Base
| CLIN | Description | Unit | Base Year Qty | Proposed Price (FFP CLINs) | Proposed Wrap Rate (Hourly Rate CLINs) | Proposed Target Cost | ||
| (CPFF CLINs) | Fixed Fee Dollar Amount | |||||||
| (CPFF CLINs) | Evaluated CLIN Cost | |||||||
| 0001 | Data | Lot | ||||||
| 0002 | Government Property | Months | 2 | $ - 0 | ||||
| 0003 | PMI Phase I (stand-alone) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 0004 | PMI Phase II (stand-alone) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | Each | 3.21 | $ - 0 | ||||
| 0007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 0009 | OW PMI (ordered w/ ow refurbishment) | Each | 3.00 | $ - 0 | ||||
| 0010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 0011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 0014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 0016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | Each | 0.10 | $ - 0 | ||||
| 0017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | Each | 1.03 | $ - 0 | ||||
| 0018 | PMI EP-3 Delta (ordered w/ X009) | Each | 0.71 | $ - 0 | ||||
| 0019 | SSI-K - P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 0020 | Zone 5 (wings-on) - P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 0021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | Each | 0.21 | $ - 0 | ||||
| 0022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.21 | $ - 0 | ||||
| 0023 | Zone 5 and SSI-K - BMUP LSRS | Each | 0.10 | $ - 0 | ||||
| 0024 | Zone 5 and SSI-K - SPA | Each | 0.10 | $ - 0 | ||||
| 0025 | Zone 5 and SSI-K - EP-3 | Each | 0.10 | $ - 0 | ||||
| 0026 | OW Refurbishment (planks 1-9) - All T/M/S | Each | 3.00 | $ - 0 | ||||
| 0027 | Outer Wing Installation - P-3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 0028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 1.34 | $ - 0 | ||||
| 0029 | Outer Wing Installation and CWSR - BMUP LSRS | Each | 1.03 | $ - 0 | ||||
| 0030 | Outer Wing Installation and CWSR - SPA | Each | 0.31 | $ - 0 | ||||
| 0031 | Outer Wing Installation - EP-3 | Each | 0.10 | $ - 0 | ||||
| 0032 | Outer Wing Installation and CWSR - EP-3 | Each | 1.03 | $ - 0 | ||||
| 0033 | Explosive Suppressant Foam Removal | Each | 2.28 | $ - 0 | ||||
| 0034 | Explosive Suppressant Foam Installation | Each | 2.28 | $ - 0 | ||||
| 0035 | ALD-9 Removal | Each | 0.31 | $ - 0 | ||||
| 0036 | Outer Wing Paint Strip | Each | 0.88 | $ - 0 | ||||
| 0037 | BL 65 Domenut Replacement | Each | 2.69 | $ - 0 | ||||
| 0038 | NDI / Prev Inspection = SSI | Each | 0.10 | $ - 0 | ||||
| 0039 | NDI / Prev Inspection = ESSI | Each | 0.10 | $ - 0 | ||||
| 0040 | NDI / Prev Inspection = ESSI w/ CWSR | Each | 0.10 | $ - 0 | ||||
| 0041 | NDI / Prev Inspection = SSI-K | Each | 0.10 | $ - 0 | ||||
| 0042 | NDI / Prev Inspection = New Lower Surface | Each | 0.10 | $ - 0 | ||||
| 0043 | NDI / Prev Inspection = New Outer Wing | Each | 0.10 | $ - 0 | ||||
| 0044 | NDI-LH Forward Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 0045 | NDI-RH Forward Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 0046 | NDI-LH Aft Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 0047 | NDI-RH Aft Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 0048 | Tooling | |||||||
| 0049 | Drop-In Modifications | Hours | 3,000 | $ - 0 | ||||
| 0050 | Drop-In Maintenance | Hours | 3,000 | $ - 0 | ||||
| 0051 | Sustaining Engineering | Hours | 18,000 | $ - 0 | ||||
| 0052 | Travel | |||||||
| 0053 | Over and Above Labor | Hours | 81,000 | $ - 0 | ||||
| 0054 | Material | Dollars | ||||||
| 0055 | Conditional Inspections | Hours | 4,500 | $ - 0 | ||||
| 0056 | RNAV Mode S AFC-719 – P-3C | Each | 0.10 | $ - 0 | ||||
| 0057 | RNAV Mode S AFC-719 Part 2 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 0058 | RNAV Mode S AFC-719 Part 3 – SPA | Each | 0.10 | $ - 0 | ||||
| 0059 | 5V Lighting AFC-720 | Each | 0.10 | $ - 0 | ||||
| 0060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | Each | 0.10 | $ - 0 | ||||
| 0061 | EFDS AFC-603 Part 5 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 0062 | MLR-2020A-1 AFC-686 – P-3C | Each | 0.10 | $ - 0 | ||||
| 0063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 0064 | ARC-210 AFC-693 – P-3C | Each | 0.10 | $ - 0 | ||||
| 0065 | Digital Autopilot AFC-696 | Each | 0.10 | $ - 0 | ||||
| 0066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | Each | 0.10 | $ - 0 | ||||
| 0067 | ASX-6 (MMIS) AFC-705 | Each | 0.10 | $ - 0 | ||||
| 0068 | RNAV Mode S AFC-719 – P-3C Field Team | Each | 0.10 | $ - 0 | ||||
| 0069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | Each | 0.10 | $ - 0 | ||||
| 0070 | 5V Lighting AFC-720 Field Team | Each | 0.10 | $ - 0 | ||||
| 0071 | Digital Autopilot AFC-696 Field Team | Each | 0.10 | $ - 0 | ||||
| 0072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | Each | 0.10 | $ - 0 | ||||
| 0073 | ASX-6 (MMIS) AFC-705 Field Team | Each | 0.10 | $ - 0 | ||||
| 0074 | Support Infrastructure - PMI Stand-Alone | Dollars | 0.41 | $ - 0 | ||||
| 0075 | Support Infrastructure - SSI-K Stand-Alone | Dollars | 0.21 | $ - 0 | ||||
| 0076 | Support Infrastructure - SSI-K w/ PMI | Dollars | 0.21 | $ - 0 | ||||
| 0077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | Dollars | 0.10 | $ - 0 | ||||
| 0078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 0079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | Dollars | 0.10 | $ - 0 | ||||
| 0080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 0081 | Support Infrastructure - SSI-K and Zone 5 | Dollars | 0.41 | $ - 0 | ||||
| 0082 | Support Infrastructure - SSI-K and Zone w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 0083 | Support Infrastructure - OW Refurbishment w/ PMI | Dollars | 3.00 | $ - 0 | ||||
| 0084 | Support Infrastructure - OW Installation | Dollars | 0.21 | $ - 0 | ||||
| 0085 | Support Infrastructure - OW Installation w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 0086 | Support Infrastructure - OW Installation w/ CWSR | Dollars | 0.10 | $ - 0 | ||||
