AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide respones to bidder questions and revise N00024-15-R-6400 accordingly.
1. CONTRACT ID CODE PAGE OF PAGES
U 1 64
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-May-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N00024-15-R-6400
X 9B. DATED (SEE ITEM 11)
09-Apr-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-May-2015
CODE
NAVAL SEA SYSTEMS COMMAND (HQ)
1333 ISAAC HULL AVE SE
WASHINGTON NAVY YARD DC 20376-2030
N00024 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N00024-15-R-6400
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0103
The CLIN extended description has changed from Base Year - MK48 MOD 7 G&C
Section (Note F) to Option Year 1 - MK48 MOD 7 G&C Section (Note F).
CLIN 0104
The CLIN extended description has changed from Base Year - MK48 MOD 7 CBASS
Upgrade Kits (Note F) to Option Year 1 - MK48 MOD 7 CBASS Upgrade Kits (Note F).
CLIN 0105
The CLIN extended description has changed from Base Year - Factory Test Equipment
(Note F) to Option Year 1 - Factory Test Equipment (Note F).
CLIN 0108
The CLIN extended description has changed from Base Year - Engineering Services and Support (Note B and E) to Option Year 1 - Engineering Services and Support (Note B and
E).
CLIN 0109
The CLIN extended description has changed from Base Year - Hardware Repair and
Maintenance (Note C and E) to Option Year 1 - Hardware Repair and Maintenance (Note C and
CLIN 0203
Section (Note F) to Option Year 2 - MK48 MOD 7 G&C Section (Note F).
CLIN 0204
Upgrade Kits (Note F) to Option Year 2 - MK48 MOD 7 CBASS Upgrade Kits (Note F).
CLIN 0205
(Note F) to Option Year 2 - Factory Test Equipment (Note F).
CLIN 0208
and Support (Note B and E) to Option Year 2 - Engineering Services and Support (Note B and
CLIN 0209
Maintenance (Note C and E) to Option Year 2 - Hardware Repair and Maintenance (Note C and
CLIN 0303
Section (Note F) to Option Year 3 - MK48 MOD 7 G&C Section (Note F).
CLIN 0304
Upgrade Kits (Note F) to Option Year 3 - MK48 MOD 7 CBASS Upgrade Kits (Note F).
CLIN 0305
(Note F) to Option Year 3 - Factory Test Equipment (Note F).
CLIN 0308
and Support (Note B and E) to Option Year 3 - Engineering Services and Support (Note B and
CLIN 0309
Maintenance (Note C and E) to Option Year 3 - Hardware Repair and Maintenance (Note C and
CLIN 0403
Section (Note F) to Option Year 4 - MK48 MOD 7 G&C Section (Note F).
CLIN 0404
Upgrade Kits (Note F) to Option Year 4 - MK48 MOD 7 CBASS Upgrade Kits (Note F).
CLIN 0405
(Note F) to Option Year 4 - Factory Test Equipment (Note F).
CLIN 0409
Maintenance (Note C and E) to Option Year 4 - Hardware Repair and Maintenance (Note C and
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
PART 3: SCOPE OF WORK
3.1 Background
The MK 48 Mod 7 Heavyweight Torpedo is the U.S. Navy’s primary submarine launched anti-submarine (ASW) and anti-surface warfare (ASuW) weapon. The MK 48 Mod 7 is a high performance, self-propelled underwater vehicle that contains complex electronic and mechanical subassembly systems for providing propulsion, steering, navigation, and target detection. The system technologies include acoustic sonar, guidance and control electronics, electrical power, hydraulic systems, mechanical pumps, and propulsion.
The MK 48 Mod 7 is 19 feet long, 21 inches in diameter and weighs about 3,700 pounds. The MK 48 Mod 7 consists of over 600 parts, including Functional Item Replacement (FIR) units (similar to modular replaceable “plug and play” units in other systems), torpedo shells, cables, fuel and lubricants, consumable piece parts, etc. A number of FIRs are currently in production while others have not been produced in over ten years.
This RFP is for the G&C Section of the MK 48 Mod 7 Torpedo. The G&C section performs the functions listed below.
a. Weapon Control and Safety functions - Allocates and controls torpedo resources throughout the run and ensures protection for the launch craft and other friendly vessels. Ensures operational software is not compromised.
b. Guidance functions - Controls the dynamic behavior and maintains position and altitude data. Converts seawater depth pressure to serial digital data.
c. Sonar functions - Performs broadband signal processing, active and passive beam forming, acquires target and generates target position data required for target engagement.
d. Power Distribution functions - Converts input power into DC voltages that are distributed to the subsystems internal to the nose section.
Further, MK 48 Mod 7 CBASS Upgrade Kits defined in CLINs 0004, 0104, 0204, 0304, and 0404 will be purchased under this contract to further upgrade the current MK 48 inventory. The CBASS Upgrade Kit is a subset of the G&C section.
This will be the third consecutive contract under which the US Navy purchases MOD 7 CBASS components. As such, there are extensive obsolescence issues within the current design that impact the current software (SW), middleware (MW), and firmware (FW). The Government will be supplying the SW, MW, and FW in the current design in order to support the Contractor’s efforts on this contract. A white paper describing the current known obsolescence in the Mk 48 Mod 7 design is provided (Attachment 16), and an example of a successful and similar obsolescence redesign is also provided as GFI (Attachment 3). The Contractor shall modify, reuse, or replace the provided SW, MW, and FW as necessary to meet the requirements of the Contract Baseline (Attachment 1).
