This performance specification outlines requirements for a Rough Terrain Container Handler (RTCH) service life extension program. The Marine Corps requires refurbishing approximately 117 RTCH vehicles to restore them to like-new condition and improve functionality. Key modifications include developing a new electrical control unit with equivalent functionality to the legacy system, installing rear-view camera and display systems, and upgrading the operator cab interior. The RTCH must retain the original operational capabilities and comply with transportation regulations. The service life extension efforts must not degrade performance as outlined in the purchase description documents. The specification defines verification methods and contractor certification requirements to ensure compliance with all technical and functionality standards.
Attachment 2_Performance Specification
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE SPECIFICATION
FOR ROUGH TERRAIN CONTAINER HANDLER
Attachment 2, Dated 1/31/2019
Version 1.0
1. SCOPE
This specification defines the performance requirements that shall be maintained of the Rough Terrain Container Handler (RTCH) in its current configuration and additional requirements that shall be obtained upon the completion of the Service Life Extension Program (SLEP) efforts. The RTCH is a container handler with a 20-foot to 40 foot expandable top handler capable of handling International Organization for Standardization (ISO) family of 8 (eight) foot wide containers loaded to a gross weight of 53,000 pounds while operating on beaches and unimproved surfaces.
1.1 Refurbishment
The RTCH SLEP intends to refurbish and improve the RTCH to a like new condition through modification; inspection and component repair/replacement, followed by inspection and validation. The RTCH shall be returned back to the original condition and maintain performance requirements of Section 3.
1.2 Improvements/Modifications (3):
The RTCH shall incorporate the following improvements and modifications to meet the performance requirements of Paragraph 3.
a) Develop an Electrical Control Unit (ECU) that will maintain the same functionality as the legacy system.
b) Install a Camera/Visual Imaging System.
c) Install an updated operator’s cab interior.
2. APPLICABLE DOCUMENTS
2.1 General.
The documents listed in this section are specified in Sections 3, 4, and 5 of this Performance Specification. This section does not include documents that are referenced in other sections of this Performance Specification, recommended for additional information or examples. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements of documents cited in Sections 3, 4, and 5 of this Performance Specification, whether or not they are listed.
2.2 Government Documents.
The following specifications, standards, and handbooks form a part of this document as specified herein. These documents may be listed in the Department of Defense Index of Specification and Standards (DoDISS) which indicates the latest version. If the revision is not specified, documents shall be the issue current on the date of the solicitation.
Department of Defense Specifications
| MIL-PRF-2104 |
| - |
| Lubricating Oil, Internal Combustion Engine, Combat/Tactical service |
| MIL-PRF-2105 |
| - |
| Lubricating Oil, Gear, Multipurpose |
| MIL-PRF-46167 |
| - |
| Lubricating Oil, Internal Combustion Engine, Arctic |
| MIL-B-46176 |
| - |
| Brake Fluid, Silicone, Automotive, All Weather, Operational and Preservative, Metric |
| MIL-C-53072 |
| - |
| Chemical Agent Resistant Coating (CARC) System Application Procedures and Quality Control |
| NATO F-34 |
| - |
| Turbine Fuel, Aviation, Kerosene Type, JP-8 |
| STANAG 4074 |
| - |
| Auxiliary Power Unit Connections for Starting Tactical Land Vehicles, Type I |
Federal Standards
| RR-G-1602 |
| - |
| Grating, Metal, Other than Bar Type (Floor, Except for Naval Vessels) |
Commercial Item Descriptions
A-A-50271
| - |
| Plate, Identification |
| A-A-52550 |
| - |
| Pintle Assembly, Towing, Manual Release, 18,000, 40,000 and 100,000 lbs. Capacity |
Department of Defense Standards
| MIL-STD-209 |
| - |
| Lifting and Tiedown Provisions |
| MIL-STD-810 |
| - |
| Environmental Engineering Considerations and Laboratory Tests |
| MIL-STD-1366 |
| - |
| Transportability Criteria |
| MS51318 |
| - |
| Headlight, Blackout, 24 Volt Waterproof |
| MS52125 |
| - |
| Composite Light, Tail Stop, Turn, and Marker |
| MS52126 |
| - |
| Composite Light, Front, Turn, Park and Marker |
| MS500048 |
| - |
| Towbar, Motor Vehicle: Light, Medium and Heavy Duty (For Vehicles 2-1/2 to 50 Tons & Heavier) |
(Unless otherwise indicated, copies of the above specifications, standards, and handbooks are available from the Standardization Documents Order Desk, 700 Robbins Avenue, Building 4D, Philadelphia, PA 19111-5094).