| 0087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | Dollars | 3.62 | $ - 0 | ||||
| 0088 | Program Coordination | Lot | 1.00 | $ - 0 | ||||
| 0089 | Program Plans | Lot | 1.00 | $ - 0 | ||||
| Yellow | OW CLINs | Total Evaluated Cost Base Year | $ - 0 | |||||
| Green | Hourly Rate CLINs | Total Evaluated Cost Option I | $ - 0 | |||||
| Blue | Support Infrastructure CLINs | Total Evaluated Cost Option II | $ - 0 | |||||
| Grey | Unevaluated CLINs | Total Evaluated Cost Option III | $ - 0 | |||||
| Dark Blue | Value to be entered by Offeror | Total Evaluated Cost Option IV | $ - 0 | |||||
| Total Evaluated Cost Option V | $ - 0 | |||||||
| Total Evaluated Cost | $ - 0 |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Base Year
&CN00019-09-R-0216
Attachment 20
Option I
| CLIN | Description | Unit | Option I Qty | Proposed Price (FFP CLINs) | Proposed Wrap Rate (Hourly Rate CLINs) | Proposed Target Cost | ||
| (CPFF CLINs) | Fixed Fee Dollar Amount | |||||||
| (CPFF CLINs) | Evaluated CLIN Cost | |||||||
| 1001 | Data | Lot | ||||||
| 1002 | Government Property | Months | 12 | $ - 0 | ||||
| 1003 | PMI Phase I (stand-alone) – P3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 1004 | PMI Phase II (stand-alone) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | Each | 9.62 | $ - 0 | ||||
| 1007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | Each | 1.24 | $ - 0 | ||||
| 1009 | OW PMI (ordered w/ ow refurbishment) | Each | 8.00 | $ - 0 | ||||
| 1010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 1011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 1014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 1016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | Each | 0.31 | $ - 0 | ||||
| 1017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | Each | 3.10 | $ - 0 | ||||
| 1018 | PMI EP-3 Delta (ordered w/ X009) | Each | 1.88 | $ - 0 | ||||
| 1019 | SSI-K - P3C / NP-3 | Each | 1.24 | $ - 0 | ||||
| 1020 | Zone 5 (wings-on) - P3C / NP-3 | Each | 1.24 | $ - 0 | ||||
| 1021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | Each | 0.62 | $ - 0 | ||||
| 1022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.62 | $ - 0 | ||||
| 1023 | Zone 5 and SSI-K - BMUP LSRS | Each | 0.31 | $ - 0 | ||||
| 1024 | Zone 5 and SSI-K - SPA | Each | 0.31 | $ - 0 | ||||
| 1025 | Zone 5 and SSI-K - EP-3 | Each | 0.31 | $ - 0 | ||||
| 1026 | OW Refurbishment (planks 1-9) - All T/M/S | Each | 8.00 | $ - 0 | ||||
| 1027 | Outer Wing Installation - P-3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 1028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 4.03 | $ - 0 | ||||
| 1029 | Outer Wing Installation and CWSR - BMUP LSRS | Each | 3.10 | $ - 0 | ||||
| 1030 | Outer Wing Installation and CWSR - SPA | Each | 0.93 | $ - 0 | ||||
| 1031 | Outer Wing Installation - EP-3 | Each | 0.31 | $ - 0 | ||||
| 1032 | Outer Wing Installation and CWSR - EP-3 | Each | 3.10 | $ - 0 | ||||
| 1033 | Explosive Suppressant Foam Removal | Each | 6.83 | $ - 0 | ||||
| 1034 | Explosive Suppressant Foam Installation | Each | 6.83 | $ - 0 | ||||
| 1035 | ALD-9 Removal | Each | 0.93 | $ - 0 | ||||
| 1036 | Outer Wing Paint Strip | Each | 2.35 | $ - 0 | ||||
| 1037 | BL 65 Domenut Replacement | Each | 8.07 | $ - 0 | ||||
| 1038 | NDI / Prev Inspection = SSI | Each | 0.31 | $ - 0 | ||||
| 1039 | NDI / Prev Inspection = ESSI | Each | 0.31 | $ - 0 | ||||
| 1040 | NDI / Prev Inspection = ESSI w/ CWSR | Each | 0.31 | $ - 0 | ||||
| 1041 | NDI / Prev Inspection = SSI-K | Each | 0.31 | $ - 0 | ||||
| 1042 | NDI / Prev Inspection = New Lower Surface | Each | 0.31 | $ - 0 | ||||
| 1043 | NDI / Prev Inspection = New Outer Wing | Each | 0.31 | $ - 0 | ||||
| 1044 | NDI-LH Forward Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 1045 | NDI-RH Forward Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 1046 | NDI-LH Aft Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 1047 | NDI-RH Aft Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 1048 | Tooling | |||||||
| 1049 | Drop-In Modifications | Hours | 9,000 | $ - 0 | ||||
| 1050 | Drop-In Maintenance | Hours | 9,000 | $ - 0 | ||||
| 1051 | Sustaining Engineering | Hours | 52,000 | $ - 0 | ||||
| 1052 | Travel | |||||||
| 1053 | Over and Above Labor | Hours | 236,000 | $ - 0 | ||||
| 1054 | Material | Dollars | ||||||
| 1055 | Conditional Inspections | Hours | 13,000 | $ - 0 | ||||
| 1056 | RNAV Mode S AFC-719 – P-3C | Each | 0.31 | $ - 0 | ||||
| 1057 | RNAV Mode S AFC-719 Part 2 – EP-3 | Each | 0.31 | $ - 0 | ||||
| 1058 | RNAV Mode S AFC-719 Part 3 – SPA | Each | 0.31 | $ - 0 | ||||
| 1059 | 5V Lighting AFC-720 | Each | 0.31 | $ - 0 | ||||
| 1060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | Each | 0.31 | $ - 0 | ||||
| 1061 | EFDS AFC-603 Part 5 – EP-3 | Each | 0.31 | $ - 0 | ||||
| 1062 | MLR-2020A-1 AFC-686 – P-3C | Each | 0.31 | $ - 0 | ||||
| 1063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | Each | 0.31 | $ - 0 | ||||
| 1064 | ARC-210 AFC-693 – P-3C | Each | 0.31 | $ - 0 | ||||
| 1065 | Digital Autopilot AFC-696 | Each | 0.31 | $ - 0 | ||||
| 1066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | Each | 0.31 | $ - 0 | ||||
| 1067 | ASX-6 (MMIS) AFC-705 | Each | 0.31 | $ - 0 | ||||
| 1068 | RNAV Mode S AFC-719 – P-3C Field Team | Each | 0.31 | $ - 0 | ||||
| 1069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | Each | 0.31 | $ - 0 | ||||
| 1070 | 5V Lighting AFC-720 Field Team | Each | 0.31 | $ - 0 | ||||
| 1071 | Digital Autopilot AFC-696 Field Team | Each | 0.31 | $ - 0 | ||||
| 1072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | Each | 0.31 | $ - 0 | ||||
| 1073 | ASX-6 (MMIS) AFC-705 Field Team | Each | 0.31 | $ - 0 | ||||
| 1074 | Support Infrastructure - PMI Stand-Alone | Dollars | 1.24 | $ - 0 | ||||
| 1075 | Support Infrastructure - SSI-K Stand-Alone | Dollars | 0.62 | $ - 0 | ||||
| 1076 | Support Infrastructure - SSI-K w/ PMI | Dollars | 0.62 | $ - 0 | ||||
| 1077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | Dollars | 0.31 | $ - 0 | ||||
| 1078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | Dollars | 0.93 | $ - 0 | ||||
