Government Response to Bidders' Questions - 06 MAY 2016

View the file

Other files

File Type Posted
N00024-16-R-2321-0011.pdf PDF
N00024-16-R-2321-0012_-_CONFORMED.pdf PDF
N00024-16-R-2321-0012.pdf PDF
N00024-16-R-2321-0012_-_CONFORMED_(REDLINE).pdf PDF
N00024-16-R-2321-0011_CONFORMED_(REDLINE).pdf PDF
N00024-16-R-2321-0011_CONFORMED.pdf PDF
N00024-16-R-2321-0009.pdf PDF
Conformed_N00024-16-R-2321_-_Amendment_0010_(REDLINE).docx DOCX document
N00024-16-R-2321_-_Amendment_0010.pdf PDF
Conformed_N00024-16-R-2321_-_Amendment_0010.docx DOCX document
Government_Responses_to_Bidder's_Questions__12.pdf PDF
N00024-16-R-2321-0008.pdf PDF
Government_Responses_to_Bidder's_Questions__11.pdf PDF
Ehbt_A_-_Contract_Data_Requirements_List_DD_FORM_1423_(2).pdf PDF
N00024-16-R-2321-0007.pdf PDF
Government_Responses_to_Bidder's_Questions__10.pdf PDF
N00024-16-R-2321-0006.pdf PDF
Government_Responses_to_Bidder's_Questions__9.pdf PDF
J-13_Past_Performance_Questionnaire.doc DOC document
Government_Responses_to_Bidder's_Questions__8.pdf PDF
J-8_-_Cost_Exhibit.xls XLS spreadsheet
Government_Responses_to_Bidder's_Questions__7.pdf PDF
N00024-16-R-2321-0005.pdf PDF
Government_Responses_to_Bidder's_Questions__6.pdf PDF
N00024-16-R-2321-0004.pdf PDF
N00024-16-R-2321-0003.pdf PDF
Government_Responses_to_Bidder's_Questions__5.pdf PDF
N00024-16-R-2321_Amendment_0002.pdf PDF
Government_Responses_to_Bidder's_Questions__3.pdf PDF
N00024-16-R-2321_-_Amendment_0001.pdf PDF
J-8_-_Cost_Exhibit.xls XLS spreadsheet
Government_Responses_to_Bidder's_Questions__2.pdf PDF
Government_Responses_to_Bidder's_Questions.pdf PDF
16-R-2321_FBO_Attachments.zip ZIP file
N00024-16-R-2321.pdf PDF
N00024-16-R-2321.pdf PDF
16-R-2321_FBO_Attachments.zip ZIP file
16-R-2321_Draft_RFP_Bidder's_Question_Responses_09MAR16.pdf PDF
16-R-2321_Draft_RFP_Bidder's_Question_Responses_03MAR16.pdf PDF
N00024-16-R-2321_-_DRAFT_RFP_-_19JAN2016.pdf PDF
J-6_-_Work_Item_Specifications.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP N00024-16-R-2321

Government Responses to Bidder's Questions

Question Number:

Question Source:

(RFP, attachment #, GFI title, etc.)

Page number and paragraph header from source: Question: Government Response

1 Section B, Note C Page 6 of 164, Note C

Solicitation Instruction: The rates, by Government Fiscal Year (GFY), for each direct labor category and the indirect rates provided in Exhibits L0005 and L0006 of Attachment J-8 Cost Exhibits of the Contractor’s proposal shall be the maximum GFY rates allowed under any order placed under this contract.

Question: Based upon potential out-year workload fluctuations and the Navy's new "Contracting Strategy", proposing maximum GFY direct labor and indirect rates through GFY 2021 represents a significant financial risk to prospective bidders. Is this solicitation language focused on Delivery Order cost estimating/negotiations or incurred cost limitations? Request the Navy revise this maximum GFY rate guidance to eliminate the direct labor rates and out-year indirect rates from the Maximum GFY rate scenario. This GFY direct labor rate and indirect rate "MAXIMUM" language is considered unreasonable given the workload uncertainty and labor cost/expense issues associated with the out-years. Please advise soonest.

The inclusion of Note C, maximum rates, provides an appropriate means for the Government to competitively award to a single source now and facilitates reduced administrative effort to place orders under the IDIQ in the future. This maximum rate cap applies to cost estimating for negotiations, and does not limit incurred costs on cost reimbursable orders. On CPAF orders, all allowable and allocable costs are reimbursable. For FFP orders, the successful contractor will be limited to the total price agreed upon, including profit which will be appropriately negotiated commensurate to the scope and risk associated with each future order.

2 Section C pg 30.Sec C.Item 0001.para h; pg 31.Item 0001 .Sec C.para q.sub para 2.iii; pg

32. Sec C.Item 0002 and 0003.para a

Request a copy of the DDG 1000 Class Design Build Process Specification

(DBPS)

The DBPS is not being provided with the RFP; portions of the DBPS will be provided to the successful contractor as needed after award. All information required to evaluate the 4E specs for proposal purposes are contained within the 4E work specs themselves (J-201)

3 RFP, Section L Page 138, Paragraph A, Physical Format

In the table provided on the subject page, please verify that all items for which the page count is listed as N/A are excluded from the page count.

All items for which the page count is listed as N/A are excluded from the page count.

4 RFP, Section L Page 148, Section IV, Past Performance

The subject paragraph directs offerors to prepare and send out Past Performance Questionnaires (PPQs) provided as Attachment J-13. Due to push back from Government contracting officers/program managers concerning redundant effort, several recent solicitations have specified that PPQs need not be sent out if the availability/contract is already covered by a completed CPARS Report. Will the Government revise the solicitation to include this exception for submitting PPQs?

The RFP is not being amended to include exceptions for submitting PPQs. Please note, however, that as stated on page 148, "offerors will not be evaluated negatively for a lack of past performance questionnaires received in response to this RFP."

5 RFP, Section L Page 138, Paragraph A, Physical Format

The table provided on the subject page refers to a Craft/Trade Staffing Plan in the row for Non-Cost Section IV. The detailed instructions for Non-Cost Proposal Section IV on RFP pages 147 and 148 make no reference to a Craft/Trade Staffing Plan. Is the Craft/Trade Staffing Plan referred to in the table the same as the Manhour and Material Matrix (Attachment J-9) required by the instructions for Non-Cost Section II, Element 2, on RFP page 146? Please clarify.

The Craft/Trade Staffing Plan referred to in the table on page 138 is not the same as the Trade/Craft Hours and Material Exhibit (Attachment J-9) required by the instructions for Non-Cost Section II, Element 2, on RFP page 146. Attachment J-9 is specific to the hours proposed for CLIN 0002 Order 0001 (DDG 1000 Industrial Efforts).

Non-Cost; Section IV: Facilities/Production Capabilities requires Yard-Wide Facility Utilization Data. This data shall be presented in Yard-Wide Man- Power Loading Charts and Yard-Wide Craft/Trade Staffing Plans for the ordering period.

