Attachment_11_-_Fault_Isolation_Process_Rev_01.pdf

PDF 203 KB Posted

Attached to
FY16 MK54 Lightweight Torpedo (LWT) Common Parts Kit TDP
Solicitation number
N00024-14-R-6410
Issued by

About this file

Attachment 11 - Fault Isolation Process Rev 01

View the file

Other files

File Type Posted
Q A_Posted_12_Feb_2016.pdf PDF
Attachment_1_-_Contract_Baseline_Rev_01.pdf PDF
Conformed_Copy_of_N00024-15-R-6406_Amendment_0001.doc DOC document
Industry_Day_vs_RFP_Amendment_0001_Deltas.pdf PDF
Amendment_0001_-_Q A_1-17.pdf PDF
Exhibit_C_Spares_Rev_01.xlsx XLSX spreadsheet
Exhibit_A_-_CDRL_A_-_MK54_Common_Parts_Kits_Rev_01.pdf PDF
Exhibit_E_-_Production_Support_Materials_List_Rev_01.xlsx XLSX spreadsheet
Attachment_4_-_Government_Furnished_Equipment_Rev_01.pdf PDF
Attachment_8_-_Unique_Identification_(UID)_Items_Rev_01.pdf PDF
N00024-15-R-6406_Amendment_0001.pdf PDF
Exhibit_D_-_Exercise_Fuel_Tank_Parts_List_Rev_01.xlsx XLSX spreadsheet
Attachment_3_-_Government_Furnished_Information_Rev_01.pdf PDF
Attachment 4 - Government Furnished Equipment Rev1.pdf PDF
Exhibit E - Production Support Materials List Rev1.pdf PDF
Attachment 13_7017 List.pdf PDF
Exhibit C Spares Rev1.pdf PDF
Attachment 14_7028 List.pdf PDF
Attachment 7 - Quality Assurance Surveillance Plan.pdf PDF
Attachment 9 - FOSS CSS.pdf PDF
Exhibit D - Exercise Fuel Tank Parts List.pdf PDF
Attachment 12 - Non-Disclosure Agreement.pdf PDF
Exhibit A - CDRL A - MK54 Common Parts Kits.pdf PDF
Attachment 2 - Shipping Instruction Data Rev2.pdf PDF
Attachment 3 - Government Furnished Information Rev1.pdf PDF
Exhibit F - Build-to-Print Items and Assemblies.pdf PDF
Attachment 5 - Government Furnished Facilities.pdf PDF
Exhibit B - CDRL B - MK54 Common Parts Kits.pdf PDF
Attachment 1 To Exhibits A and B.pdf PDF
Attachment 1 - Contract Baseline.pdf PDF
Attachment 8 - Unique Identification —
N00024-15-R-6406_Final_Executed.pdf PDF
Attachment 10 - Test Capabilities Rev 01.pdf PDF
Attachment 11 - Fault Isolation Process.pdf PDF
Attachment 6 - DD254.pdf PDF
DD254_CONTRACT_SECURITY_CLASSIFICATION_SPECIFICATION.pdf PDF
SF312-13 _classified_information_nondisclosure_agreement.pdf PDF
TDP_material_request_form.docx DOCX document
TDP_classified_material_request_form.pdf PDF
DD254 _CONTRACT_SECURITY_CLASSIFICATION_SPECIFICATION.PDF PDF
SF312-13 _classified_information_nondisclosure_agreement.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00024-15-R-6406

Attachment 11

Fault Isolation Process

Rev 01

Base

RECORD OF CHANGES

Revision Comment Date

Base Initial Revision (RFP: N00024-15-R-6406) 27 July 2015

Rev 01 Typo correction under FIT responsibilities 11 Jan 2016

1. PURPOSE:

This attachment provides the processes utilized for fault isolation of non-conformances identified by the Government, as well as the means for tracking both Government and Contractor failure analysis efforts to closure.

2. FAILURES IDENTIFIED BY THE GOVERNMENT:

When non-conformances are identified by the Government, either within an Intermediate Maintenance Activity (IMA) or during a Government test event, the Government will document the nonconformance via a failure TMIS (Torpedo Management Information System) within the Automated Process Control System (APCS). The Government will then begin preliminary fault isolation, to determine the party responsible for the failure.

3. FAULT ISOLATION TEAM:

The Government will host and the Contractor will support a Fault Isolation Team (FIT) weekly meeting, in accordance with the contract’s Statement of Work (SOW). The purpose of the FIT is to track nonconforming material that is identified during Government and Contractor testing. The FIT will then determine the appropriate actions to prevent additional nonconforming material. Only Contractor failures reportable under CDRL A005 will be tracked within the FIT meetings.

3.1 FIT RESPONSIBILITIES

The FIT is collectively responsible for:

a. Determining the responsibility of nonconforming material

b. Discussing and guiding failure analysis efforts and corrective actions

c. Determining actions required to prevent processing of additional nonconforming material

d. Ensuring that action is taken to prevent recurrence of the nonconformance

e. Tracking Government failure analysis efforts to closure

f. Tracking Contractor FRACA Reports to closure and providing disposition of those

Reports

3.2. FIT COMPOSITION:

The FIT is chaired by the Production Acceptance Lead or other PMS 404 appointed Government representative and will include members consisting of the following: Subject Matter Experts (SMEs) from the In-Service Engineering Agent (ISEA), Intermediate Maintenance Activity (IMA), NUWC Keyport’s Production Acceptance team, the Contractor, NUWC Newport, PMS404, NAVSEA02, and Defense Contract Management Activity (DCMA).

3.3. FIT WORKING PROCESS:

New non-conformances will be introduced to the FIT either via a new TMIS documented by the Government, or via new FRACA reports submitted by the contractor. The FIT will discuss preliminary fault isolation of the failure. Once enough information is known about the failure, the FIT Chair, with recommendation from the FIT members, will assign the nonconformance against either the Government or Contractor. This practice results in a list of open FRACA reports and Government TMIS documents that are discussed and tracked to closure during the weekly meetings.

3.4. NON-CONFORMANCE RESPONSIBILITY

3.4.1. CONTRACTOR RESPONSIBILITY

In the event a nonconformance is determined to be the Contractor’s responsibility and the hardware has yet to be final accepted per Section E of the contract, the Contractor shall conduct failure analysis IAW with the FRACA requirements of the contract.

I. GOVERNMENT RESPONSIBILITY

In the event a nonconformance is determined to be the Government’s responsibility, the ISEA or TDA, partnered with the Production Acceptance Engineer (PAE), will determine what actions are necessary to bring the hardware back to a useable condition. The Government will document and track the nonconformance to closure.

4. ACRONYMS

APCS Automated Process Control System

CTR

Contractor

DCMA Defense Contractor Management Agency

FTE Depot Factory Test Equipment

FAT Factory Acceptance Test

FIT Fault Isolation Team

FRACA

Failure Reporting and Corrective Action

FRB

Failure Review Board

IAW

In Accordance With

IMA

Intermediate Maintenance Activity

ISEA

In-Service Engineering Agent

NAVSEA

Naval Sea Systems Command

PAE

Production Acceptance Engineer

RCCA

Root Cause and Corrective Action

TMIS

Torpedo Management Information System

SME

Subject Matter Expert

SOW

Statement of Work