N00024-18-R-4406_0006.pdf

PDF 638 KB Posted

Attached to
USS O'Kane (DDG 77) FY19 Extended Selected Restricted Availability (ESRA)
Solicitation number
N00024-18-R-4406
Issued by

About this file

Amendment 0006

View the file

Other files

File Type Posted
N00024-18-R-4406_conformed_through_0006.pdf PDF
N00024-18-R-4406_0005.pdf PDF
N00024-18-R-4406_conformed_through_0005.pdf PDF
USS_O'KANE_PPI_QA5.xlsm XLSM spreadsheet
N00024-18-R-4406_conformed_through_0004.pdf PDF
N00024-18-R-4406_0004.pdf PDF
USS_O'KANE_PPI_QA4.xlsm XLSM spreadsheet
N00024-18-R-4406_conformed_through_0003.pdf PDF
N00024-18-R-4406_0003.pdf PDF
USS_O'KANE_PPI_QA3.xlsm XLSM spreadsheet
N0002418R4406_Conformed_though_0002.pdf PDF
USS_O'KANE_PPI_QA2.xlsm XLSM spreadsheet
USS_O'KANE_PPI_QA1.xlsm XLSM spreadsheet
N0002418R4406_0002.pdf PDF
N0002418R4406_Conformed_through_0001.pdf PDF
N0002418R4406_0001.pdf PDF
N00024-18-R-4406.pdf PDF
S-4_PP_Reference_List.docx DOCX document
S-2_Past_Performance_Questionnaire.docx DOCX document
S-3_PPI_O'Kane_DDG_77_N00024-18-R-4406.xlsm XLSM spreadsheet
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N0002418FR93077

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0006 includes the items below :

Section B: Grow th Reservation CLIN 0029 renumbered to CLIN 0051 and Option CLIN 0029 added; NOTE A updated to reflect current CLIN structure; NOTE F updated to ref lect current CLIN structure; updated CLIN 0019 description to appropriately match Attachment J-4 description Section C: Updated part 6.15 to reflect current CLIN structure Section E: Updated to include addition of CLIN 0029 Section F: Delivery schedule updated to ref lect current CLIN structure Section I: Revised clause 52.217-7 to reflect current CLIN structure.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 16

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N0002418R4406

X 9B. DATED (SEE ITEM 11)

15-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Aug-2018

CODE

NAVAL SEA SYSTEMS COMMAND (HQ)

1333 ISAAC HULL AVE SE

WASHINGTON NAVY YARD DC 20376-2030

N00024 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0002418R4406

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0019

The CLIN description has changed from TYCOM Integrated Shipboard Network Sys to PEO IWS OrdAlt 86628 OJ-663 CRT COTS.

The CLIN extended description has changed from:

Integrated Shipboard Network System (ISNS) Support Service; provide (Non-prorated WIs - See Attachment J-4 for list)See Notes C and G

To:

OrdAlt 86628 OJ-663 CRT COTS Upgrade, OA 89524 AWS: OJ-663 CRO Monitor Upgrade, OA 88649 Fiber Optic Switchbox Replacement, Alteration Installation Team (AIT) Support Service; provideSee Notes C and G

CLIN 0029

This CLIN has been renumbered to CLIN 0051.

CLIN 0029 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

1 Lot

OPTION TYCOM Integrated Shipboard Network

FFP

Integrated Shipboard Network System (ISNS) Support Service; provide (Non-prorated WIs - See attachment J-4 for list)

See Notes C and G NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

PSC CD: J999

NET AMT

The following have been modified:

SPECIAL INSTRUCTIONS NOTE F

NOTE F: SPECIAL AGREEMENT FOR CHANGES WITH A PRICE OF $25,000 OR LESS

1. To make administration of small dollar value changes more efficient, both parties agree to pre-price contract scope changes with an estimated price of $25,000 or less.

2. The amount included in this Contract for the Changes described above shall be equal to a quantity of 156 Changes for growth computed at a firm fixed price of $8,626 per Change, as associated with the following CLINs.

CLINs 0002, 0004, 0006, 0030 – 0048, 0050, 0051

3. A Waterfront Circuit Team comprised of a small group of Contractor and Government representatives will administer the Special Agreement for Changes with a Price of $25,000 or Less (“the Program”). The Contractor and the Navy shall establish a group of empowered representatives to be located in close proximity to the ship during the availability period. These individuals will interact and administer the Program. Specific arrangements for the Waterfront Circuit Team shall be mutually agreed between the Contractor and the RMC.

