This is a Questions and Answers document for the Mobile Tactical Cannon-Tracked (MTC-T) and Resupply Vehicle-Tracked (RSV-T) Capability Solutions Call for Solutions (CFS) under MOSAIC-27-01. The document clarifies key requirements for the Phase I submission regarding system definitions, pricing structure, and evaluation criteria.
The Government defines a "system" as the complete Mobile Tactical Cannon-Tracked Self-Propelled Howitzer (MTC-T SPH) with an accompanying Resupply Vehicle-Tracked (RSV-T), collectively referred to as a "set." Offerors must provide discrete unit Rough Order of Magnitude (ROM) costs for one (1) MTC-T SPH and one (1) RSV-T, as well as ROM costs for three (3) units of each component, with pricing broken out separately to allow Government evaluation of individual component and complete set costs. Additionally, offerors must provide ROM pricing for five increments of three sets (15 systems total). All cost items (i through x) in the submission require ROM pricing, not estimates. Regarding evaluation, all criteria—including Technical, Schedule, Cost, and Data Rights/Intellectual Property (DR/IP)—are evaluated holistically during Phase I without hierarchical prioritization. The complete Phase I submission consists of a 19-page proposal, data rights assertions, representations and certifications, and must adhere to Arial 12-point font for all text, including graphics and tables, with no deviations permitted.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Number Document Page Paragraph Question USG Response
1 Call For Solutions 10 1.e.i. Paragraph states in part: "delivery for three (3) system and/or set within twelve (12) months". Please clarify the difference, if any, between a "set" and a "system." As identified in the Background and Problem Statement, system refers to the Mobile Tactical Cannon-Tracked Self-Propelled Howitzer (MTC-T SPH) artillery system.
The MTC-T set consists of a tracked MTC-T Self-Propelled Howitzer (MTC-T SPH) and an accompanying Resupply Vehicle - Tracked (RSV-T).”
| 2 | Call For Solutions | 10 | 1.e.iii. | Please clarify whether the proposed unit cost is for one (1) MTC-T SPH or for three (3) MTC-T SPH. | For Paragraph 1.e.iii, Offerors shall provide the discrete unit ROM cost for one (1) MTC-T SPH, as well as the ROM cost for three (3) MTC-T SPH units. Please ensure unit pricing for the MTC-T SPH is broken out separately from the RSV-T so the Government can evaluate both individual component costs and complete set costs. |
| 3 | Call For Solutions | 10 | 1.e.v. | Please clarify whether the proposed unit cost is for one (1) RSV-T or for three (3) RSV-T. | For Paragraph 1.e.v, Offerors shall provide the discrete unit ROM cost for one (1) RSV-T, as well as the ROM cost for three (3) RSV-T units (if applicable to the proposed solution). |
| 4 | Call For Solutions | 11 | e. Cost i) | Requires ROM for 5 increments of 3 sets (=15 systems); and ii) a ROM for one each of MTC-T and RSV. Do you want both or is it the 5 sets of three? | USG requests ROMS for increments of three as well as the ROM for one set |
| 5 | Call For Solutions | 11 | e. Cost: | It appears i. is a ROM but the remaining costs ii through x are estimates. Is that an accurate assumption? | USG is requesting ROM pricing for all items (i through x) as part of the Phase I submission. |
| 6 | Call For Solutions | 11 | f. Solution Brief Evaluation | How are DR / IP prioritized among all equal Eval Criteria (Technical/Schedule/Cost/)? | All evaluation criteria stated in the Call for Solutions, including Technical, Schedule, Cost, and Data Rights/Intellectual Property (DR/IP), are evaluated holistically during Phase I. |
| 7 | Call For Solutions | 13 | Submission | Is it the case that the USG wants the 19 page proposal, the data rights assertions (but can hold off on SLA) and Reps n Certs as the whole of the submission? | Yes |
| 8 | Call For Solutions | Can font type and size in graphics or tables included within the solution response deviate from Arial 12? | No |