An amendment will be issued to clarify the requirement that yard-wide data shall be presented in man-power loading charts and craft/trade staff plans for the IDIQ ordering period.

6 RFP

Section L, Page 140, (B) General Content Requirements (7th paragraph)

The subject paragraph states, "Submission to the Government of the Offeror's proposal, including the entire RFP…… will constitute an offer…….."

Question: Is it the intent of this paragraph that the Offeror submit the entire RFP with its proposal, or is the intent of this paragraph to just reiterate that the Offeror's proposal including the RFP will constitute an offer but only sections of the RFP requiring fill-ins and signatures are (as opposed to the entire RFP) are to be submitted with the proposal?

In accordance with page 140 (B) General Content Requirements, paragraph 7, "Submission to the Government of the Offeror's proposal, including the entire RFP [minus Sections L and M] and all of its attachments (completed as necessary) -- will constitute an offer and will indicate the Offeror's unconditional assent to the terms and conditions in this RFP and its attachments."

The intent of this paragraph is to instruct the offeror to submit the enitre RFP, minus Sections L and M, with its proposal.

7 RFP Attachment J-101

Attachment J-101 provides 6 work items for various management and support functions to support CLIN 0001. For pricing purposes, please clarify that no individual price breakdown is required for these work items since it appears that the requirements are subsets of the CLIN 0001 SOW in Section C and because, as stated in Section L, Offerors shall propose costs for the Government proovided hours for CLIN 0001 Order 0001."

No individual cost breakdown of the work items for CLIN 0001, Order 0001 is required. The requirements are subsets of the CLIN 0001 SOW in Section C and are provided for offerors to propose costs based on the Government-provided total labor hours expected for this order.

The labor mix for CLIN 0001 should be determined based on the provided CLIN 0001 statement of work and requirements of CLIN 0001- Order 0001, as provided in Attachments J-100, J-101, and J-102.

An amendment will be issued to edit Attachment J-8, L0004 to remove the cost breakdown by Work Item for CLIN 0001, Order 0001 only.

8 RFP

Section L, , Table L-4, paragraph (d) - Attachment J- 8 Exhibit L-4

The description of Exhibit L-004 states that it is specifically for listing subcontractors utilized for CLINs 0002, Order 0001 and CLIN 0001, Order 0001. Please provide clarification of what data requirements may be needed for subcontractors for the CLINs other than 0001 and 0002, in order for all subcontracts to roll up to the total subcontracts on Exhibit L001

In accordance with "Instructions for Attachment J-8 - Exhibit L0003 – CLIN Cost Element Breakdowns," subcontractor costs must also be included in the Offeror’s (prime contractor) cost exhibit. All Subcontractor costs shall be included in the ‘Subcontractors’ section of L0003. The elements identified as Subcontractor costs must exactly equal the cumulative bottom line totals from Attachment J-8-Exhibit L0003 submitted by the Subcontractor(s).

Data requirements for Subcontracts are included on page 155 - Section III: - Subcontractor Cost Data

Section J-201, WI 171-11-002, Mast/Above Deck structure (ADS Update);

accomplish

Drawing 180- 8634704_Rev_A, MAST

UPDATE STRUCTURAL

FABRICATION DWG

Contractor notes upon review of Reference that Drawing 180- 8634704_Rev_A, MAST UPDATE STRUCTURAL FABRICATION DWG was provided but not invoked by the Specification.

• Sheet 6 and 7, state ATTENTION TCDL Foundation installation is alignment Critical

• Sheet 16, states ATTENTION Mast Collor installation is alignment Critical

Can Contractor be provided a drawing illustrating the Centerline/Elemental Benchmarks?

Drawing BD702004, Centerline/Elemental Benchmarks, will be provided via an amendment to the RFP attachments.

Section J-201, WI 171-11-002, Mast/Above Deck structure (ADS Update);

accomplish

Page 2 of 41, Paragraph 3.1, Reference 2.4, Contractor notes, Ref 2.4 drawing 528-8659810_Rev_A, identifies the following listed Items as being provided IAF the only Manufacture part numbers provided are for

BIW.

• Item F0003, 2 each, penetration, composite deck drain assembly IAW

NGSS DWG., 4.512” THICK

P/N 13224-871

• Item F0012, 2 each, pad, mounting, steel, for composite decks and bulkheads, IAW DETAIL 124A & 15-4B NGSS STANDARD DWG, 82.9 – 89.2mm thick P/N 17071-637

• Item F0013, 2 each, penetration, for steel and can pipe deck or bulkhead, 1-1/2” NPS P/N 13225-770

• Item F0026, 2 each, penetration, for steel and can pipe deck or bulkhead, 2” NPS

P/N 13225-869

Contractor requests clarification as to if this material is being provided as GFM and not IAF?

The following items identified within Ref 2.4 drawing 528- 8659810_Rev_A are IAF:

• Item F0003, 2 each, penetration, composite deck drain assembly

IAW NGSS DWG., 4.512” THICK, P/N 13224-871

• Item F0012, 2 each, pad, mounting, steel, for composite decks and bulkheads, IAW DETAIL 124A & 15-4B NGSS STANDARD DWG, 82.9 – 89.2mm thick, P/N 17071-637

• Item F0013, 2 each, penetration, for steel and can pipe deck or bulkhead, 1-1/2” NPS, P/N 13225-770

• Item F0026, 2 each, penetration, for steel and can pipe deck or bulkhead, 2” NPS, P/N 13225-869 The P/Ns addressed above are catalog numbers listed in column, "PY Use Only". These catalog numbers are inconsequential information within the drawing.

Section J-201, WI 441-11-010, Program of Record (POR) Antennas C4I Configuration Alternative;

accomplish

Page 4 of 7, Paragraph 3.1, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.7, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds, has not been received as of 04/18/2016,

• Ref 2.8, SP002006_Rev_F, Composite Structure Standard Procedures for Mounting Misc Foundations, has not been received as of 04/18/2016,

• Ref 2.10, drawing 304-8294041_Rev_F, Main Wireway Key Plan, has not been received as of 04/18/2016,

• Ref 2.14, 2A447C001_Rev_-, LOS/BLOS HF Systems Cable Integrity Verification, has not been received as of 04/18/2016,

• Ref 2.15, 2A447C002_Rev_A, LOS/BLOS UHF Systems Cable Integrity Verification, has not been received as of 04/18/2016,

• Ref 2.16, 2A448C001D_Rev_-, SATCOM Element Cable Integrity Verification, has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following references will be provided via an amendment to the RFP attachments:

• Ref 2.7, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds

• Ref 2.8, SP002006_Rev_F, Composite Structure Standard Procedures for Mounting Misc Foundations

• Ref 2.10, drawing 304-8294041_Rev_F, Main Wireway Key Plan

• Ref 2.14, 2A447C001_Rev_-, LOS/BLOS HF Systems Cable Integrity Verification

• Ref 2.15, 2A447C002_Rev_A, LOS/BLOS UHF Systems Cable Integrity Verification

• Ref 2.16, 2A448C001D_Rev_-, SATCOM Element Cable Integrity Verification

Section J-201, WI 448-11-008, Program of Record (POR) Antennas Sponsons and C4I Configuration Alternative;

accomplish

Pages 2 of 48, Paragraph 3.1, Reference 2.2, Contractor notes, Ref 2.2 drawing 100-8697528_rev_A, identifies the following listed 2nd tier drawings for Composite structure side shell & deck.

