This file is a Questions and Responses document for RFP 2016000096 Microwave Replacement, issued by the State of Colorado Office of Information Technology (OIT). The project involves design and build services for a microwave backhaul network replacement across five phases, with Phase 1 anticipated to run from June 2016 through July 2017, though these dates are subject to finalization in the resulting contract. The State requires a complete turnkey solution addressing all project systems, subsystems, components, and options. However, transmission lines and microwave dishes associated with critically loaded towers will be installed by the State, which will purchase this equipment from the Contractor. A mandatory pre-submittal conference was scheduled for January 14, 2016, to distribute confidential appendices and allow OIT staff to discuss the project. Prequalification submittals were due January 26, 2016, and selected teams would advance to Step 2 oral presentations and sealed cost proposals. The project must be complete no later than June 30, 2019, with funding provided over a five-year period and a lump sum design/build bid required for all five phases.
Qualifications and corporate experience will be weighted at 60 percent of the scoring matrix, while cost will comprise 40 percent. The State requires bidders to demonstrate prior design/build contracting services within the last five years for at least two projects each exceeding $10 million in hard costs, with all three most relevant projects valued in excess of $10 million. Equipment and labor warranty is three years after each phase is accepted. The project is funded through Capital Construction Funds. For new tower construction, contractors must use one of the State's pre-qualified tower vendors: EasTex Tower Inc., Rex Industries, Advanced Tower Services, and Hudspeth & Associates Inc. All permits will be obtained by the Contractor, and Davis-Bacon wages do not apply to this project. The State will provide a structural assessment of towers identified as 100 percent or above maximum member stress, and contractors are encouraged to minimize equipment loads on existing towers to achieve compliance with current TIA-222 standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Bond.doc | DOC document | |
| RFP 2016000096 FINAL.docx | DOCX document | |
| Appendix F budget.docx | DOCX document | |
| Appendix D8 Cost Proposal Forms .xlsx | XLSX spreadsheet | |
| LMBond.doc | DOC document | |
| Appendix E Building codes.doc | DOC document | |
| Appendix A1-2.docx | DOCX document | |
| Appendix B2 SC8.1.doc | DOC document | |
| Appendix D1- Non Disclosure Agreement .docx | DOCX document | |
| Appendix D8 1COST PROPOSAL Summary.docx | DOCX document | |
| Appendix D Specifications.docx | DOCX document | |
| RFP 2016000096 REVISED 1-14.docx | DOCX document | |
| Appendix D9 Compliance Matrix.xlsx | XLSX spreadsheet | |
| Appendix C. UI Formdocx.docx | DOCX document | |
| Appendix D8 Pricing Instructions.docx | DOCX document | |
| Appendix B1 Sc 8.0.docx | DOCX document | |
| Authorization to Bid.doc | DOC document | |
| FINAL Round 2 QA.docx | DOCX document | |
| PerfBond.doc | DOC document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Responses
RFP 2016000096
Microwave Replacement
| No |
| Question |
| Response |
| 1 |
| As a turnkey provider of communications services we are able to construct our own towers. Can we be pre-qualified and added to the list in order to self-perform tower construction? |
| No, not at this time |
| 2 |
| The RPF is silent on the use of adaptive modulation. Does the State have an opinion/requirement on the use of adaptive modulation? |
| The State is open to different modulation schemes as part of the proposal response. |
| 3 |
| Are the latency specification given in Appendix D 4.2 of less than 40 ms per hop/path? |
| The entire path not shall not be more that 40 ms. |
| 4 |
| Given the scope of the RFP and the short time frame for initial response will there be another opportunity for questions. |
| Yes and a revised schedule will be provided. |
| 5 |
| Can you advise what the funding source for this project is? |
| Capital Construction Funds. |
| 6 |
| What other procurements are expected to place as part of the PSMB effort? |
| At this time no other procurements are planned. |
| 7 |
| Who was the consultant selected for the Public Safety Broadband Coverage Assessment RFP (#2015000063)? Can you advise the contract date/amount? |
| Signal Analytics and $ 481,000. Contract date: 6/3/2015 However, the Signal Analytics contract is not related in any way to this project. |
| 8 |
| In Section B. Minimum Qualifications, the first bullet states: |
• Provided Design/Build Contracting services within the last five (5) years for at least two (2) projects each in excess of $ 10,000,000 (hard costs), utilizing the expertise present in their current office.