2.2.1 Other Government documents, drawings and publications. The following other Government documents, drawings and publications form part of this document to the extent specified herein. Unless otherwise specified, the issues are those cited in the solicitation.
National Stock Number (NSN)
| 1005-00-073-9421 |
| - |
| Rifle, 5.56 Millimeter |
| 1005-01-303-7493 |
| - |
| Rifle, 5.56 Millimeter |
| 5340-00-158-3805 |
| - |
| Padlock |
| 9905-00-565-6267 |
| - |
| Sign Kit, Vehicle Classification |
(Application for copies of NSN should be obtained from the Government.)
2.3 Non-Government publications. The following document(s) form part of this document to the extent specified herein. Unless otherwise specified, the issues of the documents which are DoD adopted are those listed in the issue of the DODISS cited in the solicitation. Unless otherwise specified, the issues of the documents not listed in the DODISS are the issues of the documents cited in the solicitation (see 6.2).
International Organization for Standardization (ISO)
| ISO 668 |
| - |
| Series 1 Freight Containers – Classification, Dimensions and Ratings |
| ISO 1161 |
| - |
| Series 1 Freight Containers – Corner and Intermediate Fittings - Specifications |
| ISO 2330 |
| - |
| Fork-lift trucks – Fork arms – Technical characteristics and testing |
| ISO 2631 |
| - |
| Evaluation of Human Exposure to Whole-Body Vibration |
| ISO 3287 |
| - |
| Symbols for Operator Controls and Other Displays |
| ISO 5010 |
| - |
| Rubber-tyred Machines |
| ISO 5349 |
| - |
| Measurement and Evaluation of Human Exposure to Hand-Transmitted Vibration |
| ISO 6393 |
| - |
| Earth-Moving Machinery – Determination of Sound Power Level |
| ISO 6394 |
| - |
| Earth-Moving Machinery – Determination of Emission Sound Pressure Level at Operator’s Position |
| ISO 6682 |
| - |
| Zones of Comfort and Reach for Controls |
| ISO 9249 |
| - |
| Engine Test Code –Net Power |
| ISO/DIS 13564 |
| - |
| Test Methods for Verification of Visibility |
(Application for copies should be addressed to the American National Standards Institute, Inc., 1430 Broadway, New York, NY 10018)
Society of Automotive Engineers (SAE) Documents
| 98 |
| - |
| Personnel Protection for General Purpose Industrial Machines |
| 115 |
| - |
| Safety Signs |
| 153 |
| - |
| Operator Precautions |
| 154 |
| - |
| Operator Space Envelope Dimensions for Off-Road Machines |
| 169 |
| - |
| Design Guidelines for Air Conditioning Systems for Off-Road Operator Enclosures |
| 180 |
| - |
| Electrical Charging Systems for Off Highway Work Machines |
| 185 |
| - |
| Access Systems for Off-Road Machines |
| 198 |
| - |
| Windshield Wiper Systems – Trucks, Buses and Multipurpose Vehicles |
| 209 |
| - |
| Instrument Face Design and Location for Construction and Industrial Equipment |
| 231 |
| - |
| Minimum Performance Criteria for Falling Object Protective Structure (FOPS) |
| - |
| Operator Restraint System for Off Road Work Machines |
| 514 |
| - |
| Hydraulic Tube Fittings |
| - |
| Hydraulic Hose Fittings |
| 517 |
| - |
| Hydraulic Hose |
| 518 |
| - |
| Hydraulic Flanged Tube, and Hose Connections, Four-Bolt Split Flange Type. |
| 524 |
| - |
| Seamless Low-Carbon Steel Tubing Annealed for Bending and Flaring |
| 525 |
| - |
| Welded and Cold Drawn Low-Carbon Steel Tubing Annealed for Bending and Flaring |
| 534 |
| - |
| Lubrication Fittings |
| 553 |
| - |
| Circuit Breakers |
| 689 |
| - |
| Curbstone Clearance, Approach, Departure, and Ramp Breakover Angles- Passenger Car and Light Truck |
| 695 |
| - |
| Turning Ability and Off Tracking-Motor Vehicles |
| 744 |
| - |