• Ref 3, Drawing 100-8294272. COMPOSITE STRUCTURE DECK 04 LVL ZONE

• Ref 7, Drawing 100-8694355, COMPOSITE STRUCTURE PORT SIDESHELL

ASSEMBLY SEQUENCE 03-07 LVL

• Ref 8, Drawing 100-8694356, COMPOSITE STRUCTURE PORT SIDESHELL

ASSEMBLY SEQUENCE 03-07 LVL

Ref 2.4 drawing 555-8697544_Rev_A, identifies the following listed 2nd tier drawing for Composite structure for mounting Piping.

• Ref 5, SP002008, COMPOSITE STRUCTURE STANDARD PROCEDURES FOR

MOUNTING PIPING

Contractor request the Planning yard provide copies of the above listed 2nd tier references.

The following reference will be provided via an amendment to the RFP attachments:

• Ref 5, SP002008, COMPOSITE STRUCTURE STANDARD PROCEDURES

FOR MOUNTING PIPING

• Ref 3, Drawing 100-8294272. COMPOSITE STRUCTURE DECK 04 LVL

ZONE 4140

• Ref 7, Drawing 100-8694355, COMPOSITE STRUCTURE PORT

SIDESHELL ASSEMBLY SEQUENCE 03-07 LVL

• Ref 8, Drawing 100-8694356, COMPOSITE STRUCTURE STBD

SIDESHELL ASSEMBLY SEQUENCE 03-07 LVL

Section J-201, WI 448-11-008, Program of Record (POR) Antennas Sponsons and C4I Configuration Alternative;

accomplish

Pages 2 & 3 of 48, Paragraph 3.1, References 2.8, 2.12, 2.13, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.8, SP002005_Rev_B, Composite Structure Standard Procedures for Composite Reinforcement, has not been received as of 04/18/2016,

• Ref 2.12, drawing 472-8298152_Rev_A, Special Treatments Installation Procedures Manual DDG 1000, has not been received as of 04/18/2016, Contractor request the above listed references and missing pages be made available.

• Ref 2.13, drawing 635-8299256_Rev_A2, Arrangement and Installation Details for Topside Insulation on Hangar and Deckhouse, has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following reference will be provided via an amendment to the RFP attachments the RFP:

• Ref 2.8, SP002005_Rev_B, Composite Structure Standard Procedures for Composite Reinforcement

• Ref 2.12, drawing 472-8298152_Rev_A, Special Treatments Installation Procedures Manual DDG 1000

• Ref 2.13, drawing 635-8299256_Rev_A2, Arrangement and Installation Details for Topside Insulation on Hangar and Deckhouse

Section J-201, WI 448-11-080, X/KA Antenna System Installation;

Accomplish

Pages 1 & 2 of 23, Paragraphs 3.1, 3.4, 3.5, 3.6.1, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.3, PL8243741-1, Antenna Installation X/KA, (PC0136, REV A, MARKUP) (PARTS LIST), has not been received as of 04/18/2016,

• Ref 2.4, PL8243741-2, Antenna Installation X/KA, (Shelf Life Items) (PARTS LIST), has not been received as of 04/18/2016,

• Ref 2.5, PL8247866-1, IKEE Kit, Electrical (PARTS LIST) has not been received as of 04/18/2016,

• Ref 2.6, 44800-8243741, Antenna Installation XKA, (PC01036, REV A, MARKUP 06/30/14), has not been received as of 04/18/2016,

• Ref 2.7, DDX_RCIA_02440, DDX Request for Clarification, Interpretation or Assistance, has not been received as of 04/18/2016,

• Ref 2.8, 44800-8270783, XKa Antenna assembly – Installation, (PC01036, REV A, MARKUP 06/30/14), has not been received as of 04/18/2016,

• Ref 2.9, SSG-M6001-053, Revision Date 07/05/2012, Carbon Vinyl Ester Composite Panel Boring, Cutting and Milling Requirements

• Ref 2.10, SP002005_Rev_B, Composite Structure Standard Procedures for Composite Reinforcement, has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following references will be provided via an amendment to the RFP attachments:

• Ref 2.3, PL8243741-1, Antenna Installation X/KA, (PC0136, REV A, MARKUP) (PARTS LIST)

• Ref 2.4, PL8243741-2, Antenna Installation X/KA, (Shelf Life Items)

(PARTS LIST)

• Ref 2.5, PL8247866-1, IKEE Kit, Electrical (PARTS LIST)

• Ref 2.6, 44800-8243741, Antenna Installation XKA, (PC01036, REV A, MARKUP 06/30/14)

• Ref 2.7, DDX_RCIA_02440, DDX Request for Clarification, Interpretation or Assistance

• Ref 2.8, 44800-8270783, XKa Antenna assembly – Installation, (PC01036, REV A, MARKUP 06/30/14)

• Ref 2.9, SSG-M6001-053, Revision Date 07/05/2012, Carbon Vinyl Ester Composite Panel Boring, Cutting and Milling Requirements

• Ref 2.10, SP002005_Rev_B, Composite Structure Standard Procedures for Composite Reinforcement

Section J-201, WI 472-11-002, Passive Electronic Warfare System Upgrades;

accomplish

Page 2 of 14, Paragraph 3.1, References 2.8, 2.10, 2.11, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.8, drawing 472-8298152_Rev_A, Special Treatment Installation Procedures Manual DDG 1000, has not been received as of 04/18/2016,

• Ref 2.10, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds, has not been received as of 04/18/2016

• Ref 2.11, SP002006-BIW_Rev_F, Composite Structure Standard Procedures for Mounting Misc Foundations, has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following references will be provided via an amendment to the RFP attachments:

• Ref 2.10, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds

• Ref 2.11, SP002006-BIW_Rev_F, Composite Structure Standard Procedures for Mounting Misc Foundations

• Ref 2.8, drawing 472-8298152_Rev_A, Special Treatment Installation Procedures Manual DDG 1000

Section J-201, WI 492-11-002, Reinstate Advance Flight Deck Lights (AFDL) Installation:

Accomplish

Page 2 of 19, Paragraphs 3.7, 3.11.1, 3.12, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.5, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds, has not been received as of 04/18/2016

• Ref 2.6, BD406003_Rev_B, Grounding and Bounding Standard Methods for Composite Structures, has not been received as of 04/18/2016

• Ref 2.8, 3C588C001, AFDL Intensity and Operational Test

Contractor request the above listed missing references be made available.