| 1079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | Dollars | 0.31 | $ - 0 | ||||
| 1080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 1081 | Support Infrastructure - SSI-K and Zone 5 | Dollars | 1.24 | $ - 0 | ||||
| 1082 | Support Infrastructure - SSI-K and Zone w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 1083 | Support Infrastructure - OW Refurbishment w/ PMI | Dollars | 8.00 | $ - 0 | ||||
| 1084 | Support Infrastructure - OW Installation | Dollars | 0.62 | $ - 0 | ||||
| 1085 | Support Infrastructure - OW Installation w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 1086 | Support Infrastructure - OW Installation w/ CWSR | Dollars | 0.31 | $ - 0 | ||||
| 1087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | Dollars | 10.86 | $ - 0 | ||||
| 1088 | Program Coordination | Lot | 1.00 | $ - 0 | ||||
| Yellow | OW CLINs | Total Evaluated Cost Option I | $ - 0 | |||||
| Green | Hourly Rate CLINs | |||||||
| Blue | Support Infrastructure CLINs | |||||||
| Grey | Unevaluated CLINs | |||||||
| Dark Blue | Value to be entered by Offeror |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Option I
&CN00019-09-R-0216
Attachment 20
Option II
| CLIN | Description | Unit | Option II Qty | Proposed Price (FFP CLINs) | Proposed Wrap Rate (Hourly Rate CLINs) | Proposed Target Cost | ||
| (CPFF CLINs) | Fixed Fee Dollar Amount | |||||||
| (CPFF CLINs) | Evaluated CLIN Cost | |||||||
| 2001 | Data | Lot | ||||||
| 2002 | Government Property | Months | 12 | $ - 0 | ||||
| 2003 | PMI Phase I (stand-alone) – P3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 2004 | PMI Phase II (stand-alone) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | Each | 9.62 | $ - 0 | ||||
| 2007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | Each | 1.24 | $ - 0 | ||||
| 2009 | OW PMI (ordered w/ ow refurbishment) | Each | 2.00 | $ - 0 | ||||
| 2010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 2011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 2014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.31 | $ - 0 | ||||
| 2016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | Each | 0.31 | $ - 0 | ||||
| 2017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | Each | 3.10 | $ - 0 | ||||
| 2018 | PMI EP-3 Delta (ordered w/ X009) | Each | 0.47 | $ - 0 | ||||
| 2019 | SSI-K - P3C / NP-3 | Each | 1.24 | $ - 0 | ||||
| 2020 | Zone 5 (wings-on) - P3C / NP-3 | Each | 1.24 | $ - 0 | ||||
| 2021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | Each | 0.62 | $ - 0 | ||||
| 2022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.62 | $ - 0 | ||||
| 2023 | Zone 5 and SSI-K - BMUP LSRS | Each | 0.31 | $ - 0 | ||||
| 2024 | Zone 5 and SSI-K - SPA | Each | 0.31 | $ - 0 | ||||
| 2025 | Zone 5 and SSI-K - EP-3 | Each | 0.31 | $ - 0 | ||||
| 2026 | OW Refurbishment (planks 1-9) - All T/M/S | Each | 2.00 | $ - 0 | ||||
| 2027 | Outer Wing Installation - P-3C / NP-3 | Each | 0.62 | $ - 0 | ||||
| 2028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 4.03 | $ - 0 | ||||
| 2029 | Outer Wing Installation and CWSR - BMUP LSRS | Each | 3.10 | $ - 0 | ||||
| 2030 | Outer Wing Installation and CWSR - SPA | Each | 0.93 | $ - 0 | ||||
| 2031 | Outer Wing Installation - EP-3 | Each | 0.31 | $ - 0 | ||||
| 2032 | Outer Wing Installation and CWSR - EP-3 | Each | 3.10 | $ - 0 | ||||
| 2033 | Explosive Suppressant Foam Removal | Each | 6.83 | $ - 0 | ||||
| 2034 | Explosive Suppressant Foam Installation | Each | 6.83 | $ - 0 | ||||
| 2035 | ALD-9 Removal | Each | 0.93 | $ - 0 | ||||
| 2036 | Outer Wing Paint Strip | Each | 0.59 | $ - 0 | ||||
| 2037 | BL 65 Domenut Replacement | Each | 8.07 | $ - 0 | ||||
| 2038 | NDI / Prev Inspection = SSI | Each | 0.31 | $ - 0 | ||||
| 2039 | NDI / Prev Inspection = ESSI | Each | 0.31 | $ - 0 | ||||
| 2040 | NDI / Prev Inspection = ESSI w/ CWSR | Each | 0.31 | $ - 0 | ||||
| 2041 | NDI / Prev Inspection = SSI-K | Each | 0.31 | $ - 0 | ||||
| 2042 | NDI / Prev Inspection = New Lower Surface | Each | 0.31 | $ - 0 | ||||
| 2043 | NDI / Prev Inspection = New Outer Wing | Each | 0.31 | $ - 0 | ||||
| 2044 | NDI-LH Forward Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 2045 | NDI-RH Forward Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 2046 | NDI-LH Aft Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 2047 | NDI-RH Aft Corner Fittings | Each | 0.31 | $ - 0 | ||||
| 2048 | Tooling | |||||||
| 2049 | Drop-In Modifications | Hours | 9,000 | $ - 0 | ||||
| 2050 | Drop-In Maintenance | Hours | 9,000 | $ - 0 | ||||
| 2051 | Sustaining Engineering | Hours | 40,000 | $ - 0 | ||||
| 2052 | Travel | |||||||
| 2053 | Over and Above Labor | Hours | 194,000 | $ - 0 | ||||
| 2054 | Material | Dollars | ||||||
| 2055 | Conditional Inspections | Hours | 10,000 | $ - 0 | ||||
| 2056 | RNAV Mode S AFC-719 – P-3C | Each | 0.31 | $ - 0 | ||||
| 2057 | RNAV Mode S AFC-719 Part 2 – EP-3 | Each | 0.31 | $ - 0 | ||||
| 2058 | RNAV Mode S AFC-719 Part 3 – SPA | Each | 0.31 | $ - 0 | ||||
| 2059 | 5V Lighting AFC-720 | Each | 0.31 | $ - 0 | ||||
| 2060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | Each | 0.31 | $ - 0 | ||||
| 2061 | EFDS AFC-603 Part 5 – EP-3 | Each | 0.31 | $ - 0 | ||||
| 2062 | MLR-2020A-1 AFC-686 – P-3C | Each | 0.31 | $ - 0 | ||||
| 2063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | Each | 0.31 | $ - 0 | ||||
| 2064 | ARC-210 AFC-693 – P-3C | Each | 0.31 | $ - 0 | ||||
| 2065 | Digital Autopilot AFC-696 | Each | 0.31 | $ - 0 | ||||
| 2066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | Each | 0.31 | $ - 0 | ||||
| 2067 | ASX-6 (MMIS) AFC-705 | Each | 0.31 | $ - 0 | ||||
| 2068 | RNAV Mode S AFC-719 – P-3C Field Team | Each | 0.31 | $ - 0 | ||||
| 2069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | Each | 0.31 | $ - 0 | ||||
| 2070 | 5V Lighting AFC-720 Field Team | Each | 0.31 | $ - 0 | ||||
| 2071 | Digital Autopilot AFC-696 Field Team | Each | 0.31 | $ - 0 | ||||
| 2072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | Each | 0.31 | $ - 0 | ||||