| Hydraulic Pump and Motor Mounting and Drive Dimensions |
| 753 |
| - |
| Maintenance Interval Chart |
| 821 |
| - |
| Electrical Wiring Systems for Construction, Agricultural and Off-Road Machines |
| 833 |
| - |
| Human Physical Dimensions |
| 898 |
| - |
| Control Locations for Off-Road Work Machines (ISO 6682) |
| 899 |
| - |
| Operator’s Seat Dimensions for Off-Road Self-Propelled Work Machines |
| 925 |
| - |
| Minimum Service Access Dimensions for Off-Road Machines (ISO 2860) |
| 942 |
| - |
| Passenger Car Windshield Washer Systems |
| - |
| Alarm – Backup – Electric Laboratory Performance Testing |
| 1029 |
| - |
| Lighting and Marking of Construction, Earthmoving Machinery |
| - |
| Performance Criteria for Rollover Protective Structure for Construction, Earthmoving, Forestry and Mining Machinery |
| - |
| Motor Vehicle Dimensions |
| 1127 |
| - |
| Low Voltage Battery Cable |
| 1165 |
| - |
| Reporting Cleanliness Levels of Hydraulic Fluids |
| 1176 |
| - |
| External Leakage Classifications for Hydraulic Systems |
| 1292 |
| - |
| Automobile and Motor Coach Wiring |
| 1298 |
| - |
| Hydraulic Couplings – Diagnostic Port Size and Locations |
| 1308 |
| - |
| Fan Guard for off-Road Machines |
| 1349 |
| - |
| Engine Power Test Code-Spark Ignition and Compression Ignition-Net Power Rating |
| 1362 |
| - |
| Graphical Symbols for Operator Controls and Displays on Off-road Self-Propelled Work Machines |
| 1384 |
| - |
| Vibration Performance Evaluation of Operator Seats |
| 1385 |
| - |
| Classification of Earthmoving Machines for Vibration Tests of Operator Seats |
| 1446 |
| - |
| On-Machine Alarm Test and Evaluation Procedure for Construction and General Purpose Industrial Machinery |
| 1453 |
| - |
| Specifications for O-Ring Face Seal Connectors |
| 1473 |
| - |
| Brake Performance – Rubber Tired Earthmoving Machines |
| 1493 |
| - |
| Guarding of Starter System Energization |
| 1502 |
| - |
| Hydraulic Couplings - Diagnostic |
| 1503 |
| - |
| Performance Test for Air-Conditioned, Heated and Ventilated Off-Road Self-Propelled Work Machines |
| 1511 |
| - |
| Steering for Off-Road, Rubber-Tired Machines |
| 1535 |
| - |
| Performance Test for Windshield Defrosting Systems for Off-Road Self-Propelled Work Machines |
| 1625 |
| - |
| Heavy-Duty Circuit Breakers |
| 1708 |
| - |
| Serial Data Communications Between Microcomputer Systems in Heavy-Duty Vehicle Applications |
| 1814 |
| - |
| Operator Controls – Off-Road Machines |
| 1939 |
| - |
| Recommended Practice for Serial Control and Communications Vehicle Network (with applicable Layers) |
| 1941 |
| - |
| Coolant Concentrate (Low Silicate, Ethylene Glycol Type Requiring an Initial Charge of Supplemental Coolant Additive) for Heavy-Duty Engines |
(Application for copies should be addressed to the Society of Automotive Engineers, 400 Commonwealth Drive, Warrendale, PA 15096)
American National Standards Institute (ANSI)
| Z26.1 |
| - |
| Safety Glazing Materials for Glazing Motor Vehicles and Motor Vehicle Equipment Operating on land Highways |
| Z535.4 |
| - |
| Product Safety Signs and Labels |
| Z535.5 |
| - |
| Safety Tags and Barricade Tape (for Temporary Hazards) |
(Application for copies should be addressed to the American National Standards Institute, Inc., 1430 Broadway, New York, NY 10018)
National Fluid Power Association (NFPA)
| T3.20.2 |
| - |
| Hydraulic Fluid Power – Quick Action Coupling – Test Methods |
(Application for copies should be addressed to the National Fluid Power Association, 3333 N Mayfair Rd, Suite 311, Milwaukee, WI 53222
American Society of Mechanical Engineers (ASME)
B56.6
| - |
