LBNF-342884-BWQ Addendum 2.pdf

PDF 9 MB Posted

Attached to
Construction Manager as Advisor for upcoming Near Site Construction
Solicitation number
LBNF-342884-BWQ
Issued by

About this file

This document is an addendum to a solicitation for Construction Manager as Advisor (CMa) services for the Long-Baseline Neutrino Facility (LBNF) Near Site Conventional Facilities (NSCF) project. The NSCF project involves constructing new service buildings, underground enclosures, utilities, roads, and other facilities to support the operation of the LBNF beamline and DUNE near detector at the Fermi National Accelerator Laboratory site.

The addendum provides additional information on the pre-proposal conference presentation and attendance list. It also reiterates that all other terms and conditions of the original solicitation remain unchanged. The solicitation requires proposals to be submitted by 5:00 pm Central Time on May 8, 2024, and anticipates an award in January 2025. The CMa services will be procured using a best value trade-off approach, with mandatory requirements related to corporate experience, safety, and quality. The CMa will function as part of the combined project team to provide guidance, oversight, and coordination of the construction subcontractors' work.

View the file

Other files

File Type Posted
LBNF-342884-BWQ Addendum 5.pdf PDF
LBNF-342884-BWQ Addendum 4.pdf PDF
CMa_Proposal_Q15_Response.zip ZIP file
LBNF-342884-BWQ Addendum 3.pdf PDF
LBNF-342884-BWQ Addendum 1.pdf PDF
CMa Checklist 3-12-24.pdf PDF
Sections J-x Documents.zip ZIP file
CMa RFP and Sample Subcontract 3-12-24.pdf PDF
Forms for Submission.zip ZIP file
CMa Transmittal Letter 3-12-24.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM TO SOLICITATION

ADDENDUM NO.

DATE OF ADDENDUM:

4/12/2024

SOLICITATION NO.

LBNF-342884-BWQ

DATE ISSUED:

3/12/2024

PROJECT NO.

N/A

OPENING DATE:

5/08/2024

TITLE OF PROJECT:

LONG BASELINE NEUTRINO FACILITY (LBNF) NEAR SITE CONVENTIONAL FACILITIES (NSCF)

CONSTRUCTION MANAGER-AS-ADVISOR

Bidders must acknowledge this Addendum prior to the hour and date set forth in the solicitation by one of the following methods:

1. By completing the Representations, Certifications and Acknowledgments (PUR-466), or

2. By separate email.

If by virtue of this Addendum you desire to change a bid already submitted, such change may be made by email, provided such email makes reference to the Solicitation and this Addendum and is received prior to the time set for opening.

This Addendum is providing additional information on the items below:

I. Pre-Proposal Conference Presentation

FRA Pre-Proposal Presentation referenced Central Standard Time (CST). This has been corrected to read “Central Time” in the attached presentation on slides 23 and 82.

II. Attendance List from Pre-Proposal Conference

ALL OTHER TERMS AND CONDITIONS AS REFERENCED UNDER THE SUBJECT RFP REMAIN UNCHANGED.

Attachments: Pre-Proposal Conference Presentation from 4/10/24 Attendance List

Fermi Research Alliance, LLC Brian Quinn P.O. Box 500 Project Procurement Specialist Batavia, IL 60510 (630) 840-5777 M.S 210

CMa Pre-Proposal Conference

LBNF/DUNE-US Near Site Conventional Facilities Team 10 April 2024 v1 – posted 10 April

Welcome

Craig Schmitz Near Site Procurement Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference2

Presenters

• Craig Schmitz, Near Site Procurement Manager

• Tom Hamernik, NSCF Project Manager

• Brian Quinn, NSCF Procurement Specialist

• John Szott, NSCF Construction Manager

• Kevin Fahey, LBNF/DUNE-US – Quality Assurance Manager

• Frank Louis, Project Manager, AECOM (NSCF A/E-of-Record)

• Kennedy Hartsfield, NSCF Project Engineer and NSCF Deputy Project Manager

• Mike Andrews, LBNF/DUNE-US – ESH Manager

- Emergency contact: 3131 from any Lab phone or 630-840-3131

- Safety minute: tornado and storm shelter locations

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference3

Agenda

• Welcome

• Introduction

• Procurement

• CMa Overview

• Environment, Safety & Health (ESH)

• Quality

• Scope of Construction

• Conference Wrap-up

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference4

Notice to Offerors

• Oral explanations or instructions given before the award of a contract will not be binding.

Any information given a prospective Offeror concerning a solicitation will be furnished promptly to all other prospective Offerors as an amendment to the solicitation, if that information is necessary in submitting proposals or if the lack of it would be prejudicial to other prospective Offerors.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference5

Introduction

Tom Hamernik NSCF Project Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference6

DUNE at LBNF – An international endeavor hosted by the U.S. D.O.E

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference7

The Deep Underground Neutrino Experiment (DUNE), supported by the Long-Baseline Neutrino Facility (LBNF), is an international endeavor hosted by the U.S. Department of Energy’s Fermilab. DUNE brings together scientists and engineers from more than 35 countries around the world, all sharing the same goal: to understand the neutrino, one of the most elusive and mysterious subatomic particles in the universe.

More information can be found at www.lbnf-dune.fnal.gov http://www.lbnf-dune.fnal.gov/

DUNE at LBNF – An international endeavor hosted by the U.S. D.O.E

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference8

The Deep Underground Neutrino Experiment (DUNE), supported by the Long-Baseline Neutrino Facility (LBNF), is an international endeavor hosted by the U.S. Department of Energy’s Fermilab. DUNE brings together scientists and engineers from more than 35 countries around the world, all sharing the same goal: to understand the neutrino, one of the most elusive and mysterious subatomic particles in the universe.

