Exhibit_2c__TRAP_Software_Development_PWS_Amend_0001.docx

DOCX document 685 KB Posted

Attached to
TFITS Consolidated Systems Integrator (TCSI) Federal contract opportunity
Solicitation number
M67854-14-R-4802
Issued by
United States Marine Corps

About this file

Exhibit 2c_Amend 0001

View the file

Other files for this federal contract opportunity

Other files attached to TFITS Consolidated Systems Integrator (TCSI), newest first.
File Type Posted
RFP_M67854-17-R-7802_Amend_00001.docx DOCX document
Exhibit_2a__TRAP_Transition_PWS_Amend_0001.docx DOCX document
Exhibit_9_The_Marine_Corps_Systems_Command_Technical_Review_Handbook_Amend_0001.pdf PDF
Attachment_4a__Post_Award_Orientation_and_Planning_PWS_Amend_0001.docx DOCX document
Exhibit_10__Industry_Questions_and_Answers_Amend_0001.xlsx XLSX spreadsheet
Attachment_1_SI_Consolidation_PWS_Amend_0001.docx DOCX document
M67854-14-R-4802_Amend_01.doc DOC document
Exhibit_8_The_SUPPLEMENT_TO_GUIDEBOOK_for_Acquisition_of_Naval_Intensive_Systems_Amend_0001.PDF PDF
M67854-14-R-4802_conformed_Amend_01.doc DOC document
Exhibit_4d_TRAP_RTM.xls XLS spreadsheet
Exhibit_2b__TRAP_PDSS_PWS_Amend_0001.docx DOCX document
Attachment_7_DD254__Amend_0001.pdf PDF
Attachment_7_DD254_draft_M14-R-4802_Updated.pdf PDF
Exhibit_2c__TRAP_Software_Development_PWS_Final_.docx DOCX document
Attachment_4a_Enclosure_1_DD_2875_SAAR_MC_MCCDC_MCBQ.pdf PDF
Exhibit_3c_TFITS_Performance_Measurement_Plan.pdf PDF
Exhibit_3e_TFITS_Risk_Management_Plan.pdf PDF
Exhibit_3a_TFITS_SEP.pdf PDF
Attachment_3_TFITS_SI_Overarching_Quality_Assurance_Surveillance_Plan_(QASP)x.docx DOCX document
M67854-14-R-4802_RFP.pdf PDF
Exhibit3f_TFITS_STES.pdf PDF
Exhibit4b_TRAP_Contingency_Plan.docx DOCX document
Exhibit_7-_Past_Performance_Questionnaire.docx DOCX document
Exhibit_4c_TRAP_SLA.docx DOCX document
Exhibit_3d_TFITS_Requirements_Management_Plan.pdf PDF
Exhibit_6-_Past_Performance_Statement.docx DOCX document
Attachment_1_SI_Consolidation_PWS_Final_.docx DOCX document
Exhibit_4a_TRAP_CITDB.xlsx XLSX spreadsheet
Exhibit_3b_TFITS_CMP.pdf PDF
Attachment_4a_Enclosre_2_LName_FName_Combined_SAAR_9_Sept_2013.pdf PDF
Exhibit_2b__TRAP_PDSS_PWS_Final_.docx DOCX document
Exhibit_2a__TRAP_Transition_PWS_Final_.docx DOCX document
Exhibit_5_Planned_Systems_to_Consolidate.pdf PDF
Exhibit_1_Navy_Small_Business_Subcontracting_Plan_Goals.pdf PDF
Attachment_4a__Post_Award_Orientation_and_Planning_PWS_Final.docx DOCX document
Attachment__7_DD254_draft.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Total Force Information Technology Systems

TRAP Software Development

ECP0001

Performance Work Statement

February 2014 Table of Contents

Table of Contents1
List of Figures2
List of Tables2
1Introduction3
1.1Purpose and Scope3
1.2Background3
1.3ECP 0001 Overview5
2Software Development5
2.1Requirements Analysis Phase.5
2.2System Design Phase.5
2.3Development Phase.6
2.4Deployment Phase.6
3Task Management7
3.1TRAP Software Development Task Initiation7
3.2TRAP Software Development Resource Coordination and management7
3.3Software Development Task Execution7
3.4Software Development Task Performance Management8
3.5Software Development Task Closeout8
4Integrated Master Schedule8
4.1System IMS.8
5Performance Standards10
6Applicable Documents / References11
6.1Program Documentation11
6.2Systems Documentation12
6.3TFITS Management Plans13
6.4Other Guidance & Standards14
7Deliverables and Schedule15
8Government Furnished Equipment (GFE) and Information (GFI)18
9Period of Performance18
10Place of Performance18
11Travel and Other Direct Costs18
Appendix A. AcronymsA-1
Appendix B. Screen Mock UpsB-1
Appendix C. TRAP ECP0001 CharacteristicsC-1