In Section IV. - EVALUATION CRITERIA, Item 4. The PRIOR PROJECT EXPERIENCE/SUCCESS section is requesting that the proposer provide three (3) most relevant projects and provide, at a minimum, the following:
• The project/contract name
• Description of services provided
• Overall design/construction cost of project, as applicable, including initial contract value and change orders including reasons for change orders
• Organizational structure of service delivery under the contract (include the owner’s organization as it interfaced with the respondent’s contract)
• Key assigned in-house staff (name and title)
• Subcontracts (service) used in the performance of the contract
• Schedule history
• Reference(s) for Owner as described in IV.A.3
• Continuing services, if any.
Is it a requirement that the third project identified in Section IV be valued in excess of $10,000,000 (hard cost)?
Yes
| 9 |
| 2. Section II - PREQUALIFICATION SUBMITTALS (STEP I) Bullet A, Item 1 refers to the 2010 RFP. Is this a typo? If not, where can we get a copy of the 2010 RFP to use as a point of reference? |
| The 2010 RFP is for the Pre-qualified Tower Vendors. A copy will be available via email upon request. |
| 10 |
| 3. Bullet A Item - Submittals (Prequalification: Step I) is Due on 1/21/2016. The last paragraph in this section states “Ten (10) hard copies of the Prequalification submittals are due January 26, 2016 and shall be received no later than 2:30PM (MST), |
Are the Submittals (Prequalification: Step I) Due on 1/21/2016 or 1/26/16?
A new schedule will be provided
| 11 |
| Bullet A Item - Anticipated Construction Start/Finish June 2016 – July 2017. Is this anticipated schedule duration for Phase 1? |
| This is the anticipated time frame for the Phase one construction. |
| 12 |
| In Section I. - General Information Section A it states “Project must be complete no later than June 30, 2019.” The last paragraph in this section states “This project is to be funded over a five year period with the intent being that a ring per year can be feasibly planned and constructed. (Indicated that funding for Phase one is available now and that work will proceed with phase one upon award and funding for the next four phases is anticipated annually however, the lump sum design/build bid is for all five phases).” If construction started in June 2016 assuming five phases lasting one year each the project would end in June 2021. Please clarify the desired project end date? |
| This date will be finalized in the resulting RFP and is subject to the date provided in the proposals. |
| 13 |
| We will be receiving the confidential appendices with the intent of addressing any questions during the pre-submittal conference. If there are additional questions regarding this confidential information will we be able to be ask additional questions prior to the Step 2 Oral Presentation and Pricing Proposal? |
| Yes |
| 14 |
| What sort/how long of a warranty and maintenance does the State expect? |
| The equipment and labor to install failed equipment warranty period is for three years after each Phase is accepted. |
| 15 |
| How much of the work is expected to be completed in Phase 1? What is the time frame for that? What percent of the budget is allocated for Phase 1? |
| We are looking to the Contract to propose each phase and the project time line. The percent of budget will be negotiated as part of the project. |
| 16 |
| What kind of a mix will the jury comprise of? How many people will be on the jury? |
| The Jury panel will have a mix of qualified panelists with a professional interest in the project the number will not be disclosed |
| 17 |
| How long will the oral interview be? Who conducts it? How many of us can go? |
| The interviews will be 30-45 minutes long we request that no more than three representatives attend. |
| 18 |
| What is the completion date for the project? The RFP schedule says July 2017 but the Microwave Backhaul Specifications says June 30, 2019. |
| The dates are all estimates and will be finalized in the resulting contract. |
| 19 |
| When is the project start date? The RFP schedule says June 2016 but the Microwave Backhaul Specifications says February 1, 2016. |
| The date is all estimates and will be finalized in the resulting contract. |
| 20 |
| When is the preliminary design due? The RFP schedule says design start is May 2016 and construction start is June 2016. The Microwave Backhaul Specifications says 60 days after contract execution. |
| It is anticipated to be due 60 days after contract execution. |
| 21 |
| Sealed cost proposals will be required only from those teams who are interviewed and are to be submitted as indicated in this RFP. Both qualifications and cost will be considered in the final ranking of teams with qualifications given 60% of the value of the weighted criteria and costs in the sealed Cost Proposal given 40%. |
This statement was pulled from Appendix D Technical Specifications and inserted below,
2.6 Proposal Evaluation
1. Qualifications and corporate experience, 70% of the scoring matrix.
5. c. Cost is 30% of the scoring matrix QUESTION 8: Final ranking discrepancy noted within RFP and Appendix D Technical Spec documents. Which is the correct criteria?
Qualifications and corporate experience, 60% of the scoring matrix. Cost will be 40%
| 22 |
| A. MANDATORY PRE-SUBMMITTAL CONFERENCE |
1. To ensure sufficient information is available to teams preparing submittals, a mandatory pre-submittal conference has been scheduled. The intent of this conference is to distribute the confidential appendices and to have the OIT staff available to discuss the project. Teams preparing submittals must attend and sign-in in order to have their submittals accepted. The pre-submittal conference will be January 14, 2016 2016 from 1:00 - 3:00 pm MST held at:
Q: Will there be another window to submit questions based on review of confidential appendices distributed at pre-submittal meeting or will questions need to be presented to the OIT staff at that time?
Yes
| 23 |
| A. The State requires, a complete turnkey solution addressing all project systems, subsystems, components, and options as stated in this RFP. However, the transmission lines and microwave dishes (antenna network) associated with the critically loaded towers as identified herein will be installed by the State. This equipment shall be purchased from the Contractor by the State and will carry the full 3-year warranty. Proposal options – Requirements described as an “OPTION” or “OPTIONAL” refer to features or equipment which the State may or may not purchase or items whose quantities are not determined yet. CONTRACTORS DO NOT |
HAVE THE OPTION TO RESPOND TO THESE REQUIREMENTS. CONTRACTORS ARE REQUIRED TO RESPOND TO ALL OPTIONAL REQUIREMENTS TO THE GREATEST EXTENT POSSIBLE.
Q: The antenna work mentioned above will be installed by the state on critically loaded towers. How many towers fall into this category?
This will be provided at the pre-bid conference.
It shall be the responsibility of the State to provide a structural assessment of towers identified as 100% or above maximum member stress in Appendix D5. Contractors are encouraged to consider using the smallest equipment possible such that the load on the existing towers can be minimized in an attempt to bring towers that are currently overloaded into compliance with current TIA-222 standards. The State will be responsible for installing all new tower-mounted microwave antenna equipment and transmission lines ordered under this RFP and identified in Appendix D5.
Q: Is the contractor to provide any tower related installations?
Yes except for the critically loaded towers. We will expect the awarded contractor to install equipment at all other identified locations.
| 24 |
| If a new tower is required to be built as part of the project the Contractor shall use one of OIT’s pre-qualified tower vendors for the build. The tower vendors will be required to transfer all existing antennas and transmission lines. Depending on the location, the Forest Service or Bureau of Land Management may require a guyed tower to be replaced by a free standing tower. |
List of Current awarded Tower Vendors;
EasTex Tower Inc. Colorado Springs, CO 719-632-8822 Rex Industries Golden, CO 303-324-4199 Advanced Tower Services, Albuquerque, New Mexico 505-244-3321 Hudspeth & Associates Inc., Rifle CO 970-625-5310 Q: Can the contractor and/or its subcontractor become a qualified tower vendor and be added to this list?
No not at this time.
| 25 |
| Is the state currently working directly with any of these qualified tower vendors on current projects and/or other RFP requests? |
| Yes we currently have three RFP’s in process for tower replacements as part of our controlled maintenance schedule outside of this project. |
| 26 |
| 1. The Contractor shall design, supply and erect all necessary equipment for a fully functional communication tower compliant with all applicable laws, codes and standards. |
Q: Can this only be completed by utilizing one of the qualified tower vendors listed above?
Yes
| 27 |
| Tower Foundations: |
1. The Contractor shall design, supply and construct all necessary components for a fully functional tower foundation/anchor system, compliant with all applicable laws, codes and standards. The Contractor shall supply all equipment necessary to transport and construct the foundation(s)/anchor(s) according to all applicable laws, codes and standards.
Q: Can this only be completed by utilizing one of the qualified tower vendors listed above?
Yes
| 28 |
| Tower Removal: The existing tower shall be disassembled by the Contractor within 14 days of notice of authorization to disassemble the tower by the State |
Q: Can this only be completed by utilizing one of the qualified tower vendors listed above?
Yes
| 29 |
| Cable Bridge: 1. The Contractor shall design, supply and erect all necessary equipment for a fully functional cable bridge and foundation that is compliant with all applicable laws, codes and standards. The Contractor shall supply all equipment necessary to transport and erect the bridge and foundation(s) according to all applicable laws, codes and standards. |
Q: Can this only be completed by utilizing one of the qualified tower vendors listed above?
Yes
| 30 |
| A. The Contractor shall submit to the State all required documentation in electronic (PDF) format and on paper with three copies. All computer generated drawings shall be furnished to the State in an electronic format of the software in which the drawings were created. The State reserves the right to utilize a maximum of 5 business days for the review of each submittal. The Contractor shall submit the following documents for approval by the State prior to beginning procurement, fabrication, installation or construction: |
1. Copies of all permits obtained by the Contractor. Contractor and the State shall coordinate permit process as to avoid duplication.
Q: Does the State perceive minimal permitting on the contractor’s behalf or will the majority of permits be obtained through the Contractor’s efforts?
All permits will be obtained by the contractor.
| 30 |
| . Section 2.3 of Appendix D states that there was a December 3rd 2015 mandatory pre-proposal conference. Is this just a typo or was there an actual conference on that date? |
| This was a typo the only pre-bid meeting will be held on 1/14/2016. |
| 31 |
| Is Appendix E for the Building Codes current? |
| Yes |
| 32 |
| What is the existing capacity of the network in Mbps? |
| Ring capacity 180 Mbps instead of 200 Mbps |
Appendix D, 3.3, FF The capacity on the existing network is variable depending on link or path. Most of the existing microwave components transport circuit switched, TDM data from a minimum of one T1 circuits, to at most, three DS-3 circuits. Please reference RFP 4.3.D for requirements.
| 33 |
| Please clarify the bonding requirement. Isn’t this dictated by statue? And, isn’t the statutory requirement that the bond is sufficient to cover the cost of the project? For example, if the bid comes in at $20 million then the bond would be for $20 million. Further, if each phase will be completed before the next phase is approved and commences, doesn’t the bonding requirement become the amount to cover each phase? |
| The bonds must cover the full contract amount. |
| 34 |
| Will Davis-Bacon wages apply to this project? |
| No |
| 35 |
| Since the Appendices to Appendix D won't be available until the 14th of January, will you allow an additional round of questions beyond January 8th? |
| Yes |
| 36 |
| Appendix B1 and B2 General |
The contract included in the RFP appears to be a form of contract which would cover a major design/build construction project such as a new office building. Although a limited number of towers will be built as part of this project, the main purpose of the RFP appears to be the purchase of a microwave backhaul network replacement, the basic design of which is included in the RFP documents, and not a construction project.
Would you consider using a contract form typically used for information technology systems such as the purchase of the microwave network? Differences between a System contract and a Construction contract include different types of warranty provisions. For example, a system contract typically includes both equipment and software warranties and also typically includes a warranty that the system will operate as designed. System contracts also include software license agreements under which the State would have the license to use the software that operates the system. In addition, rather than provisions discussing the right of occupancy or final inspection, typically a system contract will include System Acceptance provisions that describe system functionality tests and operational burn-in tests as discussed in Sections 7.6, 7.7, and 7.8 of Appendix D.
In addition, the construction contract form appears to have sections that are not applicable to a contract to build a microwave system such as the requirement in Section 2.5.13 for 30%, 60% and 90% construction documents. Certainly these are necessary for a construction project, but to build towers, which is the only “construction” element to this project, one round of drawings is typically sufficient.
No, at this time we anticipate using the standard construction contract attached.
| 37 |
| Appendix D 2.6 This section describes a 70% weight factor applied to qualifications/experience and 30% applied to cost. However, Appendix A2 cites the ratio as 60% qualifications, 40% cost. Just noting this small discrepancy and seeking clarification. |
| 60% qualifications, 40% cost |
| 38 |
| Appendix D 4.1.4 E This section states the contractor shall be responsible for coordination and licensing fees, if applicable. It's common for the contractor to perform frequency searches, assemble and populate information required on FCC applications, and submit completed forms to the customer. Is the State also requiring the contractor pay the FCC application/license fees? This fee is typically paid by the end-user customer. |
| We want the contractor to be responsible for these costs. |
| 39 |
| Appendix D 4.3.F.2 Are these two TDM drops intended for future TDM traffic after existing TDM traffic is migrated to IP? |
| Yes |
| 40 |
| Appendix D 4.3.F.5 Please clarify if both TDM and IP traffic need to support Encryption |
| Per RFP 4.3.F "The microwave radio shall meet the follow minimum requirements...supports Advanced Encryption Standard, Federal Information Processing Standards Publications, AES FIPS PUBS 197, using 256-bit cryptographic key to encrypt and decrypt data in blocks of 128 bits. |
| 41 |
| Appendix D 4.4.C Will Appendix D2 include a DS-1 channel plan, per site (e.g. T1, DS3, OC3), and will the information contain the end points for all existing TDM traffic? |
| No this information will not be provided as part of appendices. This will be provided to the awarded Contactor during contract negotiations. |
| 42 |
| Appendix D 4.7.A |
Is it the State's intent to complete the five phases by June 30, 2019; or do you prefer the vendor to suggest the most realistic schedule based on the design, topology, past experience, etc.?
The State desires that the Contractors propose a schedule as part of the RFP response.
| 43 |
| Appendix D 5.1.A |
This section indicates the State will be responsible for installing all new tower-mounted antenna equipment and transmission lines ordered under this RFP. However, section 1.3.A indicates the State will install transmission lines and microwave dishes (antenna network) associated with critically loaded towers. Will the State install microwave antenna systems on all towers or just the critically loaded towers?
Just the critically loaded towers.
| 44 |
| Appendix D 5.3.3.G |
This section indicates the need for an independent inspection and testing firm. Will the State provide an independent verification entity, as is typical of past projects? Or, is this requirement intended to be performed by the Architect/Engineer and Construction Manager (superintendent) disciplines described in Appendices B1 and B2 RFP 7.4.G.1 states, "The State and the Contractor’s Project Manager shall conduct an inspection of each installation upon substantial completion, and shall document any deficiencies on a single punch list provided to the Contractor for resolution."
| 45 |
| Appendix D 7.2.C.1 Is the State requiring only the Denver Metro ring/spurs to be staged, such that all other phases/rings/spurs are will not be staged? |
| All phases/rings/spurs are required to be staged, whether at the vendor's facility or locally. The Denver area equipment should be physically located close to the required vendor facility (per RFP 7.2.C). Please reference Appendix D 7.2.C.2 as for the intent of D 7.2.C.1. |
| 46 |
| Appendix D 7.2.C.2 7.2.C.9 |
These sections indicate staging will occur in the field (7.2.C.2) while also requiring the Contractor to fund the travel and per diem costs for State personnel to attend a remote staging event. Is it your intent to stage the system in the field, or do you prefer staging to occur at the Contractor's staging facility? If acceptable, we prefer staging to occur at our staging facility.
Per RFP 7.2.C.2 " Staging of the subsystems shall take place in the United States. The intent of the staging tests is to demonstrate to the State that the system is ready for shipment and installation."
| 47 |
| Appendix D 7.5.B Will the State provide the storage facility for the removed equipment? |
| RFP 7.5 outlines specific vendor storage requirements answering this question. |
| 48 |
| Appendix D 7.6 7.7 7.8 Is it safe to assume Final Acceptance Testing, Final Documentation and 30-Day Burn-in events are to occur in conjunction with each phase? |
| Yes, for each phase and then final acceptance upon completion of the entire project. |
| 49 |
| Appendix D 7.9 Is acceptable to execute System Acceptance for each phase, followed by final system acceptance once all phases are complete? |
| Yes. |