It is expected that changes under this term will not have schedule impacts. For any changes that the Government or the Contractor determine affect the critical path, internal milestones, or require lead times (i.e., material) may require adjudication under the other change terms and conditions of the contract.

4. The Contractor shall continue to report proposed Changes through the normal CFR process in accordance with Contract terms. The Contractor shall use the description block of the CFR to describe the problem and cite the corrective action required.

5. For those Changes that the Waterfront Circuit Team identifies a price of $25,000 or less, within 24 hours of the final approved change, the Waterfront Circuit Team shall use commercially reasonable efforts to confirm the Contractor's estimated price and document the agreed-to scope of work.

6. Once the Waterfront Circuit Team reaches agreement that the price of the Change is $25,000 or less and on the scope of the Change, the Contracting Officer shall authorize the Change. Authorized Changes will be followed by documentation to appropriately reflect specification revisions. No work on the Change shall commence until authorized by the Contracting Officer.

7. Multiple work items shall not be addressed under a single RCC. For the purposes of this Small Value Change clause, the value of each RCC shall be based on an individual Condition Found Report. Conversely, Condition Found Reports shall not be broken into smaller parts for the purposes of breaking up the requirement.

8. The 4-E specification change document will be provided, as necessary, prior to the approval of the change.

9. If the Waterfront Circuit Team is not able to reach agreement that the price of the Change is $25,000 or less and/or with regard to the scope of the Change, then it will be administered and adjudicated through the normal Contract change process as if the price of the Change was more than $25,000.

10. The Contractor and the Contracting Officer will each develop a work authorization tracker to identify and record the number of Changes authorized under this clause.

11. If the total number of Changes specified in paragraph B is depleted, the Contractor and the Contracting Officer may mutually agree to increase the quantity and contract price by applying the firm fixed price per Change in paragraph B to the number of additional Changes mutually agreed upon.

12. Within thirty (30) days after the end of the availability period of performance, the Contractor and Contracting Officer, utilizing the work authorization tracker, will determine the number of pre-priced changes not authorized under this Contract. This number shall be determined by subtracting from the number of changes identified in paragraph B, as amended, the number of pre-priced changes approved. Thereafter, the Contracting Officer will decrease the contract price by an amount calculated by multiplying the remaining number of changes by the pre-established firm fixed price per change.

SPECIAL INSTRUCTIONS: NOTE A

NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR

1. The Contractor agrees to provide the level of effort to completion which shall be 40,261 man hours and $910,901 materials in the performance of reservation CLINs (0002, 0004, 0006, 0030 – 0048, 0050, 0051) in support of historically based growth under this contract.

2. The total level of effort to completion is determined by the total value of all negotiated reservation task requests (RTRs) may not exceed the total dollar value of the level of effort listed above. Upon negotiation of each RTR, the agreed to level of effort shall convert to a completion effort. The total level of effort to completion for the performance of the above CLINs shall be man-hours of direct labor and the associated material required to support that labor and effort. The mix of labor and material may be adjusted, but may not exceed the dollar value of each CLIN listed above.

3. Effort performed in fulfilling the level of effort to completion obligations specified above shall only include effort performed in direct support of this contract and shall not include time and effort expended on such things as (local travel to and from an employee's usual work location), uncompensated effort while on travel status, truncated lunch periods, work (actual or inferred) at an employee's residence or other non- work locations, or other time and effort which does not have a specific and direct contribution to the tasks described in Sections B and C.

4. RTRs are within the general scope of the work stated in the contract. RTRs may not be used to: (1) direct a change as defined in, “FAR 52.243-1 CHANGES FIXED –PRICE clause of this contract,

(2) increase or decrease the contract price or estimated contract amount (including fee) as applicable, the level of effort to completion, or the time required for contract performance; or (3) change any of the terms or conditions of the contract.

5. If, in the opinion of the Contractor, any RTR calls for effort outside the scope of the contract or is inconsistent with this requirement, the Contractor shall notify the Contracting Officer in writing within two (2) working days after the receipt of any such instruction. The Contractor shall not proceed with the work affected by the RTR unless and until the Contractor is notified by the Contracting Officer that the RTR is within the scope of this contract.