The following references will be provided via an amendment to the RFP attachments:

• Ref 2.5, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds

• Ref 2.6, BD406003_Rev_B, Grounding and Bounding Standard Methods for Composite Structures

• Ref 2.8, 3C588C001, AFDL Intensity and Operational Test

Section J-201, WI 711-11-002, Advanced Gun System Inter-Ship Replenishment System (AIRS):

update

Page 2 of 5, Paragraph 3.2, Contractor notes, Para 3.2, states “Contractor to provide the services of a qualified Raytheon BAE Systems Original Equipment Manufacturer (OEM), field service technical representative to oversee, direct and verify the installation and testing of the AIRS system components, as directed by the PMS 500 Representative”.

• Contractor notes that Raytheon & BAE Systems are not the same company.

Contractor request clarification of correct OEM technical representative that is required to be provided?

The correct OEM technical representative is BAE Systems. 711-11-002 Para 3.2 will be correct and updated via an amendment to the RFP.

Section J-201, WI 711-11-002, Advanced Gun System Inter-Ship Replenishment System (AIRS):

update

Page 2 of 5, Paragraph 3.4, Para 3.4, states “Accomplish the fabrication of new MT61 and MT62 AIRS Tip Stand and Tip Stand Assembly foundations, MT61 and MT62 Amplifier foundations, MT62 Pass Through Assembly foundation, MT61 Rotate Motor Table Control foundation, and AC Magnetic Controller foundation in accordance with sheets 14 through 22 of 2.2”.

• Para 5.1.1, states “As identified on sheets 24 through 26 of Ref 2.2” as (GFM) material.

• Contractor notes that all of the material is identified as (IAF) on sheets 24 through 26 of Ref 2.2.

• Contractor further notes that (MT61 and MT62 Amplifier foundations) that are shown on sheet 24 are identified as assemblies, A001 for MT62 Amplifier foundation and A002 for MT61 Amplifier foundation.

Contractor requests clarification regarding if all of the material identified on sheets 24 through 26 of Ref 2.2, will be provided as (GFM) material vice (IAF) and are the assemblies A001 (MT62 Amplifier foundation) and A002 (MT61 Amplifier foundation) be provided (GFM) as completed assemblies including all required machining and drilling?

All of the material identified on sheets 24 through 26 of Ref 2.2 are IAF with the Contractor procuring and fabricating the assemblies for A001 (MT62 Amplifier foundation) and A002 (MT61 Amplifier foundation), including all required machining and drilling. Paragraph 5, GFM, shall be revised accordingly and updated via an amendment to the RFP.

19 RFP Page 1, Block 9 Request an extension of 3 weeks to the bid due date due to the new and unique complexities of this Solicitation. This extension will allow the necessary time to properly develop a thorough, responsive proposal.

An amendment will be issued extending the proposal due date by two weeks (10 June 2016).

20 RFP RFP Section J-10 Please provide 2nd tier reference 8 of Drawing 582-8293829, Number 321- 8294070 titled, "HV Power System One-Line Diagram."

The following reference will be provided via an amendment to the RFP attachments:

• 2nd tier reference 8 of Drawing 582-8293829, Number 321-8294070 titled, "HV Power System One-Line Diagram."

21 RFP

Section L, Page 138, Additional Information to Offerors

The RFP is silent regarding a shipcheck of the vessel. A shipcheck is essential to the development of accurate, responsive estimates for the 14 work items in CLIN 0002. Please provide a shipcheck opportunity and details and extend the bid due date an appropriate amount of time to allow incorporation of the shipcheck findings into the estimate/bid.

Shipcheck opportunities will not be provided until after award of the IDIQ, CLIN 0001 Order 0001, and CLIN 0002 Order 0001. Shipchecks will occur during the DDG 1000 PDA planning period from the ship's arrival in homeport (San Diego, CA) until transit from the Naval Station to the Execution Yard. Prior to the start of PDA, the execution yard and the Navy will modify CLIN 0002 Order 0001 to incorporate the remaining level of effort (LOE) PDA work specifications into the availability. The offeror's proposal should be estimated based upon the available information provided within the RFP and attachments.

RFP Section J, Attachment J-6

Attachment J-6

The 54 drawings listed in Attachment 1 of this question are referenced in the specification to either accomplish or for reference purposes, however, they were not provided with the specification. In addition, for line 48 of the attachment, there appears to be a more current Rev 3 available. For line 54 of the attachment, it is unclear which revision of the drawing was provided and how it corresponds to the specification since the specification requires Rev (-), the title block of the drawing shows Rev (a) but the revision block and the follow pages of the drawing indicate that it is Rev (B). Please provide missing drawings and clarify the two drawing discrepancies as soon as possible. Thank you.

The drawings referenced in this question will be answered as individual bidders questions.

23 RFP Section J, Attachment J-6

Attachment J-6

For Work Item 448-11-008, the following drawings are missing pages:

Drawing 100-8697528 Rev A is missing page 2. Drawing 600-8697534 Rev A is missing page 1. Drawing 555-8697544 Rev A is missing page 2. Drawing 512-8696744 Rev A is missing page 2. Please provide as soon as possible in order to be able to complete estimates.

On drawings: 100-8697528, Rev A; 555-8697544 Rev A; and 512- 8697444, sheet 2 is not used per the index on sheet 1 of each of those drawings.

For drawing 600-8697534 Rev A, sheet 1 was included with the final RFP attachments.

171-11-002, 448-11- 008, 461-11-001, 472-11-002

Drawing Drawing 472-8298152-A Not available in disc provided Drawing 472-8298152-A will be provided via an amendment to the RFP attachments.

25 171-11-002 Drawing Drawing 447-8696705-A Not available in disc provided Drawing 447-8696705-A was provided with the RFP attachments. See page 145 of filename: 171-11-002 Mast Install Navy Review.

26 171-11-002 Drawing Drawing 512-8659808-A Not available in disc provided Drawing 512-8659808-A was provided with the RFP as filename: 171- 11-002-V-Bundle.

27 171-11-002 Test Procedure Test Procedure 2C612C001 Not available in disc provided Test Procedure 2C612C001 will be provided via an amendment to the RFP attachments.

171-11-002, 448-11- 008, 448-11-080

Procedure Procedure SP002005-B Not available in disc provided Procedure SP002005-B will be provided via an amendment to the RFP attachments.

29 171-11-002 Drawing Drawing 304-8294041-F Not available in disc provided Drawing 304-8294041-F will be provided via an amendment to the RFP attachments.

