This document is an industry day briefing presentation for the USS Arizona Memorial (AZM) Tour Boat acquisition program conducted by the U.S. Navy's Program Executive Office (PEO USC) and Project Management Office (PMS 300G) on March 18-19, 2026.
The government is seeking replacement or refurbishment solutions for six aging tour boats currently operating at Pearl Harbor. The existing 78-foot vessels carry up to 149 passengers and operate 362 days annually with twin Cummins diesel engines experiencing accelerated wear from continuous low-load operation. Current system challenges include propulsion stress causing carbon buildup and injector fouling, raw water cooling vulnerabilities requiring frequent maintenance and occasional diver intervention, propulsion train wear affecting alignment and seal integrity, electrical system corrosion from saltwater exposure, and mission-impacting failures occurring approximately weekly with severe dual-engine loss events quarterly. The government is exploring two acquisition paths—new construction or modernization—considering all propulsion types with identified infrastructure requirements. Top-level requirements mandate a crew of three or fewer, minimum 149 passengers with six wheelchair spaces, minimum five-knot speed at full load, maximum 80-foot length overall, maximum 33-foot beam with fendering, maximum five-foot draft, and 46 CFR Subchapter T compliance. Desirable attributes include clean energy-efficient propulsion, low maintenance costs, reduced noise for increased solemnity, improved maneuverability, minimal spray, integrated brow/gangway supporting motorized scooters up to 400 pounds, and optimized total ownership cost. Contract award is anticipated in FY27. The industry day included vessel inspections, operational tours, and government one-on-one meetings with nine qualified marine contractors on March 19, 2026, to gather preliminary feedback on vessel conditions, proposed solutions, cost estimates, infrastructure needs, and project risks.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USS Arizona Memorial Tour Boat
Industry Day 18-19 Mar 2026
Spencer Melillo
Naval Architect / Project Engineer
PEO USC/PMS 300G
U.S. Navy and Foreign Military Sales Boats & Craft Program Office
ACCELERATE | INNOVATE | DELIVER 1
Introductions
Spencer Melillo
PMS 300G Naval Architect / Project Engineer
Brian Stocker
PMS 300G Principal Assistant Program Manager
Frank Sabella
PMS 300G Acquisition Analyst
Tom Williams
Port Operations Program Manager
2ACCELERATE | INNOVATE | DELIVER
DISTRIBUTION STATEMENT A. Approved for Public Release: Distribution Unlimited
Objectives of Industry Day
3ACCELERATE | INNOVATE | DELIVER
• Allow government and industry partners to:
✓ Experience USS Arizona Memorial
(AZM) Tour Boat (TB) mission and operations firsthand
✓ Inspect hull conditions
✓ Meet and speak with operators, technicians, and maintainers
✓ Understand what is working well and what could be improved
✓ Ask questions!
• Incorporate industry feedback to inform acquisition approach
• Assign and obtain updated RFI response given takeaways from Industry Day
Overview of Industry Day (Day-1)
4ACCELERATE | INNOVATE | DELIVER
06:00 Access Control at Visitor’s Center
09:00 AZM TB Industry Day Brief
Then Lunch Break
13:00 Inspect (4) AZM TBs and Installation Boat Maintenance Center (IBMC) at Ford Island
14:45 Dock & Shoreside Infrastructure Upgrade
Tour w/ NAVFAC (Ford Island)
15:45 Mission Experience on Current AZM TBs (Ford Island)
16:30 Debark, Q&A, and Wrap-up
Overview of Industry Day (Day-2)
5ACCELERATE | INNOVATE | DELIVER
• Day-2: Govt. “one-on-one” meetings with each industry organization
• Location: Ford Island
• Topics of Discussion:
✓ Current condition of the vessels
✓ Most viable/proposed solution(s) and scopes of effort
✓ Build New or Modernization?