6. Nothing in the foregoing paragraph shall be construed to excuse the Contractor from performing that portion of the contractual work statement which is not affected by the disrupted RTR.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

SCOPE OF WORK

1. GENERAL REQUIREMENTS

1.1 The Contractor under the direction of the Regional Maintenance Center (RMC) and as an independent Contractor and not as an agent of the Government, shall furnish the material, support (electrical, crane, rigging, etc.) and facilities (except those furnished by the Government under express provisions of this contract) and provide the management, technical, procurement, production, testing and quality assurance necessary to prepare and accomplish the repair and alteration of the FY19 USS O’KANE (DDG 77) Extended Selected Restricted Availability (ESRA) in accordance with the requirements stated in this Section, the Work Item Specifications and Work Item Plans, Drawings, and Other References, the Delivery Schedule, and all other terms and conditions set forth in this contract. The Contractor shall lead or participate in periodic meetings, as required, to facilitate status reporting related to USS O’KANE (DDG 77) FY19 ESRA. Forums will be conducted at a time mutually agreed to by primary participants. These meetings include, but are not limited to, the following:

1.1.1 Post Award Conference (Participate)

1.1.2 Contract Reading (Participate)

1.1.3 Arrival Conference (Participate)

1.1.4 Schedule Model Review in which the A-30 days Integrated Schedule is presented and reviewed for full integration of other government work (Lead). The Integrated Production Schedule (IPS) shall be developed and maintained and shall include all work project work including but not limited to: Lead Maintenance Activity or Prime Contractor (LMA), Sub-Contractor, Alteration Installation Team (AIT), Ship’s Force and Intermediate or I-Level work. Attachment J-7 provides the meeting requirements and deliverables. Project Maintenance Team forums designed to enhance work package integration and certification for Government Designated Planning Activity, NSA, Third Party/AITs, Ship's Force, and Prime Contractor. (Lead)

1.1.5 Project Management Reviews such as the 25%, 50%, 75%, and other meetings required to manage the overall availability to completion. (Participation)

1.1.6 Daily Production meetings. (Lead)

1.1.7 Weekly Progress meeting (Participate)

1.1.8 Weekly Commanding Officer briefs. (Participate)

1.1.9 Integrated Project Team Development (IPTD) C+21 days Meeting (Participate)

1.2 Category I NAVSEA FY19 Standard Items through CHG 2 identified under Attachment J-1 are applicable to all items without further reference. Category II NAVSEA FY19 Standard Items through CHG 2 are applicable when invoked and/or referenced in individual work items specified in Attachment J-1.

NAVSEA Standard items may be found at:

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx

1.3 The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Material as identified in work item specifications, and for accomplishment of production work.

1.4 The Contractor shall provide an integrated milestone plan for the availability. These milestones will include a schedule of key events necessary to meet the contract delivery dates. A critical path analysis and a milestone schedule shall be used to measure schedule accomplishment of the functions and elements required to successfully complete the repair and alteration of FY19 USS O’KANE (DDG 77) ESRA within the availability dates herein.

1.5 INTEGRATED PRODUCTION SCHEDULE DEVELOPMENT, UPDATE, AND REVIEWS –

In support of NAVSEA Standard Item requirements and to confirm the contractor has all available input for development of the Integrated Production Schedule, including the development of the Integrated Work Package, Production Schedule, Integration of O, I and D level Work, Integration of AIT and SHIPALT requirements and any other contractor assigned or Third Party work scheduled for accomplishment concurrent with the CNO availability, the contractor shall, with the Regional Maintenance Center (RMC), conduct the Work Package Execution Review (WPER). The WPER will take place at the RMC located at the vessel’s homeport. The RMC will schedule the WPER per the Joint Fleet Maintenance Manual (JFMM) Milestones either as a separate event or concurrent with an Integrated Project Team Development (IPTD) event no later than A-30 for CNO availabilities. This review shall be accomplished following the JFMM, Volume II, Integrated Fleet Maintenance requirements including the Critical Time Period, First 100 Hour Plan. Final 100 Hour plan and identify any schedule or scope impact. See Appendix E of the JFMM II-I-2E-1. The JFMM can be found at https://www.submepp.csd.disa.mil/JFMM/index.htm.

The Contractor shall formally present its Integrated Production Schedule to the Navy Supervisory Authority (NSA) at the WPER, Start of the Availability, 25% complete conference, 50% complete conference, 75% complete conference, production completion meetings, and for pre Sea Trials requirements. The Integrated Production Schedule shall include Alteration Installation Teams (AIT), Government-Contracted Third Party Maintenance Providers, Ship's Force, Commercial Industrial Services (CIS), and Fleet Maintenance Activity (FMA) work to the maximum extent this information is available. At each meeting, the contractor shall present and explain, at minimum, the following information:

1.5.1 The Contractor's latest, Government approved, Integrated Production Schedule created in full compliance with Standard Item 009-60. In accordance with NSI 009-60 paragraph 3.1.5, the Navy hereby specifies that the contractor may complete the Availability utilizing other than a 5-day workweek.