3.2 Applicable Documents
To the extent referenced herein, the following documents form a part of this SOW and are hereby incorporated by reference. In the event of a conflict between the documents referenced herein and the contents of this SOW, the contents of this SOW shall take precedence. Other documents and specifications provided as Government
Furnished Information (GFI) are identified in Attachment 3.
3.2.1 Department of Defense Specifications
3.2.1.1.1 Contract Baseline Documents
See Attachment 1, Contract Baseline, for a list of design specifications, performance specifications, interface requirement documents, assembly drawings, and source control drawings. In the case where a particular assembly drawing is provided as both a PDF and in a native file format the PDF version shall be the controlling document and supersede the native file format version.
3.2.1.2 Program Unique Documents
Title Date and/or Revision
OPNAVINST S5513.5C – Undersea Warfare Program Security Classification 26 April 2010
Guides (SCGs) SCG ID: 139.2, MK 48 ADCAP (MODS 5 and beyond), MK 50, AND MK 54 Torpedoes (See Attachment 11)
Undersea Weapons Program Office Risk Process Description (See Attachment 11)
8 September, 2003
MK48 ADCAP CBASS Systems Safety Program Plan (SSPP) (See Attachment 11)
November 2003, Rev 1
Configuration Management Plan for Undersea Weapons Program (PMS404), PEO SUB S0199-133-A-O-C (See Attachment 11)
August 2010, Rev D
Manufacturing Quality Assurance Specification, Torpedo Functional Item Replacement (Document Number: 8595331) (Attachment 11)
March 3, 2015
3.2.1.3 Other Government Documents
Title Date and/or Revision
Failure, Reporting, Analysis and Corrective Action Taken (MIL-HDBK-2155) (See http://www.assistdocs.com)
11 December 1995
Electrostatic Discharge Control Handbook for Protection of Electrical and Electronic Parts, Assemblies and Equipment (Excluding Electrically Initiated Explosive Devices) (Metric) (MIL-HDBK-263) (See http://www.assistdocs.com)
31 July 1994, Rev. B
Electrostatic Discharge Control Program For Protection of Electrical and Electronic Parts, Assemblies and Equipment (Excluding Electrically Initiated Explosive Devices) (MIL-STD-1686) (See http://www.assistdocs.com)
25 October 1995, Rev. C
Navy Manufacturing Screening Program (NAVMAT P-9492) (See http://www.assistdocs.com)
May 1979
Environmental Stress Screening (ESS) of Electronic Equipment (MIL-HDBK-
344) (See http://www.assistdocs.com)
16 August 1993, Rev A
Configuration Management Guidance (MIL-HDBK-61) (See http://www.assistdocs.com)
7 February 2001, Rev A
DoD Standard Practice System Safety (MIL-STD-882) (See http://www.assistdocs.com)
11 May 2012, Rev E
Department of the Navy Weapons System Explosives Safety Review Program (NAVSEAINST 8020.6E) (See Attachment 11)
11 March 2008
Federal Acquisition Regulation (See https://acquisition.gov/far/) Available Online
National Aerospace Standard, Hazardous Materials Management Program (NAS 411) (See http://www.assistdocs.com)
19 January 1995
Parts Management (MIL-STD-3018) (See http://www.assistdocs.com) 27 October 2011 GIDEP Operations Manual (NAVSEA S0300-BT-PRO-010) (See http://www.gidep.org/about/opmanual/opmanual.htm)
September 2009
3.2.1.4 Non-Government Documents
Title Description Date and/or Revision
ANSI/ISO/ASQ Q9001 Quality Management Systems – Requirements Standard (See http://webstore.ansi.org/)
November 2008
AS9100C Quality Systems - Aerospace - Model for Quality Assurance in Design, Development, Production, January 2009 http://www.assistdocs.com/ http://www.assistdocs.com/ http://www.assistdocs.com/ http://www.assistdocs.com/ http://www.assistdocs.com/ http://www.assistdocs.com/ https://acquisition.gov/far/ http://www.assistdocs.com/ http://www.assistdocs.com/
Installation and Servicing (See http://standards.sae.org/as9100c/)
ANSI/EIA-649-B National Consensus Standard for Configuration Management (See http://webstore.ansi.org/)
June 2011
IPC J-STD-001E Joint Industry Standard Requirements for Soldered Electrical and Electronic Assemblies (See https://portal.ipc.org/ipc-store.htm)
April 2010
IEEE/EIA Std. 12207-
Systems and Software Engineering—Software Life Cycle Processes (See http://www.astm.org/standards)
February 2008
IPC-A-610E Acceptability of Electronic Assemblies (See https://portal.ipc.org/ipc-store.htm)
April 2010
IPC/WHMA-A-620 Requirements and Acceptance for Cable and Wire Harness Assemblies (See https://portal.ipc.org/ipc-store.htm)
October 2012, Rev B
3.3 Requirements
3.3.1 Program Management
The Contractor shall develop and provide a Program Management Plan in accordance with CDRL A001. The PMP shall contain detail to allow the Government to verify the Contractor’s management and scheduling of all efforts necessary to meet the Contract requirements to include completion of program reviews and completion of associated
CDRL deliverables. The Contractor shall include a description of their process of identifying and tracking risks and opportunities in the PMP. Where these efforts are event as opposed to calendar driven, schedule estimates shall be provided. The Contractor shall designate a full time Contractor Program Manager who shall have responsibility for all aspects of this contract, and shall be responsible for providing Contractor’s Progress, Status, And Management
Report: Program Manager’s Report (CDRL A002), see SOW section 3.3.2.
