19R5519 Bidder Questions Responses 12.20.2019.pdf

PDF 497 KB Posted

Attached to
SEWIP BLOCK 3 EA SUBSYSTEM PRODUCTION AND AN/SLQ-32(V)7 INTEGRATION
Solicitation number
N0002419R5519
Issued by

About this file

This document provides responses to bidder questions for solicitation number N00024-19-R-5519 from the Department of the Navy Naval Sea Systems Command. The solicitation seeks offers for the Surface Electronic Warfare Improvement Program Block 3 Electronic Attack subsystem production and integrated AN/SLQ-32(V)7 system. Responses clarify that the contractor shall inspect government furnished information and property within 60 days of award rather than 20 days as originally stated. Additionally, the list of government furnished property has been updated to reflect that furnished items are in condition code A except for specific Block 3 systems which are provided "as is" but expected to be in condition A.

View the file

Other files

File Type Posted
N0002419R5519-003 SEWIP Block 3 Production 12.20.2019.pdf PDF
N0002419R5519-004 SEWIP Block 3 Production Conformed 1.06.2020.pdf PDF
19R5519 Questions Responses 1.6.2020.pdf PDF
N0002419R5519-004 SEWIP Block 3 Production 1.06.2020.pdf PDF
N0002419R5519-002 SEWIP Block 3 Production 12.10.2019.docx DOCX document
19R5519 _ J-3 GFP List 12182019.pdf PDF
19R5519 _ J-2 GFI List 12192019.pdf PDF
N0002419R5519-003 SEWIP Block 3 Production 12.20.2019.pdf PDF
N0002419R5519-003 SEWIP Block 3 Production Conformed 12.20.2019.pdf PDF
N0002419R5519-002 SEWIP Block 3 Production 12.10.2019.docx DOCX document
N0002419R5519-002 SEWIP Block 3 Production Conformed 12.10.2019.docx DOCX document
19R5519 Bidder Questions Responses 12.10.2019.pdf PDF
N00024-19-R-5519 Exh A - CDRLs.pdf PDF
N0002419R5519-001 SEWIP Block 3 Production Conformed.pdf PDF
N0002419R5519-001 SEWIP Block 3 Production Amendment 001.pdf PDF
J-6 Production Readiness Review (PRR) Checklist.pdf PDF
J-4 CDRL Glossary 10232019.docx DOCX document
J-14 Resource Distribution Table Example.xls XLS spreadsheet
J-S6 - Classified Material Request Form.docx DOCX document
J-2 GFI List 11082019.pdf PDF
J-S5 - N00024-19-R-5519 Unclassified Terms of Use Agreement.pdf PDF
N0002419R5519 SEWIP Block 3 Production.pdf PDF
J-5_CSDR_20191007_NSEA-19-E-C1_Approved.pdf PDF
J-S4 - N00024-19-R-5519 Classified Terms of Use Agreement.pdf PDF
J-S3 - Bidder Library Access Instructions - SEWIP Block 3.docx DOCX document
Responses to Draft RFP Questions.pdf PDF
J-S2 - Question Submittal Form.xlsx XLSX spreadsheet
A001 Integrated Program Management Report (IPMR)_Signed.pdf PDF
J-3 GFP List 11082019.pdf PDF
SEA 0255-076 SEWIP Block 3 quotes 11.19.2019.pdf PDF
J-13 Quantity Data Report format Template.xlsx XLSX spreadsheet
J-1 DD254 N0002419R5519.pdf PDF
J-S1 - Contractor Award Information.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00024-19-R-5519 Bidder Questions' Responses 12/20/2019

Question Number:

Question Source: (RFP, attachment #, GFI title, etc.)

Page number and paragraph header from source:

Question: Response:

RPF;

Exh A CDRLs Page 41, Section C 4.0;

Page 173, A057

RFP Section C 4.0 requires "The Contractor shall inspect GFI and GFP within 20 working days of receipt" but Exh. A CDRLs A057 identifies date of first submission as "60 DAC". Offeror requests that the clauses be reconciled. Offeror also requests, due to the complexities of the GFP, that each clause be updated to require reporting X days after discovery that GFP is deficient.

In accordance with CDRL A057, the contractor shall inspect GFI within 60 days after contract award. Section C para 4.0 has been updated, however, no further changes to GFP reporting.

J-3 GFP List 11082019

All pages

Each Government Furnished Property item is provided "as-is". Per RFP clause FAR 52.245-1, Government Property, subsection (d)(2)(iii), the contractor has an "opportunity to inspect ...

[but] [a]ny repairs, replacement, and/or refurbishment [of such items] shall be at the Contractor's expense."

Similar to the statement in Delivery Note 3, the Offeror requests that GFE is only provided “as is” if the Offeror was the same contractor who delivered to the United States Government that GFE item. Additionally, due to the complexity of these parts, there is a low likelihood a Contractor will be able to fully inspect these items and a significant risk that a failure will negatively impact Contractor performance despite the identified items not being furnished by the contractor.

Attachment J-3, GFP List, has been updated to add Block 3 systems as GFP for the integration CLINs. These systems are the systems which would be delivered under corresponding production CLINs from this same contract. Block 3 systems are listed as being provided "as is" which is expected to be "A" condition. For all other GFP, the attachment has been updated to reflect that the condition is not as is, and condition code A has been assigned.

File details come from the government source that posted it. Updated .