1.5.2 The Contractor's current progress in preparing for and/or executing the Availability in accordance with their Integrated Production Schedule. The Contractor shall provide an explanation and mitigation plan for any preparation or execution delays in comparison to their Integrated Production Schedule.

1.5.2.1 The Contractor's plan shall describe opportunities for schedule acceleration (at no cost to the Government unless directly related to a Government caused delay) and potential risks and mitigations to remaining schedule attainment.

1.6 Wherever the term “Job Order” is used in this solicitation/award, it also means “Contract.”

1.7 The Contractor shall report and recommend corrective action during contract performance for those deficiencies discovered which are not covered by the work specifications. As found conditions, needed repairs and corrective action reports will be submitted to the Government in the form of a Condition Found Report (CFR). The Contractor's conditions found reporting shall be in accordance with that set forth in Standard Item 009-01.

1.8 The Navy may send a site inspection team to perform an inspection of the contractor's facility prior to arrival of the vessel

1.9 GOVERNMENT FURNISHED MATERIAL: Government Furnished Material (GFM) cited in work specification(s) and/or Statement of Work (SOW) will be delivered or made available to be picked up as identified in the contract. The successful offeror is to email the SWRMC Property Administrators at swrmc.c400.propadmin@navy.mil, and the Project Manager, Rebecca Triplett at Rebecca.triplett@navy.mil

The following is applicable to out of homeport contractors: Government Furnished Material (GFM) cited in the solicitation will be shipped to the contractor’s facility for NAVSEA and TYCOM items.

The contractor is to coordinate delivery of Government Furnished Material with the Project Manager.

The following is applicable to in homeport contractors: Government Furnished Material (GFM) cited in the solicitation will be shipped to the contractor’s facility for NAVSEA items only. The contractor is to coordinate delivery of NAVSEA GFM with the Project Manager. The contractor is to pickup and coordinate pickup of TYCOM GFM from the Naval Base with the Project Manager.

GFM will be available at A-30 from one building on the Naval Base. Contractor shall develop pick up schedule accordingly. Transportations costs shall be included in the contract. Change order will only be issued if there is a Government caused change to the pickup.

GFM from any and all locations within Government property or permanently removed from a vessel that requires a Property Administrator's disposition instructions shall be properly prepared for shipment and be delivered by the contractor as directed by the Property Administrator.

1.10 FIRE PREVENTION: The contractor will meet requirements of the NAVSEA Industrial Ship Safety Manual for Fire Prevention and Response (8010) Manual and the NAVSEA Standard Item 009-08.

The contractor will account for required fire drills in the proposed work schedule.

1.11 PAINT ABATEMENT: Paint abatement, to include removal of hot paint, will be conducted in accordance with NAVSEA Standard Item 009-32. Paint abatement will be included as part of pricing for all proposals and is not subject to additional growth.

1.12 NAVSEA Standard Item 009-81 COMPARTMENT CLOSEOUT: Paragraph 3.1.1 shall read as

“The compartment closeout schedule shall contain the following minimum information:” The Government will not provide an additional listing of affected spaces with attached key event/ milestone. Contractor guidance for locations is provided by each specification, and guidance for each key event/ milestone is provided by the contract and each attachment.

1.13 QUALITY ASSURANCE

1.13.1 QUALITY ASSURANCE PROGRAM - The Contractor shall provide and maintain a quality assurance program acceptable to the Government, and shall perform or have performed the inspections and tests pursuant to that program to substantiate that the material and workmanship provided pursuant to the job order conform to the drawings, specifications, job orders, and contract requirements listed herein. The Contractor's quality assurance program shall be in accordance with that set forth in Standard Item 009-

04. In addition to its rights under clause 252.217-7005 “Inspection and Manner of Doing Work”, the Government shall have the right to deem work or material furnished by the Contractor to be incomplete and not in accordance with the requirements of the job order by reason of the Contractor's failure to comply with the requirements of its quality assurance program and, as such, the Contractor shall not be entitled to progress payments for said work and material.

1.13.2 Quality Assurance Surveillance Plan (QASP) - The Contractor shall meet the performance/acceptable quality level requirements for each deliverable/assessment area in the QASP, Attachment J-5. There will be monetary deductions based on unfavorable contractor performance as stated in the QASP. The sum of deductions assessed against the Contractor for failing to meet the performance/acceptable quality level requirements, across all contractor performance elements stated in the QASP, shall not exceed 5% of the awarded price of the Availability, including all Base and Option Items.