3.3.1.1 Security Requirements
The Contractor shall establish and maintain a facility clearance of at least SECRET as issued by the Defense
Investigative Service. Specific Contractor security access requirements are outlined in the Contract Security
Classification Specification (DD254) in accordance with Attachment 6. The Contractor shall issue the proper classification markings and maintain security for all classified items, including documentation, hardware, firmware, middleware, and software generated for the MK 48 MOD 7 G&C Sections and CBASS Upgrade Kits in accordance with OPNAVINST S5513.5 – Undersea Warfare Program Security Classification Guides (SCGs) SCG ID: 139.2, MK 48 ADCAP (MODS 5 and beyond), MK 50, AND MK 54 Torpedoes. The Contractor must have the capability to handle, store, and process classified information across all mediums (hard-copy, electronic, CD/DVD, etc.) at the
Secret level for their cleared facility.
The Contractor shall have the necessary clearances and processes necessary to ship and receive classified shipments.
The Contractor shall either establish the procedures and processes necessary to declassify all potentially classified hardware being delivered under this contract or contain all of their necessary Factory Test Equipment (both
Contractor developed and Government Furnished) in classified areas. All declassification processes and procedures shall be approved by the Defense Security Service (DSS), prior to delivery.
3.3.1.2 Parts Management
The Contractor shall establish and maintain a Parts Management Program in accordance with the requirements of applicable document “Parts Management (MIL-STD-3018)” for all designs or modified GFE. The Contractor shall verify that the use of parts meet the contractual requirements, reduce proliferation of parts within and across
Department of Defense (DoD) weapons systems and equipment through standardization, enhance reliability and supportability to meet material readiness objectives, and reduce total life-cycle costs. Also, the Contractor shall describe how the parts management process is validated, how process improvements are incorporated, and how process variation is controlled. The Contractor shall prepare and deliver the Parts Management Plan in accordance with CDRL A003 covering the period of performance of this contract.
The Parts Management Plan shall address the following parts management elements:
1. Parts selection baseline
2. Parts selection and authorization process
3. Obsolescence management
4. Parts list
5. Subcontractor management
6. Part and supplier quality
7. Part level documentation procedures
8. Substitute and alternative part procedures
9. Customer-contractor teaming
10. Counterfeit parts
11. Lead-free electronic parts
12. Long lead material
The Contractor shall conduct engineering analysis of the TDPs provided in the Contract Baseline (Attachment 1) and provided Government Furnished Information (Attachment 3) to identify changes required to resolve obsolescence issues (including the modification of any effected hardware and software, and validation of the modified hardware and software), reflect current best practices, and update supplier information to ensure a producible design. The Parts Management Plan shall define the contractor’s process that mitigates the risk associated with technology obsolescence; proprietary technologies; the loss or impending loss of manufacturers or suppliers of components, assemblies, or materials used in the system; and provide rationale for reliance on a single source of supply over the life of the system. The Parts Management Plan shall contain provisions to minimize the impact of obsolescence during contract execution, effectively manage obsolescence through planned modernization, and avoid additional costs from being incurred by the Government due to obsolescence. The Parts Management
Plan shall address means and approach for providing the Government with information regarding obsolescence and
Diminishing Manufacturing Sources and Material Shortages (DMSMS) issues, access and insight into the
Contractor’s DMSMS forecasting tool, part list screening, part list monitoring, processing of Government Industry
Data Exchange Program (GIDEP) DMSMS alerts, processing of DLA DMSMS alerts, communication with and availability of information to the Government, a means and approach for establishing obsolescence and DMSMS solutions, and a plan for managing commercial off the shelf items (COTS).
The contractor shall actively participate in the Government Industry Data Exchange Program in accordance with the
GIDEP Operations Manual, S0300-BT-PRO-010. The contractor shall submit information concerning critical or major nonconformances, as defined in FAR 46.407/DFARS 246.407, to the GIDEP information system. GIDEP
Alerts and Safe-Alert Reports shall be submitted in accordance with CDRL A040.
The Parts Management Plan shall include Technology Road-mapping reports which establish the points along the service life of MK 48 MOD 7 G&C Sections and CBASS Upgrade Kits when it is optimal to change, or "refresh," both custom-built and COTS system components to ensure continued supportability throughout their lifecycle. It includes supplying the MK 48 User with hardware and software that is technically capable, available, sustainable, and cost effective. To ensure key torpedo systems are sustained through End-Of-Life, road-mapped efforts support the evaluation of the system technology and design, identification of technology/design options, assessment of the technical and cost trade-offs, and prioritization and recommendation of solutions. As a key tool of collaborative technology planning and coordination with IPT members, it allows the torpedo manufacturer, vendors, and integrators to make more informed business decisions when identifying and deploying appropriate technology alternatives to enhance design longevity.
The Contractor shall recommend design changes to ensure continuous manufacturing and/or repairing capabilities in accordance with the Configuration Management requirements of this contract.