| 2073 | ASX-6 (MMIS) AFC-705 Field Team | Each | 0.31 | $ - 0 | ||||
| 2074 | Support Infrastructure - PMI Stand-Alone | Dollars | 1.24 | $ - 0 | ||||
| 2075 | Support Infrastructure - SSI-K Stand-Alone | Dollars | 0.62 | $ - 0 | ||||
| 2076 | Support Infrastructure - SSI-K w/ PMI | Dollars | 0.62 | $ - 0 | ||||
| 2077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | Dollars | 0.31 | $ - 0 | ||||
| 2078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | Dollars | 0.93 | $ - 0 | ||||
| 2079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | Dollars | 0.31 | $ - 0 | ||||
| 2080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 2081 | Support Infrastructure - SSI-K and Zone 5 | Dollars | 1.24 | $ - 0 | ||||
| 2082 | Support Infrastructure - SSI-K and Zone w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 2083 | Support Infrastructure - OW Refurbishment w/ PMI | Dollars | 2.00 | $ - 0 | ||||
| 2084 | Support Infrastructure - OW Installation | Dollars | 0.62 | $ - 0 | ||||
| 2085 | Support Infrastructure - OW Installation w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 2086 | Support Infrastructure - OW Installation w/ CWSR | Dollars | 0.31 | $ - 0 | ||||
| 2087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | Dollars | 10.86 | $ - 0 | ||||
| 2088 | Program Coordination | Lot | 1.00 | $ - 0 | ||||
| Yellow | OW CLINs | Total Evaluated Cost Option II | $ - 0 | |||||
| Green | Hourly Rate CLINs | |||||||
| Orange | CPFF CLIN (only proposed fee will be evaluated when applied to above costs) | |||||||
| Blue | Support Infrastructure CLINs | |||||||
| Grey | Unevaluated CLINs | |||||||
| Dark Blue | Value to be entered by Offeror |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Option II
&CN00019-09-R-0216
Attachment 20
Option III
| CLIN | Description | Unit | Option III Qty | Proposed Price (FFP CLINs) | Proposed Wrap Rate (Hourly Rate CLINs) | Proposed Target Cost | ||
| (CPFF CLINs) | Fixed Fee Dollar Amount | |||||||
| (CPFF CLINs) | Evaluated CLIN Cost | |||||||
| 3001 | Data | Lot | ||||||
| 3002 | Government Property | Months | 12 | $ - 0 | ||||
| 3003 | PMI Phase I (stand-alone) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 3004 | PMI Phase II (stand-alone) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | Each | 3.21 | $ - 0 | ||||
| 3007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 3009 | OW PMI (ordered w/ ow refurbishment) | Each | 2.00 | $ - 0 | ||||
| 3010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 3011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 3014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 3016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | Each | 0.10 | $ - 0 | ||||
| 3017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | Each | 1.03 | $ - 0 | ||||
| 3018 | PMI EP-3 Delta (ordered w/ X009) | Each | 0.47 | $ - 0 | ||||
| 3019 | SSI-K - P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 3020 | Zone 5 (wings-on) - P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 3021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | Each | 0.21 | $ - 0 | ||||
| 3022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.21 | $ - 0 | ||||
| 3023 | Zone 5 and SSI-K - BMUP LSRS | Each | 0.10 | $ - 0 | ||||
| 3024 | Zone 5 and SSI-K - SPA | Each | 0.10 | $ - 0 | ||||
| 3025 | Zone 5 and SSI-K - EP-3 | Each | 0.10 | $ - 0 | ||||
| 3026 | OW Refurbishment (planks 1-9) - All T/M/S | Each | 2.00 | $ - 0 | ||||
| 3027 | Outer Wing Installation - P-3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 3028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 1.34 | $ - 0 | ||||
| 3029 | Outer Wing Installation and CWSR - BMUP LSRS | Each | 1.03 | $ - 0 | ||||
| 3030 | Outer Wing Installation and CWSR - SPA | Each | 0.31 | $ - 0 | ||||
| 3031 | Outer Wing Installation - EP-3 | Each | 0.10 | $ - 0 | ||||
| 3032 | Outer Wing Installation and CWSR - EP-3 | Each | 1.03 | $ - 0 | ||||
| 3033 | Explosive Suppressant Foam Removal | Each | 2.28 | $ - 0 | ||||
| 3034 | Explosive Suppressant Foam Installation | Each | 2.28 | $ - 0 | ||||
| 3035 | ALD-9 Removal | Each | 0.31 | $ - 0 | ||||
| 3036 | Outer Wing Paint Strip | Each | 0.59 | $ - 0 | ||||
| 3037 | BL 65 Domenut Replacement | Each | 2.69 | $ - 0 | ||||
| 3038 | NDI / Prev Inspection = SSI | Each | 0.10 | $ - 0 | ||||
| 3039 | NDI / Prev Inspection = ESSI | Each | 0.10 | $ - 0 | ||||
| 3040 | NDI / Prev Inspection = ESSI w/ CWSR | Each | 0.10 | $ - 0 | ||||
| 3041 | NDI / Prev Inspection = SSI-K | Each | 0.10 | $ - 0 | ||||
| 3042 | NDI / Prev Inspection = New Lower Surface | Each | 0.10 | $ - 0 | ||||
| 3043 | NDI / Prev Inspection = New Outer Wing | Each | 0.10 | $ - 0 | ||||
| 3044 | NDI-LH Forward Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 3045 | NDI-RH Forward Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 3046 | NDI-LH Aft Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 3047 | NDI-RH Aft Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 3048 | Tooling | |||||||
| 3049 | Drop-In Modifications | Hours | 3,000 | $ - 0 | ||||
| 3050 | Drop-In Maintenance | Hours | 3,000 | $ - 0 | ||||
| 3051 | Sustaining Engineering | Hours | 16,000 | $ - 0 | ||||
| 3052 | Travel | |||||||
| 3053 | Over and Above Labor | Hours | 74,000 | $ - 0 | ||||
| 3054 | Material | Dollars | ||||||
| 3055 | Conditional Inspections | Hours | 4,000 | $ - 0 | ||||
| 3056 | RNAV Mode S AFC-719 – P-3C | Each | 0.10 | $ - 0 | ||||
| 3057 | RNAV Mode S AFC-719 Part 2 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 3058 | RNAV Mode S AFC-719 Part 3 – SPA | Each | 0.10 | $ - 0 | ||||
| 3059 | 5V Lighting AFC-720 | Each | 0.10 | $ - 0 | ||||
| 3060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | Each | 0.10 | $ - 0 | ||||
| 3061 | EFDS AFC-603 Part 5 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 3062 | MLR-2020A-1 AFC-686 – P-3C | Each | 0.10 | $ - 0 | ||||
| 3063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 3064 | ARC-210 AFC-693 – P-3C | Each | 0.10 | $ - 0 | ||||