441-11-010, 448-11- 008, 472-11-002, 980-90-105

Manual Owners Manual For DDG1000 Composite Deckhouse and Hanger Not available in disc provided

Owners Manual for DDG 1000 Composite Deckhouse and Hangar was provided with the RFP in J-7 Attachment.

441-11-010, 461-11- 001, 472-11-002, 492-11-002, 711-11-

Drawing Drawing SP002001-BIW-C Not available in disc provided Drawing SP002001-BIW-D is the latest version and will be provided via an amendment to the RFP attachments.

441-11-010, 472-11-

Drawing Drawing SP002006-F Not available in disc provided Drawing SP002006-F will be provided via an amendment to the RFP attachments.

33 441-11-010 Drawing Drawing 304-8294041-F Not available in disc provided Drawing 304-8294041-F will be provided via an amendment to the RFP attachments.

34 441-11-010 Drawing Drawing 406-8289952-B Not available in disc provided

Ref 2.11 of the Work Item 441-11-010 references Drawing 406- 8298952-B, Drawing 406-8289952-B appears to be a typographical error. Drawing 406-8298952-B will be provided via via an amendment to the RFP attachments.

35 441-11-010 Test Procedure Test Procedure 2A447C001 Not available in disc provided Test Procedure 2A447C001 will be provided via an amendment to the RFP attachments.

36 441-11-010 Test Procedure Test Procedure 2A447C002-A Not available in disc provided Test Procedure 2A447C002-A will be provided via an amendment to the RFP attachments.

37 441-11-010 Test Procedure Test Procedure 2A448C001D Not available in disc provided Test Procedure 2A448C001D will be provided via an amendment to the RFP attachments.

38 448-11-008 Drawing Drawing 635-8299256-A2 Not available in disc provided Drawing 635-8299256-A2 will be provided via an amendment to the RFP attachments.

39 448-11-080 Drawing Drawing PL8273741-1 Not available in disc provided Drawing PL8273741-1 will be provided via an amendment to the RFP attachments.

40 448-11-080 Drawing Drawing PL8243741-2 Not available in disc provided Drawing PL8243741-2 will be provided via an amendment to the RFP attachments.

41 448-11-080 Drawing Drawing PL8247866-1 Not available in disc provided Drawing PL8247866-1 will be provided via an amendment to the RFP attachments.

42 448-11-080 Drawing Drawing 44800-8243741 Not available in disc provided Drawing 44800-8243741 will be provided via an amendment to the RFP attachments.

43 448-11-080 Unknown DDX RCIA 02440 Not available in disc provided DDX RCIA 02440 will be provided via an amendment to the RFP attachments.

44 448-11-080 Drawing Drawing 44800-8270783 Not available in disc provided Drawing 44800-8270783 will be provided via an amendment to the RFP attachments.

45 448-11-080 Unknown SSG-M6001-053 Not available in disc provided SSG-M6001-053 will be provided via an amendment to the RFP attachments.

46 457-11-001 Mfg Drawing Mfg Drawing 46100-8244776 Not available in disc provided Mfg Drawing 46100-8244776 will be provided via an amendment to the RFP attachments.

47 457-11-001 Mfg Drawing Mfg Drawing 46100-8244767 Not available in disc provided Mfg Drawing 46100-8244767 will be provided via an amendment to the RFP attachments.

48 457-11-001 Mfg Drawing Mfg Drawing 46100-8244792 Not available in disc provided Mfg Drawing 46100-8244792 will be provided via an amendment to the RFP attachments.

49 457-11-001 Mfg Drawing Mfg Drawing 46100-8244769 Not available in disc provided Mfg Drawing 46100-8244769 will be provided via an amendment to the RFP attachments.

50 457-11-001 Mfg Drawing Mfg Drawing 46100-8244771 Not available in disc provided Mfg Drawing 46100-8244771 will be provided via an amendment to the RFP attachments.

51 457-11-001 Mfg Drawing Mfg Drawing 46100-8244774 Not available in disc provided Mfg Drawing 46100-8244774 will be provided via an amendment to the RFP attachments.

52 457-11-001 Mfg Drawing Mfg Drawing 46100-8244772 Not available in disc provided Mfg Drawing 46100-8244772 will be provided via an amendment to the RFP attachments.

53 457-11-001 Mfg Drawing Mfg Drawing 46100-8244773 Not available in disc provided Mfg Drawing 46100-8244773 will be provided via an amendment to the RFP attachments.

54 457-11-001 Mfg Drawing Mfg Drawing 46100-8244585 Not available in disc provided Mfg Drawing 46100-8244585 will be provided via an amendment to the RFP attachments.

55 457-11-001 Mfg Drawing Mfg Drawing 46100-8244775 Not available in disc provided Mfg Drawing 46100-8244775 will be provided via an amendment to the RFP attachments.

56 457-11-001 Mfg Drawing Mfg Drawing 46100-8244796 Not available in disc provided Mfg Drawing 46100-8244796 will be provided via an amendment to the RFP attachments.

57 457-11-001 Drawing Drawing 807-5037407-A Not available in disc provided Mfg Drawing 807-5037407-A will be provided via an amendment to the RFP attachments.

58 457-11-001 Test Procedure Test Procedure 2A461C007 Not available in disc provided Test Procedure 2A461C007 will be provided via an amendment to the RFP attachments.

59 457-11-001 Drawing Drawing 583-8294002-B Not available in disc provided Drawing 583-8294002-B will be provided via an amendment to the RFP attachments.

60 461-11-001 Drawing Drawing 470-8306541-B Not available in disc provided Drawing 470-8306541-B will be provided via an amendment to the RFP attachments.

61 461-11-001 Drawing Drawing 470-8306542-B Not available in disc provided Drawing 470-8306542-B will be provided via an amendment to the RFP attachments.

62 461-11-001 Test Procedure Test Procedure 2A461C006 Not available in disc provided Test Procedure 2A461C006 will be provided via an amendment to the RFP attachments.

63 492-11-002 Test Procedure Test Procedure 3C588C001 Not available in disc provided Test Procedure 3C588C001 will be provided via an amendment to the RFP attachments.

64 522-20-001 Drawing Drawing 8100-2400-0062-BH Not available in disc provided Drawing 8100-2400-0062-BH will be provided via an amendment to the RFP attachments.

65 711-11-002 Drawing Drawing B117009-B Not available in disc provided Drawing B117009-B will be provided via an amendment to the RFP attachments.

66 711-11-002 Mfg Drawing Mfg Drawing BFD370005-B Not available in disc provided Drawing BFD370005-B will be provided via an amendment to the RFP attachments.