The Contractor shall ensure all known and forecasted DMSMS issues are identified and have a mitigation plan, so that the Government is not left with an unsupportable system due to DMSMS. The Contractor shall provide prompt notification to the Government for any DMSMS/Obsolescence issues in accordance with section 2.4. Approved changes shall be made in accordance with the Configuration Management requirements of this contract.
The Contractor shall develop and flow down to all of its subcontractors and vendors at all tiers DMSMS requirements sufficient to ensure that the end items and services provided meet all requirements of this contract.
3.3.2 Program Reporting
The Contractor Program Manager shall provide the Contractor’s Progress, Status, And Management Report:
Program Manager’s Report in accordance with CDRL A002, covering all efforts under this Contract including
Subcontractor/Suppliers performance against the schedule baseline established in the Program Management Plan, Technical Instructions/Engineering Services, Obsolescence Reviews, Risk Management, Failure Analysis, Returned
Goods, and other work performed under the contract during the month of the report, in addition to Design, Development, Manufacture, Test, and Production efforts on the MK 48 MOD 7 G&C Sections, CBASS Upgrade
Kits, and Factory Test Equipment.
3.3.2.1 Obsolescence Reporting Requirements
The Contractor is responsible for the identification of all DMSMS/Obsolescence/Producibility issues associated with production and delivery of hardware under this contract in accordance with the Technical Design Package (TDP) and section 2.4 of Section C.
The Contractor shall submit Forecasting Diminishing Manufacturing Sources and Material Shortages (DMSMS)
Source Data in accordance with CDRL A005.
The Contractor shall provide obsolescence tasking updates as part of the Contractor’s Progress, Status, And
Management Report: Program Manager’s Report (CDRL A002). The obsolescence tasking updates shall address the results of the on-going review and identification of actual and potential issues within Contractor and their sub-vendors Bills of Material (BOM). The Contractor is encouraged to use the DoD DMSMS Center of Excellence
Shared Data Warehouse for the purpose of exchanging obsolescence information across the DoD enterprise.
For purposes of this contract, Producibility is defined as the ability to procure, fabricate, assemble, and test an item using available production technology while still meeting the necessary quality and performance requirements. This definition shall apply to all technical data supplied as a part of any change issued under this contract if the additional
DMSMS/ Obsolescence/ Producibility effort is required by reason of a Government-issued change. In which case this provision entitles the Contractor to an equitable adjustment for which the amount shall be included in the settlement of the change order for the Government-issued change.
3.3.2.2 Risk Management Process
The Contractor shall implement a comprehensive risk management process that is focused on program risk areas and the program’s critical path to systematically identify and mitigate cost, schedule, and technical risks. The Contractor shall use the Undersea Weapons Program Office Risk Process Description, contained in Attachment 11, as the basis for their risk management process. The Contractor shall provide risk item reports, to include the identification and adjudication of risk items in accordance with CDRL A002, Program Manager’s Report and address during reviews.
3.3.2.3 Reviews and Meetings
The Contractor shall be responsible for hosting the reviews and meetings required in paragraphs 3.3.2.3.1 through
3.3.2.3.5. Hosting shall include providing for meeting location at or near the Contractor’s facility with all necessary administrative support as well as development, coordination, and distribution of the agenda and Program Review and IPT Presentation Packets in accordance with CDRL A006 and Design Review Information Package (CDRL
A024) (as applicable) for each review. At PMS404 discretion, Government arranged facilities and administrative support may be used to support the meeting.
The Contractor shall record, generate, and process submittal of the review minutes from the participants of reviews, and track all action items after the reviews. The Contractor shall report these minutes and action item tracking data as Record of Meeting/Minutes – Meeting/Minutes Logs in accordance with CDRL A007. Progress and updated status on action items shall also be included in the Contractor’s Progress, Status, and Management Report: Program
Manager’s Report (CDRL A002).
Unless otherwise noted by the Government for the individual review or meeting events, the Contractor shall provide unclassified electronic and video or audio teleconference capability, allowing remote participation of conference room presentation screen by, and verbal participation of, Government personnel located in internet-connected
Government offices, including NUWC Newport and NUWC Keyport locations. The Contractor shall provide internet-based ability to access or download unclassified program review documentation, models and data to
Government personnel located in internet-connected Government offices.
3.3.2.3.1 Inter-Organizational Contract Processes Familiarization Workshop
Within 30 Days after Contract Award (DAC), the Contractor shall support the Government in preparing for and attending an Inter-Organizational Contract Processes Familiarization workshop, which will be facilitated by the
Defense Acquisition University (DAU). As risk mitigation to miscommunications and other inter-organizational performance delays, this workshop allows Government and Contractor personnel to become familiarized with the organizational structures and processes under the new contract effort.
The Contractor shall review the agenda of the workshop and prepare for the applicable presentation for the workshop prior to the dates of the workshop. On the dates of the workshop, the Contractor shall participate in the workshop on-site and provide presentations during the workshop. The Contractor shall host this meeting one time.
The Government will provide slide packages to the Contractor two days in advance of the workshop. The
Contractor will print-out the reading packages (including the Government and Contractor slide packages) for the participating members of the workshop. Aside from the information to support the agenda, the Contractor shall also provide the following data (CDRL A012):
Introduction to Contractor Personnel, Internal Processes, and Tools.