List of Figures

Figure 1. TRAP System Operational Diagram4
Figure 2. Physical Representation of the TRAP Production Architecture4
Figure 3. TRAP Database Architecture (pre-ECP0001)C-2
Figure 4. Notional TRAP Database Architecture (past-ECP0001)*C-3

List of Tables

Table 1. Meetings8
Table 2. ECP0001 Milestones9
Table 3. Performance Standards10
Table 4. TRAP Program Documentation & Databases11
Table 5. TRAP System Documentation12
Table 6. TFITS Management Plans13
Table 7. Other Guidance & Standards14
Table 8. Deliverables17
Table 9. TRAP System CharacteristicsC-1

Introduction Purpose and Scope This Performance Work Statement (PWS) identifies requirements and performance standards for the elicitation, design, development and deployment of Engineering Change Proposal (ECP) 0001, Personnel Contact Data. The Total Force Information Technology Systems (TFITS) Consolidated Systems Integrator’s (TCSI’s) response shall encompass all required systems engineering processes as reflected in the Marine Corps Systems Command Technical Review Handbook, v1.04, April 2009 and the TFITS Systems Engineering Plan.

Background The TFITS RFP Assessment Program (TRAP) provides daily accountability of all Marines, other Service members and affiliated personnel under administrative and operational control of the Marine Corps. TRAP has 5,000 users across the Marine Corps, reached Full Operational Capability in 2012 and is currently in the Operations and Support (O&S) phase. The system is assigned a Mission Assurance Category (MAC) II, Sensitive. TRAP operates in a Non-classified Internet Protocol Router (NIPR) and Secret Internet Protocol Router (SIPR) web-based environment, with its production system hosted at Marine Corps Base Quantico.

TRAP includes custom application software and tailored Commercial-Off-The-Shelf (COTS) software. The TRAP application software was developed using C-Sharp (C#) on an ASP.Net framework. The database is built in Oracle 11g.

An overview of the system including interfaces is provided in Figure 1.

Figure 1. TRAP System Operational Diagram

Figure 2 provides the TRAP architecture layout.

Figure 2. Physical Representation of the TRAP Production Architecture ECP 0001 Overview The TRAP Advocate identified the need to expand existing personnel information captured in the TRAP system to provide an ability to recall personnel as well as having emergency contact information within the TRAP system. Information to be added for each person includes:

· Commanding Officer

· Supervisor Information

· Emergency Information In addition, the Advocate has stated that they want new reports to be made available.

The Advocate has developed initial screen mock-ups which are provided as Government Furnished Information (GFI) in Appendix B. The TRAP Project Manager’s initial assessment indicates ~30 new data elements will be required to support the new capability along with a number of new reports for both Basic and Super Users and is a third second octet change with full technical review. For this specific second octet change, the entire ATO effort associated with this ECP is included in the PDSS of TRAP.

Software Development Requirements Analysis Phase.

The key Objective of the Requirements Analysis Phase is to transform the Government’s needs into a technical view of a required product that will deliver those needs. Efforts involve defining User needs and requirements in the context of planned User use, environments, and identified system characteristics to determine requirements for system functions. At a minimum, the TCSI shall:

Elicit TRAP ECP 0001 derived requirements.

Perform an iterative process of decomposing TRAP ECP 0001 requirements into system functional requirements and establishing traceability.

Maintain traceability between the TRAP ECP 0001 derived and Government- provided requirements.

Align TRAP ECP 0001 requirements analysis efforts with Marine Corps Systems Command (MCSC) acquisition requirements (TFITS Management Plans, and Systems Engineering Technical Review (SETR) process).

Provide TRAP ECP 0001 documentation needed to support the MCSC SETR process for System Requirements Reviews (SRR) and System Functional Reviews (SFR).