1.14 IDENTIFICATION OF CONDITION FOUND - In accordance with the requirements of NAVSEA

Standard Item 009-01, the contractor shall identify needed repairs and recommend corrective action during contract performance for work/deficiencies discovered which are not covered by the existing work package. For conditions to impact the critical path(s) /controlling item(s), the contractor shall notify the government via electronic media within 24-hours of discovery. This initial notification need not include all content required for a Condition Found Report (CFR), but must include a description of the condition/deficiency and an estimated timeframe for the offeror's professional recommendation for resolution, which shall not exceed five (5) working days as specified below.

Recommended repairs and corrective actions shall be submitted to the Government in the form of a CFR (intended to represent the "Work Request" described in DFARS 252.217-7028 “Over and Above Work”) per CDRL A002.

1.14.1 CONDITION FOUND NOTIFICATION TO GOVERNMENT

CFRs shall be submitted through the Navy Maintenance Database Re-platform (NMDR) within five (5) working days of discovery of the condition. At a minimum, the CFR will include the following:

(1) Identify contract, ship, and hull number

(2) Serialized by CFR number

(3) Identification of the applicable Work Item number

(4) Date requirement was discovered

(5) Description of the work requirement

(6) Specific location of the work

(7) Recommendation for corrective action

(8) Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change, future CNO or Continuous Maintenance Availability). Provide supporting rationale for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.

(9) Identification of related changes, if any, to the internal milestones and production and contract completion dates.

1.14.2 GOVERNMENT REVIEW AND RESPONSE TO CFR

The Maintenance Team will review the CFR. If the CFR is inadequate or incomplete, it will be rejected with time continuing to accrue (relative to five (5) working day requirement). As appropriate, the Government and contractor will need to meet, conduct ship checks and/or discuss the recommendation for corrective action further to determine the full scope of work required prior to final approval of the CFR. The contractor's accuracy reflected in the CFRs submitted may be evaluated in CPARS and utilized for past performance ratings on future requirements. Additionally, deductions may be assessed in accordance with Attachment J-5, QASP.

1.15 DATA REQUIRED FOR RESERVATION TASK REQUESTS (RTRs) and REQUEST FOR

CONTRACT CHANGES (RCCs) In the event a growth requirement or new work is validated and fully scoped, the Government may generate a Request for Contract Change (RCC) or Reservation Task Request (RTR) which the ACO may request a firm fixed price proposal from the contractor.

The contractor shall provide all Change Order Price Analysis (COPA) proposals to the ACO in response to RCCs and RTRs within seven (7) calendar days. A contractor’s COPA shall remain valid for a minimum of 14 calendar days, unless otherwise specified on an individual RCC or RTR by the ACO; if another timeline is specified by the Government on an individual RCC or RTR, the contractor’s COPA shall remain valid for that amount of time. A COPA addressing a change to the FFP contract shall include at a minimum:

a. Labor hours to be performed by the Prime Contractor __________

b. Subcontractor Quote (If applicable) * $__________

c. Material Quote (If applicable)** $__________

d. Mark-up (If applicable) $__________

*Subcontractor quotes shall include labor hours, labor rate, material (part number, description, unit cost, quantity, total cost, and vendor quotes for each line item), and tiered subcontractor quotes (if applicable)

** Material quote shall include the part number, description, unit cost, quantities, total cost, and vendor quotes for each line item

Note 1: Labor hours for both prime and subcontract shall be provided broken down by trade and labor mix.

Note 2: The required documentation must accompany the COPA for the COPA to be considered submitted to the ACO. See Attachment J-5, QASP, for deductions associated with late or invalid COPA submittals.

If circumstances arise where the contractor is unable to submit a COPA within seven (7) calendar days, the contractor shall notify the ACO in writing of the specific circumstances and provide a revised date in which a COPA proposal will be submitted. Additional time needed to complete a COPA may be granted solely at the discretion of the ACO. The new timeframe granted, solely at the discretion of the ACO and may differ from the contractor’s request, shall be met by the contractor.

Deductions may be assessed in accordance with Attachment J-5, QASP

1.16 NAVY MAINTENANCE DATABASE (NMD): The Contractor shall use NMD for the submission of Condition Found Reports throughout the administration of this contract. In addition to the submission of reports, the contractor shall also utilize NMD to enter in data fields for check points (scheduling, inspection data, inspection results), entering test and inspection plan (TIP) data, entering and adjudicating Corrective Action Requests (CAR) information, and CFR and Required Report submittal and management inside the program NMD is located at https://mfom.sscno.nmci.navy.mil/MFOM/DodStatement.aspx.