Contractor Cost Monitoring Techniques
Contractor Organization Chart with roles, names, email addresses, and phone numbers
3.3.2.3.2 Integrated Baseline Review (IBR)
The Contractor shall host a post-Award IBR within 120 Days after Contract Award (DAC). During the post-Award
IBR, the Contractor shall present its Program Management Plan. The IBR shall detail the Contractor's planning to ensure complete coverage of the work effort required by the contract, logical scheduling of work activities, adequate resourcing, understanding of technical requirements, and identification of inherent risks and risk mitigation plans.
Completion of the post-Award IBR will result in establishment of a baseline for all elements of the MK 48 MOD 7
G&C Sections, CBASS Upgrade Kits, and Factory Test Equipment production schedules provided in the Program
Management Plan. Contractor shall update CDRL A001 according to results of IBR action items and resubmit for
Government approval. The Contractor shall submit an IBR agenda and IBR presentations in accordance with
CDRL A006. The contractor shall host the post-Award IBR one time.
3.3.2.3.2.1 Entrance Criteria
The baseline is established by the Contractor reflecting the entire scope of work for the performance of the contract.
Project schedule key milestones are identified and documented.
Program Risks and Opportunities are identified.
Technical Scope of Work is consistent with Performance Specifications.
Resources such as budget, Facilities, and personnel are planned for the program and measured for
Variances.
Tasks are planned and can be measured objectively relative to the technical progress.
The program schedule is executable and updated.
The program has an executable budget plan established and is being measured for variances.
Management processes are documented for execution of the project.
Earned Value Management System (EVMS) is in place, including a plan for earned value collection and periodic status (Applicable to CLIN 0001 only).
3.3.2.3.2.2 Exit Criteria
Technical scope of work is fully included and is consistent with authorizing documents.
Formal cost and schedule baselines established and approved.
IBR Action Items completed and approved.
3.3.2.3.3 Systems Engineering Technical Reviews (SETR))
The Contractor shall host the SETRs listed below throughout the performance of this contract in order to demonstrate readiness to proceed in its hardware and software development efforts for the MK 48 MOD 7 G&C
Sections, CBASS Upgrade Kits, and Factory Test Equipment under the approving authority of the Undersea
Weapons Program Manager. These SETRs shall be captured as program milestones in the Contractor’s Systems
Engineering Management Plan (CDRL A008) and the plan to complete necessary SETR tasking shall be described.
The Contractor shall present all of the information detailed in DI-SESS-81757 at the applicable SETRs and deliver to the Government the Design Review Information Package CDRL A024. The Contractor shall include any necessary Objective Quality Evidence (OQE) (e.g. test procedures, test reports, specification documents, design documents, interface documents, user manuals, configurations item data bases, schedules, etc.) referenced or needed to support the information presented in the Design Review Information Package with the CDRL A024 delivery.
System Requirements Review (SRR)
System Functional Review (SFR)
Software Specification Review (SSR)
Hardware Preliminary Design Review (HPDR)
Software Preliminary Design Review (SPDR)
Hardware Critical Design Review (HCDR)
Software Critical Design Review (SCDR)
Test Readiness Review (TRR)
Physical Configuration Audit (PCA)
Functional Configuration Audit (FCA)
The Contractor may combine multiple SETRs into a single meeting if they are able to present all of the necessary information and the COR approves of combining the SETRs. In order to receive COR approval, the Contractor shall send a formal request to combine multiple SETRs into a single meeting at least 30 days before the planned meeting date.
The Contractor shall include Firmware design discussions as part of the HPDR and HCDR.
In accordance with the Design Review Information Package CDRL A024, the SRR, SFR, SSR, and SPDR will not be subject to Government approval. For these Contractor approved reviews, the Contractor shall provide the
Government with no less than 30 days’ notice before conducting Contractor Approved SETRs and provide physical and remote access to allow the Government to attend the reviews. The Government reserves the right to provide comments that shall be adjudicated for Contractor approved reviews. Government approval shall be required for the
HPDR, HCDR, SCDR, TRR, PCA, and FCA in accordance with Design Review Information Package CDRL A024.
The PCA and FCA will be Government initiated and subject to Government approval in accordance with Design
Review Information Package CDRL A024. The Contractor shall host all SETR meetings for the G&C Sections, CBASS upgrade kits, and Test Equipment.
3.3.2.3.3.1 Test Readiness Review (TRR)
In addition to the DI-SESS-81757 requirements for the TRR, the Contractor shall present for Government review and approval test plans and procedures, test assets, facilities, risks in the upcoming test periods, and other related items.
The Contracting Officer’s Representative will provide authorization for the Contractor to proceed with the TRR once the following have been completed:
a. Approved Test Procedure – First Article Test Procedures (CDRL A034) and Test Procedure – Factory
Acceptance Test Procedures (CDRL A025)
b. Approved Contractor Validation Plan – Factory Test Equipment Certification Plan (CDRL A026)
c. Completed Factory Test Equipment TDP and Software (CDRLs B003, B006, B007)
d. Updated Systems Engineering Management Plan (CDRL A008)
The TRR shall comply with all requirements specified in the Systems Engineering Management Plan (CDRL A008) and all action items generated during the TRR shall require resolution and closure and reported via CDRLA007.
Once all requirements are met, the Contracting Officer’s Representative will issue a TRR closure letter authorizing the Contractor to proceed into formal Qualification Testing.