Document the TRAP ECP 0001 functional baseline.

System Design Phase.

The overarching objective for the System Design Phase is the on-time delivery to the Governmentemnt of Government-approved documentation providing the detailed design of each configuration item in the approved product baseline. The System Design phase produces a design that is based on the functional descriptions and products developed during the Requirements Analysis phase. The design is reflected in the products developed and delivered by the TCSI.

At a minimum, the TCSI shall:

Provide the TCSI’s TRAP ECP 0001 design process, including the use of design and modeling tools, analyses, and tradeoffs.

Align the TCSI’s process with the TFITS Management Plans and the MCSC SETR process for Preliminary and Critical Design Reviews (PDRs/CDRs).

Provide the TRAP ECP 0001 documentation needed to support the PDR and CDR.

Document the TRAP ECP 0001 Allocated and Product baselines.

Development Phase.

The prime objective for the Development Phase is the on-time delivery of a Government-tested and accepted capability solution.

At a minimum the TCSI shall:

Develop, integrate, assemble and test TRAP ECP 0001 capability.

Provide TRAP ECP 0001 in-process reviews.

Align the TCSI’s process with the TFITS Management Plans and MCSC SETR process for TRAP ECP 0001 Test Readiness Review (TRR), System Verification Review (SVR), Production Readiness Review (PRR) and Physical Configuration Review (PCR).

Provide documentation needed to support the TRAP ECP 0001 TRR, SVR, PRR, and PCR.

Support TRAP ECP 0001 Government Acceptance Testing, code review, and cyber-penetration testing. The IV&V has been waived.

Deployment Phase.

The prime objective for the Deployment Phase is the deployment of the Government- accepted capability into the production environment in accordance with the established performance standards.

At a minimum the TCSI shall:

Document the TCSI’s deployment process.

Validate that all certifications and accreditations are in place prior to deployment.

Prepare the system user community to receive and use capability.

At a minimum the TCSI shall:

Provide TRAP Support Documentation and Materials.

Ensure all TRAP user support materials are updated to reflect the changes being introduced by ECP 0001.

Provide User Training.

Develop and deliver differences training materials to support the deployment of ECP0001.

Warranty the software for three months from any defects.

Coordinate and deliver the deployment package within the PDSS Release Management process.

Task Management At a minimum, the TCSI task management efforts shall provide the following TRAP Task Management requirements:

TRAP Software Development Task Initiation TRAP Software Development Resource Coordination and management TRAP Software Development Roles and Responsibilities.

Individual TRAP Software Development Security Clearances Provide evidence of Top Secret Individual Clearance for any TRAP system administrator and/or individual with root access for the TRAP SIPRNET enclave.

Provide evidence that all individuals performing on classified aspects of TRAP have a current Secret Clearance and will be required to maintain access to Secret Information. Secret access is required in order to attend meetings and perform daily work inside approved areas. Access to Secret data requires unescorted access into Secret spaces and access to Secret information and/or systems [SECRET Internet Protocol Router Network (SIPRNET)].

Provide evidence of necessary Cybersecurity certifications as appropriate for individuals supporting the TRAP system.

Software Development Task Execution At a minimum, Software Development Task Execution requires the TCSI to:

Perform quality assurance in accordance with the QAPP.

Identify and manage risks and update the Risk Management Plan, as necessary.

Host and/or Aattend, provide agenda, provide meeting minutes, and participate in any adhoc Working Groups, Integrated Product Teams (IPT), Technical reviews, Technical Interchange meeting, In Process Reviews (IPR), and/or any other system specific meetings to support the requirements of the Task.

Attend the following meetings as provided in Table 1.

Meeting
Duration
Weekly Tier 2 IPT
2-3 hrs
Weekly Dial-up
30 mins
Technical Interchange Meeting
1 hr

Table 1. Meetings Software Development Task Performance Management Include Software Development activities and progress towards the Performance Standard and Acceptable Quality Levels (AQLs) in the SPDSS Monthly Status Report (MSR).

Software Development Task Closeout Provide orderly closeout of the task order including final delivery of any remaining Government products, and preparation of a final report to include lessons learned and analysis of task.

