Attachment_4a__Post_Award_Orientation_and_Planning_PWS_Final.docx

DOCX document 267 KB Posted

Attached to
TFITS Consolidated Systems Integrator (TCSI) Federal contract opportunity
Solicitation number
M67854-14-R-4802
Issued by
United States Marine Corps

About this file

14-R-4802 Att 4a

View the file

Other files for this federal contract opportunity

Other files attached to TFITS Consolidated Systems Integrator (TCSI), newest first.
File Type Posted
RFP_M67854-17-R-7802_Amend_00001.docx DOCX document
M67854-14-R-4802_Amend_01.doc DOC document
Exhibit_8_The_SUPPLEMENT_TO_GUIDEBOOK_for_Acquisition_of_Naval_Intensive_Systems_Amend_0001.PDF PDF
M67854-14-R-4802_conformed_Amend_01.doc DOC document
Exhibit_4d_TRAP_RTM.xls XLS spreadsheet
Exhibit_2c__TRAP_Software_Development_PWS_Amend_0001.docx DOCX document
Exhibit_2b__TRAP_PDSS_PWS_Amend_0001.docx DOCX document
Attachment_7_DD254__Amend_0001.pdf PDF
Exhibit_2a__TRAP_Transition_PWS_Amend_0001.docx DOCX document
Exhibit_9_The_Marine_Corps_Systems_Command_Technical_Review_Handbook_Amend_0001.pdf PDF
Attachment_4a__Post_Award_Orientation_and_Planning_PWS_Amend_0001.docx DOCX document
Exhibit_10__Industry_Questions_and_Answers_Amend_0001.xlsx XLSX spreadsheet
Attachment_1_SI_Consolidation_PWS_Amend_0001.docx DOCX document
Attachment_7_DD254_draft_M14-R-4802_Updated.pdf PDF
Attachment_3_TFITS_SI_Overarching_Quality_Assurance_Surveillance_Plan_(QASP)x.docx DOCX document
M67854-14-R-4802_RFP.pdf PDF
Exhibit3f_TFITS_STES.pdf PDF
Exhibit4b_TRAP_Contingency_Plan.docx DOCX document
Exhibit_3b_TFITS_CMP.pdf PDF
Attachment_4a_Enclosre_2_LName_FName_Combined_SAAR_9_Sept_2013.pdf PDF
Exhibit_2b__TRAP_PDSS_PWS_Final_.docx DOCX document
Exhibit_2a__TRAP_Transition_PWS_Final_.docx DOCX document
Exhibit_5_Planned_Systems_to_Consolidate.pdf PDF
Exhibit_1_Navy_Small_Business_Subcontracting_Plan_Goals.pdf PDF
Attachment__7_DD254_draft.pdf PDF
Exhibit_7-_Past_Performance_Questionnaire.docx DOCX document
Exhibit_4c_TRAP_SLA.docx DOCX document
Exhibit_3d_TFITS_Requirements_Management_Plan.pdf PDF
Exhibit_6-_Past_Performance_Statement.docx DOCX document
Attachment_1_SI_Consolidation_PWS_Final_.docx DOCX document
Exhibit_4a_TRAP_CITDB.xlsx XLSX spreadsheet
Exhibit_2c__TRAP_Software_Development_PWS_Final_.docx DOCX document
Attachment_4a_Enclosure_1_DD_2875_SAAR_MC_MCCDC_MCBQ.pdf PDF
Exhibit_3c_TFITS_Performance_Measurement_Plan.pdf PDF
Exhibit_3e_TFITS_Risk_Management_Plan.pdf PDF
Exhibit_3a_TFITS_SEP.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Marine Corps Systems Command Program Manager Information Systems & Infrastructure

Total Force Information Technology Systems (TFITS) Systems Integrator Consolidation Post Award Orientation and Planning Performance Work Statement