More information can be found at www.lbnf-dune.fnal.gov

Far Site Near Site http://www.lbnf-dune.fnal.gov/

LBNF/DUNE-US Near Site Conventional Facilities (NSCF)

• New service buildings, underground enclosures, utilities, roads, hardstands, and other facilities needed to house and support the operation of the LBNF Beamline and DUNE Near Detector

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference9

N

(LBNF 30) ABSORBER

SERVICE BUILDING

DECAY REGION

(UNDERGROUND)

ABSORBER HALL

(UNDERGROUND)

NEAR DETECTOR HALL

(UNDERGROUND)

(LBNF 40)

NEAR DETECTOR

SERVICE BUILDING

(LBNF 20)

TARGET

COMPLEX

PRIMARY BEAM

ENCLOSURE

(UNDERGROUND)

(LBNF 5)

PRIMARY BEAM SERVICE BLDG.

EXTRACTION

ENCLOSURE

(UNDERGROUND)

MAIN

INJECTOR

LBNF/DUNE-US Near Site Conventional Facilities (NSCF)

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference10

A beam of protons will be extracted from the Main Injector and precisely directed toward the DUNE detectors.

Traveling through a brand-new beamline, they will smash into a cylindrical rod of graphite, called the target, releasing neutrinos and other subatomic particles. The neutrinos will continue toward the Far Site while the remaining particles will be absorbed.

LBNF/DUNE-US Project Organization

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference11

LBNF/DUNE-US

Project

Far Detectors

Near Detectors

Far Site Excavation

Far Site Buildings & Site

Infrastructure

Near Site Conventional Facilities

+ Beamline

Near Site Conventional Facilities (NSCF)

Beamline

Subproject Organization

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference12

LBNF/DUNE-US

Project

Far Detectors

Near Detectors

Far Site Excavation

Far Site Buildings & Site

Infrastructure

Near Site Conventional Facilities

+ Beamline

Near Site Conventional Facilities (NSCF)

Five Subprojects

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference13

LBNF/DUNE-US

Project

Far Detectors

Near Detectors

Far Site Excavation

Far Site Buildings & Site

Infrastructure

Near Site Conventional Facilities

+ Beamline

Near Site Conventional Facilities (NSCF)

Beamline

Far Site

(SURF)

Near Site (Fermilab)

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference14

LBNF/DUNE-US

Project

Far Detectors

Near Detectors

Far Site Excavation

Far Site Buildings & Site

Infrastructure

Near Site Conventional Facilities

+ Beamline

Near Site Conventional Facilities (NSCF)

CMa will support the NSCF

Near Site Conventional Facilities (NSCF) Organization

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference15

NSCF

Project Manager, T Hamernik

Deputy Project Manager, K Hartsfield

NSCF

Construction Manager

J Szott

LBNF/DUNE Project Office Support:

Construction Coordinators x 3 Near Detector Complex Construction Subcontract

Beamline Complex Construction Subcontract

Consultant and Fermilab Resources:

CMa

A/E-of-Record CxA

Other Specialty Consultants Fermilab ESH, SEMD, ISD, AD, PPD, Communication

ESH

Legal

Procurement Compliance

Project Controls

Systems Engineering Quality Assurance Risk Management

Financial Management Review Office

Near Site Conventional Facilities (NSCF) Organization

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference16

NSCF

Project Manager, T Hamernik

Deputy Project Manager, K Hartsfield

NSCF

Construction Manager

J Szott

LBNF/DUNE Project Office Support:

Construction Coordinators x 3 Near Detector Complex Construction Subcontract

Beamline Complex Construction Subcontract

Consultant and Fermilab Resources:

CMa

A/E-of-Record CxA

Other Specialty Consultants Fermilab ESH, SEMD, ISD, AD, PPD, Communication

ESH

Legal

Procurement Compliance

Project Controls

Systems Engineering Quality Assurance Risk Management

Financial Management Review Office

CMa among consultant and Fermilab resources under the direction of the NSCF Construction Manager – many interfaces

Procurement

Brian Quinn NSCF Procurement Specialist

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference17

• Type of Subcontract: Time and Material

• FRA will pay for actual hours worked and for materials used in the performance of the subcontract.

• Other Allowable Direct Costs

• FRA will make an Award using the Best Value with Trade-Offs approach

• The selection of the most advantageous offer to the government based on a combination of factors, including price and other non-cost factors. The government evaluates proposals against the stated evaluation criteria and may make trade-offs between price and other factors to determine the best overall value.

• FRA may award a Subcontract on the basis of the proposal initially submitted, without discussion, clarification, or modification, or on the basis of negotiation with the Offeror.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference18

• Mandatory Evaluation Factors

- The following are the Mandatory Requirements. Unless otherwise indicated, these requirements refer to the Offeror as a company, not specific individuals.

• Submittal of all items listed under Enclosures in RFP Cover Letter.

• Evidence of annual revenues greater than $50 million for each of the past five (5) years. If partnering with other firms, show total amount of all firms to demonstrate compliance with this requirement.

• EMR less than 1.0

• Corporate Quality Assurance/Quality Control Plan in accordance with an internationally recognized standard (ISO 9001 or equivalent).

• Submitted list of potential primary Subcontractors/subconsultants.

• Submitted list of key personnel with resumes for the following roles: Project Manager, Deputy

Project Manager/Project Engineer, Environment, Safety, and Health (ES&H) Manager, Quality Control Coordinator, Cost Manager, and Scheduler.