Integrated Master Schedule TRAP is a fictitious system, do not include any of TRAP System Integrated Master Schedule (IMS) reportable events in the actual SI Consolidated Contract IMS.

System IMS.

At a minimum, the TCSI shall incorporate the TRAP Software Development into the System IMS and shall provide the ability to understand how it intends to manage the TRAP Software Development with visibility of:

4.1.1 Tasks;

4.1.2 Activities;

4.1.3 Schedule;

4.1.4 Deliverables; and

4.1.5 Other TRAP Task Orders (TOs).

Key Task Milestones The key milestone dates in the below table are based on an award of ECP 0001 Task Order (TO) on April 01, 2014.

Milestone
Threshold Date
System Requirements Review
April 15, 2014
System Functional Review
May 15, 2014
Preliminary Design Review
June 15, 2014
Critical Design Review
July 15 , 2014
Test Readiness Review
August 15, 2014
Production Readiness Review
September 18, 2014
Deploy
Part of September 2014 Maintenance Release

Table 2. ECP0001 Milestones TRAP System Enhancement- ECP 0001 Performance Work Statment

Performance Standards The TCSI shall be monitored against the following performance standards and Acceptable Quality Levels.

Desired Outcomes
Performance Standard
Monitoring Method
Acceptable Quality Levels (AQLs)
Successful completion of Government Acceptance Test (GAT)
The software has no Severity 1 and/or 2 defects as defined in the TFITS System Test and Evaluation Strategy
· GAT Scorecard

· SETR results

· = Standard

Successful completion of SETR reviews (SRR, SFR, PDR, CDR, TRR, and PRR)
The review has no critical RFAs as defined in the TFITS Management Plans and the MCSC SETR Handbook
· Review exit criteria
· All critical RFAs are adjicated within five business days
The software deploys on schedule
Software deployment is completed in accordance with the TCSI developed and Government approved integrated master schedule (IMS) with no more than a two day negative schedule variance.
· Weekly Tier 2 IPT

· Weekly Status Reports

· Monthly Status Reports

· Updated IMS

· GAT Scorecard

· Five business day negative schedule variance.

Users know how to use TRAP with ECP 0001 before ECP 0001 is deployed
Differences training should be part of the deployment package.

· Training plans

· User post-training surveys

· GAT Scorecard

· = Standard

Table 3. Performance Standards

Applicable Documents / References The following documents provide essential programmatic information that needs to be considered in the TCSI’s proposed Annex and Deliverables package.

Program Documentation

Document / Reference
Intended Use
TRAP Service Level Agreement (SLA) with Hosting Environment
Identifies agreements and coordination POCs with the TRAP hosting environment
*Interface Control Documents and/or System Interface Agreements
Documents the roles/responsibilities and data exchange information between TRAP and another system.
TRAP Contingency Plan
Provides guidance on the decision-making process and its timely response to any disruptive or extended interruption of normal business operations and services.
*TRAP Risk Register
Contains all TRAP risks. TCSI personnel will require a Common Access Card (CAC) to access.
*TRAP ECP Tracker Database
Contains all TRAP ECPs. TCSI personnel will require a CAC to access.
*TRAP Trouble Ticket Database
Contains all TRAP Trouble Tickets. TCSI personnel will require a CAC to access.
TRAP Requirements Traceability Matrix
Government requirements document.

Table 4. TRAP Program Documentation & Databases

* Note: The documents that are noted with an asterisk are notional. No copies will be provided.

Systems Documentation

Document / Reference
Intended Use
*TRAP System Maintenance and Administration Manual
Describes the administrative functions to maintain the TRAP system
TRAP Configuration Item Technical Database
Describes the hardware and software configuration items
TRAP Database Architecture
Describes the TRAP database architecture
*TRAP User Manual
Provides TRAP Users with a quick reference to the tasks expected to be performed in TRAP.
*TRAP Training Material
Instructor training material to support classroom training
*TRAP Test Scripts
Set of instruction executed by a person to ensure TRAP is functioning correctly.

Table 5. TRAP System Documentation

* Note: The documents that are noted with an asterisk are notional. No copies will be provided.