✓ Estimate for Total Ownership Costs compared to the current systems
✓ Opinions on need for associated electrical infrastructure upgrades and cost/schedule/scope of effort to accomplish
✓ Estimation of extension of service life of the vessels
✓ Identify High-Priority Risks with the project and COAs (Cost, Schedule, Operational, Technical, Discovery, etc.)
✓ Buy plan/work schedule/cost relationship (High end and Low end)
• Meeting schedule will be provided in back-up slides
Note: Any data, materials, or information provided by industry during the event will be treated as informational only and will not be considered as formal proposals or binding offers. Submission or discussion of materials does not confer any competitive advantage, nor will it form the basis for any contractual obligation unless otherwise stated in a future solicitation
You will NOT need to Renew Visitor Pass at Visitor Control Center
Meeting Times
6ACCELERATE | INNOVATE | DELIVER
DISTRIBUTION STATEMENT A. Approved for Public Release: Distribution Unlimited
Company Start Time End Time
Shipwright 08:00 08:20
Ockerman 08:25 08:45
TAI 08:50 09:10
P&R Watertaxi /Schottel 09:15 09:35
Marine Group Boat Works 09:40 10:00
Rozema 10:05 10:25
Breaux Brothers 10:30 10:50
PACMAR 10:55 11:15
Baker Marine Solutions 11:20 11:40
Lunch / Room Unavailable 11:45 13:15 Snow 13:15 13:40
Pass and ID Control & Briefing Location
7ACCELERATE | INNOVATE | DELIVER
TB Docks
Port Operation
BLDG 3
Overflow Parking
JBPHH Pass & ID BLDG 3455 1250 South Drive, Honolulu, HI 96818Main Gate
Dining (McDonald’s & NEX)
Briefing Room Location
Parking
Tour Area Overview
8ACCELERATE | INNOVATE | DELIVER
TB Docks – Meeting Area for TB Ride Transit to Visitor Center = 1 nm
Installation Boat Maintenance Center Independence St, Honolulu, HI 96818
Ford Island Locations
9ACCELERATE | INNOVATE | DELIVER
Mighty Mo
Notional Government
Acquisition/Refurbishment Plan
• Currently in “Market Research” phase
• Expectation is to award contract for the
AZM TBs in FY27
• Exploring options optimizing for:
✓ Value
✓ Efficiency (Energy, Personnel, etc.)
✓ Total Ownership Cost
• Identifying two major paths
✓ New Construction
✓ Refurbishment
• Considering all propulsion types (with infrastructure requirements identified)
10ACCELERATE | INNOVATE | DELIVER
Disclaimer: All information on this slide is subject to change and does not constitute a solicitation, request for proposal (RFP), or offer to contract.
Current System - Overview
11ACCELERATE | INNOVATE | DELIVER
Characteristics Overall Length: 78 ft (23.7 m) (72.5 ft LWL) Beam: 22 ft (6.7 m) Draft (FLD): ~5 ft (1.5 m) Full Load Disp: ~96,000 lbs (estimate) Dry Hoisting Weight: 65,000 lbs (known) Top Speed: 11 knots Crew: 3 (2 crew, 1 NP Ranger) Passengers: 149 (w/ 6 wheelchair spots) Max Capacity: 152 Steering: Hydraulic Engines:
• Twin, inboard Cummins Diesel Engines
• Model: QSB 5.9-230
• 230 hp per engine
• (1,350 lb) x 2 = 2,700 lb Gear:
• ZF Marine 301-1C
• Gear ratio: 2.694 : 1
• (~200 lb) x 2 = ~400 lb Propellers:
• 4 Bladed, ZF Marine 28” X 20”
Fuel System:
• 100% Biodiesel (B100)
• Two symmetric, aluminum fuel tanks (P&S)
• Total capacity: 200 gal (757 L)
• Shared, 5 gal fuel additive tank (Stainless)
• Fuel Cons: 22 gal/hr @ 2,600 RPM (~84 L/hr) Electrical System:
• 24V / 12V DC system
• Engine-driven alternator
• Output: 24V, 80 amps Bow Thruster:
• Eaton Corporation hydraulic bow thruster
Current System – Inboard Profile
12ACCELERATE | INNOVATE | DELIVER
• Fiberglass foam-core hull construction
• Built using fire-retardant vinylester resin
• Six continuous longitudinal hull stringers
• Six longitudinal deck beams
• Eight transverse bulkheads
(nine total compartments)
• Engine Room (5th Compartment)
• Steering Room / Lazarette (8th Compartment)
ForepeakComp 1
Comp 2Comp 3…
Current System – Main Deck Plan
13ACCELERATE | INNOVATE | DELIVER
Current System – Console Diagram
14ACCELERATE | INNOVATE | DELIVER
Operational Profile and Environment
15ACCELERATE | INNOVATE | DELIVER
Players:
• (6) Total TBs
✓ (2) Operating
✓ (2) Standby, one primary
✓ (2) In Scheduled Maintenance
• Spare TBs are usually not swapped into mission during the day
CONOPS:
• 362 days per year (Only off on Christmas, Thanksgiving, and New Years!)
• 8.5 hours per day (Sometimes longer if special tours are given during evening hours)
• Up to 149 passengers per trip (Usually full on every run!)
• Two TBs cycle, opposite each other, between Visitor Center and AZM (0.6 nm distance)
• Transit speed at full load is ~5 knots and takes ~7 minutes one way
• Engines let to idle during load/unload period which is approximately 5 minutes
• Distances: 1 nm + (16) x 0.6 nm x 2 (since round trip) + 1 nm = 21.2 nm/day
• Environment: Calm, protected waters
• Go/No Go Criteria: 25 knot winds or above (trade winds are the primary environmental issue and are consistently strong in this location)
Operational Profile and Environment
16ACCELERATE | INNOVATE | DELIVER
Tour TB Typical Day
0700: Two TBs warm up 0715: Pre-operation checks 0745: TB1 departs docks to Visitor Center 0800: TB1 begins transit TB2 departs docks to Visitor Center 0815: TB1 drops pax and begins return trip TB2 loads pax and begins transit 0830: TB1 exchanges pax and begins transit TB2 exchanges pax and begins return 0845: TB1 exchanges pax and begins return TB2 exchanges pax begins transit
Cycle Continues until 1600…….. Visitor Center
USS Arizona Memorial
Return Route
Transit Route
TB Maintenance
17ACCELERATE | INNOVATE | DELIVER
Maintenance Program
• Regular Overhaul (ROH) every 5–6 years per
Navy Guidance/Policy
• Preventative done regularly by civil servant technicians at the Installation Boat Maintenance Center (IBMC)
• Depot-level repairs and overhauls performed by local commercial shipyards
Vessel Condition
• Hulls in good condition with no systemic fiberglass cracking, delamination, or deck softness
• Hull upkeep primarily quarterly cleaning and inspection
• Boats are mechanically labor-intensive due to age and frequent repairs
Overhauls
• Four ferries recently completed major overhaul
✓ New engines, transmissions, hydraulic systems
✓ Shaft alignment/truing and full vessel repaint
✓ Limited electrical modernization to control cost
Ballpark Annual Costs per TB
• O&M: ~$400k
• Labor, Parts, Fuel: ~$150k
• Prorated Overhaul: ~$250k
Cost Drivers
• Engines and propulsion systems
• Shafting and marine gear repairs
• Hydraulic systems
Hulls remain in good condition; lifecycle cost pressures are driven primarily by aging propulsion and mechanical systems.