• Attendance at mandatory pre-proposal conference.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference19

• Structure of RFP

- Pages 2-19; Subcontract document. This will form the basis of the Subcontract between FRA and the Offeror selected for award. Please list any exceptions to FRA terms in your proposal response. Note: FRA's ability to accommodate exceptions is limited. Taking exception to FRA terms may preclude considering Offeror for award.

- Pages 20-24; Section L ‐ Instructions, Conditions, and Notices to Offerors. Please read and familiarize yourself with requirements for Proposal submission. Be sure to separate Technical portion from Cost portion. For the Cost Proposal Form, a Microsoft Excel version of the T&M fixed hourly rate schedule is provided for the Offeror’s convenience and use.

- Pages 25-30; Section M ‐ Evaluation Factors for Award. FRA will utilize these factors to evaluate each proposal based on its own merit. The award will be made to the offer that meets all mandatory requirements and provides the best value (i.e. combination of price and technical merit, awardee may or may not be the lowest price).

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference20

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference21

• Refer to the RFP Letter for important information concerning the services sought and the organization of the RFP document. Utilize the RFP Submittals Checklist as an aid when finalizing your proposal.

• Ensure all items listed as Enclosures/Submittals are provided with your response.

• Address all Mandatory Requirements.

• Provide responses addressing all Technical Evaluation Factors.

• Technical Evaluation Factors

- Criterion 1: Project Approach and Demonstrated (preferred) Project Experience

- Criterion 2: Project Management

- Criterion 3: Corporate Execution

• Oral Presentations

- FRA may elect to hold oral presentations. If oral presentations are held, those

Offerors determined to be in the competitive range will be invited. The oral presentation shall be restricted to the Offeror’s technical proposal and requested scope of work. Oral presentations will be solely for the purpose of clarification of the offer, and not an opportunity to offer services in addition to those described in the written proposal.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference22

• Questions due in writing by 5:00 p.m. Central Time on April 24, 2024.

• Questions received during the solicitation period will be answered by subsequent amendment.

• Proposals due by 5:00 p.m. Central Time on May 8, 2024.

• Award anticipated January of 2025.

• Continue to monitor SAM.gov for updates/amendments: Notice ID LBNF-342884-BWQ

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference23

CMa Overview

John Szott NSCF Construction Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference24

CMa Overview

• The CMa Scope of Work is not meant to be "all-inclusive" but representative of the CMa's role in the NSCF Construction processes. The CMa's day-to-day responsibilities will be refined jointly with FRA to meet the needs of NSCF construction.

• The CMa is viewed as an extension of the FRA NSCF Team (i.e. eyes, ears, boots, etc.).

The CMa is expected to be on-site when the construction sub-contractors are on site.

• Proactively assisting the Construction Subcontractors to perform the construction of the NSCF (i.e. developing "best in class" work process flows, accountability of NSCF Team to durations, sharing lessons learned, etc.) successfully.

• CMa will manage and implement the NSCF Quality Assurance program under the oversight of the LBNF/DUNE-US Quality Assurance Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference25

CMa Overview – Web Based Project Management System (WBPMS)

• CMa will purchase/lease licenses for the use by the NSCF Team including Construction Subcontractors and Consultants

• Software is the choice of the CMa, subject to FRA review and approval, but must be commercially available.

• It is intended that all construction work processes (i.e. Submittals, RFIs, certificates of insurance, payment applications, cost control, etc.) and documentation (images, material testing, monitoring data, etc.) be housed in the WBPMS.

• CMa will develop all construction workflow processes (approval routings) with FRA in the

WBPMS.

• CMa will develop training and WBPMS orientation for all NSCF Team Members.

• CMa will develop with FRA the customized WBPMS reporting to all levels of the LBNF/DUNE-US Project Team.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference26

CMa Overview – Environmental Baselining/Monitoring

• Develop an Environmental Baseline Plan (proposed equipment, locations, baseline duration, etc.) for Sound, Light and Vibration Levels.

• Gather data and establish sound, light and vibration levels prior to the start of construction.

• Monitor and analyze Construction Phase data for compliance with Local Ordinances and Contract Documents.

• Catalog data and analysis for FRA reference if questions or concerns arise during construction.

• Required for the LBNF/DUNE-US to meet Environmental Assessment (EA) commitment.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference27

CMa Overview – Pre-Construction Surveys

• Review existing site conditions and ascertain if they are represented accurately on the Contract Documents.

• Notify and document conditions of residential, industrial and commercial foundations west of Kirk Road prior to the start of the Near Detector Complex construction.

• Search, notify and survey the existing water wells that could be affected by the NSCF dewatering operations.

• Document pre-existing conditions onsite prior to the start of the Construction Phase.

• Work with and secure a copy of the Construction Subcontractors' pre-existing condition surveys.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference28

CMa Overview – Cost & Schedule Management

• Develop and maintain a Monthly NSCF Cost Report to forecast (estimated, submitted, negotiated, finalized Potential Change Orders (PCO), etc.) the final NSCF cost.

• Develop Independent Cost Estimates for each PCO.

• Review and advise FRA on submitted PCO proposals.

• Assist the Construction Subcontractors in the development of their Cost Loaded

Construction Schedules. Analyze the submitted Subcontractor's Schedule logic, durations, resources, cost loading, etc. for scheduling requirements and best practices.

• Analyze (Fuse) Subcontractor Monthly Schedule updates for scheduling requirements and best practices.

• Review the proposed Subcontractor's Monthly Payment Application "pencil draft" based on observed construction progress.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference29

CMa Overview – Quality Assurance (QA)

• The Construction Subcontractors are responsible for the NSCF Construction Quality Control (QC). The CMa will provide the QA (10% representative sampling) for the NSCF Construction.