| 3065 | Digital Autopilot AFC-696 | Each | 0.10 | $ - 0 | ||||
| 3066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | Each | 0.10 | $ - 0 | ||||
| 3067 | ASX-6 (MMIS) AFC-705 | Each | 0.10 | $ - 0 | ||||
| 3068 | RNAV Mode S AFC-719 – P-3C Field Team | Each | 0.10 | $ - 0 | ||||
| 3069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | Each | 0.10 | $ - 0 | ||||
| 3070 | 5V Lighting AFC-720 Field Team | Each | 0.10 | $ - 0 | ||||
| 3071 | Digital Autopilot AFC-696 Field Team | Each | 0.10 | $ - 0 | ||||
| 3072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | Each | 0.10 | $ - 0 | ||||
| 3073 | ASX-6 (MMIS) AFC-705 Field Team | Each | 0.10 | $ - 0 | ||||
| 3074 | Support Infrastructure - PMI Stand-Alone | Dollars | 0.41 | $ - 0 | ||||
| 3075 | Support Infrastructure - SSI-K Stand-Alone | Dollars | 0.21 | $ - 0 | ||||
| 3076 | Support Infrastructure - SSI-K w/ PMI | Dollars | 0.21 | $ - 0 | ||||
| 3077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | Dollars | 0.10 | $ - 0 | ||||
| 3078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 3079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | Dollars | 0.10 | $ - 0 | ||||
| 3080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 3081 | Support Infrastructure - SSI-K and Zone 5 | Dollars | 0.41 | $ - 0 | ||||
| 3082 | Support Infrastructure - SSI-K and Zone w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 3083 | Support Infrastructure - OW Refurbishment w/ PMI | Dollars | 2.00 | $ - 0 | ||||
| 3084 | Support Infrastructure - OW Installation | Dollars | 0.21 | $ - 0 | ||||
| 3085 | Support Infrastructure - OW Installation w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 3086 | Support Infrastructure - OW Installation w/ CWSR | Dollars | 0.10 | $ - 0 | ||||
| 3087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | Dollars | 3.62 | $ - 0 | ||||
| 3088 | Program Coordination | Lot | 1.00 | $ - 0 | ||||
| Yellow | OW CLINs | Total Evaluated Cost Option III | $ - 0 | |||||
| Green | Hourly Rate CLINs | |||||||
| Blue | Support Infrastructure CLINs | |||||||
| Grey | Unevaluated CLINs | |||||||
| Dark Blue | Value to be entered by Offeror |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Option III
&CN00019-09-R-0216
Attachment 20
Option IV
| CLIN | Description | Unit | Option IV Qty | Proposed Price (FFP CLINs) | Proposed Wrap Rate (Hourly Rate CLINs) | Proposed Target Cost | ||
| (CPFF CLINs) | Fixed Fee Dollar Amount | |||||||
| (CPFF CLINs) | Evaluated CLIN Cost | |||||||
| 4001 | Data | Lot | ||||||
| 4002 | Government Property | Months | 12 | $ - 0 | ||||
| 4003 | PMI Phase I (stand-alone) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 4004 | PMI Phase II (stand-alone) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | Each | 3.21 | $ - 0 | ||||
| 4007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 4009 | OW PMI (ordered w/ ow refurbishment) | Each | 2.00 | $ - 0 | ||||
| 4010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 4011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 4014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.10 | $ - 0 | ||||
| 4016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | Each | 0.10 | $ - 0 | ||||
| 4017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | Each | 1.03 | $ - 0 | ||||
| 4018 | PMI EP-3 Delta (ordered w/ X009) | Each | 0.47 | $ - 0 | ||||
| 4019 | SSI-K - P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 4020 | Zone 5 (wings-on) - P3C / NP-3 | Each | 0.41 | $ - 0 | ||||
| 4021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | Each | 0.21 | $ - 0 | ||||
| 4022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.21 | $ - 0 | ||||
| 4023 | Zone 5 and SSI-K - BMUP LSRS | Each | 0.10 | $ - 0 | ||||
| 4024 | Zone 5 and SSI-K - SPA | Each | 0.10 | $ - 0 | ||||
| 4025 | Zone 5 and SSI-K - EP-3 | Each | 0.10 | $ - 0 | ||||
| 4026 | OW Refurbishment (planks 1-9) - All T/M/S | Each | 2.00 | $ - 0 | ||||
| 4027 | Outer Wing Installation - P-3C / NP-3 | Each | 0.21 | $ - 0 | ||||
| 4028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 1.34 | $ - 0 | ||||
| 4029 | Outer Wing Installation and CWSR - BMUP LSRS | Each | 1.03 | $ - 0 | ||||
| 4030 | Outer Wing Installation and CWSR - SPA | Each | 0.31 | $ - 0 | ||||
| 4031 | Outer Wing Installation - EP-3 | Each | 0.10 | $ - 0 | ||||
| 4032 | Outer Wing Installation and CWSR - EP-3 | Each | 1.03 | $ - 0 | ||||
| 4033 | Explosive Suppressant Foam Removal | Each | 2.28 | $ - 0 | ||||
| 4034 | Explosive Suppressant Foam Installation | Each | 2.28 | $ - 0 | ||||
| 4035 | ALD-9 Removal | Each | 0.31 | $ - 0 | ||||
| 4036 | Outer Wing Paint Strip | Each | 0.59 | $ - 0 | ||||
| 4037 | BL 65 Domenut Replacement | Each | 2.69 | $ - 0 | ||||
| 4038 | NDI / Prev Inspection = SSI | Each | 0.10 | $ - 0 | ||||
| 4039 | NDI / Prev Inspection = ESSI | Each | 0.10 | $ - 0 | ||||
| 4040 | NDI / Prev Inspection = ESSI w/ CWSR | Each | 0.10 | $ - 0 | ||||
| 4041 | NDI / Prev Inspection = SSI-K | Each | 0.10 | $ - 0 | ||||
| 4042 | NDI / Prev Inspection = New Lower Surface | Each | 0.10 | $ - 0 | ||||
| 4043 | NDI / Prev Inspection = New Outer Wing | Each | 0.10 | $ - 0 | ||||
| 4044 | NDI-LH Forward Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 4045 | NDI-RH Forward Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 4046 | NDI-LH Aft Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 4047 | NDI-RH Aft Corner Fittings | Each | 0.10 | $ - 0 | ||||
| 4048 | Tooling | |||||||
| 4049 | Drop-In Modifications | Hours | 3,000 | $ - 0 | ||||
| 4050 | Drop-In Maintenance | Hours | 3,000 | $ - 0 | ||||
| 4051 | Sustaining Engineering | Hours | 16,000 | $ - 0 | ||||
| 4052 | Travel | |||||||
| 4053 | Over and Above Labor | Hours | 74,000 | $ - 0 | ||||
| 4054 | Material | Dollars | ||||||
| 4055 | Conditional Inspections | Hours | 4,000 | $ - 0 | ||||
| 4056 | RNAV Mode S AFC-719 – P-3C | Each | 0.10 | $ - 0 | ||||
| 4057 | RNAV Mode S AFC-719 Part 2 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 4058 | RNAV Mode S AFC-719 Part 3 – SPA | Each | 0.10 | $ - 0 | ||||