TFITS Management Plans

Document / Reference
Intended Use
TFITS Systems Engineering Plan
Describes the systems engineering approach for TFITS projects
TFITS Configuration Management Plan
Describes the processes the TFITS Product Management Offices follow to define, document, implement, account for and audit changes to requirements and baselines, supporting processes and documents for each of the projects in its portfolio
TFITS System Test & Evaluation Strategy
Defines the test & evaluation (T&E) approach for the TFITS Product Management Offices.
TFITS Requirements Management Plan
Defines the TFITS process of developing and maintaining requirements as well as controlling any changes to those requirements throughout the system life cycle.
TFITS Risk Management Plan
Provides guidance for implementing a risk management process, to assess the root cause of program risks, and to develop strategies to manage these throughout a systems’ lifecycle for TFITS projects.
TFITS Performance Measurement Plan
Provides all managed projects with a framework for reporting a set of core and specialized metrics to baseline system element performance and report a standardized set of Key Performance Indicator (KPIs) to stakeholders.

Table 6. TFITS Management Plans

Other Guidance & Standards – Most current version of the following:

Document / Reference
Intended Use
MIL-STD-881 / Work Breakdown Structures
Guidance on building WBS
DoDI 5000.02 / Operation of the Defense Acquisition System
General Acquisition execution guidance
DoDD 5000.01 / Defense Acquisition System
Acquisition guidance
CJCSI 3170.01G / Joint Capabilities Integration and Development System
Requirements guidance
DoD 8570.01 / IA Workforce Improvement Program
Cybersecurity
DoDI 8510.01 / Defense Information Assurance Certification and Accreditation Process (DIACAP)
Cybersecurity
DoDI 8500.2 / Information Assurance Implementation
Cybersecurity

Federal Acquisition Regulation (FAR)

Federal Information Security Management Act (FISMA)
Cybersecurity, PII guidance,
MIL-HDBK-61 / Configuration Management
CM Guidance
MCSCO 4130.1 / Configuration Management Policy
CM Policy
MCSCO 5400..5 / Naval SYSCOM Systems Engineering Policy
Systems Engineering Technical Review Guidance (SETR)
IEEE/EIA 12207 / Standard for Information Technology Software Life Cycle Processes
Industry standard for Software Support
Marine Corps Systems Command Technical Review Handbook, v1.04, April 2009
Systems Engineering Technical Review Guidance (SETR)

Table 7. Other Guidance & Standards

Deliverables and Schedule The below Deliverables are notional and are not considered to be all inclusive. The TCSI shall propose the most comprehensive and cost-effective Deliverables tailored to the proposed solution. All Deliverables shall be delivered to the Government’s electronic repository (SharePoint) with a notification to the Contracting Officer, Contracting Officer’s Representative and the TRAP Project Manager.

Deliverable Number

Deliverable Title
Format
Date of first submission
Subsequent Submission
E001
Requirements Traceability Matrix (RTM)
Government- provided format
Final for SRR/SFR

Update for PDR/CDR

E002
System/Subsystem Design Description
DI-IPSC-81432A
Draft Prior to PDR
Final at CDR
E003
Software Build Plan
Contractor format
Draft Prior to PDR
Final at CDR
E004
Software Test Plan
Contractor format
Draft Prior to PDR
Final at CDR
E005
Test Scripts
Contractor format
Final at CDR
Updated at TRR
E006
Integration & Test Scorecard
Contractor format
COB each day during all testing events
N/A
E007
Release Notes
Contractor format
At Deployment
N/A
E008
Version Description Document
Contractor format
At Deployment
N/A
E009
Updated System Maintenance and Administration Manual
Contractor format
At Deployment
Five (5) working days after receipt of Government Comments
E010
Updated Training Material
Contractor format
Five (5) work days prior to Training Class (if no Training Class than 5 work days prior to deployment)Due at TRR.
Two (2) working days after receipt of Government Comments
E011
Updated Training Modules
Contractor format
As agreed upon with TRAP PMO
Based on agreements with TECOM
E012
Overarching IMS Updates
MS Project
Prior to IPR/IPT
Two (2) working days after receipt of Government Comments (after TO Award)
E014
Source Code (TRAP)
To be proposedContractor Format
within five (5) days following scheduled release
E015
Monthly Status Report
Contractor format
within one (1) working day following bi-weekly reporting period15 days after completion of the first calendar month
Monthly Report submitted by the 15th of the following month.One (1) working day after receipt of Government Comments
E016
Test Report and Defects
Contractor format
due at TRR
update at PRR.
E017
Core Software Metrics
Government-provided format
at each SETR event
update at each SETR event
E018
Meeting Minutes
Contractor format
2 business days after meeting
Five (5) working days after receipt of Government comments
E019
Agenda
Contractor format
1 day prior to meeting
N/A
E020
Other reports, analysis, papers, and presentations
Contractor format
ASREQ
ASREQ
E021
TO IMS Updates
MS Project
ASREQ
ASREQ

Table 8. Deliverables Government Furnished Equipment (GFE) and Information (GFI) There is no GFE provided to the TCSI in performance of this contract. Available GFI is identified in Section 5.