February 2014

Table of Contents

Table of Contentsi
List of Figuresi
List of Tablesii
1Introduction1
1.1Purpose and Scope.1
2Post Award Orientation and Planning2
2.1Post Award Orientation Meeting2
2.2Planning Meeting #13
2.3Task Order Planning Meeting #23
2.4Task Order Planning Meeting #34
3Task Management5
3.1Post Award Orientation and Planning Task Initiation5
3.2Post Award Orientation and Planning Resource Coordination and management5
3.3Post Award Orientation and Planning Task Execution5
3.4Post Award Orientation and Planning Task Performance Management5
3.5Post Award Orientation and Planning Task Closeout5
5.Key Task Milestones6
6.Performance Standards6
7.Deliverables and Schedule7
8.Government Furnished Equipment (GFE) and Information8
9.Period of Performance8
10.Place of Performance8
11.Travel and Other Direct Costs8
Appendix A. AcronymsA-1
Appendix B. TFITS TechnologiesB-1
Appendix C. NIPRNet System Authorization Access Request (SAAR)C-1

List of Figures

Figure 1. Consolidation Timeline1
Figure 2. Initial Transition Phasing2

List of Tables

Table 1. Key Task Milestones6
Table 2. Performance Standards6
Table 3. Deliverables8

TFITS SI Consolidation Post Award Initiation Performance Work Statement

Introduction Purpose and Scope.

Product Manager (PdM), Total Force IT Systems’ (TFITS) primary objective is to continue providing needed Marine Corps Information Technology (IT) systems in an environment of reducing budgets. One initiative is to reduce the number of System Integrators supporting programs within PdM TFITS portfolio of systems. The purpose of this Performance Work Statement (PWS) is to ensure the Consolidated Contract gets off on the right foot and will focus on topics such as:

· Ensure the TCSI has a solid understanding of the roles and responsibilities involved in the Consolidated Contract.

· Ensure the TCSI has a solid understanding of the first Transition Task Orders prior to developing TO Request For Proposal (RFP) response.

· Provide Government visibility on TCSI progress to meet demand levels.

· Collaborate on risks and risk mitigation strategies

Figures 1 and 2 shows the planned consolidation timeline and phasing. As indicated, the first seven systems to transition to the TCSI will be TFRS, RFID, RTAMMS, SPS/WAWF/EDA/FPDS, JFRG II, MDSS II and TFSMS.

Figure 1. Consolidation Timeline

Figure 2. Initial Transition Phasing Post Award Orientation and Planning Post Award Orientation Meeting One week after award of the consolidated contract a Government-TCSI combined post-award orientation meeting will be conducted at the TCSI’s facility. The Government anticipates the meeting to last five days.

Topics to be discussed by the Government include (but are not limited to):

Contract terms and conditions;

Contract requirements;

Government team organization;

Government-TCSI communications;

System consolidation timeline;

First four transition task order RFPs (the first four transition TOs will be issued at the Post Award Orientation and are due within 10 calendar days);

Steps necessary to execute the first four Transition Task Orders;

Contract data deliverables;

TFITS SharePoint site;

SI personnel authorization access request process. The TCSI shall deliver at Post Award Orientation the completed necessary SAAR forms to streamline and expedite access approval. All forms can be found via the information in Appendix C.

Topics to be addressed by the TCSI include (but are not limited to):

Organization (e.g., contract management, TO management) structure;

TCSI team and status;

Facility plan and status;

Risks and mitigation strategies aligning with the TFITS Risk Management Plan.

Planning Meeting #1 Three weeks after award of the consolidated contract the first Government-TCSI combined planning meeting will be conducted at the TCSI’s facility. The Government anticipates the meeting to last five days. Topics to be addressed include (but are not limited to):

Proposals TCSI submitted in response to the first four System Transition TO RFPs with topics to include:

Task program management, technical and logistics requirements;

PWS;

QASP;

Transition plan annexes (STrP and TMP);

Key milestones and IMS Negotiations (if necessary) Facility readiness TCSI team readiness status Risks and mitigation strategies aligning with the TFITS Risk Management Plan.

Issuance of additional RFPs and any steps necessary to execute Discussion of when the Government will issue RFPs for System PDSS TOs for the first four Systems Issuance of system transition task order RFPs five.

Task Order Planning Meeting #2 Six weeks after award of the consolidated contract the second Government-TCSI combined planning meeting will be conducted at the TCSI’s facility. The Government anticipates the meeting to last three days. Topics to be addressed by the TCSI include:

Proposals TCSI submitted in response to system transition task order RFPs five and six with topics to include:

Task program management, technical and logistics requirements;

PWS;

QASP;

Transition plan annexes (STrP and TMP);

Key milestones and IMS.