Current Challenges with the TBs
18ACCELERATE | INNOVATE | DELIVER
Propulsion System Stress
• Engines experience accelerated wear from continuous low-load operation
• Results in carbon buildup, injector fouling, and cooling inefficiencies
• Higher maintenance workload
• Periodic loss of propulsion
Raw Water Cooling Vulnerabilities
• Cooling system intakes frequently clog with marine growth and debris
• Impellers, sea strainers, and heat exchangers require frequent maintenance
• Divers are often required to clear clogged seawater intakes
Propulsion Train Wear
• Shafting, couplings, and cutlass bearings subject to vibration and sediment exposure
• Alignment drift can cause leaks, overheating seals, and increased drivetrain wear
Electrical System Degradation
• Corrosion in wiring harnesses and connectors due to saltwater environment
• Some replacement components are obsolete, complicating repairs and increasing downtime
High operational tempo and the marine environment accelerate wear on critical propulsion and support systems.
Current Challenges with the TBs
19ACCELERATE | INNOVATE | DELIVER
Mission Impacting Failure Events
• ~Once per week
• Typical issues: engine overheating, single engine loss, cooling system blockage
• Twin-engine configuration usually allows continued operation after single failures
Severe Failure Events
• Quarterly, dual-engine loss events can occur
• Common causes:
• Debris clogging seawater cooling strainers
• Electrical system failures
• Heavy rain increasing debris load in water
Operational & Public Risk
• Vessel carries ~150 civilian passengers
• Dual-engine failures require anchoring in middle of harbor and rescue by work boat
• Disrupts schedules and impacts visitor’s reservations
• Incidents frequently appear on social media and local news
• Passenger transport missions demand near-zero defect reliability
While generally operable, system failures occur frequently enough to create operational disruption and public-facing risk.
Feedback from AZM Coxswain’s & Crew
20ACCELERATE | INNOVATE | DELIVER
• Excessive engine & exhaust noise is a major operational distraction. Current mitigation relies on the outboard PA system that can compromise communication clarity
• Communication challenges are largely noise-related;
reducing overall noise levels would significantly improve crew communications
• Maneuverability
• More powerful bow thruster desired, as the current system provides insufficient maneuvering capability, especially in frequent, stiff winds
• Forward and aft helm stations recommended to improve vessel maneuverability and docking control
• Integrated brow/gangway to better accommodate passengers with mobility needs, including scooters up to ~400 lbs
• On the visitor center side there is one sailor kept on station at all times just to help lift the brow!
Pilot House
Engine Room
Notional Top-Level
Requirements & Desirable Attributes
Desirable, but not mandatory, attributes
• Clean, energy-efficient propulsion system
• Low cost and predictable maintenance
• Increased solemnity by way of decreasing operating noise
• Improved maneuverability (dual directional design or improved bow thruster)
• Minimal to no spray to passengers
• Simple design with open air passenger deck with hard rooftop
• Integrated brow/gangway to support motorized scooters
Attribute Top Level Requirement
Crew ≤ 3
Passengers ≥ 149 w/ ~6 spaces to secure wheelchairs
Speed ≥ 5 kts Full Load
Maximum Length Overall
80 ft (24 m)
Maximum Beam Overall w/ Fendering
33 ft (10 m)
Maximum Draft at Full Load
5 ft (1.5 m)
Endurance Complete a full day’s mission with margin, reliably!
Build Regulations 46CFR Subchapter T Compliant
ACCELERATE | INNOVATE | DELIVER
A commercially available, simple, and reliable ferry design that reduces lifecycle cost while improving passenger safety, accessibility, and operational reliability.