Period of Performance The expected period of performance for this task is nine months.

Place of Performance The primary place of performance will be the TCSI’s facility. In addition, work will be performed at Marine Corps Base, Quantico (TRAP hosting environment) Travel and Other Direct Costs All work is expected to be completed by personnel residing within the local commuting area to MCB Quantico and any travel necessary to complete the work is expected to be included within the TO’s FFP. While travel may be required to support the requirements of this Task, travel is expected to be limited. Travel shall be handled in accordance with the Joint Federal Travel Regulations (JFTR), at the direction and approval of the Contracting Officer’s Representative (COR). Unauthorized travel, or travel not coordinated with the COR shall not be reimbursed. Additionally, travel or other direct costs in excess of the Contract Line Item Number (CLIN) funded value shall not be reimbursed, unless changed by mutual agreement of the parties through a contract modification.

Appendix A. Acronyms

Acronym
Definition
AQL
Acceptable Quality Level
CAC
Common Access Card
CDR
Critical Design Review
CLIN
Contract Line Item Number
COR
Contracting Officer’s Representative
COTS
Commercial-Off-The-Shelf
ECP
Engineering Change Proposal
GAT
Government Acceptance Test
GFE
Government Furnished Equipment
GFI
Government Furnished Information
IMS
Integrated Master Schedule
IPR
In Process Reviews
IPT
Integrated Product Team
JFTR
Joint Federal Travel Regulations
MAC
Mission Assurance Category
MCSC
Marine Corps Systems Command
MSR
Monthly Status Report
NIPR
Non-classified Internet Protocol Router
O&S
Operations & Support
PCR
Physical Configuration Review
PDR
Preliminary Design Review
PDSS
Post Deployment Software Support
PRR
Production Readiness Review
PWS
Performance Work Statement
QAPP
Quality Assurance Program Plan
RFP
Request for Proposal
SETR
Systems Engineering Technical Review
SFR
System Functional Review
SIPR
SECRET Internet Protocol Router
SIPRNET
SECRET Internet Protocol Router Network
SLA
Service Level Agreement
SRR
System Requirements Review
SVR
System Verification Review
TCSI
TFITS Consolidated Systems Integrator
T&E
Test & Evaluation
TFITS
Total Force Information Technology Systems
TO
Task Order
TRAP
TFITS Request for Proposal Assessment Program
TRR
Test Readiness Review

A-2

Appendix B. Screen Mock Ups

Note: New Page

Note: Modified Super User Page (adds the Recall/Emergency button)

Note: Modified Basic Users Report Screen (adds reports #3 and #4).

Note: Modified Super Users Report Screen (adds reports #6 and #7).

B-5

Appendix C. TRAP ECP0001 Characteristics

Table 9 represents the TRAP system characteristics after ECP001 software is integrated into the production code.

Source Lines Of Code
23,112*
Total Function Points (FP)
216
Internal Logical Files**
45
External Inquiries**
18
External Interfaces**
27
External Inputs**
27
External Outputs**
99
Database Fields
90
Database Tables
5
Database Size
300 GBytes
Storage Area Network
6 TBytes

Table 9. TRAP System Characteristics

* Based on 107 SLOC/FP ** Based on medium complexity of 9 *Actual characteristics will be representative of TCSI’s solution

The following figures provide the TRAP database architectures. Figure 35 is the actual database architecture and Figure 46 is the projected database architecture the TRAP Project Management Office (PMO) has come up with as part of its estimation effort.

Figure 3. TRAP Database Architecture (pre-ECP0001)

Figure 4. Notional TRAP Database Architecture (past-ECP0001)*

* Developed by the TRAP PMO as part of its estimation effort.