• The QA scope of services includes:

- Surveying

- Material Testing (soil, concrete, masonry, steel, etc.)

- Weld Inspections (at the pressure vessel fabrication location)

- Other structural inspections (eg Fasteners / Bolts, Steel Deck, Concrete, Special Inspections)

• Verify the Construction Subcontractors are following their approved QC Plans.

• Reviewing the QC documentation submitted by the Construction Subcontractors

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference30

Environment, Safety, & Health (ESH)

Michael Andrews LBNF/DUNE-US ESH Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference31

ESH is Integrated into the LBNF/DUNE Project

• The Project follows Fermilab’s ESH Manual (FESHM) Chapter 1010, Laboratory Environment, Safety, and Health Management System and Its Implementation

• LBNF/DUNE and Fermilab have a goal of ZERO incidents

• ESH is the #1 Priority to the LBNF/DUNE, Fermilab, and DOE

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference32

Construction Program ESH Expectations

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference33

• LBNF/DUNE NSCF Construction Environmental, Safety, and Health Plan

- Identifies the minimum ESH requirements for Subcontractors and their lower-tier subcontractors for activities relating to LBNF/DUNE

- ESH requirements detailed in subcontract documentation

• FESHM 7010 ESH Program for Construction

- Subcontractor ESH Coordinators on-site during working shifts

- Assurance visits to validate compliance

• Subcontractor Site Specific ESH Plans

- Plans reviewed and accepted prior to start of work activities

- Subcontractor workforce ESH orientation class

- Implementation & oversight by subcontractor ESH Manager

• Work planning & Control documentation

- Build plan/job hazard analysis development and review

• LBNF/DUNE ESH assurance walkthroughs documented through Fermilab Predictive Solutions database https://docs.dunescience.org/cgi-bin/sso/RetrieveFile?docid=21711&extension=pdf&asof=2023-09-15 https://docs.dunescience.org/cgi-bin/sso/RetrieveFile?docid=21711&extension=pdf&asof=2023-09-15

Assist FRA with the Implementation of ESH Requirements

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference34

• 10 CFR 851 Worker Safety & Health Program

• OSHA 1926 & 1910 (Occupational Safety & Health)

• DOE 450.4 Integrated Safety Management (ISM)

• NFPA (Fire & Life Safety)

• NFPA 70 National Electric Code (2017)

• NFPA 70E Standard for Electrical Safety in the Workplace (2015)

• ACGIH Threshold Limit Values (TLV’s) (2016)

• ANSI B30 Series – Crane Safety

• DOE-STD-1090-2020 Hoisting and Rigging

• DOE-STD-1212-2019, Explosive Safety

• DOE 451.1B NEPA Compliance Program

• 10 CFR 40 CFR (Environmental)

• 10 CFR 49 (DOT)

• 35 IAC Illinois Environnemental Protection (Illinois EPA)

• International Building Code (IBC)

• Rules of the Division of Motor Services, Illinois

Subcontractor Site Specific ESH Plan Elements

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference35

• Subcontractors to develop, implement & enforce their approved Site Specific ESH Plan

• Site Specific ESH Plan to contain relevant elements from LBNF/DUNE NSCF Construction ESH Plan

- ESH Policy and expectations

• General Rules of Conduct

• ESH Compliance & Enforcement

- Subcontractor requirements (not a complete list)

• Job site orientation

• Training

• Work Planning & Controls (build plan/hazard analysis)

• Daily work planning meetings

• Personal Protective Equipment

• Fall Protection

• Aerial lifts

• Material handing

• Electrical safety

• ESH inspection (Internal & External)

• Emergency/incident reporting

• Site Specific ESH Plan reviewed and approved prior to start of work

• ESH expectations to be flowed down to sub-tier subcontractors

ESH Performance & Program Evaluation Criteria

• Submit the Fermilab Subcontractor Safety Questionnaire

- Past Corporate Performance regarding ESH

• Offer’s safety statistics reviewed & evaluated

- OSHA incident rates (3 yr. history)

- Insurance Experience Modification Rate (EMR) (3 yr. history)

- Support documentation OSHA 300/NCCI Workers

Compensation Experience Rating forms

• Corporate ESH Manual for reviewed

- ESH Evaluation Criteria

• EMR less than 1.0

• ESH Manager/Representative on site during all shifts

- Minimum experience

• OSHA 30 Hour training

• Fifteen (15) years (preferred) of demonstrated ESH experience

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference36

Work Planning & Controls

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference37

• Activity based Build Plan & Job Hazard Analysis (JHA) documentation

- Reviewed through a web-based document management system

• LBNF/DUNE ESH and Construction Coordinators

- Preparatory meetings to release the work activity

• FRA Field assurance and verification of work planning execution

• Safety Data Sheets (SDS)

- Reviewed by Near Site ESH Coordinator

• Permits (Coordinated through LBNF NSCF Construction Coordinator)

- Burn (welding, spark producing, hot work)

- Electrical Work Permit

- Excavation Permit (Fermilab provides utility locating, GC must give 14 working days advance notice to LBNF NS Construction Coordinator)

- Existing structure and concrete cutting or coring

- Fire Protection System Disablement Tags

- Potable and DWS plumbing modifications

- Subcontractor’s Confined Space Entry Permit (notification to Fire

Department)

• Daily Work Planning Meetings

Daily Work Planning

• Daily Work Planning Meetings

- Meeting held at the beginning of shift

- Attended by all subcontractor personnel onsite that day

- Meeting led by supervision

- Duration of the meeting approximately 10-15 minutes at minimum

- Supervisors to discuss work activities & locations for that day along with a summary of hazards

