Appendix E Milestone Pricing Summary.xlsx
XLSX spreadsheet 31 KB Posted
- Attached to
- Mobile Tactical Cannon - Tracked (MTC-T) and Resupply Vehicle – Tracked (RSV-T) Capability Solutions
- Solicitation number
- MOSAIC-27-01
- Issued by
-
Department of the Army
About this file
This is a Milestone Pricing Summary template for the MOSAIC-27-01 Call for Solutions related to the Mobile Tactical Cannon-Tracked (MTC-T) and Resupply Vehicle-Tracked (RSV-T) Capability Solutions. The document, dated September 23, 2026 (Revision 001), is a draft pricing form requiring vendors to populate milestone deliverables, timelines, and associated costs. The form is organized into multiple delivery tables covering prototype system development, cannon/breech assemblies, ammunition storage cells, training systems, and test ammunition across funded base milestones and unfunded milestones (UM).
Base milestones include delivery of Prototype MTC-T SPH Vehicle 1 (90 days after award), Vehicles 2-6 (360 days), Prototype RSV-T system deliveries on identical schedules, Cannon/Breech Assemblies for proof gun stands (120 and 150 days), ammunition storage cells for howitzer projectiles and propellant (300 days each), and training systems (270 days for Quantity 2). Service payment milestones encompass system engineering deliverables including integration master schedules, cyber risk management frameworks, armor suitability reports, and fire control/network integration completion gates, along with supply chain, test and soldier evaluation, training, and prototype production deliverables with timelines ranging from 14 to 420 days. Unfunded milestones include vehicles 7-18 for both MTC-T and RSV-T systems, additional proof gun stand cannon assemblies, additional training systems, multiple increments of test ammunition (HE projectiles, training projectiles, primers, and propelling charges), and optional technical data packages and computer software packages for targeted subsystems. All milestone prices show 0.00% completion with blank cost fields, indicating this is an unfilled template requiring vendor completion of proposed pricing and cost-share arrangements.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cover
| Appendix E |
| Milestone Pricing Summary |
| Call No. MOSAIC-27-01 |
| Revision Number: 001 |
| Date: 23 September 2026 |
DISTRIBUTION STATEMENT A: Approved for Public Release; distribution unlimited.
DRAFT
Instructions
Please see the instructions at the top of each tab in this workbook.
Approved For Public Release
Summary 4. Milestone Schedule
Summary 4. Milestone Schedule
Form Instructions: Fill in cells highlighted yellow
Milestone Number
| (WBS) | Milestone | ||
| Description | Delivery after award (days) | Contract Base / Unfunded Milestone (UM) | SOW |
| Reference | Proposed | ||
| Milestone Price | Percent of |
Total Proposed
| Price | Cost |
| Share ($) | USG |
Share ($)
| Table A1: Prototype MTC-T SPH system delivery | Vehicle 1 | 90 | Base | 0.00% | $ - | ||
| Table A1: Prototype MTC-T SPH system delivery | Vehicles 2-6 | 360 | Base | 0.00% | $ - | ||
| Table A1: Prototype MTC-T SPH system delivery (Unfunded Milestone) | Vehicles 7-9 | TBD | UM | 0.00% | $ - | ||
| Table A1: Prototype MTC-T SPH system delivery (Unfunded Milestone) | Vehicles 10-12 | TBD | UM | 0.00% | $ - | ||
| Table A1: Prototype MTC-T SPH system delivery (Unfunded Milestone) | Vehicles 13-15 | TBD | UM | 0.00% | $ - | ||
| Table A1: Prototype MTC-T SPH system delivery (Unfunded Milestone) | Vehicles 16-18 | TBD | UM | 0.00% | $ - | ||
| Table A2: Prototype RSV-T system delivery | Vehicle 1 | 90 | Base | 0.00% | $ - | ||
| Table A2: Prototype RSV-T system delivery | Vehicles 2-6 | 360 | Base | 0.00% | $ - | ||
| Table A2: Prototype RSV-T system delivery (Unfunded Milestone) | Vehicles 7-9 | TBD | UM | 0.00% | $ - | ||
| Table A2: Prototype RSV-T system delivery (Unfunded Milestone) | Vehicles 10-12 | TBD | UM | 0.00% | $ - | ||
| Table A2: Prototype RSV-T system delivery (Unfunded Milestone) | Vehicles 13-15 | TBD | UM | 0.00% | $ - | ||
| Table A2: Prototype RSV-T system delivery (Unfunded Milestone) | Vehicles 16-18 | TBD | UM | 0.00% | $ - | ||
| Table B: Cannon/Breech Assemblies for Proof Gun Stand (USG PGS) | Qty 1 | 120 | Base | 0.00% | $ - | ||
| Table B: Cannon/Breech Assemblies for Proof Gun Stand (USG PGS) | Qty 1 | 150 | Base | 0.00% | $ - | ||
| Table B: Cannon/Breech Assemblies for Proof Gun Stand (USG PGS) (Unfunded Milestone) | Qty 3 | 300 | UM | 0.00% | $ - | ||
| Table C: Ammunition storage cells for Sequential Environment Testing | Howitzer Projectile | 300 | Base | 0.00% | $ - | ||
| Table C: Ammunition storage cells for Sequential Environment Testing | Howitzer Propellant | 300 | Base | 0.00% | $ - | ||
| Table D: Training System | Qty 2 | 270 | Base | 0.00% | $ - | ||
| Table D: Training System (Unfunded Milestone) | Qty 2 | 420 | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 1 HE Projectiles | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 2 HE Projectiles | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 3 HE Projectiles | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 1 Training Projectiles | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 1 Primers | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 2 Primers | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 3 Primers | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 1 Propelling Charges | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 2 Propelling Charges | TBD | UM | 0.00% | $ - | ||
| Table E: Test Ammunition (Unfunded Milestone) | Increment 3 Propelling Charges | TBD | UM | 0.00% | $ - | ||
| Table F: Service Payment Schedule | Completion of Start of Work Meeting, Deliver Program Integrted Master Schedule (CDRL A019) | 14 | Base | 0.00% | $ - | ||
| Table F: Service Payment Schedule | Ammunition Ballistics Data (CDRL A002) | 60 | Base | 0.00% | $ - | ||
| Table F: Service Payment Schedule | Complete PMR (1 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (2 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (3 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (4 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (5 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (6 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (7 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Complete PMR (8 of 8 available) at Vendor Fill In each | TBD | Base | ||||
| Table F: Service Payment Schedule | Integration & Technical Support | monthly | Base | 0.00% | $ - | ||
| Table F - System Engineering | Delivery of Cyber Risk Management Framework Artifacts (CDRL A031), Final Inspection Record - Template (A035) | 60 | Base | 0.00% | $ - | ||
| Table F - System Engineering | Delivery of System Overview (A001), Indentured Bill of Materials (CDRL A003) | 60 | Base | 0.00% | $ - | ||
| Table F - System Engineering | Delivery of a Systems Engineer Management Plan (CDRL A052) & Model Based Systems Engineering Development Plan (CDRL A053) | 60 | Base | ||||
| Table F - System Engineering | Armor Suitability Report (CDRL A026) | 120 | Base | 0.00% | $ - | ||
| Table F - Fire Control and Network Integration | (a) Completion of Tactical Radio Integration | Prior to delivery of system 2 | Base | 0.00% | $ - | ||
| Table F - Fire Control and Network Integration | (b) Completion of Position/Navigation/Timing Device | Prior to delivery of system 2 | Base | 0.00% | $ - | ||
| Table F - Fire Control and Network Integration | (c ) Fire Mission Data Processing integration | Prior to delivery of system 2 | Base | 0.00% | $ - | ||
| Table F - Fire Control and Network Integration | (d) Completion of Command and Control Applications Integration | Prior to delivery of system 2 | Base | 0.00% | $ - | ||
| Table F - Fire Control and Network Integration | (e )Development of Vehicle Fire Control Emulator | Prior to delivery of system 2 | Base | 0.00% | $ - | ||
| Table F - Fire Control and Network Integration | (f) Submit Graphical Human Machine Interface | Prior to initial delivery | Base | 0.00% | $ - | ||
| Table F - Supply Chain | Delivery of EDFP (CDRL A029) & OMIT Data (CDRL A009) | IAW CDRL Delivery Schedule | 60 | 0.00% | $ - | ||
| Table F - Supply Chain | Delivery of Availability Assessment (CDRL A032) & Supply Chain Market Checklist (CDRL A034) | IAW CDRL Delivery Schedule | 90 | 0.00% | $ - | ||
| Table F - Test & Soldier Evaluation | Deliver Critical Crew Drill Report (CDRL A012), Health Hazard Assessment Report (CDRL A013), Safety Assessment Report (CDRL A014) | IAW CDRL Delivery Schedule | 60 | 0.00% | $ - | ||
| Table F - Test & Soldier Evaluation | US Ammunition Interfaces Report (CDRL A028) | IAW CDRL Delivery Schedule | 60 | 0.00% | $ - | ||
| Table F - Test & Soldier Evaluation | Deliver System Safety Hazard Analysis Report (CDRL A015), Failure Mode Effects and Critical Analysis (CDRL A023), Transportability Report (CDRL A024) | IAW CDRL Delivery Schedule | 90 | 0.00% | $ - | ||
| Table F - Test & Soldier Evaluation | Petroleum Oils and Lubricant List (CDRL A025) | IAW CDRL Delivery Schedule | 90 | 0.00% | $ - | ||
| Table F - Test & Soldier Evaluation | Test Support Services (est. 18 Months) | Monthly | Base | 0.00% | $ - | ||
| Table F - Test & Soldier Evaluation | MTC-T Soldier Evaluation Support (est. 12 Months) | Monthly | Base | 0.00% | $ - | ||
| Table F - Training | Complete 1st Operation and Crew Level training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Complete 2nd Operation and Crew Level training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Complete 3rd Operation and Crew Level training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Complete 4th Operation and Crew Level Training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Completion of 1st Cannon/Breech/Muzzle Brake Assembly training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Completion of 2nd Cannon/Breech/Muzzle Brake Assembly training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Completion of 1st Operator and Field Maintainer training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Completion of 2nd Operator and Field Maintainer training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Completion of 3rd Operator and Field Maintainer training | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Complete 1st vehicle familiarization training event | TBD | Base | 0.00% | $ - | ||
| Table F - Training | Complete 2nd vehicle familiarization training event | TBD | Base | 0.00% | $ - | ||
| Table F - Prototype Production | Deliver Production Capability Plan (CDRL A018) | 60 | Base | 0.00% | $ - | ||
| Table F - CSDR | Deliver Quantity Date Report (A049) and Resource Distribution Table (RDT) (A050) | TBD | Base | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 1: Technical Data -Modular System Interfaces | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 2: Technical Data - Lightweight CAD Model | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (a) Fire Control System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (b) Cannon Assembly | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (c) Human-Machine Interfaces | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (d) Electrical Power Generation, Storage and Distribution System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (e ) Ammunition Handling System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (f) Cannon Mount and Reoil System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (g) Cannon Pointing System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (h) Wheel and Tire Assembly | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (i) Armor | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (j) Integrated Fire Suppression System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 3: Technical Data - Targeted Subsystems - (k) Climate Control Systems | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 4: Computer Software Package - Targeted Subsystems - (a) Fire Control System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 4: Computer Software Package - Targeted Subsystems - (b) Human-Machine Interfaces | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 4: Computer Software Package - Targeted Subsystems - (c) Electrical Power Generation, Storage, and Distribution System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 4: Computer Software Package - Targeted Subsystems - (d) Ammunition Handling System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 4: Computer Software Package - Targeted Subsystems - (e) Cannon Pointing System | TBD | UM | 0.00% | $ - | ||
| Table F - Options (Unfunded Milestones) | Option 4: Computer Software Package - Targeted Subsystems - (f) Climate Control Systems | TBD | UM | 0.00% | $ - | ||
| Total Proposed Price | $ - | 0.00% | $ - | $ - | |||
| check |