Post TRR, any issues found during POM testing that necessitate revision of previously approved CDRLs shall be addressed and the CDRLs revised and re-submitted for Government approval prior to the Production Readiness
Review (PRR). The Contractor shall host up to three TRR’s.
3.3.2.3.4 Production Readiness Review (PRR)
The purpose of the PRR is for the Contractor to demonstrate to the Government that it has accomplished adequate production planning without incurring unacceptable risks that could breach schedule, performance, cost or other established criteria and gain concurrence from the Government to produce production units. The Contractor shall submit a PRR agenda and PRR presentations in accordance with CDRL A006.
The PRR shall comply with all requirements specified in the Systems Engineering Management Plan (CDRL A008) and all action items generated during the PRR shall require resolution prior to PRR closure. Once all PRR requirements are met, the Contracting Officer will issue a closure letter authorizing the Contractor to begin factory production deliveries. Upon completion of the PRR, the baseline for all TDPs and factory processes shall be considered established.
The Government will determine when all entrance and exit criteria for the PRR have been satisfied and the
Contracting Officer’s Representative will notify the Contractor at least 14 days prior to the milestone event to schedule the PRR. The Contractor shall host PRR one time.
3.3.2.3.4.1 Entrance Criteria
Actions from Functional Configuration Audit (FCA) completed and approved.
Actions from Physical Configuration Audit (PCA) completed and approved.
Completion and verification of Contractor First Article and POM Testing, including completion of
Government POM Testing.
Supply Sources and Vendors are in place.
Completed Assembly and Manufacturing Processes and Procedures.
Approved Critical Manufacturing Processes (CDRL A016).
Approved Quality Program Plan including QASP elements (CDRL A020).
Approved Test Procedure - Factory Acceptance Test Procedures (CDRL A025).
Approved Factory Test Equipment TDP (CDRL B003).
Approved Systems Engineering Management Plan (CDRL A008).
Contractor design has been verified by the Government to be compliant with the Technical Manual for
Nuclear Powered Submarine Atmosphere Control Manual (S9510-AB-ATM-010).
The program risks have been evaluated by a joint Contractor/Government (including the Technical Warrant
Holder, Technical Design Authority, and Program Manager) review and ascertained to be acceptable at this phase of the program.
The system product baseline has been established and documented for the system, subsystem, equipment, and software including establishing nomenclature in accordance with MIL-STD-196E Joint Type
Designation System and to enable hardware fabrication and software coding to proceed with proper configuration management.
Technical Performance Measures are in place and being regularly monitored.
The program schedule is executable and updated.
3.3.2.3.4.2 Exit Criteria
ALL PRR Action Items completed and approved by the Program Manager
3.3.2.3.5 Program Management Reviews
The Contractor shall conduct quarterly Program Management Reviews (PMRs). PMRs shall cover, at a minimum:
a. Schedule performance covering all completed and planned efforts
b. Risk management activities
c. A review of all program, contractual, and obsolescence issues
d. A review of all test efforts
e. A review of all Technical Instructions, including cost and schedule performance
f. A cost data review
g. A review of production through-put calculations
Out of the four PMRs held each year, three shall occur at the contractor’s facility or at an agreed to location by the
Government and one will be conducted in the Washington Area (within 50 driving miles of the Washington Navy
Yard). When the PMR is held at the Contractor’s facility, the Contractor shall provide administrative support and access to the facilities to attending Government personnel. The Contractor shall propose date(s) and location no less than 45 days prior to the PMR. The Government will confirm the date(s) and location no less than 30 days prior to the PMR. The Contractor shall submit a PMR agenda and PMR presentations in accordance with CDRL A006.
3.3.2.4 Integrated Product Teams
The Contractor shall coordinate and host Government/Contractor Integrated Product Teams (IPT) at the leadership and working group levels to achieve program goals. At a minimum, IPTs shall be established for the following:
a. Monthly leadership meetings to review program status and determine go forward actions as needed. The
Contractor’s Progress, Status, And Management Report: Program Manager’s Report (CDRL A002) will serve as the information package for this meeting.
b. Weekly Systems Engineering meetings to support execution of the Government approved System
Engineering Management Plan (CDRL A008)
c. Weekly working level production meetings to resolve and discuss ongoing progress, status, condition of
GFE, failure analysis, quality metrics, and program issues.
d. Meetings to update and provide status to an Integrated Master Schedule that details Government tasking related to the execution of this contract and related to Contractor efforts shall be held a minimum of twice a month, up until the completion of the Production Readiness Review (PRR). The Government will maintain this schedule.
The Contractor-coordinated regular IPT meetings shall be established no later than one (1) month after the Inter-
Organizational Contract Processes Familiarization Workshop (see paragraph 3.3.2.3.1). The Contractor shall develop and distribute the agenda and Program Review and IPT Presentation Packets prior to all IPT meetings in accordance with CDRL A006, adjust the agenda in response to Government feedback, and shall submit Record of
Meeting/Minuets – Meeting/Minutes Logs in accordance with CDRL A007 following each meeting. IPT meetings may be held via telephone.