| Safety Standard for Rough Terrain Forklift Trucks |
| B56.11.3 |
| - |
| Load Handling Symbols |
(Application for copies should be addressed to the American Society of Mechanical Engineers, 345 East 47th Street, New York, NY 10017)
American Society for Testing and Materials (ASTM)
| A123 |
| - |
| Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products |
| B633 |
| - |
| Electrodeposited Coatings of Zinc on Iron and Steel |
| D522 |
| - |
| Mandrel Bend Test of Attached Organic Coatings |
G21
| - |
| Determining Resistance of Synthetic Polymeric Materials to Fungi |
(Application for copies should be addressed to the American Society for Testing Materials, 1916 Race Street, Philadelphia, PA 19103)
American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE)
| ASHRAE 34 |
| - |
| Number Designation and Safety Classification of Refrigerants |
(Application for copies should be addressed to the ASHRAE Customer Service, 1791 Tullie Circle, NE, Atlanta, GA 30329)
(Non-Government standards and other publications are normally available from the organizations that prepare and distribute the documents. These documents may also be available in or through libraries or other information services.)
Order of precedence. In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.
3. REQUIREMENTS
3.1 Operational Requirements.
The Service Life Extension Program efforts shall not degrade the operational performance of the legacy RTCH. The RTCH shall remain the manufacturer's standard commercial product meeting all applicable U.S. Department of Transportation (DOT), Environmental Protection Agency (EPA) requirements for highway travel and be capable of traveling on rough terrain. The RTCH shall still follow normal industry practices for container handlers. The RTCH shall still conform to all standards listed in Section 2 of this Performance Specification, and the requirement and purchase description documents listed below:
20 Jan 1998
Rough Terrain Container Handler (RTCH) Family Operational Requirements Document (ORD)
25 Sep 2003
Proposed Operational and Organizational (O&O) Concept for the Rough Terrain Container Handler (RTCH)
16 Sep 2008
Purchase Description for Container Handler; Rough Terrain; 53,000 Pound Capacity; at 48 Inch Load Center
3.2 Electrical Control Module/Electrical Control Unit (ECM/ECU) The RTCH SLEP shall provide a ECM/ECU system capable of controlling the operation of the RTCH as not to degrade the performance of the legacy system as determined by the Purchase Description, dated 16 Sep 2008.
3.2.1 The ECM/ECU replacement shall provide, at minimum, the same functionality as the legacy ECU/ECM.
3.2.2 The ECM/ECU replacement shall have a service life of not less than 10 years.
3.2.3 The ECM/ECU replacement shall provide engine and transmission control that automatically engages park brake when shifting into park and prevent accidental reverse shift while in forward motion.
3.2.4 The ECM/ECU replacement shall withstand vibrations that normally occur in the RTCH.
3.3 Camera/Video Imaging System
The RTCH SLEP shall be equipped with a Camera/Video Imaging System (C/VIS) that is operable in day and night conditions. The C/VIS will be used in the operator’s work position only for purposes of improving vehicle and corresponding environmental visibility when the RTCH is driven in reverse.
3.3.1 The Field of View shall be 110 to 120 degrees to provide adequate coverage of the defined scene.
3.3.2 The camera shall be color, provide at minimum a standard definition (480p resolution) image, and identify an obstruction at a minimum of 25 ft away in all lighting conditions.