Section J-201, WI 171-11-002, Mast/Above Deck structure (ADS Update);

accomplish

Page 2 of 41, References 2.8, 2.12, 2.13, 2.17, 2.18, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.8, drawing 472-8298152_Rev_A, Special Treatment Installation Procedures Manual DDG 1000, has not been received as of 04/18/2016,

• Ref 2.12, 2C612C001, Test Procedures, Lifeline, Liferail and Helo Safety Barrier Strength and Load Test, has not been received as of 04/18/2016,

• Ref 2.13, SP002005_Rev_B, Composite Structure Standard Procedures for Composite Reinforcement, has not been received as of 04/18/2016,

• Ref 2.17, drawing 304-8294041_Rev_F, Main Wireway Key Plan, has not been received as of 04/18/2016,

• Ref 2.18, Test Procedure Volumetric Testing/Balancing DDG 1000 (TBD), has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following references were provided via Amendment 0002 to the RFP attachments:

• Ref 2.8, drawing 472-8298152_Rev_A, Special Treatment Installation Procedures Manual DDG 1000

• Ref 2.13, SP002005_Rev_B, Composite Structure Standard Procedures for Composite Reinforcement

• Ref 2.12, 2C612C001, Test Procedures, Lifeline, Liferail and Helo Safety Barrier Strength and Load Test

• Ref 2.17, drawing 304-8294041_Rev_F, Main Wireway Key Plan

• Ref 2.18, Test Procedure Volumetric Testing/Balancing DDG 1000 is revised within the WI 171-11-002 to reflect the correct Test Procedure 4C512C004, DDG 1000 Class Test Procedure for Zone, System, Compartment, and Terminal Volumetric Airflow Test and identify the applicable HVAC system to include terminal airflow rates. The revised Spec 171-11-002 will be provided via a forthcoming amendment to the RFP attachments.

Section J-201, WI 171-11-002, Mast/Above Deck structure (ADS Update);

accomplish

Page 2 of 41, Paragraph 3.1, Reference 2.5, Contractor notes,

• Ref 2.5 drawing 304-8659807, sheet 5 implies the mast is being fabricated however sheet 5 has notes that show to tubes being installed on the fabrication drawing 180-8634704.

• Ref 2.5 drawing 304-8659807, sheet 6 has the T-bars locations local note sheet 5 states holes for swage tubes are lofted and cut per Ref 6, drawing 180-8634704 not supplied with package.

Contractor requests clarification as to if the mast is being fabricated are the studs for the T-bars being installed at that time?

The mast will be provided as GFM. The swage stuffing tubes and studs for the T-bars referenced in Ref 2.5 drawing 304-8659807, shall be installed by the Contractor during erection of the mast. The holes for the swage tubes will be provided pre-cut for installation.

Section J-201, WI 171-11-002, Mast/Above Deck structure (ADS Update);

accomplish

Page 4 of 41, Paragraph 3.17, Contractor notes, Para 3.17 states “Accomplish removals, modifications and installations to piping drain, water mist, and PAO cooling systems in accordance with 2.5”.

• However Ref 2.5, drawing 304-8659807_Rev_A, Mast Update Main Cableway Installation Drawing & ML, has no pipe requirements

• Contractor believes that Para 3.17, is actually intended to accomplish the requirements of Ref 2.4, drawing 555-8659810_Rev_A, Mast Update Piping Water Mist Installation Drawing and ML.

Please, review and advise.

The revised spec 171-11-002 will be provided via a forthcoming amendment to the RFP attachments, which reflects the correct reference from Ref 2.5, drawing 304-8659807_Rev_A, Mast Update Main Cableway Installation Drawing & ML to the Ref 2.4, drawing 555- 8659810_Rev_A, Mast Update Piping Water Mist Installation Drawing

& ML.

Section J-201, WI 457-11-001, Multi-Function Towed Array System (MFTA);

install

Pages 2 & 3 of 10, Paragraphs 3.3.2, 3.4.1, 3.4.2, 3.4.3, 3.4.4, 3.4.5, 3.4.6, 3.4.7, 3.4.8, 3.4.9, 3.5, 3.24, 3.25, References 2.6 through 2.17 and 2.20, 2.22, 2.23, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.6, 46100-8244776, ODIM Spectrum Mfg Dwg, MTAH General Arrangement, has not been received as of 04/18/2016,

• Ref 2.7, 46100-8244767, ODIM Spectrum Mfg Dwg, MTAH Transom Seal Assembly, has not been received as of 04/18/2016,

• Ref 2.8, 46100-8244792, ODIM Spectrum Mfg Dwg, MTAH Maintenance Kit, MSE ID: 461-028-0101, has not been received as of 04/18/2016,

• Ref 2.9, 46100-8244769, ODIM Spectrum Mfg Dwg, MTAH Array Handling Tray, has not been received as of 04/18/2016,

• Ref 2.10, 46100-8244771, ODIM Spectrum Mfg Dwg, MTAH Drogue Handling Unit, has not been received as of 04/18/2016,

• Ref 2.11, 46100-8244774, ODIM Spectrum Mfg Dwg, MTAH Operator Control Station, has not been received as of 04/18/2016,

• Ref 2.12, 46100-8244772, ODIM Spectrum Mfg Dwg, MTAH Levelwind Assembly, has not been received as of 04/18/2016,

• Ref 2.13, 46100-8244773, ODIM Spectrum Mfg Dwg, MTAH Towing Winch, has not been received as of 04/18/2016,

• Ref 2.14, 46100-8244585, ODIM Spectrum Mfg Dwg, MTAH 440VAC Isolation Transformer, has not been received as of 04/18/2016,

• Ref 2.15, 46100-8244775, ODIM Spectrum Mfg Dwg, MTAH Power Control Cabinet, has not been received as of 04/18/2016,

• Ref 2.16, 46100-8244796, Rev – MFTA Tow Cable, MSE ID 461-029-0201, has not been received as of 04/18/2016,

• Ref 2.17, drawing 807-5037407_Rev_A, AN/SQQ-89A(V) 15 MFTA Towed Body, MSE ID 461-024-0101, has not been received as of 04/18/2016,

• Ref 2.20, BD406003_Rev_B, Grounding and Bonding Standard Methods for Composite Structure, has not been received as of 04/18/2016, The following references were provided via Amendment 0002 to the RFP attachments:

• Ref 2.23, drawing 583-8294002_Rev_B, Major Equipment Removal Routes

• Ref 2.6, 46100-8244776, ODIM Spectrum Mfg Dwg, MTAH General Arrangement

• Ref 2.7, 46100-8244767, ODIM Spectrum Mfg Dwg, MTAH Transom Seal Assembly

• Ref 2.8, 46100-8244792, ODIM Spectrum Mfg Dwg, MTAH Maintenance Kit, MSE ID: 461-028-0101