- Discuss deliveries of equipment & materials to the site

- ESH representative to discuss any ESH issues & reinforcing ESH program

- Reminding work force to follow their work planning documents & update as needed

- Feedback from work force

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference38

Personnel Protective Equipment Requirements

• Hard hats – shall meet the ANSI Z89.1 & high voltage electrical work shall meet ANSI Z89.2. Hard hats Type 2 should be marked with the appropriate designation

• Safety glasses with side shields – shall meet ANSI Z87.1

• High visibility reflective garment – minimum ANSI Class 2

• Suitable work clothing – minimum shall be short-sleeved (1/4 length) shirt, long trousers, & safety toes boots providing ankle protection meeting ANSI Z41

• Hand Protection – Cut Level 4 resistant glove

• No canvas, tennis, or deck shoes permitted in construction subcontract work area

• Underground Activities

- Cap lamp with battery & charging station

- Self-rescuer

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference39

ESH Training Requirement

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference40

• Provided by Fermilab to the CMa and other subcontractor personnel

- Fermilab Subcontractor Orientation (Video, 30 minutes)

- Fermilab General Employee Radiation Training (GERT) (Video and quiz, 30 minutes)

- These are offered every workday morning starting promptly at 07:30

- Fermilab badges will be issued after personnel complete these classes.

- All personnel working within the Main Injector Shield Zone Area (30 ft. from MI enclosure) required to receive a site-specific Radiological Worker training (1 hour)

- Personnel working in the MI tunnel will receive Fermilab Radiation Worker and LOTO 2 training (12 hours)

• Provided by Subcontractors

- Site Specific ESH Orientation

- Verification of completion of OSHA required training

• Competent training for excavation, scaffold, 30-hour OSHA

• Task specific training (LOTO, NFPA-70E, equipment operator, fall protection, respirator)

• Training & certification records available on-site

Fermilab Site Access

• All personnel accessing the site will be required to apply for a Fermilab badge

• Personnel accessing the site must be REAL ID compliant

• Workers will need to complete the Fermilab Site Access Request form

- Subcontractor workers will receive Fermilab ID number and a physical ID

Badge for site access

- Badging is coordinate by the Fermilab’s Security Emergency

Management Division (SEMD)

- Need to complete the forms Site Access Requests prior to coming on-site

• Domestic requests take approximately five working days for approval

• Foreign national requests can take up to 10 working days

• All documentation needs to be fully completed for process to be completed

• All non-badged delivery drivers will need to be fully escorted

• Fermilab site access process details

- https://get-connected.fnal.gov/accessandbadging/access/

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference41 https://fermi.servicenowservices.com/expert_shell.do?sysparm_sys_id=63f9f6a8dbd148104e65ff621f961975 https://get-connected.fnal.gov/accessandbadging/access/

Environmental

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference42

• Environmental Assessment and FONSI completed September 25, 2015

- Environmental reviews by Fermilab & DOE-FSO NEPA

Compliance Officers

• Areas of Significance:

- Good Neighbor (noise/vibration, dust, lighting, traffic/parking, security)

- Keep the air and water clean (spills & runoff)

• Environmental plan

- Spill Prevention Control and Countermeasures (SPCC)

- National Pollutant Discharge Elimination System (NPDES)

- Sustainability/recycling of waste materials

- Coordination with LBNF/DUNE ESH Coordinator

Joint Project Office ESH Staffing

LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference43

• Experienced in construction and beamline support

• Near Site ESH Coordinator

• Daily ESH field support/oversight

• ESH POC for subcontractor activities

• LBNF /DUNE ESH Manager & DUNE ESH Coordinator providing supplemental support & oversight

• FNAL ESH Division matrix support

- Radiation Safety - Fire/Life Safety – Industrial Hygiene

04.10.2024

Project ESH Oversight

• Subcontractor ESH Oversight on all shifts

- Daily ESH program oversight by the Project Manager, ESH Manager, Superintendents, &

Foremen

- Verify flow down of ESH requirements to sub tier subcontractors

• LBNF/DUNE Project Daily Oversight

- ESH Coordinators

• ESH general coordination & assurance site visits to verify work planning implementation

• External walkthroughs

- Department of Energy Fermi Site Office

- Fermilab ESH Division

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference44

Quality

Kevin Fahey LBNF/DUNE-US Quality Assurance Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference45

Quality Assurance, Control and Management

• The LBNF DUNE Quality Assurance (QA) Plan establishes principles, requirements, practices, and methods for integrating quality into the LBNF/DUNE Projects and outlines the QA requirements for all the Project Partners, encompassing all the activities performed by or for the Projects.

• The Construction Quality Management (CQM) Program assigns the responsibilities for the management of quality on the LBNF major construction activities for the Near Site Conventional Facilities (NSCF).

• Quality Control (QC) is the implementation of measures for controlling variations in processes, procedures, constructed items, etc., to within the acceptable limits, as set by LBNF requirements.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference46

Construction Quality Management Program

• Purpose and Scope

- Based on the US Army Corps of Engineers Construction Quality Management Program

- To provide principles to encourage a mutual effort on the part of the Subcontractors and the LBNF Project to produce a quality project, on time and in accordance with the requirements of the contract, specifications and drawings.

- The complete Construction Management Program is composed of the Subcontractor’s Quality Control Programs, the LBNF/DUNE QA Plan, LBNF Construction Quality Management Program.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference47

Construction Quality Management Program

• The CQM Program pertains to all LBNF Subcontractors and their Subcontractors (the latter being sub-subcontractors with respect to LBNF).