1.17 ORGANIZATION CHART AND EMPLOYEE ROSTER:

1.17.1 ORGANIZATION CHART - Within 30 days of contract award, submit a chart detailing each management, technical, engineering and production position from the highest company level to the lowest supervisory level. Include descriptions of each position describing the duties, responsibilities, authority and names of the individuals filling the positions. The organizational chart must represent the facility that will perform the work.

1.17.2 EMPLOYEE ROSTER: After receipt of award and prior to starting work aboard the vessel, the contractor must submit a list of employees who will work aboard ship to the Commanding Officer of the ship via the NSA Security Office. The list should be on company letterhead, include each employee's name and security clearance when required, and bear the signature of a company official.

1.18 AUTHORIZED CHANGES ONLY BY THE CONTRACTING OFFICER – No order, statement, or conduct of Government personnel who visit the Contractor's facilities or in any other manner communicates with Contractor personnel during the performance of this contract shall constitute a change under the "Changes" clause of this contract. The Contractor shall not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this contract.

The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and, notwithstanding provisions contained elsewhere in this contract, the said authority remains solely the Contracting Officer's. In the event the contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in charges incurred as a result thereof. The only exception to this is if the contractor is ordered to stop for a safety reason.

2. LOCATION: Government facilities are not available for this requirement. All work shall be completed at the contractor’s facilities or as otherwise directed by each individual work item.

3 SCHEDULE: USS O’KANE must be delivered, mission-ready, no later than 24 January 2020.

3.1 MILESTONES: In addition to the contract completion date of 24 January 2020, the Government has established execution dates for the milestones identified in Attachment J-3.

3.1.1 If any milestone event is not accomplished by the date provided, and the failure to accomplish any such milestone event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of subparagraph (a)(1)(ii) of the clause of this contract entitled "DEFAULT” (DFARS 252.217- 7009).

3.1.2 RESERVED.

3.2 DELAYS / DISRUPTIONS: The contractor shall coordinate the work effort with the NSA Project Manager on a daily basis to prevent changing situations from causing delays and disruptions. Disruption due to minor delays in obtaining access to spaces and operation of equipment are to be expected. A minor delay is defined as an eight (8) hour or less period. These disruptions are considered normal rather than unusual occurrences during the performance of tasks ordered under this contract. If, during contract performance, delays greater than those indicated above are encountered, the Contractor shall immediately verbally notify the Project Manager and Contracting Officer, followed by a written statement within 24 hours after occurrence of delay, stating time of impact, reason for delay, duration of impact, number of people affected, action taken to properly schedule the work, action taken to minimize impact, and the names of the Government person(s) contacted.

3.3 SCHEDULE AND ASSOCIATED REPORTS: The proposed scheduling of work, resources, key events and milestones submitted by the Contractor in accordance with Standard Item 009-60 during the course of contract performance shall not be materially different from the Schedule and Associated Reports provided in the Contractor’s technical proposal.

3.4 MILESTONES FOR CERTAIN REPORTS: Quality Assurance Plan (QASP) Attachment J-5 Deliverable 2: The Contractor shall complete the necessary work associated with the reports due on or before the first 20% of the docking duration, if applicable, as well as the reports due on or before the first 20% of the availability duration and submit to the Government the required reports in the necessary format and containing the required information as specified in the Work Item in accordance with their prescribed due dates or be subject to the deductions provided in Attachment J-5 Quality Assurance Surveillance Plan.

3.5 RESERVED.

4 SAFETY:

4.1 SAFETY INSPECTOR / FIRE MARSHALL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshall who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety Representative. This Inspector or Fire Marshall shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved Safety Plan.

4.2 PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:

(a) Protective hard hats that meet the following specifications:

(1) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated to be equally effective.

(2) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National Standard Safety requirements for Industrial Head Protection," Z89.1- 1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR

1910.135 Head Protection]

(b) Approved type Plano or prescription glasses meeting the following specifications:

(1) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.

(2) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1- 1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF

1910.133 Protective eye and face devices.]

(c) Safety toe shoes, with built-in protective toe box that meet the following specifications:

(1) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.

(2) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]

4.3 BLACK OXIDE COATED THREADED FASTENERS (BOCTFs): Due to safety concerns, use of BOCTFs is not authorized when installing or replacing threaded fasteners in the accomplishment of any work required by any Work Item in this contract.

4.4 FORCE PROTECTION CONDITION: The Navy is currently in force protection condition Bravo.

Any costs associated with delays, disruptions, or security precautions associated with this force protection condition level shall be included in your proposal. Contractors will not receive additional compensation for delays, disruptions, or security precautions associated with this force protection condition level.

