Att._10_Solicitation__Question_Response_Form-23.docx
DOCX document 20 KB Posted
- Attached to
- Range Training Systems
- Solicitation number
- M67854-13-R-7803
- Issued by
-
United States Marine Corps
About this file
Government response to question
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| M6785413R7803 | Attachment 10 | |
| SOLICITATION QUESTION/RESPONSE FORM |
RFP M67854-13-R-7803
DATE:
12 Feb 2013
CONTRACTOR QUESTION
SUBJECT: Smoke Generator Power Requirements
SPECIFIC QUESTION:
Please clarify the smoke generator requirements to remove battery and solar power, as well as powered from SAT & MAT. To provide the smoke output (volume and duration) and other capabilities required will draw in excess of 1500Watts (this was verified with multiple vendors). This can not reasonably be supported by batteries or solar panels, or the SAT, and would severely limit MAT operability (would need to return to docking station after short duration) and would actually require a sizeable (portable) generator to do so.
The only smoke generators currently available that operate on battery power are very small hand held units, typically used to verify (low volume/velocity) airflow such as around wall penetrations
| REFERENCE: | |
| PAGE NUMBER:SOW 24 of 76 | PARAGRAPH: 3.3.2.3.1, 3.3.2.3.2, 2 |
| PAGE NUMBER: SSD 16, 22, 30 of 63 | PARAGRAPH: 3.1.2.2.7.2, 3.1.2.3.12.2, 3.2.3.2 |
GOVERNMENT RESPONSE
SOW and SPEC have been updated. Solar Power has been removed. Battery Power requirements have been updated.