• CMa is responsible for QA, whereas the Construction Subcontractor is responsible for QC.

LBNF will perform oversight of both parties. Construction Quality Management (CQM) is the coordination of both the QA and QC portions and pertains solely to construction activities.

• CMa will have oversight of the Construction Subcontractor QC Program in order to ensure that the construction work conforms to specifications and drawings associated with the contract construction requirements.

• The Quality Control/Quality Assurance requirements specific to the Subcontractors will be incorporated into the applicable contracts and will meet the requirements provided in LBNF Construction Quality Management addendum.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference48

Three Phases of Control – Preparatory Phase

• Definable Features Of Work (DFOW) – Separate and distinct tasks of the work scope.

• The preparatory phase takes place prior to beginning work on each DFOW, and consists in large part in planning, procuring materials and discussions.

• The Subcontractor is required to notify LBNF NSCF-PM three days prior to the start of the preparatory phase for each DFOW.

• This phase shall include a meeting conducted by the QC Manager and attended by the QC specialists, the superintendent, and the foreman responsible for the DFOW.

• The results of all preparatory phase actions must be documented in the Preparatory Phase

Checklist.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference49

Three Phases of Control – Preparatory Phase

• Agenda

- Review each paragraph of the applicable specification sections in the Contract;

- Review the Contract drawings;

- Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and accepted;

- Review the testing plan and ensure that provisions have been made for the required QC testing;

- Plan and identify potential problems for each DFOW, and discuss the approach to adopt in order to provide quality construction;

- Discuss construction methods, construction tolerances, workmanship standards;

- Review the safety plan and appropriate activity hazard analysis to ensure that applicable safety requirements are met, and that required Safety Data Sheets (SDS) are submitted.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference50

Three Phases of Control – Initial Phase

• The Initial Phase follows the Preparatory Phase when construction crews are ready to start work.

• This phase is intended to clearly capture and anticipate how the Subcontractor’s team will integrate quality and safety into construction and to determine clear communication channels for conveying information to the crews conducting the work.

• It must be repeated for each new crew, and when specified levels of quality are not being met by an existing crew.

• The Subcontractor is required to notify LBNF NSCF-CM at least two workdays prior to the start of the Initial phase for each DFOW.

• The QC Manager conducts the initial phase with the QC Specialists, the superintendent, the foreman and the crews responsible for that definable feature of work.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference51

Three Phases of Control – Initial Phase

• The QC Manager observes the initial segment of the definable feature of work to ensure that the work complies with Contract requirements.

• The results of all initial phase actions must be documented in the Initial Phase Checklist.

• Establish with the work crew the quality of workmanship;

• Resolve conflicts.

• Check work procedures for compliance with the Safety Plan and the appropriate activity hazard analysis to ensure that applicable safety requirements are met.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference52

Three Phases of Control – Follow-Up Phase

• Follow-up phase activities are performed daily, or more frequently as necessary, on each in-progress DFOW, according to the schedule until the DFOW is complete and documented as such in the daily QC Report.

- Ensure the work for each activity is in compliance with Contract requirements;

- Maintain the required quality of workmanship;

- Ensure that testing is performed;

- Ensure that rework items are being corrected;

- Perform safety inspections.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference53

Project Reporting - Daily Reports

• Subcontractors are required to develop and provide a daily Subcontractor Production and Quality Control Report to the LBNF Project.

ー These reports are the daily record of operations on the job site.

ー This series of reports is intended to fully document the work, any test results, dimensional checks, equipment and material checks.

ー The report is to address the progress and issues with the Quality Control Program as it proceeds on the project site.

ー Space is designated for documenting actions on all three phases of control, as well as rework.

ー Documenting the controls for any “follow-up” phase work is of particular importance.

ー The report must include a certification by the QC Manager that the work is in compliance with the contract, except as noted in the report.

ー The QC portion of the report will include the reports from each sub-subcontractor working on the site.

ー Entries on the report(s) must be tied to the schedule.

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference54

Scope of Construction

Frank Louis Project Manager, AECOM (A/E-of-Record)

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference55

Scope of Construction – Definition of Work Breakdown Structure (WBS)

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference56

BEAMLINE

COMPLEX

6-15-11

NEAR DETECTOR

COMPLEX

6-15-12

WBS BREAKDOWN

BC - BEAMLINE COMPLEX

NDC - NEAR DETECTOR COMPLEX

SW – SITE WORK

EE – EXTRACTION ENCLOSURE

PBE – PRIMARY BEAM ENCLOSURE

PBSB – PRIMARY BEAM SERVICE BUILDING (LBNF 5)

TC – TARGER COMPLEX (LBNF 20)

DK – DECAY REGION

AH – ABSORBER HALL

ASB – ABSORBER SERVCE BUILDING (LBNF 30)

ND – NEAR DETECTOR

NDSB – NEAR DETECTOR SERVICE BUILDING

Scope of Construction – Site Works Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference57

• Beamline Complex

- Wetland protection & restoration

- Earth Retention/Soil

Stabilization

- Major excavation and dewatering

- Rock Blasting

- Structure movement and settlement monitoring

- Compaction and settlement control

Beamline Complex

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference58

• Extraction Enclosure (EE)

• Primary Beam Enclosure

(PBE)

• Primary Beam Service

Building (PBSB)

(LBNF-5)

• Target Complex (TC)

(LBNF-20)

• Decay Region (DK)

• Absorber Complex (AC)

(LBNF-30)

- Absorber Service

Building (ASB)

- Absorber Hall (AH)

EE

PBSBPBETCDK

AC

Scope of Construction – Extraction Enclosure Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference59

• Tie-in to existing Main Injector (MI)

