Execution
USS SAN ANTONIO (LPD 17)
FY17 DPMA: 06Mar17-27Apr18
| 417 Days | ||
| 06Mar17 - 27Apr18 (417 days) | ||
| Start Date: | 6-Mar-17 |
| EXECUTION MILESTONES / KEY EVENTS | ||||||
| Key Event/Milestone | Current | Revised | Revised | |||
| A+ | Date | A+ | Date | A+ | Date | |
| AVAIL START DATE | 0 | 06-Mar-17 | 42800 | |||
| Transit Ship to KTR Facility | 0 | 06-Mar-17 | 42800 | |||
| Start Crew move Ashore | 2 | 08-Mar-17 | 42800 | |||
| Dock | 44 | 19-Apr-17 | 42800 | |||
| 20% Open & Inspect Complete | 85 | 30-May-17 | 42800 | |||
| 25% Conference | 99 | 13-Jun-17 | 42800 | |||
| 50% Conference | 212 | 04-Oct-17 | 42800 | |||
| Undock | 234 | 26-Oct-17 | 42800 | |||
| Combat Systems PCD | 357 | 26-Feb-18 | 42800 | |||
| Habitability Work Complete | 342 | 11-Feb-18 | 42800 | |||
| Crew Move Aboard | 351 | 20-Feb-18 | 42800 | |||
| 75% Conference | 322 | 22-Jan-18 | 42800 | |||
| EPPCD | 357 | 26-Feb-18 | 42800 | |||
| Engineering Hot Plant Testing | 357 | 26-Feb-18 | ||||
| Light Off Assessment | 399 | 09-Apr-18 | 42800 | |||
| Dock Trials | 404 | 14-Apr-18 | 42800 | |||
| Fast Cruise | 406 | 16-Apr-18 | 42800 | |||
| Sea Trials Begin | 409 | 19-Apr-18 | 42800 | |||
| Sea Trials Complete | 417 | 27-Apr-18 | ||||
| Transit Ship to NAVSTA | 417 | 27-Apr-18 | 42800 | |||
| Sea Trial Correction Period | 417 | 27-Apr-18 | 42800 | |||
| AVAIL COMPLETION | 417 | 27-Apr-18 | 42800 | |||
| 42800 | 42800 | |||||
| -42800 | 42800 | 42800 | ||||
| -42800 | 42800 | 42800 | ||||
| 42800 |