In addition to the above Contractor-coordinated meetings, the Contractor shall support the following Government-coordinated and hosted meetings:
a. Fault Isolation Team (FIT) weekly meetings to review failures or nonconformances on Contractor deliveries, score the nonconformances as either Contractor or Government responsibility, and provide disposition of previously submitted Failure Analysis and Corrective Action Report – Failures During First
Article, POM, Factory Acceptance Testing, Conditional Acceptance and Government POM Testing
(CDRL A032). The Government will provide the information packages for this meeting. The FIT weekly meetings will be established after the successful completion of the TRR. The FIT will utilize Attachment
13 (Fault Isolation Process) to perform fault isolation of nonconformances identified by the Government and track both Government and Contractor failure analysis efforts to closure.
The Contractor shall ensure appropriate Contractor personnel are in attendance or on telephone conferences with
Government personnel to resolve and discuss ongoing progress, status, condition of GFE, and program issues. The
Contractor shall be flexible and shall adopt improved processes developed by these IPT’s in a timely manner, react quickly to mitigate risk, increase efficiency through appropriate use of IPT products, and streamline management oversight.
3.3.2.5 Other Reports
The Contractor shall provide other reports required as detailed in sections 3.3.2.5.1 and 3.3.2.5.2.
3.3.2.5.1 Minimum Sustaining Quantities
The Contractor shall submit a Technical Report – Study/Services - Minimum Sustaining Rate (MSR) and Economic
Order Quantity (EOQ) Report in accordance with CDRL A009. The MSR and EOQ shall be prepared for the production of G&C CBASS Sections, CBASS Upgrade Kits, and Factory Test Equipment (CLINs 0003, 0004, 0005, and (IF OPTIONS EXERCISED) 0103, 0203, 0303, 0403, 0104, 0204, 0304, 0404, 0105, 0205, 0305, and
0405).
The MSR and EOQ Reports provide the Government with vital information to be used for production and budget purposes to help manage MK48 Mod 7 G&C procurements. The Contractor shall provide the MSR and EOQ report, which at a minimum, includes the following information:
a. The lowest monthly production rate on a 1-8-5 (1 shift – 8 hrs/day – 5 days/week) basis at which this business entity can produce MK48 Mod 7 G&C Sections without increasing the unit cost.
b. The optimum (least cost) quantity of MK48 Mod 7 G&C Sections which should be produced monthly.
c. Rationale as to how the numbers were calculated.
3.3.2.5.2 Cost Reporting
For the full value of each Firm Fixed Price CLIN, the Contractor shall provide a CLIN Cost Report documenting the composition of costs associated with the performance within the scope of this contract in accordance with
CDRL A010. Under CDRL A010, the Contractor shall segregate the cost report by CLIN, and then by WBS elements (the WBS elements shall be mapped to show costs at the level of Program Management, System
Engineering, Material, Inspections, Assembly (in-house), Quality Assurance (separate by major assemblies), and acceptance testing.
The Contractor shall submit Functional Cost Hour Report in accordance with CDRL A011 to report Contractor costs on CLINs 0003 and 0004.
The Contractor shall submit Progress Curve Report in accordance with CDRL A039 for CLINs 0003, 0004, and
(IF OPTIONS EXERCISED) 0103, 0203, 0303, 0403, 0104, 0204, 0304, and 0404. Under CDRL A039, the
Contractor shall further separate the units of the CLINs 0003, 0004, and (IF OPTIONS EXERCISED) 0103, 0203, 0303, 0403, 0104, 0204, 0304, and 0404 into the following groups: first 5 units, second 5 units, then lots of
10 units, and planned attritions.
3.3.3 Data Management
The Contractor shall submit Data Accession List (DAL) in accordance with CDRL A012. The Data Accession List shall identify all Contractor data that is not otherwise listed in the Contract Data Requirements Lists (CDRLs), but has been generated by the Contractor in compliance with the work efforts prescribed in this contract. All data listed under the DAL shall be subject to Section I clauses 252.227-7026 DEFERRED DELIVERY OF TECHNICAL
DATA OR COMPUTER SOFTWARE and 252.227-7027 DEFERRED ORDERING OF TECHNICAL DATA OR
COMPUTER SOFTWARE.
The Contractor shall provide the Government access to and upload electronic data to a Contractor created and controlled website to enable Government personnel, connected to the internet through NMCI network computers, the ability to upload, download, read, copy, comment, and print the unclassified program documentation, models, and data. The Contractor shall provide the Government with twenty (20) no-cost user accounts for accessing the
Contractor-created and controlled website.
The Contractor shall maximize the development, storage and delivery of unclassified data products (including
CDRLs) electronically using the Contractor provided website. When CDRL item electronic delivery is not possible, the Contractor shall deliver the CDRL item using best commercial practices. The Contractor website shall provide an Integrated Digital Environment (IDE) platform that meets the CDRL requirements.
The Contractor shall return to the Government all data at contract termination, completion, or upon the request of the Government. All data obtained or created for the performance of this contract shall become and remain the property of the Government with the rights defined herein, and shall be returned or disposed of in accordance with the Contracting Officer’s Representative’s (COR’s) instructions at the conclusion of this contract.
If necessary, the Contractor will be authorized Common Access Cards (CAC) for up to 10 personnel to allow for access to the required Government web based data systems.
3.3.3.1 Full Disclosure of Design
The Contractor shall provide full disclosure of design of the MK 48 MOD 7 G&C Sections, CBASS Upgrade Kits, and Factory Test Equipment procurement per DFARS 252.227-7013, 252.227-7014, and 252.227-7015. This disclosure shall be all-inclusive and the Government shall be authorized for distribution to other contractors and/or vendors to support the MK 48 Mod 7 HWT system.