4.5 FIRE DRILL: The Contractor shall coordinate the execution of a full scale fire drill with the NSA within the first 30 days after the ship's arrival at the contractor's facility. The drill will include at a minimum the requirements of the drill specified in NAVSEA Standard Items 009-08 (Fire Protection at Contractor's Facility; Accomplish) and 009-28 (Fire Prevention Requirements). For the contractor, this drill will require all production work to stop for a minimum of 4 hours during day shift on the selected day. As part of the drill, the contractor is required to evacuate the ship, provide a muster report of all personnel safely off ship, support the drill with any firefighting personnel/company emergency procedures, and support the disconnection of temporary services at the drill site. Temporary services at the drill site will be disconnected in the process of the drill, and the contractor will be responsible for restoring them after the drill. This drill will require involvement with the local fire department. For awareness, the government will be conducting the drill and using the evaluation criteria found in CH-12, 13, and Appendix A, of S0570-

AC-CCM-010/8010

5 OTHER REQUIREMENTS

5.1 USE/POSSESSION OF PERSONAL ELECTRONIC DEVICES (PED'S) - The possession and use of portable electronic devices (PED's) within the confines of any naval vessel, or in the contractor's facility where equipment removed from the vessel is being worked, is strictly controlled. Cellular phones with digital imaging capabilities are strictly prohibited. PED's may not be connected to any Navy-owned or controlled network. PED's may not be used to store or process any digital information associated with the conduct of the contract without written authorization from the Naval Supervising Activity (NSA). PED's include:

mobile computing devices such as personal digital assistants (PDA's);

hand-held or laptop computers;

mobile telephone devices such as data-enabled cellular telephones;

two-way pagers, including those with e-mail capability;

analog and digital sound recorders; and digital cameras, including cellular phones with digital imaging capabilities.

5.2 NON SMOKING POLICY - For bidding purposes, contractors are advised that in light of the Navy's policy regarding smoke-free facilities, the entire vessel, topside and below decks, is to be considered a "No Smoking Area" unless otherwise indicated by shipboard policy.

5.3 CITIZENSHIP REQUIREMENTS - The contractor shall comply with the Department of Defense Industrial Security Manual (DoD 5220.22), and any revisions to that manual as of the Bid Opening Date prescribed, for verification of all U. S. Citizens. Prospective offerors shall refer all questions pertaining to the above to NSA, Security Manager. The DoD Industrial Security Manual can be found at:

http://www.dtic.mil/whs/directives/corres/pdf/522022_vol3_2014.pdf

5.4 FIREMAIN - Ship's force fire main will not be available for contractor use as a temporary firemain or for firefighting purposes due to work on the system (ships force and contractor).

5.5 Critical work authorization during and beyond business hours: The contractor shall accept any form of electronic media or verbal authorizations to proceed from the Contracting Officer during and after normal hours, including weekends and holidays.

6 ACCOUNTABILITY OF MANHOUR AND MATERIAL RESERVATION

6.1 Accomplish the following, in addition to the specific requirements of the Job Order, for Growth Reservation CLINs which identify reservation of manhours or material dollars.

6.2 Identify task/discrepancies and initiate an estimate of manhours and material dollars on Reservation Task Request/Control Form (Attachment A) / RCC price proposal for each discrepancy or task identified to be accomplished under a reservation item or reservation paragraph, entering the date and estimate of labor and material, and deliver the estimate to the SUPERVISOR.

6.2.1 Reservation taskings shall not be used to accomplish work outside the scope of the specific Work Item identifying a reservation work paragraph.

6.3 The SUPERVISOR shall review the estimate submitted and if in agreement, shall sign the "RMC/NSA Authorization Agreement to Quote" blank, authorizing the work at the manhour and material dollars quoted. The contractor shall also sign the appropriate documentation acknowledging the final negotiated value or RCC negotiation summary sheet. The RMC/NSA contracts representative shall initial the form in the blank provided.

6.3.1 If there is a difference of opinion in the estimate provided by the contractor and RMC/NSA, the manhours and material dollars shall be negotiated immediately to resolve the difference. The negotiated manhour and material dollars shall then be entered in the provided "Revised Estimate" blocks for each RTR and shall be documented on a final negotiated summary sheet for each RCC with the required signatures as indicated in 6.3.

6.4 The Contractor shall enter the work completion date, sign and date the control form, and submit to the SUPERVISOR within two (2) days after completion of the tasking authorized.

6.5 Submit one legible copy, in approved transferrable media, of a weekly report listing all Work Items with manhour and material reservation paragraphs identified to the SUPERVISOR.