| 4059 | 5V Lighting AFC-720 | Each | 0.10 | $ - 0 | ||||
| 4060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | Each | 0.10 | $ - 0 | ||||
| 4061 | EFDS AFC-603 Part 5 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 4062 | MLR-2020A-1 AFC-686 – P-3C | Each | 0.10 | $ - 0 | ||||
| 4063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | Each | 0.10 | $ - 0 | ||||
| 4064 | ARC-210 AFC-693 – P-3C | Each | 0.10 | $ - 0 | ||||
| 4065 | Digital Autopilot AFC-696 | Each | 0.10 | $ - 0 | ||||
| 4066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | Each | 0.10 | $ - 0 | ||||
| 4067 | ASX-6 (MMIS) AFC-705 | Each | 0.10 | $ - 0 | ||||
| 4068 | RNAV Mode S AFC-719 – P-3C Field Team | Each | 0.10 | $ - 0 | ||||
| 4069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | Each | 0.10 | $ - 0 | ||||
| 4070 | 5V Lighting AFC-720 Field Team | Each | 0.10 | $ - 0 | ||||
| 4071 | Digital Autopilot AFC-696 Field Team | Each | 0.10 | $ - 0 | ||||
| 4072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | Each | 0.10 | $ - 0 | ||||
| 4073 | ASX-6 (MMIS) AFC-705 Field Team | Each | 0.10 | $ - 0 | ||||
| 4074 | Support Infrastructure - PMI Stand-Alone | Dollars | 0.41 | $ - 0 | ||||
| 4075 | Support Infrastructure - SSI-K Stand-Alone | Dollars | 0.21 | $ - 0 | ||||
| 4076 | Support Infrastructure - SSI-K w/ PMI | Dollars | 0.21 | $ - 0 | ||||
| 4077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | Dollars | 0.10 | $ - 0 | ||||
| 4078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | Dollars | 0.31 | $ - 0 | ||||
| 4079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | Dollars | 0.10 | $ - 0 | ||||
| 4080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 4081 | Support Infrastructure - SSI-K and Zone 5 | Dollars | 0.41 | $ - 0 | ||||
| 4082 | Support Infrastructure - SSI-K and Zone w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 4083 | Support Infrastructure - OW Refurbishment w/ PMI | Dollars | 2.00 | $ - 0 | ||||
| 4084 | Support Infrastructure - OW Installation | Dollars | 0.21 | $ - 0 | ||||
| 4085 | Support Infrastructure - OW Installation w/ PMI | Dollars | 0.10 | $ - 0 | ||||
| 4086 | Support Infrastructure - OW Installation w/ CWSR | Dollars | 0.10 | $ - 0 | ||||
| 4087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | Dollars | 3.62 | $ - 0 | ||||
| 4088 | Program Coordination | Lot | 1.00 | $ - 0 | ||||
| Yellow | OW CLINs | Total Evaluated Cost Option IV | $ - 0 | |||||
| Green | Hourly Rate CLINs | |||||||
| Blue | Support Infrastructure CLINs | |||||||
| Grey | Unevaluated CLINs | |||||||
| Dark Blue | Value to be entered by Offeror |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Option IV
&CN00019-09-R-0216
Attachment 20
Option V
| CLIN | Description | Unit | Option V Qty | Proposed Price (FFP CLINs) | Proposed Wrap Rate (Hourly Rate CLINs) | Proposed Target Cost | ||
| (CPFF CLINs) | Fixed Fee Dollar Amount | |||||||
| (CPFF CLINs) | Evaluated CLIN Cost | |||||||
| 5001 | Data | Lot | ||||||
| 5002 | Government Property | Months | 10 | $ - 0 | ||||
| 5003 | PMI Phase I (stand-alone) – P3C / NP-3 | Each | 0.14 | $ - 0 | ||||
| 5004 | PMI Phase II (stand-alone) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | Each | 2.14 | $ - 0 | ||||
| 5007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | Each | 0.28 | $ - 0 | ||||
| 5009 | OW PMI (ordered w/ ow refurbishment) | Each | 0.00 | $ - 0 | ||||
| 5010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.14 | $ - 0 | ||||
| 5011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.14 | $ - 0 | ||||
| 5014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | Each | 0.07 | $ - 0 | ||||
| 5016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | Each | 0.07 | $ - 0 | ||||
| 5017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | Each | 0.69 | $ - 0 | ||||
| 5018 | PMI EP-3 Delta (ordered w/ X009) | Each | 0.00 | $ - 0 | ||||
| 5019 | SSI-K - P3C / NP-3 | Each | 0.28 | $ - 0 | ||||
| 5020 | Zone 5 (wings-on) - P3C / NP-3 | Each | 0.28 | $ - 0 | ||||
| 5021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | Each | 0.14 | $ - 0 | ||||
| 5022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.14 | $ - 0 | ||||
| 5023 | Zone 5 and SSI-K - BMUP LSRS | Each | 0.07 | $ - 0 | ||||
| 5024 | Zone 5 and SSI-K - SPA | Each | 0.07 | $ - 0 | ||||
| 5025 | Zone 5 and SSI-K - EP-3 | Each | 0.07 | $ - 0 | ||||
| 5026 | OW Refurbishment (planks 1-9) - All T/M/S | Each | 0.00 | $ - 0 | ||||
| 5027 | Outer Wing Installation - P-3C / NP-3 | Each | 0.14 | $ - 0 | ||||
| 5028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | Each | 0.90 | $ - 0 | ||||
| 5029 | Outer Wing Installation and CWSR - BMUP LSRS | Each | 0.69 | $ - 0 | ||||
| 5030 | Outer Wing Installation and CWSR - SPA | Each | 0.21 | $ - 0 | ||||
| 5031 | Outer Wing Installation - EP-3 | Each | 0.07 | $ - 0 | ||||
| 5032 | Outer Wing Installation and CWSR - EP-3 | Each | 0.69 | $ - 0 | ||||
| 5033 | Explosive Suppressant Foam Removal | Each | 1.52 | $ - 0 | ||||
| 5034 | Explosive Suppressant Foam Installation | Each | 1.52 | $ - 0 | ||||
| 5035 | ALD-9 Removal | Each | 0.21 | $ - 0 | ||||
| 5036 | Outer Wing Paint Strip | Each | 0.00 | $ - 0 | ||||
| 5037 | BL 65 Domenut Replacement | Each | 1.79 | $ - 0 | ||||
| 5038 | NDI / Prev Inspection = SSI | Each | 0.07 | $ - 0 | ||||
| 5039 | NDI / Prev Inspection = ESSI | Each | 0.07 | $ - 0 | ||||
| 5040 | NDI / Prev Inspection = ESSI w/ CWSR | Each | 0.07 | $ - 0 | ||||
| 5041 | NDI / Prev Inspection = SSI-K | Each | 0.07 | $ - 0 | ||||
| 5042 | NDI / Prev Inspection = New Lower Surface | Each | 0.07 | $ - 0 | ||||
| 5043 | NDI / Prev Inspection = New Outer Wing | Each | 0.07 | $ - 0 | ||||
| 5044 | NDI-LH Forward Corner Fittings | Each | 0.07 | $ - 0 | ||||
| 5045 | NDI-RH Forward Corner Fittings | Each | 0.07 | $ - 0 | ||||
| 5046 | NDI-LH Aft Corner Fittings | Each | 0.07 | $ - 0 | ||||
| 5047 | NDI-RH Aft Corner Fittings | Each | 0.07 | $ - 0 | ||||
| 5048 | Tooling | |||||||
| 5049 | Drop-In Modifications | Hours | 2,000 | $ - 0 | ||||
