be via the Intelink tool unless the system has failed, in which case the contractor shall submit CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 5: PWS paragraphs: 3.1.1.6, 3.1.2, 3.1.2.1, 3.1.2.2, 3.1.2.3, 3.1.2.5, 3.1.2.6, 3.1.2.6.1, 3.1.2.6.12, 3.1.2.6.13, 3.1.2.10, 3.1.2.13, 3.1.4.4, 3.1.4.6, 3.1.4.7, 3.2.1.1, 3.2.4.3, 3.2.4.4, 3.2.5.1, 3.3.2.1, 3.3.2.2, 3.3.2.6, 3.3.4.3, 3.3.4.4, 4.1.7, 4.6

Reports may include one or more of the following but are not limited to:

A) Specialty Engineering Reports B) Impact Assessments C) GFE Delivery Plan D) White Papers E) Material Production Form F) Cybersecurity Configuration Change Report G) Test Results

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 3 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A004

Product Drawings / Model and Associated Lists

DI-SESS-81000E

5. CONTRACT REFERENCE

SEE BLK 16

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 5: PWS paragraphs: 3.1.2.4, 3.1.2.6.3, 3.1.2.6.4, 3.1.2.6.5, 3.1.2.6.6, 3.1.2.6.7, 3.1.2.6.8, 3.1.2.6.9, 3.1.2.6.11, 3.1.2.7.4, 3.1.2.7.6, 3.1.3.7, 3.2.2.1, 3.2.3, 3.3.2.3, 3.3.3.3

Reports may include one or more of the following but are not limited to:

A) Installation Control/Installation Requirements Drawings (ICDs/IRDs) B) Outline and Installation Drawings C) Cable Run Sheets D) Cable Block Diagrams E) Fabrication Drawings F) Miscellaneous Hardware Design

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

IPMs 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 4 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A005

Intergrated Logistics Documentation

DI-SESS-81000E

5. CONTRACT REFERENCE

PWS 3.1.2.6.10, 4.3, 4.3.2, 4.5.1

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

Submit electronically as specified in each task order. Delivery should be via the Intelink tool unless the system has failed, in which case the contractor shall submit CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

Documents may include one or more of the following but are not limited to:

A) Integrated Logistics Documentation B) Platform system/equipment baseline checklists C) Top-Down Breakdown (TDBD)

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 5 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A006

Quality Records

DI-MISC-80508B

5. CONTRACT REFERENCE

PWS 3.1.2.7.7, 3.1.4.5, 3.1.4.7.1, 4.4.1,

4.4.2

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

Reports may include one or more of the following but are not limited to:

A) Completed Work Instruction QC Checklists B) Completed Test Data Records C) Material Discrepancy Reports (MDRs) D) Test Equipment Calibration Request Form E) Quality Control Plan

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 6 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A007

Bill of Materials

DI-MGMT-81994

5. CONTRACT REFERENCE

PWS 3.1.2.8, 3.2.2.2, 3.3.2.4

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 7 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A008

Engineering Change Proposals

DI-SESS-80639D

5. CONTRACT REFERENCE

PWS 3.1.2.9, 3.3.2.5, 3.3.3.1

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 8 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A009

Notice of Revision

DI-SESS-80642D

5. CONTRACT REFERENCE

PWS 3.1.2.9, 3.3.2.5, 3.3.3.1

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 9 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A010

Specification Change Notice

DI-SESS-80643D

5. CONTRACT REFERENCE

PWS 3.1.2.9, 3.3.2.5, 3.3.3.1

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 10 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A011

Human Engineering System Analysis Report

DI-HFAC-80745C

5. CONTRACT REFERENCE

PWS 3.1.2.12.2, 3.1.2.12.3, 3.2.2.3

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 11 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A012

As-Built Configuration List (ABCL)

DI-CMAN-81516

5. CONTRACT REFERENCE

PWS 3.1.3.3

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 12 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A013

Configuration Status Accounting Information

DI-SESS-81253C

5. CONTRACT REFERENCE

PWS 3.1.3.4

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 13 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A014

Shipboard Completion Report

DI-SESS-81245B

5. CONTRACT REFERENCE

PWS 3.1.3.5, 3.1.5.7.1, 3.3.5.9

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

The Final Shipboard Completion Report shall contain at a minimum the following information:

A) Technical issues—including MDR status B) Planned/Completed Installation—including Rack status C) Test Status D) Familiarization and ILS Package E) Delivered/Undelivered Items—including TRF Reports F) Trial Card status G) Sparing H) Work Deferral Report (WDR) status I) Requirements needed for follow-on TO

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 14 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP X TM _ _ OTHER ____

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A015

Test Plan / Procedures

Platform Test Plan

DI-SESS-81704

5. CONTRACT REFERENCE

PWS 3.1.4.1, 3.1.4.2, 3.1.4.3, 3.1.4.4,

3.2.4.1, 3.2.4.2, 3.2.4.3, 3.3.4.1, 3.3.4.2

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

Reports may include one or more of the following but are not limited to:

A) Test Problem Report and Resolution (TPRR)

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 15 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A016

Platform Integrated Master Schedule

DI-MGMT-81861A

5. CONTRACT REFERENCE

PWS 3.1.5, 3.3.5

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 4 - Use Format No. 6

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 16 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A017

Execution Plan

DI-MISC-80508B

5. CONTRACT REFERENCE

PWS 3.1.5.7.1, 3.3.5.5, 4.1.1

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

Submit electronically for each hull or class as specified in each task order. Delivery should be via the Intelink tool unless the system has failed, in which case the contractor shall submit CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 17 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A018

Report, Record of Meeting/Minutes

Meeting Minutes

DI-ADMN-81505

5. CONTRACT REFERENCE

PWS 4.1.2

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 18 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A019

Trip Reports

DI-MISC-81943

5. CONTRACT REFERENCE

PWS 4.1.2

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 19 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A020

Contractor’s Progress, Status, and Management Report

Monthly Status Report (MSR)

DI-MGMT-80227

5. CONTRACT REFERENCE

PWS 4.1.3, 4.1.4

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

MTHLY

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

BLOCK 4: The CPSMR shall be submitted electronically and consist of three parts. The first two parts shall be provided in the Excel format of CDRL A020 Government Formats 1 and 2 with all cells filled in. The third part shall be provided in Word format and consist of a narrative addressing, at a minimum:

a. Performance Status – Identify significant accomplishments and progress made during the affected reporting period by SOW/PWS paragraph. Also identify significant challenges or risks encountered that impact the successful delivery of required services. Identify any new or previous problem areas as well as their current status. Include any current action items and status.

b. Schedule Status – Identify schedule for and status of all deliverables. If the efforts are not on schedule, indicate the reason for the delay and provide a revised completion /delivery date.

c. Financial Status –Identify at a summary level and by SOW/PWS paragraph the total amount planned by appropriation, total amount received to date by appropriation, planned vs actual burn rate by appropriation and Estimate At Completion (EAC). In addition to the reporting requirements identified in Attachment 1, identify any travel accomplished with sufficient detail to support costs and provide a detailed description of the ODCs authorized at time of award and ODC costs incurred to date. This description does not waive the requirement for formal Limitation of Funds/Cost notifications, when warranted

d. Personnel Status/Staffing Plan – Identify labor hours planned for each employee charging to the contract/task order by SOW/PWS paragraph, CLIN, labor categories used, name of employees charged to each labor category, the number of hours and direct unburdened labor cos for each employee, and a listing of employee anmes with CLIN and number of hours charged to each Task Order. the actual cumulative total to date, CAC and training status per Attachment 1. Identify by Employee Code, labor category, fully burdened labor rate per Attachment 2. This requirement applies to the Prime and any sub-contractors supporting this effort. Subcontractors may provide the information directly to the Contracting Officer and COR

e. Environmental Health and Safety – Identify and report any accidents, injuries, incidents, and/or safety violations in the workplace involving personnel. This requirement applies to te Prime and any subcontractors supporting this effort.

Delivery should be via the Intelink tool unless the system has failed, in which case the contractor shall submit CDRLs to the addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial monthly report no later than the 15th of the month following the first full month after TO award. Subsequent submissions due no later than the 15th of each month thereafter.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 20 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A021

Integrated Program Management Report

DI-MGMT-81861A

5. CONTRACT REFERENCE

PWS 4.1.4, 4.1.4.1, 4.1.4.2

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 21 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A022

Cybersecurity Workforce Report

BEST PRACTICES

5. CONTRACT REFERENCE

PWS 4.1.11.2

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final

CDRLs to the COR via email. Submit hard copies upon request only.

BLOCK 4: Use Format No. 6.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.

COR: Mike Murphy, PMW 750 E-mail: mike.l.murphy@navy.mil

COR 1

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 22 of 28 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP _ _ TM _ _ OTHER __X__

D. SYSTEM/ITEM

CTII FO

E. CONTRACT/PR NO.

N00039-17-R-0043

F. CONTRACTOR

A023

Material Status Report

5. CONTRACT REFERENCE

PWS 4.4.4

6. REQUIRING OFFICE

PEO C4I, PMW 750

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1ST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16 Draft

Final addressee in Block 14 via email. Submit hard copies upon request only.

BLOCK 9: The following information shall be included on the deliverable: DISTRIBUTION STATEMENT D: Distribution authorized to the DoD and U.S. DoD contractors only;

Administrative or Operational Use; 12 November 2013. Other requests shall be referred to

PEO C4I, PMW 750.

BLOCK 12 & 13: The Contractor shall deliver the initial report and any subsequent submissions as specified in each task order.