Final Thoughts
Comments & Questions
22ACCELERATE | INNOVATE | DELIVER
23ACCELERATE | INNOVATE | DELIVER
Back-Up Slides
24ACCELERATE | INNOVATE | DELIVER
25ACCELERATE | INNOVATE | DELIVER
26ACCELERATE | INNOVATE | DELIVER
27ACCELERATE | INNOVATE | DELIVER
28ACCELERATE | INNOVATE | DELIVER
29ACCELERATE | INNOVATE | DELIVER
30ACCELERATE | INNOVATE | DELIVER
31ACCELERATE | INNOVATE | DELIVER
32ACCELERATE | INNOVATE | DELIVER
33ACCELERATE | INNOVATE | DELIVER
34ACCELERATE | INNOVATE | DELIVER
35ACCELERATE | INNOVATE | DELIVER
36ACCELERATE | INNOVATE | DELIVER
37ACCELERATE | INNOVATE | DELIVER
38ACCELERATE | INNOVATE | DELIVER
39ACCELERATE | INNOVATE | DELIVER
40ACCELERATE | INNOVATE | DELIVER
41ACCELERATE | INNOVATE | DELIVER
42ACCELERATE | INNOVATE | DELIVER
43ACCELERATE | INNOVATE | DELIVER
44ACCELERATE | INNOVATE | DELIVER
45ACCELERATE | INNOVATE | DELIVER
46ACCELERATE | INNOVATE | DELIVER
47ACCELERATE | INNOVATE | DELIVER
48ACCELERATE | INNOVATE | DELIVER
49ACCELERATE | INNOVATE | DELIVER
50ACCELERATE | INNOVATE | DELIVER
51ACCELERATE | INNOVATE | DELIVER
| Default Section |
| Slide 1: USS Arizona Memorial Tour Boat Industry Day 18-19 Mar 2026 Spencer Melillo Naval Architect / Project Engineer PEO USC/PMS 300G U.S. Navy and Foreign Military Sales Boats & Craft Program Office |
| Slide 2: Introductions |
| Slide 3: Objectives of Industry Day |
| Slide 4: Overview of Industry Day (Day-1) |
| Slide 5: Overview of Industry Day (Day-2) |
| Slide 6: Meeting Times |
| Slide 7: Pass and ID Control & Briefing Location |
| Slide 8: Tour Area Overview |
| Slide 9: Ford Island Locations |
| Slide 10: Notional Government Acquisition/Refurbishment Plan |
| Slide 11: Current System - Overview |
| Slide 12: Current System – Inboard Profile |
| Slide 13: Current System – Main Deck Plan |
| Slide 14: Current System – Console Diagram |
| Slide 15: Operational Profile and Environment |
| Slide 16: Operational Profile and Environment |
| Slide 17: TB Maintenance |
| Slide 18: Current Challenges with the TBs |
| Slide 19: Current Challenges with the TBs |
| Slide 20: Feedback from AZM Coxswain’s & Crew |
| Slide 21: Notional Top-Level Requirements & Desirable Attributes |
| Slide 22: Final Thoughts Comments & Questions |
| Back-up Slides |
| Slide 23: Back-Up Slides |
| Slide 24: Back-Up Slides |
| Slide 25: Back-Up Slides |
| Slide 26: Back-Up Slides |
| Slide 27: Back-Up Slides |
| Slide 28: Back-Up Slides |
| Slide 29: Back-Up Slides |
| Slide 30: Back-Up Slides |
| Slide 31: Back-Up Slides |
| Slide 32: Back-Up Slides |
| Slide 33: Back-Up Slides |
| Slide 34: Back-Up Slides |
| Slide 35: Back-Up Slides |
| Slide 36: Back-Up Slides |
| Slide 37: Back-Up Slides |
| Slide 38: Back-Up Slides |
| Slide 39: Back-Up Slides |
| Slide 40: Back-Up Slides |
| Slide 41: Back-Up Slides |
| Slide 42: Back-Up Slides |
| Slide 43: Back-Up Slides |
| Slide 44: Back-Up Slides |
| Slide 45: Back-Up Slides |
| Slide 46: Back-Up Slides |
| Slide 47: Back-Up Slides |
| Slide 48: Back-Up Slides |
| Slide 49: Back-Up Slides |
| Slide 50: Back-Up Slides |
| Slide 51: Back-Up Slides |
File details come from the government source that posted it. Updated .