3.3.3 The cameras and their mounting shall be rugged. The cameras, cables, and connectors shall be weatherproof or installed in weatherproof housing with transparent aperture to protect camera lenses, and positioned to avoid collection of dust, snow, ice, and other debris. The housing shall be easy to clean by the operator and maintenance personnel. The camera shall be positioned to avoid contact outside the original envelope of the RTCH.
3.3.4 The C/VIS shall be designed to withstand vibrations that normally occur in the RTCH.
3.3.5 The monitor shall provide a mirror (or reverse) real-time or near real-time visual image of the scene captured by the camera.
3.3.6 The monitor will not replace a mirror. It will supplement the mirror and should provide a comprehensive view of the desired scene with minimum distortion.
3.3.7 The monitor shall not encroach on the direct forward or side scenes of the operator’s work position. The monitor shall have a screen size of at least 7” diagonally.
3.4 Operator’s Cab
The RTCH SLEP operator’s cab interior upgrades shall still meet the Ownership and Support Requirements in Paragraph 3.6 of the Purchase Description, dated 16 Sep 2008.
3.5 Exterior Panels
Exterior panels shall be free of imperfections. Dents shall not be larger than 3” x 3” area. There shall be no holes or cracks present in the panels.
4. VERIFICATION.
4.1 General
The RTCH SLEP compliance with the requirements listed in Section 3 shall be verified using the methods established in Section 4. Refer to Table 1 for a summary of the verification method.
4.2 Methods of Verification
This performance specification will require verification if the SLEP efforts requires more than a corrective or preventative maintenance activity that alters the configuration of the legacy RTCH. The manufacturer, prior to shipment of the RTCH, shall perform quality assurance inspections and provide appropriate certifications of compliance with the specification. Compliance with the requirements listed in Section 3 shall be verified using one of the methods listed below.
4.2.1 Analysis (A). Analyses shall be conducted by the Contractor as specified herein or the Government utilizing established technical or mathematical models or simulations, algorithms, charts, graphs, circuit diagrams, or other scientific principals and procedures.
4.2.2 Demonstration (D). Demonstrations shall be conducted by the Contractor as specified herein; or the Government at a Government-designated test agency involving the actual operation of the system to provide evidence that the required functions were accomplished under specific scenarios. The system may be instrumented and performance monitored.
4.2.2.1 Paragraphs 3.2.3, 3.2.4, and 3.2.5 will be assessed by the Government to evaluate effectiveness of the updates made to the ECM/ECU replacement functionality. User survey feedback during the User Evaluation will also be reviewed and assessed.
4.2.2.2 Paragraph 3.3 C/VIS will be assessed by the Government to evaluate effectiveness of the field of view and display. User survey feedback during the User Evaluation will also be reviewed and assessed.
4.2.2.3 Paragraph 3.4 Operators Cab will be assessed by the Government to evaluate effectiveness of the updates made to the cab and instrument panel. User survey feedback during the Equipment User Assessment will also be reviewed and assessed.
4.2.3 Inspection (I). Inspections shall be conducted by the Contractor as specified herein; or by the Government at a Government-designated test agency or by a Quality Assurance Representative (QAR) at the Contractor's facility utilizing sight, hearing, smell, or touch; simple physical manipulation; and mechanical and electrical gauging and measurement.
4.2.3.1 Paragraph 3.5 Exterior Panels will be inspected by the Government to verify the RTCH panels.
4.2.4 Test (T). Tests shall be conducted by the Contractor as specified herein; or by the Government at a Government-designated test agency applying scientific principles and procedures to determine the properties or functional capabilities of the system.
4.3 Responsibility for compliance
The absence of any verification method within this performance specification shall not relieve the Contractor of the responsibility for acceptance and compliance. Unless otherwise specified within the contract or performance specification, the Contractor is responsible for the execution of all inspections and certifications as stated in this performance specification. The Contractor is responsible for ensuring that components and materials are manufactured, inspected, and tested in accordance with referenced specifications and standards, as applicable. Failure to comply with any of the requirements shall be cause for rejection.