Negotiations (if necessary) Facility readiness TCSI team readiness status Risks and mitigation strategies.

Issuance of additional RFPs and any steps necessary to execute Discussion of when the Government will issue RFPs for System PDSS TOs for the next System Issuance of system transition task order RFPs six and seven Task Order Planning Meeting #3 Ten weeks after award of the consolidated contract the second Government-TCSI combined planning meeting will be conducted at the TCSI’s facility. The Government anticipates the meeting to last two days. Topics to be addressed by the TCSI include:

Proposal TCSI submitted in response to system transition task order RFP seven with topics to include:

Task program management, technical and logistics requirements;

PWS;

QASP;

Transition plan annexes (STrP and TMP);

Key milestones and IMS.

Negotiations (if necessary) Facility readiness TCSI team readiness status Risks and mitigation strategies.

Issuance of additional RFPs and any steps necessary to execute Discussion of when the Government will issue RFPs for System PDSS TOs for the next Systems Potential issuance of additional system transition task order RFPs Task Management At a minimum, the TCSI task management efforts shall provide the following task management requirements:

Post Award Orientation and Planning Task Initiation Post Award Orientation and Planning Resource Coordination and management Roles and Responsibilities.

Individual Security Clearances No classified clearance is anticipated for this task order.

Post Award Orientation and Planning Task Execution At a minimum, Task Execution includes:

Perform quality assurance in accordance with the QAPP;

Identify and manage risks and update the Risk Management Plan, as necessary;

Attend, provide agenda, provide meeting minutes, and participate in any adhoc Working Groups, Integrated Product Teams (IPT), Technical reviews, Technical Interchange meeting, In Process Reviews (IPR), and/or any other system specific meetings to support the requirements of the Task.

Post Award Orientation and Planning Task Performance Management Provide a Weekly Status Report Post Award Orientation and Planning Task Closeout Provide orderly closeout of the contract including final delivery of any remaining Government products, and preparation of a final report to include lessons learned and analysis of task.

4. Integrated Master Schedule

4.1 As this is the first IMS to be submitted for actual contract performance, this TO IMS will be the basis for the SI Consolidated Contract IMS, and will incorporate reportable events and interdependencies from all subsequent TO IMSs.

4.2 System IMS.

At a minimum, each IMS shall provide the ability to understand how it intends to manage the proposed effort with visibility of:

4.2.1 Tasks;

4.2.2 Activities;

4.2.3 Schedule; and

4.2.4 Deliverables

5. Key Task Milestones The key milestone dates in the below table are based on an anticipated award of the post award orientation and planning task order.

Milestone
Expected Date
Post Award Orientation Meeting
One week after Consolidate Contract Award
Task Order Planning Meeting #1
Three weeks after Consolidate Contract Award
Task Order Planning Meeting #2
Six weeks after Consolidate Contract Award
Task Order Planning Meeting #3
Ten weeks after Consolidate Contract Award

Table 1. Key Task Milestones

6. Performance Standards The TCSI shall be monitored against the following performance standards and Acceptable Quality Levels.

Desired outcomes
Performance Standard
Monitoring Method
Acceptable Quality Levels (AQLs)
TCSI adhered to the schedule for all meetings
All post award meetings happen on or before scheduled time
· Review of the IMS

· Meeting minutes

· Schedule variance of 2 days

TCSI provided appropriate resources at all meetings
All TCSI team members actively participate at all meetings
· Meeting minutes
· =Standard
TCSI deliver task order proposals within the appropriate deadline
All task order proposals were delivered on or before the scheduled time
· Government receipt of proposals
· =Standard

Table 2. Performance Standards

7. Deliverables and Schedule The below Deliverables are notional and is not considered to be all inclusive. The Offeror should propose the most comprehensive and cost effective Deliverables as tailored to the proposed solution. All Deliverables will be delivered to the Government’s electronic repository (SharePoint) with a notification to the Contracting Officer, Contracting Officer’s Representative and the TFITS Project Manager.

