Water Cooled
| GOVERNMENT FURNISHED INFORMATION | ||
| ATTACHMENT # | J 3 | PR # N00024- |
| PROGRAM TITLE: | CPS TI-16 Build To Print | CONTRACT NO.: | N00024-15-R-5201 | DATE: | October 16, 2014 |
| CODE: |
| LINE ITEM NUMBERS | MOD | |
| (3) | EQUIPMENT NOMENCLATURE |
EQUIPMENT DESIGNATOR
DOCUMENT TITLE
DOCUMENT NUMBER
| (4) | (5) | DOC DATE | |
| (6) | GFI DUE DATE |
(7)
| SCHEDULE | ||||||||||
| (1) | A/C | |||||||||
| (2) | VOL | PRT | REV | CHG | SUP | |||||
| Item 1 | ||||||||||
| Disk 1 of 5 | PEO IWS Instruciton 3058.1 Risk Management | 02 August 2004 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||||
| PEO IWS Instruciton 4130.1B PEO IWS Enterprise Configuration Control Process | 14 September 2011 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||||
| PEO IWS Instruciton 5450.1 PEO IWS Organization | 28 January 2012 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||||
| Item 2 | ||||||||||
| Disk 1 of 5 | MCE Cabinet TDP | August 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||||
| Item 3 | ||||||||||
| Disk 1 of 5 | Packaging, Handling, Storage, and Transportation (PHS&T) Plan | 1.0 | 15 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 4 | ||||||||||
| Disk 1 of 5 | Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management Plan |
Document # PEOIWS Management Plan
| (Applicable to Variants A & B) | June 2005 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 5 | ||||||||
| Disk 1 of 5 | Physical Configuration Audit Plans | 1.0 | 29 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||
| Functional Audit Plans | 1.0 | 29 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 6 | ||||||||
| Disk 1 of 5 | Technical Review Manual (TRM) | 2.0 | 18 December 2009 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||
| Item 7 | ||||||||
| Disk 1 of 5 | Bill of Materials (BOM) | 30 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 8 | ||||||||
| Disk 1 of 5 | Marking Plan | 1.1 | 18 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||
| Item 9 | ||||||||
| Disk 1 of 5 | CDS/CPS CM Plan | 17 January 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 10 | ||||||||
| Disk 1 of 5 | Installation Control Drawings | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 11 | ||||||||
| Disk 1 of 5 | LRU Cross Refence List | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 12 | ||||||||
| Disk 1 of 5 | Spares/INCO List | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 13 Disk 1 of 5 | MCE Circuit Breaker Drawing | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 1 | ||||||||
| Disk 2 of 5 | System Requirements Document (SRD) for the Computing Enclosure (CE) | |||||||
| and CCS | 1.1 | 25 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| System Requirements Document (SRD) for the Core Computing System (CCS) | 1 | 25 August 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 2 | ||||||||
| Disk 2 of 5 | Critical Item Design Specifications (CIDS) for ASAN | 1.0 | 25 August 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||
| Critical Item Design Specifications (CIDS) for CCS | 1.0 | 15 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Critical Item Design Specifications (CIDS) for PS2 | 1.0 | 15 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 3 | ||||||||
| Disk 2 of 5 | Factory Acceptance Test (FAT) for ASAN | 1.0 | 23 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||
| Factory Acceptance Test (FAT) for CCS | 1.0 | 23 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Factory Acceptance Test (FAT) for PS2 | 1.0 | 23 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 4 | ||||||||
| Disk 2 of 5 | CISCO Inspection and Cleaning Instrucitons | 1.0 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 1 | ||||||||
| Disk 3 of 5 | Advanced Storage Area Network (ASAN) Drawings | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 2 | ||||||||
| Disk 3 of 5 | Core Computing System (CCS) Drawings | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 3 | ||||||||
| Disk 3 of 5 | Processing and Storage System (PS2) Drawings | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 4 | ||||||||
| Disk 3 of 5 | Common Drawings | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | ||||||
| Item 5 | ||||||||
| Disk 3 of 5 | Work Instructions | 26 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 1 | ||||||||
| Disk 4of 5 | Oracle Virtual Machine (VM) Virtual Box 4.3.14-95030 | 4.3.14-95030 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 2 | ||||||||
| Disk 4 of 5 | VM VirtualBox Extension Pack 4.3.14-95030 | 4.3.14-95030 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 3 | ||||||||
| Disk 4 of 5 | WinSCP Version 5.5.5 | 5.5.5 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. | |||||
| Item 1 | ||||||||
| Disk 5 of 5 | TI16 FAT procedures (VM format) | 1 | 23 September 2014 | [Provided with the solicitation] - Upon receipt of the Terms of Use letter by the Contract Specialist, the Competition Library will be made available in a secure manner to the Offeror so long as the Offeror has met the security requirements. |
NAVSEA 4340/02 (Rev.4-2008) &"-,Bold"&12PAGE &P OF &N