4.4 Conformance inspections/tests
A RTCH that has met all inspections, test, and certification requirements at the factory, shall be shipped to a Government site. The Government reserves the right to validate requirement conformance through independent analyses, inspections and/or testing. RTCH deficiencies found as a result of testing/inspection shall be a cause for rejection until the Contractor has provided evidence that corrective action has been taken to eliminate the deficiency. The Contractor, at no additional cost to the Government, shall correct such deficiencies on all RTCHs.
4.5 Contractor Certifications
The Contractor shall provide independent certification that the RTCH complies with all specific operating, operating environment, interface, ownership, and support requirements stated within this performance specification.
4.5.1 Paragraph 3.1 Operational Requirements will require Contractor certification verifying the RTCH functionality, as a result of the modifications, has not been degraded from the legacy system performance standards.
4.5.2 Paragraph 3.2 Engine Control Module/Engine Control Unit will be require Contractor certification verifying the RTCH functionality has not been degraded from the legacy system performance standards.
Table 1 Tests and Inspection Schedule
5 PACKAGING
5.1 The packaging requirements shall be as specified in the contract.
6. NOTES
6.1 Intended Use. The RTCH will facilitate Marine Air Ground Task Forces (MAGTF) operations requiring the capability to load, unload, and warehouse ISO containerized cargo and equipment from shipping, aircraft, and vehicles. The RTCH shall be capable of operating in all climates and capable of conducting beach, terminal, and MAGTF rear area operations. The RTCH will have the capability to operate effectively on both improved and unimproved surfaces with the rated load. The rated load shall be ISO 668 and ISO 1161 designated 1A, 1AA, 1AAA, 1AX, 1C, 1CC and 1CX containers with heights ranging from 4’3” to 9’6”, each loaded to a maximum gross weight of 53,000 pounds. Nominal load center shall be at the center of the container for the lateral and horizontal load centers with the vertical load center between 20 to 30 inches high as measured from the container floor. The RTCH shall meet the following performance requirements:
The RTCH shall withstand the usage encountered in military operations without damage, permanent deformation or failure of components. Military operations include handling and stacking of containers at the rated load, and the loading and unloading of containers from flatbed trailers and random rail cars (double stacked deep well and Container on Flatcar (COFC), first rail). Operations shall be on prepared surfaces and over rough terrain, including unprepared, un-stabilized surfaces such as beaches, snow, mud and cross country, where high flotation, high stability and increased traction and torque are needed.
6.2 Definitions.
Failure. A failure is the malfunction of any single component that will prevent the system from performing as specified in this document.
Government. Any reference to Government applies to the United States Government only.
Performance Objective. The performance objective value is that desired by the Government. The objective value represents an operationally meaningful increment of performance value.
Performance Threshold. The performance threshold value is the minimum acceptable value required by the Government.
“Provisions For”. “Provisions for” includes “SPACE PROVISION”, “WEIGHT PROVISION” and “POWER PROVISION”; and means that complete installation provisions, including all necessary supports brackets, wiring, tubing, connectors, interconnecting cables, fittings, etc. will be provided for securing the item or equipment in place, ready for operation, without further alterations or additional fabrication of parts. Associated fastenings such as nuts and bolts for the item or equipment are not included. The item or equipment, including its provisions, will be included in the weight empty, unless specifically stated to be mission load or special equipment.
Use of Should, May, Shall, and Will. “Should” and “May” are used whenever it is necessary to express non-mandatory but desirable provisions. “Shall” and “Will” are used whenever it is necessary to express mandatory provisions.
Analysis. Analysis is a study of data and is used to verify that an item or function meets specified requirements, or portions thereof. Analysis data may contain derived analytical data from mathematical expressions, and/or technical evaluation of existing data from related tests, observation or accepted source documents.
Demonstration. Demonstration is a variation of test used to verify performance without the use of elaborate equipment. Operation of a unit in or near its use-environment would be defined as a “demonstration” rather than a “test.” Demonstration involves operation, movement (including necessary adjustment) of the item in performing its design functions, under a specific set of conditions without recording of quantitative data. The item may be instrumented and qualitative performance may be monitored, but check sheets are used rather than the recording of performance data. Verification by demonstration may also be done by analysis data recorded during testing of the next higher assembly to prove that an item or function meets the specified requirements.