• Ref 2.9, 46100-8244769, ODIM Spectrum Mfg Dwg, MTAH Array Handling Tray

• Ref 2.10, 46100-8244771, ODIM Spectrum Mfg Dwg, MTAH Drogue Handling Unit

• Ref 2.11, 46100-8244774, ODIM Spectrum Mfg Dwg, MTAH Operator Control Station

• Ref 2.12, 46100-8244772, ODIM Spectrum Mfg Dwg, MTAH Levelwind Assembly

• Ref 2.13, 46100-8244773, ODIM Spectrum Mfg Dwg, MTAH Towing Winch

• Ref 2.14, 46100-8244585, ODIM Spectrum Mfg Dwg, MTAH 440VAC Isolation Transformer

• Ref 2.15, 46100-8244775, ODIM Spectrum Mfg Dwg, MTAH Power Control Cabinet

• Ref 2.16, 46100-8244796, Rev – MFTA Tow Cable, MSE ID 461-029-

• Ref 2.17, drawing 807-5037407_Rev_A, AN/SQQ-89A(V) 15 MFTA Towed Body, MSE ID 461-024-0101

Section J-201, WI 461-11-001, Nixie SLQ Variant and Winch System:

accomplish

Pages 1 & 2 of 6, Paragraphs 3.4.2, 3.7, 3.8, 3.9, 3.16, 3.20.1, 3.21, 3.22, References 2.4, 2.5, 2.6, 2.7, 2.13, 2.15, 2.16, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.4, K939000065_Rev_E, Foundation “C” Winch 25A, has not been received as of 04/14/2016,

• Ref 2.5, K939000050_Rev_G, Transmitter Foundation 25A, has not been received as of 04/14/2016,

• Ref 2.6, drawing 470-8306541_Rev_B, Fleet Angle Compensator (Unit 10, 11,) AN/SLQ-25C, has not been received as of 04/14/2016,

• Ref 2.7, drawing 470-8306542_Rev_B, Deck Sheave (Unit 12, 13,) AN/SLQ- 25C, has not been received as of 04/14/2016,

• Ref 2.13, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds, has not been received as of 04/18/2016,

• Ref 2.15, drawing 472-8298152_Rev_A, Special Treatments Installation Procedures Manual DDG 1000, has not been received as of 04/18/2016,

• Ref 2.16, 2A461C006 Rev_-, Towed Torpedo Countermeasures-NIXIE Load Test, has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following reference were provided via Amendment 0002 to the RFP attachments:

• Ref 2.13, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds Ref 2.6, drawing 470-8306541_Rev_B, Fleet Angle Compensator (Unit

10, 11,) AN/SLQ-25C

• Ref 2.7, drawing 470-8306542_Rev_B, Deck Sheave (Unit 12, 13,)

AN/SLQ-25C

• Ref 2.15, drawing 472-8298152_Rev_A, Special Treatments Installation Procedures Manual DDG 1000

• Ref 2.16, 2A461C006 Rev_-, Towed Torpedo Countermeasures-NIXIE Load Test

• Ref 2.4, K939000065_Rev_E, Foundation “C” Winch 25A

• Ref 2.5, K939000050_Rev_G, Transmitter Foundation 25A

Section J-201, WI 711-11-002, Advanced Gun System Inter-Ship Replenishment System (AIRS):

update

Pages 1 & 2 of 5, Paragraphs 3.4.1, 3.4.2, 3.5.1, 3.9.2, 3.11.2, 3.13, 3.14, 4.1 & 4.3, References 2.5, 2.6, 2.9, 2.11, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.5, B117009_Rev_B, AIRS Mechanical Interface Control Drawing, has not been received as of 04/18/2016,

• Ref 2.6 BAE Systems BFD370005_Rev_B, DDG 1000 Class, Advance Gun System Installation and Alignment Document, MK100, MK117 and MK119, has not been received as of 04/18/2016,

• Ref 2.9, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds, has not been received as of 04/18/2016,

• Ref 2.11, drawing 602-8296114_Rev_A, Deck Markings Interior, Exterior, Flight Deck Non Skid, has not been received as of 04/18/2016, Contractor request the above listed missing references be made available.

The following references were provided via Amendment 0002 to the RFP attachments:

• Ref 2.9, SP002001-BIW_Rev_C, Standard Methods for Mounting Electrical Equipment under 100 pounds

• Ref 2.5, B117009_Rev_B, AIRS Mechanical Interface Control Drawing

• Ref 2.6 BAE Systems BFD370005_Rev_B, DDG 1000 Class, Advance Gun System Installation and Alignment Document, MK100, MK117 and MK119

• Ref 2.11, drawing 602-8296114_Rev_A, Deck Markings Interior, Exterior, Flight Deck Non Skid will be provided post-award. Offerors shall use Ref 2.11, drawing 602-8296114_Rev_-, Deck Markings Interior, Exterior, Flight Deck Non Skid, provided via Amendment 0002 to the RFP attachments, to estimate the scope of work for Spec 7111- 11-002. WI 711-11-002 will be revised to reflect the STD Item and provided via a forthcoming amendment to the RFP attachments.

Section J-201, WI 980-90-105, (AWI 01002)

Temporary Mast, Radar and Communication Removals

Page 1 of 2, Paragraphs 3.1 & 3.2, References 2.1.1, 2.1.2, & 2.2.1, 2.2.2, Contractor notes upon review of the Specification that the following list of references have not been made available.

• Ref 2.1.1, NAVSEA DWG 451-7162-9815, Temporary Radar and Comms Consolidated Elec Dwg, has not been received as of 04/18/2016,

• Ref 2.1.2, NAVSEA DWG 600-7162-9815, Temporary Radar Comms Installation

• Ref 2.2.1, NAVSEA DWG 600-7162-9820, Temp Communication Instl Hull/Structure

• Ref 2.2.2, NAVSEA DWG 440-7162-9820, Temp Communication Elec Ripout and Install

Contractor request the above listed missing references be made available.

The following drawings are referenced within the installation drawings and not in the removal specification:

• Ref 2.1.1, NAVSEA DWG 451-7162-9815, Temporary Radar and Comms Consolidated Elec Dwg, has not been received as of 04/18/2016,

• Ref 2.1.2, NAVSEA DWG 600-7162-9815, Temporary Radar Comms Installation

• Ref 2.2.1, NAVSEA DWG 600-7162-9820, Temp Communication Instl Hull/Structure

• Ref 2.2.2, NAVSEA DWG 440-7162-9820, Temp Communication Elec Ripout and Install

These drawings are not required to accomplish the scope of the specification and will not be provided.

74 171-11-002 Test Procedure Volumetric Testing/Balancing DDG1000 Not available in disc; No document number

Test Procedure Volumetric Testing/Balancing DDG 1000 was provided via Amendment 0002 to the RFP attachments.

457-11-001, 492-11-

Test Procedure Test Procedure BD406003-B Not available in disc provided

Test Procedure BD406003-B is an incorrect reference. It is a drawing and not a test procedure. Ref 2.6 Drawing BD406003-B was provided for Work Item 492-11-002 via Amendment 0002 to the RFP attachments.

