Att.10_-_Solicitation_Question_Response_Form-06.docx
DOCX document 22 KB Posted
- Attached to
- Range Training Systems
- Solicitation number
- M67854-13-R-7803
- Issued by
-
United States Marine Corps
About this file
Government response to question.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| M6785413R7803 | Attachment 10 | |
| SOLICITATION QUESTION/RESPONSE FORM |
RFP M67854-13-R-7803
DATE: 11 Feb 13
CONTRACTOR QUESTION
SUBJECT: Instructions regarding solicitation requirement for Cross Reference Matrix
SPECIFIC QUESTION:
Since the basis for award of M67854-13-R-7803 is Trade-Off Analysis (‘Best Value’) please clarify the required content of Vol I and Vol II. Is the Cross Reference Matrix (attachment 12 to solicitation) a requirement for proposal submission?
If yes, is the contractor required to complete both tabs (‘Sheet1’ and ‘Reqts’)?
PM TRASYS intent is not clear in regard to the ‘Reqts’ tab of Cross Reference Matrix ( Attachment 12), specifically is column F, or any other column, intended for government use or is the contractor required to complete all columns on the spread sheet?
Can RFP respondents (contractors) safely assume that PM TRASYS intent is to identify the best value overall solution to the RTSII specifications, or should we assume that the intent is to gauge compliance of the solution line by line (versus in total)?
REFERENCE: Solicitation
| PAGE NUMBER: Attachment 12 | PARAGRAPH: ‘Sheet1’, ‘Reqts’ |
| PAGE NUMBER: 168-175 of 189 | PARAGRAPH: L.1 –L10 |
GOVERNMENT RESPONSE
The RTM is required with both tabs completed. Government use columns will be left blank. Refer to section M for evaluation procedures.
| FOR GOVERNMENT USE ONLY: | CONTROL NUMBER: 06 | |
| PREPARED BY: | DATE: 20FEB2013 |