Inspection. Inspection is used to verify that an item or function meets its specified requirements or is suitable to perform its functions by visual inspection of engineering documentation and equipment for workmanship, assembly and fit, mechanical safety, marking, materials, parts, finish/surface treatments, etc. Inspection may also invoke verification of content and completeness. Inspection is non-destructive and consists of visual inspections or simple tests or measurements without the use of precision measurement equipment.
Test. Test is used to verify the operation of an item or function and the recording of quantitative data, which are compared to the specified performance parameters. The test process shall generate data, and these data are normally recorded by precision measurement equipment or procedures. Analysis is subsequently performed on the data derived from the testing.
_1618392774.xls Table 1
REQUIREMENT OBJECTIVE
Weight <69,825 lbs
Length < 499.8 in
Width < 102 in
Height < 142 in
Lift Capacity 40 ton
Ground Clearance >15 in
Fording (without fording aids) >60 in
Speed On improved surfaces > 45 mph
Table 1
Table
Task Element Estimated Hours of Annual Operation
Start up procedures 1 <10
Movement w/in site 2 200+
Load/move/unload/move 3,6 500+
Movement between sites 6 <100
Movement to/from decontamination (DECON) site 4 <40
End of shift procedures 5 <10
Standby Time (Idle, engine operating) <100
TOTAL 1000
Table 2 Operational summary/mission profile
NOTES:
1. Start –up procedures include preventive maintenance checks and services.
2. Movement time includes all unloaded movement among the various classes of cargo inside the cargo yard area.
3. Load/move/unload/move time includes separating loads, lifting the equipment/item.
4. Decontamination time includes driving to/from the DECON site and not the actual DECON process itself.
5. Includes performance of preventive maintenance checks and services at end of shift.
6. Unloaded, includes searching for and identifying equipment/item to be moved
Table 2
Climate Type % Fleet Distribution Terrain * % Cargo Handling Hours % Traveling Hours
Hot 10% Improved 30 25
Non-Extreme 85% Unimproved 45 60
Cold 5% Cross-Country 25 15
Table 3 Operational Environmental Conditions
NOTES:
Improved terrain is considered to be a hard surface and/or gravel area; unimproved terrain is an area that has been leveled with large obstacles removed; and cross-country is an area in which no excavation, or grading has been done.
Table 3
# Requirement Title/Description Requirement Paragraph Inspect/Certify at Factory Test and/or Inspection
001 Operational Requirements 3.1 *C D
002 ECM/ECU 3.2, 3.2.1, 3.2.2 *C D
003 ECM/ECU 3.2.3, 3.2.4, 3.2.5, 3.2.6 *C D & A
004 C/VIS 3.3 I I & D
005 Operator's Cab 3.4 I & *C I, D, & A
006 Exterior Panels 3.5 I I
KEY: I = Inspection, T = Test, C = Contractor certification, D = Demonstration, A = Analysis
*Contractor must provide certification to confirm meeting Government requirements.
Operational Environment
b. Movement Table 4
Terrain * % Cargo Handling Hours % Traveling Hours
Improved 30% 25%
Unimproved 45% 60%
Cross-Country 25% 15%
c. Climatic design Table 5
Climate Type % Fleet Distribution
Hot 10%
Non-Extreme 85%
Cold 5%
Mission Profile
The mission profile assumes 72-hour high intensity usage. Table 6
72 HOUR HIGH INTENSITY USAGE
Event Duration
Standby 2
Warm-up/Preventive Maintenance 1.5
Movement 4.5
Operation 48
After Operation Preventive Maintenance 16
Total hours of Operation 72
Normal usage under a 24-hour period. Table 7 The expected length of a mission for the RTC is 4.0 hours (1.2 for travel and 2.8 for lifting).
NORMAL OPERATION (24 HOUR)
Event Duration
Standby 10
Warm-up/Preventive Maintenance 1
Movement 2.4
Operation 5.6
After Operation Preventive Maintenance 1
Total Hours of Operation 20
Attachment usage for the crane. Table 8
ATTACHMENT USAGE
Attachment % Usage
Concrete Bucket 0.010%
Clamshell Bucket 0.020%
Total Hours of Operation 0.030%