- Specialty timing of work

- Installation of ERS

- Excavation of active soil and steel

- Openings in north wall of MI

- Monitoring of movement of MI and earthwork shielding

EXISTING MI-14

PROPOSED ERS

EXISTING MI

BEAMLINE

MIN. EARTHWORK

SHIELDING

Scope of Construction – Extraction Enclosure Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference60

• Coordination of MI-14

- Utilities will need to tie-in to MI-14 and be sequenced with ERS

- Inclinometer and tiltmeter monitoring

(including at BNB Enclosure)

• Specialty QA/QC

- Alignment of EE with Beamline

- Monitoring of ERS movements

- Monitoring of MI and portion of new

EE tunnel via survey points and crack monitors

EXISTING MI-14

Scope of Construction – Primary Beam Enclosure Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference61

• WBS Connections

- Extraction Enclosure

- Major Vehicle/Primary

Beam Service Building

- Target Complex

• Coordination with future Beamline systems and equipment

• Monitoring of survey points and cracks

PRIMARY BEAM ENCLOSRE

Scope of Construction – Primary Beam Enclosure Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference62

• Coordination with and Protection of Indian Creek Culvert and Duct Bank

- Drilled shaft clearances

- Bridging over culvert

• Specialty QA/QC

- Alignment and settlement of PBE with Beamline points

- Inclinometer monitoring

- Movement monitoring of

Main Injector

- Earthwork and compaction testing

- Drilled shaft testing INDIAN CREEK

CULVERT

EXISTING CONC.

DUCTBANK

Scope of Construction – Primary Beam Service Building

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference63

• Indian Creek Culvert

- Coordination with existing culvert with concrete apron, utility yard, and future U/G utilities

• PBE Berm

- Coordinate Major

Vehicle Access and south of PBE with berm.

• Owner Provided Equipment

- Coordinate OPE with subcontractor provided equipment and connection

Scope of Construction – Target Complex Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference64

• WBS Coordination

- Upstream PBE connection

- Downstream DK connection with

ERS

DK REGION

PRIMARY BEAM

ENCLOSURE

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference65

• Shielding and Rad Safety Requirements

- Concrete and steel shielding

- Owner-provided shielding steel

• Technical Requirements

- Target Bunker pressure vessel

- Construction materials not permitted

- Air seals and over-pressurized air volume strategy

- Snout and connection to DK Vessel

- Cranes

DK REGION

DK VESSEL

AND SNOUT

BEAMLINE

TARGET HALL

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference66

• Specialty Mechanical Systems

- Nitrogen Handling Units

- Tritium Evaporation

System

- Upstream end of Decay

Region pressure vessels

NHU-1 AND

NHU-2

DECAY REGION TARGET COMPLEX

NITROGEN

DUCTING

DECAY REGION

SNOUT

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference67

• Specialty QA/QC

- NHU-1 and 2

- Pressure vessels and pressure vessel welds

- Drilled shaft integrity testing

- Earthwork and Compaction

Testing

DECAY REGION TARGET COMPLEX

NITROGEN

DUCTING

DECAY REGION

SNOUT

Scope of Construction – Decay Region Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference68

• WBS Coordination

- Target Complex

- Absorber Hall

• Continuity of Pressure Vessels

• Excavation into Rock

- Changes to foundation systems

- ERS needed

- Extensive dewatering system needed for open-cut excavation

- Grout curtain

- Rock bolting

PRESSURE

VESSEL

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference69

• Mass Concrete

- Staggering of joints and construction joint details

• Slide Bearing Plates

- Bottom Rails

- Side Braces

MASS

CONCRETE

POURS

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference70

• Air Seal between DK and AH

- Requires special connections

- Air tests required

• Specialty QA/QC

- Drilled shaft testing

- Mass concrete

- Helium and Nitrogen Pressure Vessels

- Beamline survey

- Air Seal Installation

Scope of Construction – Absorber Hall Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference71

• WBS Coordination

- Tie-in with DK, air seal, pressure vessel, and dewatering system

- Supports Absorber Service Building (above at grade)

• Absorber construction

• Implementation of Muon

Kern shielding steel

- Owner-provided shielding steel

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference72

• Waterproofing and descaling system

• Excavation into Rock

- Extensive dewatering system needed for open-cut excavation (in conjunction with DK)

- Grout curtain

- Rock bolting

- Cross-trench bracing

• Extensive dewatering (in conjunction with DK)

• Specialty QA/QC

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference73

• Specialty QA/QC

- AH Waterproofing

- Geosynthetic system

- Backfill

Scope of Construction – Absorber Service Building Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference74

• WBS Coordination

- At grade extension of the Absorber Hall, vertical transportation and MEP systems

Scope of Construction – Absorber Service Building Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference75

• Coordination of Beamline and Conventional Facilities equipment

- Space has been reserved within plans for Beamline equipment

• Backfill settlement around

ASB

• OPAV installation

Near Detector Complex

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference76

• Near Detector Service Building (LBNF-40)

• Near Detector Hall

- Looks and feels like a

CSO pump station

NDC

Scope of Construction – Site Works Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference77

• Near Detector Complex

- Noise, light, & vibration monitoring

- Dewatering

Scope of Construction – Near Detector Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference78

• WBS Coordination

- Integrates with Near Detector

Service Building

- Permanent utilities delivered to

NDC by BC subcontractor

• Earth and Rock Excavation

- Requires blasting

- Must monitor noise impacts and comply with local ordinances, consider as part of daily excavation activities

- Special worker ventilation requirements

NEAR DETECTOR

CAVERN @

-215’ BELOW GRADE

ACCESS SHAFT

EGRESS SHAFT

NEAR DETECTOR

SERVICE BUILDING

Scope of Construction – Near Detector Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference79