3.3.3.2 Technical Data Package
The Contractor shall submit Technical Data Packages (TDP) in accordance with all CDRLs in Exhibit B, MK 48
MOD 7 G&C Sections, CBASS Upgrade Kits, and Factory Test Equipment Product Baseline TDP CDRLs.
The Contractor shall submit the complete package of each TDP (MK 48 MOD 7 G&C Sections and Factory Test
Equipment) in accordance with CDRLs B001, B003, B008, and B009. For base year and each year of option exercise of Production Items (CLINs 0003, 0004, 0005, and (IF OPTIONS EXERCISED) 0103, 0203, 0303, 0403, 0104, 0204, 0304, 0404, 0105, 0205, 0305, and 0405), the Contractor shall submit all revised CLIN 0007 data, in accordance with all CDRLs in Exhibit B, with all Change Notices, approved ECPs, and NORs incorporated.
Within any given production year, the Contractor shall deliver the same baseline of hardware that is common to MK
48 MOD 7 G&C Sections and CBASS Upgrade Kits.
The Contractor shall deliver copies of software and firmware images and associated source code developed under this contract to the Government under CDRLs B004 and B006. The Contractor shall provide software documentation, including detailed design description, build procedures and build environment information under
CDRLs B005 and B007. The software submissions under CDRLs B004, B005, B006, and B007 shall include the data listed in the Software Requirements (Attachment 9).
The Contractor shall provide a Configuration Data Item Status List that reflects the up-to-date drawing/data status, in accordance with CDRL A033. The Configuration Data Item Status List shall include a list of all Exhibit B data items, and shall indicate the latest revision status, and each data item entry shall include a list of corresponding un-incorporated Change Notices and ECP/Test/Inspection Report –Margin Testing, HASS, and POL NOR, if any.
3.3.3.3 NDI and COTS Technical Data Package
The Contractor shall provide full design disclosure of each item of Technical Data (TD), Computer Software (CS), Computer Software Documentation (CSD), and Non-Developmental Items (NDI) or Commercial off-the-shelf
(COTS) data utilized in the MK 48 MOD 7 G&C Sections, CBASS Upgrade Kits, and Factory Test Equipment.
The Contractor shall provide the performance and functional requirements used to evaluate each item of TD, CS, CSD, and NDI or COTS data and all the results including test data. The Contractor shall incorporate each item of
TD, CS, CSD, and NDI or COTS data utilized in MK 48 MOD 7 G&C Sections, CBASS Upgrade Kits, and Factory
Test Equipment, including Vendor Item Drawings and/or source control drawings, into the MK 48 MOD 7 G&C
Sections, CBASS Upgrade Kits, and Factory Test Equipment TDPs in accordance with CDRL A015 the
Contractor’s Configuration Management Plan. Each item shall be incorporated into the MK 48 MOD 7 G&C
Sections, CBASS Upgrade Kits, and Factory Test Equipment baseline (Exhibit B).
3.3.3.4 Assembly Procedure
The Contractor shall develop and submit Critical Manufacturing Processes in accordance with CDRL A016. The
Contractor shall clearly identify all steps in the G&C Section build, assembly, and test process. The Intermediate
Maintenance Activity (IMA) Build Procedures for the G&C Section (provided as GFI in Attachment 3) are provided to serve as a starting point for the creation of CDRL A016. The Contractor may use the IMA Build
Procedures for the G&C “as-is” or propose red-lines to the procedures for use at the Contractor’s facility.
The final electronic assemblies and sub-assemblies delivered under this contract shall meet the IPC Class 3 Industry
Standard requirements of the following specifications: Requirements for Soldered Electrical and Electronic
Assemblies (IPC/EIA J-STD-001), Acceptability of Electronic Assemblies (IPC-A-610), and Requirements and
Acceptance for Cable and Wire Harness Assemblies (IPC/WHMA-A-620).
3.3.3.5 Configuration Management
The Contractor shall develop Contractor’s Configuration Management Plan in accordance with CDRL A015. The
Contractor shall utilize and implement the approved Configuration Management Policies and Procedures to ensure traceability for each MK 48 MOD 7 G&C Sections, CBASS Upgrade Kits, and Factory Test Equipment deliverables
(including repair action), hardware, software and documentation management, change control, and status accounting during the contract period of performance. The Contractor’s Configuration Management Policies and Procedures shall be developed using the Configuration Management Plan for Undersea Weapons Program (PMS404) PEO SUB
S0199-133-A-O-C and National Consensus Standard for Configuration Management (ANSI/EIA-649-A) guidelines to establish and maintain a Product Baseline accordingly.
The Contractor shall document changes to the MK 48 MOD 7 G&C Sections, CBASS Upgrade Kits, and Factory
Test Equipment, and shall incorporate corrective actions identified in Failure Analysis and Corrective Action report
– Failures Prior to Factory Acceptance Test and During HASS CDRL A031 and Failure Analysis and Corrective
Action Report – Failures During First Article, POM, Factory Acceptance Testing, Conditional Acceptance and
Government POM Testing CDRL A032. These changes shall be documented and submitted as Change Notices in accordance with CDRL A013, as Engineering Change Proposals (ECP) in accordance with CDRL A017 along with the related Notice of Revisions (NOR), detailing the proposed changes to the TDP, in accordance with CDRL…