| 5050 | Drop-In Maintenance | Hours | 2,000 | $ - 0 | ||||
| 5051 | Sustaining Engineering | Hours | 8,000 | $ - 0 | ||||
| 5052 | Travel | |||||||
| 5053 | Over and Above Labor | Hours | 40,000 | $ - 0 | ||||
| 5054 | Material | Dollars | ||||||
| 5055 | Conditional Inspections | Hours | 2,000 | $ - 0 | ||||
| 5056 | RNAV Mode S AFC-719 – P-3C | Each | 0.07 | $ - 0 | ||||
| 5057 | RNAV Mode S AFC-719 Part 2 – EP-3 | Each | 0.07 | $ - 0 | ||||
| 5058 | RNAV Mode S AFC-719 Part 3 – SPA | Each | 0.07 | $ - 0 | ||||
| 5059 | 5V Lighting AFC-720 | Each | 0.07 | $ - 0 | ||||
| 5060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | Each | 0.07 | $ - 0 | ||||
| 5061 | EFDS AFC-603 Part 5 – EP-3 | Each | 0.07 | $ - 0 | ||||
| 5062 | MLR-2020A-1 AFC-686 – P-3C | Each | 0.07 | $ - 0 | ||||
| 5063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | Each | 0.07 | $ - 0 | ||||
| 5064 | ARC-210 AFC-693 – P-3C | Each | 0.07 | $ - 0 | ||||
| 5065 | Digital Autopilot AFC-696 | Each | 0.07 | $ - 0 | ||||
| 5066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | Each | 0.07 | $ - 0 | ||||
| 5067 | ASX-6 (MMIS) AFC-705 | Each | 0.07 | $ - 0 | ||||
| 5068 | RNAV Mode S AFC-719 – P-3C Field Team | Each | 0.07 | $ - 0 | ||||
| 5069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | Each | 0.07 | $ - 0 | ||||
| 5070 | 5V Lighting AFC-720 Field Team | Each | 0.07 | $ - 0 | ||||
| 5071 | Digital Autopilot AFC-696 Field Team | Each | 0.07 | $ - 0 | ||||
| 5072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | Each | 0.07 | $ - 0 | ||||
| 5073 | ASX-6 (MMIS) AFC-705 Field Team | Each | 0.07 | $ - 0 | ||||
| 5074 | Support Infrastructure - PMI Stand-Alone | Dollars | 0.28 | $ - 0 | ||||
| 5075 | Support Infrastructure - SSI-K Stand-Alone | Dollars | 0.14 | $ - 0 | ||||
| 5076 | Support Infrastructure - SSI-K w/ PMI | Dollars | 0.14 | $ - 0 | ||||
| 5077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | Dollars | 0.07 | $ - 0 | ||||
| 5078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | Dollars | 0.21 | $ - 0 | ||||
| 5079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | Dollars | 0.07 | $ - 0 | ||||
| 5080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | Dollars | 0.07 | $ - 0 | ||||
| 5081 | Support Infrastructure - SSI-K and Zone 5 | Dollars | 0.28 | $ - 0 | ||||
| 5082 | Support Infrastructure - SSI-K and Zone w/ PMI | Dollars | 0.07 | $ - 0 | ||||
| 5083 | Support Infrastructure - OW Refurbishment w/ PMI | Dollars | 0.00 | $ - 0 | ||||
| 5084 | Support Infrastructure - OW Installation | Dollars | 0.14 | $ - 0 | ||||
| 5085 | Support Infrastructure - OW Installation w/ PMI | Dollars | 0.07 | $ - 0 | ||||
| 5086 | Support Infrastructure - OW Installation w/ CWSR | Dollars | 0.07 | $ - 0 | ||||
| 5087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | Dollars | 2.41 | $ - 0 | ||||
| 5088 | Program Coordination | Lot | 1.00 | $ - 0 | ||||
| Yellow | OW CLINs | Total Evaluated Cost Option V | $ - 0 | |||||
| Green | Hourly Rate CLINs | |||||||
| Blue | Support Infrastructure CLINs | |||||||
| Grey | Unevaluated CLINs | |||||||
| Dark Blue | Value to be entered by Offeror |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Option V
&CN00019-09-R-0216
Attachment 20
Summary
| CLIN | Description | Evaluated CLIN Cost | |||||||
| Base Year | Evaluated CLIN Cost | ||||||||
| Option I | Evaluated CLIN Cost | ||||||||
| Option II | Evaluated CLIN Cost | ||||||||
| Option III | Evaluated CLIN Cost | ||||||||
| Option IV | Evaluated CLIN Cost | ||||||||
| Option V | Total Evaluated CLIN Cost | ||||||||
| X001 | Data | ||||||||
| X002 | Government Property | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X003 | PMI Phase I (stand-alone) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X004 | PMI Phase II (stand-alone) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X005 | PMI Phase IIE (stand-alone) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X006 | PMI Phase I (ordered w/ ow install) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X007 | PMI Phase II (ordered w/ ow install) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X008 | PMI Phase IIE (ordered w/ ow install) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X009 | OW PMI (ordered w/ ow refurbishment) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X010 | PMI Phase I (ordered w/ SSI-K) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X011 | PMI Phase II (ordered w/ SSI-K) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X012 | PMI Phase IIE (ordered w/ SSI-K) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X013 | PMI Phase I (ordered w/ Zone 5 wings-on) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X014 | PMI Phase II (ordered w/ Zone 5 wings-on) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X015 | PMI Phase IIE (ordered w/ Zone 5 wings-on) – P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X016 | PMI EP-3 Delta (ordered w/ X003, X004, or X005) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X017 | PMI EP-3 Delta (ordered w/ X006, X007, or X008) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X018 | PMI EP-3 Delta (ordered w/ X009) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X019 | SSI-K - P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X020 | Zone 5 (wings-on) - P3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X021 | Zone 5 Installation and CWSR (w/wings on) - P-3C/NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X022 | Zone 5 and SSI-K - P-3C (except BMUP LSRS and SPA) / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X023 | Zone 5 and SSI-K - BMUP LSRS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X024 | Zone 5 and SSI-K - SPA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X025 | Zone 5 and SSI-K - EP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X026 | OW Refurbishment (planks 1-9) - All T/M/S | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X027 | Outer Wing Installation - P-3C / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X028 | Outer Wing