6.5.1 The report shall contain the following; Work Item number, reservation control form serial number, reservation paragraph number, total original manhours and material dollars allocated in each paragraph, the manhour and material dollars negotiated for each authorized tasking, and the remaining balances of manhour and material dollars.

6.6 Submit one legible copy, in approved transferrable media, of a final report no later than five days after completion of the availability to the SUPERVISOR.

6.6.1 The report shall contain the same information specified in 6.5.1.

6.7 The reservation manhours and material dollar requirements listed in the individual Growth Reservation CLINs are a part of this contract under the original solicitation and award. Therefore they are subject to the provisions, terms, conditions and clauses of this contract job order and the Master Ship Repair Agreement (MSRA)/The Agreement for Boat Repair (ABR).

6.7.1 The manhour reservation shall include both prime contractor and sub contractor efforts.

6.8 The balance of hours remaining in the Growth Reservation CLINs after negotiations have concluded, and it is evident that no additional work will be tasked, is subject to a decrease change order.

6.9 Only actual production manhours expended will be considered towards the contractors obligation to provide the defined reservation manhour effort. While supervision, quality assurance, and other nonproductive labor should be included in the pricing for reservation items in the original bid, they shall not count towards satisfying the contractors obligation to provide reserved manhours. The production manhour reservation shall not include any allowance for technical representatives or for any other Government directed source unless specifically addressed in the individual Work Item.

6.10 Material dollars shall be based on actual costs to the Contractor of acquiring the materials provided. Material dollars may include freight or duties which would be reflected on the invoice for the material. The Contractor shall not be allowed to add material handling charges, overhead (including G & A), or profit into the actual cost of materials expended toward the reservation.

6.11 The information received in the consolidated final report of 6.3 will be used by the Contracting Officer in the issuance of one contract modification, which will be a final settlement for all reservation Work Items.

6.12 The reservations listed in the Growth Reservation CLINs are Level of Effort to Completion. Once the scope of work for a task has been listed and a mutually agreeable number of manhours or materials has been agreed to, neither party will be entitled to an adjustment based on actual manhours or material dollars required.

6.13 Each task shall receive approval by the Navy Project Manager and the Administrative Contracting Officer (ACO). Each task shall not exceed 25 mandays without approval of the SUPERVISOR.

6.14 The SUPERVISOR will serialize each reservation control form as well as assign an individual number for each RCC.

6.15 Clause 5252.217-9107 GROWTH AND NEW WORK (SEP 1990) is not applicable to the following CLINs (0002, 0004, 0006, 0030-0048, 0050, 0051).

SECTION E - INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0029:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule for CLIN 0051 has been added:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

24-JAN-2020 1 N/A

FOB: Destination

SECTION I - CONTRACT CLAUSES

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 20 days prior to the availability start date. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

Applicable to CLINs 0015 – 0029

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor NLT than September 15th, 2019. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

Applicable to Growth Reservation CLINs 0002, 0004, 0006, 0030 – 0050, 0051

(End of clause)

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

DOCUMENTS/EXHIBITS/ATTACHMENTS

The following document(s), exhibit(s), and other attachment(s) form a part of this solicitation:

No. Document

Attachment S-1 Reserved Attachment S-2 Past Performance Questionnaire Attachment S-3 Pre-Proposal Information (PPI) Form Attachment S-4 Past Performance References Attachment S-5 Eligibility Criteria Data Sheet

The following document(s), exhibit(s), and other attachment(s) also form a part of this solicitation and will form a part of the contract resulting from this solicitation:

No. Document Attachment J-1 Specification Package No. TPPC-DDG77-SWRMC19-CN01, Errata 1 via

Amendment 0001, Errata 3, Errata 4, Errata 5, and Addendum 1 via Amendment 0003, Errata 6 via Amendment 0005

Attachment J-2 Work Item Plans, Drawings, and Other References

Attachment J-3 Execution Milestones and Key Event Dates Amendment 0004 Attachment J-4 Pricing Workbook, Amendment 0006 Attachment J-5 Quality Assurance Surveillance Plan Amendment 0003 Attachment J-6 Subcontracting Plan (to be incorporated upon award) Attachment J-7 Schedule Model Review

Exhibit A Contract Data Requirements List (CDRL) (DD Form 1423) A001-A003; A005-A009; A011; A012; A014 (Does not include A004, A0010, or A0013) Exhibit B Contract Data Requirements List (CDRL) (DD Form 1423) B001-B009 Exhibit C Contract Data Requirements List (CDRL) (DD Form 1423) C001-C002

(End of Summary of Changes)