Deliverable Number

Deliverable Title
Format
Date of first submission
Subsequent Submission
K001
Resolution of Government Comments to Proposal PMP
Government format
PMP Initially submitted in response to the Overarching PWS
Five (5) working days after receipt of Government Comments (after TO Award)
K002
Integrated Master Schedule Update
Government format
IMS Initially submitted in response to the Overarching PWS
Five (5) working days after receipt of Government Comments (after TO Award)
K003
Resolution of Government Comments to Proposal SDP
Government format
SDP Initially submitted in response to the Overarching PWS
Five (5) working days after receipt of Government Comments (after TO Award)
K004
Resolution of Government Comments to Proposal TrP
Government format
TrP Initially submitted in response to the Overarching PWS
Five (5) working days after receipt of Government Comments (after TO Award)
K005
Resolution of Government Comments to Proposal PDSSP
Government format
PDSSP Initially submitted in response to the Overarching PWS
Five (5) working days after receipt of Government Comments (after TO Award)
K006
Configuration Management Plan
Government format
30 days after TO Award
Five (5) working days after receipt of Government Comments (after TO Award)
K007
Weekly Status Report
Contractor Format
1st Friday following Contract Award
COB each Friday
K008
Meeting Minutes
Contractor Format
2 days after any meeting
2 days after any meeting
K009
IMS
Contractor Format
Initially submitted in response to the Overarching PWS
Five (5) working days after receipt of Government Comments (after TO Award)

Table 3. Deliverables 8.

9. Government Furnished Equipment (GFE) and Information There is no GFE or GFI provided to the TCSI in performance of this contract.

10. Period of Performance The expected period of performance for this task is 11 weeks.

11. Place of Performance The primary place of performance will be the TCSI’s facility.

12. Travel and Other Direct Costs All work is expected to be completed by personnel residing within the local commuting area to MCB Quantico and any travel necessary to complete the work is expected to be included within the TO’s FFP. While travel may be required to support the requirements of this Task, travel is expected to be limited. Travel shall be handled in accordance with the Joint Federal Travel Regulations (JFTR), at the direction and approval of the Contracting Officer’s Representative (COR). Unauthorized travel, or travel not coordinated with the COR shall not be reimbursed. Additionally, travel or other direct costs in excess of the Contract Line Item Number (CLIN) funded value shall not be reimbursed, unless changed by mutual agreement of the parties through a contract modification.

Appendix A. Acronyms

Acronym
Definition
APES
Automated Performance Evaluation System
AQL
Acceptable Quality Level
COR
Contracting Officer’s Representative
CLIN
Contract Line Item Number
GFI
Government Furnished Information
IMS
Integrated Master Schedule
IPR
In Progress Report
IPT
Integrated Product Team
JFRG II
Joint Force Requirements Generator II
JFTR
Joint Federal Travel Regulations
MDSS II
MAGTF Deployment Support System II
MMAS
Manpower Mobilization Assignment System
ODI-RMS
Optical Digital Imaging-Records Management System
PdM
Product Manager
PDSS
Post Deployment Software Support
PDSSP
PDSS Plan
PES
Performance Evaluation System
PMP
Project Management Plan
PWS
Performance Work Statement
QAPP
Quality Assurance Program Plan
QASP
Quality Assurance Surveillance Plan
RFID
Radio Frequency Identification
RFP
Request for Proposal
RTAMMS
Requirements, Transition, and Manpower Management System
SAAR
System Authorization Access Request

SDP

SI
Systems Integrator
SPA
Secure Personnel Accountability
SPS
Standard Procurement System

STrP

TCSI
TFITS Consolidated Systems Integrator
TFDW
Total Force Data Warehouse
TFITS
Total Force Information Technology Systems
TFRS
Total Force Retention System
TFSMS
Total Force Structure Management System
TO
Task Order

A-2

Appendix B. TFITS Technologies

B-1

Appendix C. NIPRNet System Authorization Access Request (SAAR) MCSC link to SAAR process and forms:

https://eis.usmc.mil/sites/missa/knowledge/Training%20Content/DD2875%20SAAR%20Downloads.aspx Also, see Attachment 4a Enclosure 1, and Enclosure 2