In Work Item 457-11-001, the drawing reference will be deleted via a forthcoming amendment to the RFP attachments., The grounding and bonding requirement is provided in Ref 2.20 MIL-STD-1310 and was provided via Amendment 0002 to the RFP attachments.

76 461-11-001 Mfg Drawing Mfg Drawing K939000065-E Not available in disc provided K939000065_Rev_E, Foundation “C” Winch 25A was provided via Amendment 0002 to the RFP attachments

77 461-11-001 Mfg Drawing Mfg Drawing K939000050-G Not available in disc provided K939000050_Rev_G, Transmitter Foundation 25A was provided via Amendment 0002 to the RFP attachments

78 711-11-002 Tech Manual Tech Manual T9630-AB-MMD-010 Rev2 Not available in disc provided. Rev 3 is most current version

Tech Manual T9630-AB-MMD-010 Rev2 will be removed from the Work Item 711-11-002. The correct reference for tank opening and gas-freeing is CAT I STD ITEM 009-7 "Confined Space Entry". WI 711- 11-002 will be revised to reflect the STD Item and provided via a forthcoming amendment to the RFP attachments.

79 711-11-002 Drawing Drawing 602-8296114-A Not available in disc provided

Ref 2.11, drawing 602-8296114_Rev_A, Deck Markings Interior, Exterior, Flight Deck Non Skid will be provided post-award. Offerors shall use Ref 2.11, drawing 602-8296114_Rev_-, Deck Markings Interior, Exterior, Flight Deck Non Skid, provided via Amendment 0002 to the RFP attachments, to estimate the scope of work for Spec 7111- 11-002. WI 711-11-002 will be revised to reflect the STD Item and provided via a forthcoming amendment to the RFP attachments.

80 980-90-105 Drawing Drawing 451-7162-9815 Not available in disc provided Drawing 451-7162-9815 was provided via Amendment 0002 to the RFP attachments

81 980-90-105 Drawing Drawing 600-7162-9815 Not available in disc provided Drawing 600-7162-9815 was provided via Amendment 0002 to the RFP attachments

82 980-90-105 Drawing Drawing 600-7162-9820 Not available in disc provided Drawing 600-7162-9820 was provided via Amendment 0002 to the RFP attachments

83 980-90-105 Drawing Drawing 440-7162-9820 Not available in disc provided Drawing 440-7162-9820 was provided via Amendment 0002 to the RFP attachments

84 457-11-001 Drawing The title block in this drawing (532-8670360-A) is Rev A; but the Revisions block states Rev B as well as the rest of the pages in the drawing. The work spec doesn't specify any revision at all.

Drawing 532-8670360-A, sheet 1, is incorrect in stating Rev A in the Rev Block. The drawing will be revised to reflect Rev B, in accordance with the index on sheet 1. Spec 457-11-001 will be revised and provided via a forthcoming amendment to the RFP attachments.

522-20-001, MT-61

AND MT-62

MAGAZINE

SPRINKLING

SYSTEM

INSTALLATION;

ACCOMPLISH

page 1 of 2 , paragraph 3.3

Paragraph 3.3 calls for the installation of new magazine piping system. T installation includes deck penetrations. There is no Cat II Standard item 009- 25, Structural Boundary Test called out in the spec. Unless otherwise directed KTR will estimate hours to cover the requirements of 009-25.

Please advise or concur.

The decks being penetrated are not water-tight decks and therefore only a local air hose tests of the deck penetration welds, in accordance with 009-25, is required. Spec 522-20-001 will be revised and provided via a forthcoming amendment to the RFP attachments.

711-11-002 , ADVANCED GUN

SYSTEM INTER-SHIP

REPLENISHMENT

SYSTEM (AIRS);

UPDATE

REF 2.2, 180-8634592, AGS

INSTALLATION AND ML

HULL STRUCTURE

The List of Materials on sheet 24, lists Assemblies A001 as Foundation Amplifier MT 62 A.I.R.S and A002 as Foundation Amplifier MT 61 A.I.R.S.

Sheet 19 shows Assy A002 as MT 62 and sheet 21 shows A001 as MT 61.

The fabrication for the two assemblies and bolting patterns are different, therefore could cause incorrect installation. Please verify the correct Assembly and MT numbers.

In drawing 180-8634592 of WI 711-01-002, the Title Block on sheets 19 and 21 are incorrect and should be Assembly A001 as MT 61 and Assembly A002 as MT 62, respectively. Drawing 180-8634592 will be revised provided via a forthcoming amendment to the RFP attachments.

Section L, Paragraph A.I.(d) Instructions for Attachment J-8 - Exhibit L0004

Exhibit L0004 has columns for Offerors to provide labor rates for Prime Contractor and Subcontractor efforts. Is it the intent that the Prime contractor labor rate include all direct labor, burdens and profit, and that the subcontractor labor rate include all prime contractor burdens and profit? if not, the total cost for the work items on this sheet will not match the total for Exhibit L0003, CLIN 0002, Order 0001 which does include all prime and subcontractor burdens and profit. If the intent of this exhibit is to express only the raw estimate of labor manhours and material dollars (excluding burdens and profit), suggest that the prime contractor labor dollar column be removed and that the total column for prime and subcontractor for each item include only a summation of manhours and material, in order for there not to be a mismatch. Note - Exhibit L0004's on prior RFPs included only manhours and materials and the total CLIN price was calculated on Exhibit L0003. Please clarify.

It is the intent that the Prime contractor labor rate include all direct labor, burdens and profit, and that the subcontractor labor rate include all prime contractor burdens and profit in Exhibit L0004. The language in Section L of the RFP will be clarified via a forthcoming amendment.

88 441-11-010 Reference 2.15, 2A447C002_Rev_A, Governments Response # 11 stated this reference would be provided via an amendment. This reference was not provided in Amendment 002. Please provide.

Reference 2.15, 2A447C002_Rev_A will be provided via a forthcoming amendment.

89 980-90-105

Ref 2.1.1, NAVSEA DWG 451- 7162-9815, Ref 2.1.2, NAVSEA DWG 600- 7162-9815, Ref 2.2.1, NAVSEA DWG 600- 7162-9820, Ref 2.2.2, NAVSEA DWG 440- 7162-9820

Please provide missing references.

The following drawings are referenced within the installation drawings and not in the removal specification:

• Ref 2.1.1, NAVSEA DWG 451-7162-9815, Temporary Radar and Comms Consolidated Elec Dwg, has not been received as of 04/18/2016,

• Ref 2.1.2, NAVSEA DWG 600-7162-9815, Temporary Radar Comms Installation

• Ref 2.2.1, NAVSEA DWG 600-7162-9820, Temp Communication Instl Hull/Structure

• Ref 2.2.2, NAVSEA DWG 440-7162-9820, Temp Communication Elec Ripout and Install

These drawings are not required to accomplish the scope of the specification and will not be provided.

Indicates update since last release of responses