Attachment_J-2_CHAMP_TRL_Table.pdf

PDF 72 KB Posted

Attached to
Common Hull Auxiliary Multi-Mission Platform (CHAMP) Federal contract opportunity
Solicitation number
N00024-18-R-2236
Issued by
Department of the Navy Naval Sea Systems Command

About this file

Attachment J-2

View the file

Other files for this federal contract opportunity

Other files attached to Common Hull Auxiliary Multi-Mission Platform (CHAMP), newest first.
File Type Posted
CHAMP_RFP_Amendment_0003.pdf PDF
Attachment_J-9__CHAMP_Section_L_CostPrice_Exhibits_Rev2.xlsx XLSX spreadsheet
N00024-18-R-2236_0002.pdf PDF
Attachment_J-9__CHAMP_Section_L_CostPrice_Exhibits_Rev1.xlsx XLSX spreadsheet
N00024-18-R-2236_0001.pdf PDF
Industry_Day_Registration_List_-_FINAL.xlsx XLSX spreadsheet
Attachment_J-8_CHAMP_DD254_Scan.pdf PDF
Attachment_J-5_IDES_Access_and_PKIIA_Awareness_Attributes.pdf PDF
Attachment_J-4_CHAMP_AoA_Table.docx DOCX document
Attachment_J-7_CHAMP_Deliverables_Schedule.pdf PDF
Attachment_J-9__CHAMP_Section_L_CostPrice_Exhibits.xlsx XLSX spreadsheet
Attachment_J-8_CHAMP_Draft_DD254.pdf PDF
N00024-18-R-2236.docx DOCX document
Attachment_J-6_CHAMP_CDRL.pdf PDF
Attachment_J-3_CHAMP_COR_CHANGE_RECOMMENDATION_FORM.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00024‐18‐R‐2236 Attachment J‐2

DISTRIBUTION STATEMENT A: Approved for public release. Distribution unlimited.

Technology Readiness Levels in the Department of Defense (DoD) (Source: DoD (2010), Defense Acquisition Guidebook)

Technology Readiness Level Description

1. Basic principles observed and reported

Lowest level of technology readiness. Scientific research begins to be translated into applied research and development. Examples might include paper studies of a technology's basic properties.

2. Technology concept and/or application formulated.

Invention begins. Once basic principles are observed, practical applications can be invented. Applications are speculative and there may be no proof or detailed analysis to support the assumptions. Examples are limited to analytic studies.

3. Analytical and experimental critical function and/or characteristic proof of concept.

Active research and development is initiated. This includes analytical studies and laboratory studies to physically validate analytical predictions of separate elements of the technology.

Examples include components that are not yet integrated or representative.

4. Component and/or breadboard validation in laboratory environment

Basic technological components are integrated to establish that they will work together. This is relatively "low fidelity" compared to the eventual system. Examples include integration of "ad hoc" hardware in the laboratory.

5. Component and/or breadboard validation in relevant environment.

Fidelity of breadboard technology increases significantly. The basic technological components are integrated with reasonably realistic supporting elements so it can be tested in a simulated environment. Examples include "high fidelity" laboratory integration of components.

6. System/subsystem model or prototype demonstration in a relevant environment.

Representative model or prototype system, which is well beyond that of TRL 5, is tested in a relevant environment.

Represents a major step up in a technology's demonstrated readiness. Examples include testing a prototype in a high‐ fidelity laboratory environment or in simulated operational environment.

7. System prototype demonstration in an operational environment.

Prototype near, or at, planned operational system.

Represents a major step up from TRL 6, requiring demonstration of an actual system prototype in an operational environment such as an aircraft, vehicle, or space.

Examples include testing the prototype in a test bed aircraft.

8. Actual system completed and qualified through test and demonstration.

Technology has been proven to work in its final form and under expected conditions. In almost all cases, this TRL represents the end of true system development. Examples include developmental test and evaluation of the system in its intended weapon system to determine if it meets design specifications.

9. Actual system proven through successful mission operations.

Actual application of the technology in its final form and under mission conditions, such as those encountered in operational test and evaluation. Examples include using the system under operational mission conditions.

TRL 8 and 9

Allowable

For

CHAMP

TRL 7

Requires Risk Plan

& Approval