Installation and CWSR - P-3C (except BMUP LSRS and SPA) / NP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X029 | Outer Wing Installation and CWSR - BMUP LSRS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X030 | Outer Wing Installation and CWSR - SPA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X031 | Outer Wing Installation - EP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X032 | Outer Wing Installation and CWSR - EP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X033 | Explosive Suppressant Foam Removal | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X034 | Explosive Suppressant Foam Installation | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X035 | ALD-9 Removal | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X036 | Outer Wing Paint Strip | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X037 | BL 65 Domenut Replacement | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X038 | NDI / Prev Inspection = SSI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X039 | NDI / Prev Inspection = ESSI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X040 | NDI / Prev Inspection = ESSI w/ CWSR | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X041 | NDI / Prev Inspection = SSI-K | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X042 | NDI / Prev Inspection = New Lower Surface | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X043 | NDI / Prev Inspection = New Outer Wing | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X044 | NDI-LH Forward Corner Fittings | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X045 | NDI-RH Forward Corner Fittings | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X046 | NDI-LH Aft Corner Fittings | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X047 | NDI-RH Aft Corner Fittings | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X048 | Tooling | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| X049 | Drop-In Modifications | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X050 | Drop-In Maintenance | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X051 | Sustaining Engineering | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X052 | Travel | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| X053 | Over and Above Labor | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X054 | Material | ||||||||
| X055 | Conditional Inspections | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X056 | RNAV Mode S AFC-719 – P-3C | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X057 | RNAV Mode S AFC-719 Part 2 – EP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X058 | RNAV Mode S AFC-719 Part 3 – SPA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X059 | 5V Lighting AFC-720 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X060 | EFDS AFC-603 Basic, Part 3, and Part 4 – P-3C | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X061 | EFDS AFC-603 Part 5 – EP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X062 | MLR-2020A-1 AFC-686 – P-3C | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X063 | MLR-2020A-1 AFC-686 Part 2 – EP-3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X064 | ARC-210 AFC-693 – P-3C | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X065 | Digital Autopilot AFC-696 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X066 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X067 | ASX-6 (MMIS) AFC-705 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X068 | RNAV Mode S AFC-719 – P-3C Field Team | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X069 | RNAV Mode S AFC-719 Part 3 – SPA Field Team | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X070 | 5V Lighting AFC-720 Field Team | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X071 | Digital Autopilot AFC-696 Field Team | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X072 | ARC-243 HF Radio/ACQ-5 Data Link AFC-738 Field Team | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X073 | ASX-6 (MMIS) AFC-705 Field Team | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X074 | Support Infrastructure - PMI Stand-Alone | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X075 | Support Infrastructure - SSI-K Stand-Alone | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X076 | Support Infrastructure - SSI-K w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X077 | Support Infrastructure - Zone 5 (wings on) Stand-Alone | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X078 | Support Infrastructure - Zone 5 (wings on) w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X079 | Support Infrastructure - Zone 5 (wings on) w/ CWSR | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X080 | Support Infrastructure - Zone 5 (wings on) w/ CWSR w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X081 | Support Infrastructure - SSI-K and Zone 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X082 | Support Infrastructure - SSI-K and Zone w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X083 | Support Infrastructure - OW Refurbishment w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X084 | Support Infrastructure - OW Installation | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X085 | Support Infrastructure - OW Installation w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X086 | Support Infrastructure - OW Installation w/ CWSR | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X087 | Support Infrastructure - OW Installation w/ CWSR w/ PMI | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X088 | Program Coordination | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| X089 | Program Plans | $ - 0 | $ - 0 | ||||||
| Yellow | OW CLINs | Total Evaluated Cost | $ - 0 | ||||||
| Green | Hourly Rate CLINs | ||||||||
| Blue | Support Infrastructure CLINs | ||||||||
| Grey | Unevaluated CLINs |
&C&"Arial,Bold"&12Pricing Worksheet Evaluated Cost Summary
&CN00019-09-R-0216
Attachment 20
Other files
Show 40 more
Latest 50 of 175 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .