These are the minutes from a mandatory pre-bid walkthrough meeting for the Port of Hood River Parking Lots 2025 project, held on May 23, 2025, at 9:00 AM, hosted by HRK Engineering and Field Services. The meeting involved representatives from multiple construction and excavation companies who gathered to discuss the project scope for two parking lot sites: a Portway parking lot and an Anchor Way parking lot. Key details included a review of the bidding process, site constraints, and specific project requirements such as relocating an existing chain-link fence, addressing erosion and sediment control near the Columbia River, removing existing trees along Anchor Way, installing two new ADA ramps, and implementing a stormwater detention system. The preferred staging area was identified as west of the Wastewater Treatment Plant, pending Port of Hood River confirmation.

Bidding information specified that all questions must be submitted via an addendum form, and a 10% Bid Bond is required. The meeting minutes indicate that contractors will receive additional documentation, including a Bid Bond template. While specific budget details were not explicitly stated in the minutes, the project involves significant infrastructure work requiring careful coordination. Contractors were advised of environmental considerations, particularly regarding erosion control due to the site's proximity to the Columbia River. The meeting concluded at 10:30 AM, with Alexandria Eck from IBC Construction agreeing to submit further questions via email for formal response, and Kevin Greenwood from the Port of Hood River providing closing remarks.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

489 N. 8TH STREET, SUITE 201

HOOD RIVER, OREGON 97031 ■ 541.386.6480

PRE-BID WALKTHROUGH MEETING HRK ENGINEERING AND FIELD SERVICES

M I N UT E S

PROJECT NAME: Port of Hood River Parking Lots 2025

MEETING TITLE: Pre-Bid Walkthrough

DATE: May 23, 2025 – 9:00 AM

LOCATION: North 8th Street / Portway Avenue

PREPARED BY: Carlos Garrido – HRK Engineering

ATTENDEES:

• Kevin Greenwood – Port of Hood River

• Carlos Garrido - HRK Engineering

• Alex Pedroza – HRK Engineering

• Alexandria Eck – IBC Construction

• Sean Baker – IBC Construction

• Jared Oddysey – Odyssey Contracting

• Yani Vaivoda – Crestline Construction

• Josh Ellingson - Granite

• Colton Nevinger - Granite

• Diana Austin – James Dean Construction

• Jesse Jones – Jones Concrete and Excavation

• Tanner Wingfield – NB Excavation

• Aaron Kreps – Artistic Excavation

• Wyatt Webber – Ajax Northwest

• Alyssa Becker – NW Construction

• Josh Sorenson – Beam Excavating

WELCOME AND INTRODUCTION:

• Kevin Greenwood welcomed the attendees and thanked them for participating in the mandatory pre-bid meeting.

• All attendees introduced themselves and signed the attendance sheet

489 N. 8TH STREET, SUITE 201

HOOD RIVER, OREGON 97031 ■ 541.386.6480

PRE-BID WALKTHROUGH MEETING HRK ENGINEERING AND FIELD SERVICES

PROJECT OVERVIEW:

• Carlos Garrido, Project Manager at HRK Engineering, presented the project scope for the proposed parking lots.

• A discussion was held regarding the project schedule and site constraints.

• Proposed staging areas were discussed. The preferred location is west of the

Wastewater Treatment Plant, to be confirmed by the Port of Hood River.

• Some contractors mentioned they might use portions of the project site for staging purposes.

BIDDING INFORMATION:

• The bidding process was reviewed.

• All bidder questions must be submitted using an addendum form provided by the Port of Hood River. This template will be distributed with the meeting minutes.

• A Bid Bond is required: 10% of the project cost. A Bid Bond template will be sent by HRK Engineering with the meeting minutes.

SITE WALKTHROUGH:

The group walked the proposed Portway parking lot site.

• It was noted that the existing chain-link fence on the west side must be relocated 5 feet west from the edge of pavement.

• Emphasis was placed on erosion and sediment control due to proximity to the

Columbia River.

The group then walked to the proposed Anchor Way parking lot.

• Alex Pedroza (HRK Engineering) explained the stormwater detention system and its discharge location.

• Two new ADA ramps will be required.

• All existing trees along Anchor Way are to be removed.

QUESTIONS AND CLARIFICATIONS:

• Alexandria Eck (IBC Construction) posed several questions, and it was agreed she would submit them via email for a formal response.

CLOSING REMARKS:

• Kevin Greenwood closed the meeting by thanking all attendees for their participation.

• The meeting adjourned at 10:30 AM