• Rock Support

- Rock bolts and shotcrete

• Extensive MEP Coordination

- Future Cryo Piping has specific support locations

- Mechanical ducting coordinated with crane and supports

- Conventional facilities and beamline equipment at mezzanines

- Sub-slab drainage level and perimeter trench drains

• Prism rail dimensional tolerances

• Specialty QA/QC

• Monitoring of noise, light, & vibration

• Air quality during construction

STEEL RAILS

EMBEDDED INTO SLAB

CLEAR AREA FOR OH

CRANE

COORDINATION OF

DUCTING WITH CRANE

AND SUPPORTS

’-0

Scope of Construction – Near Detector Service Building Specialty Conditions

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference80

• Proximity to Kirk Road and neighbors

- Noise, light, and vibration monitoring and mitigation

- Consideration for times of activities

- Potential noise mitigation measures

• Specialty QA/QC

- As noted above

KIRK ROAD

U/G NEAR DETECTOR

CAVERN

EGRESS SHAFT

NEAR DETECTOR SERVICE

BUILDING

EXTERIOR EQUIPMENT

YARD

Conference Wrap-up

Craig Schmitz Near Site Procurement Manager

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference81

Procurement Closeout

• Questions due in writing by 5:00 p.m. Central Time on April 24, 2024.

• Proposals due by 5:00 p.m. Central Time on May 8, 2024.

• Award anticipated January of 2025.

• Continue to monitor SAM.gov for updates/amendments: Notice ID LBNF-342884-

BWQ.

Questions?

04.10.2024 LBNF/DUNE-US NSCF Team | CMa Pre-Proposal Conference82

CMa Zoom Attendance

Individual Company E-mail Address

Ed Jackson Jacobs ed.jackson@jacobs.com Helen Taaffe PMA Consultants htaaffe@pmaconsultants.com Katheryn Coleman PMA Consultants kcoleman@pmaconsultants.com Peter Vogt Kiewit Infrastructure Co. peter.vogt@kiewit.com Josh Yacknowitz Arup joshua.yacknowitz@arup.com Lamar Sullivan R&M Structures, INC lamars@salesforce4rent.com Norbert Fuegenschuh Beton- und Monierbau USA, Inc norbert.fuegenschuh@bemo.net

CMaPreProposalConference.pdf
CMa Pre-Proposal Conference
Welcome
Presenters
Agenda
Notice to Offerors
Introduction
DUNE at LBNF – An international endeavor hosted by the U.S. D.O.E
DUNE at LBNF – An international endeavor hosted by the U.S. D.O.E
LBNF/DUNE-US Near Site Conventional Facilities (NSCF)
LBNF/DUNE-US Near Site Conventional Facilities (NSCF)
LBNF/DUNE-US Project Organization
Subproject Organization
LBNF/DUNE-US Project Organization
LBNF/DUNE-US Project Organization
Near Site Conventional Facilities (NSCF) Organization
Near Site Conventional Facilities (NSCF) Organization
Procurement
Procurement
Procurement
Procurement
Procurement
Procurement
Procurement
CMa Overview
CMa Overview
CMa Overview – Web Based Project Management System (WBPMS)
CMa Overview – Environmental Baselining/Monitoring
CMa Overview – Pre-Construction Surveys
CMa Overview – Cost & Schedule Management
CMa Overview – Quality Assurance (QA)
Environment, Safety, & Health (ESH)
ESH is Integrated into the LBNF/DUNE Project
Construction Program ESH Expectations
Assist FRA with the Implementation of ESH Requirements
Subcontractor Site Specific ESH Plan Elements
ESH Performance & Program Evaluation Criteria
Work Planning & Controls
Daily Work Planning
Personnel Protective Equipment Requirements
ESH Training Requirement
Fermilab Site Access
Environmental
Joint Project Office ESH Staffing
Project ESH Oversight
Quality
Quality Assurance, Control and Management
Construction Quality Management Program
Construction Quality Management Program
Three Phases of Control – Preparatory Phase
Three Phases of Control – Preparatory Phase
Three Phases of Control – Initial Phase
Three Phases of Control – Initial Phase
Three Phases of Control – Follow-Up Phase
Project Reporting - Daily Reports
Scope of Construction
Scope of Construction – Definition of Work Breakdown Structure (WBS)
Scope of Construction – Site Works Specialty Conditions
Beamline Complex
Scope of Construction – Extraction Enclosure Specialty Conditions
Scope of Construction – Extraction Enclosure Specialty Conditions
Scope of Construction – Primary Beam Enclosure Specialty Conditions
Scope of Construction – Primary Beam Enclosure Specialty Conditions
Scope of Construction – Primary Beam Service Building
Scope of Construction – Target Complex Specialty Conditions
Scope of Construction – Target Complex Specialty Conditions
Scope of Construction – Target Complex Specialty Conditions
Scope of Construction – Target Complex Specialty Conditions
Scope of Construction – Decay Region Specialty Conditions
Scope of Construction – Decay Region Specialty Conditions
Scope of Construction – Decay Region Specialty Conditions
Scope of Construction – Absorber Hall Specialty Conditions
Scope of Construction – Absorber Hall Specialty Conditions
Scope of Construction – Absorber Hall Specialty Conditions
Scope of Construction – Absorber Service Building Specialty Conditions
Scope of Construction – Absorber Service Building Specialty Conditions
Near Detector Complex
Scope of Construction – Site Works Specialty Conditions
Scope of Construction – Near Detector Specialty Conditions
Scope of Construction – Near Detector Specialty Conditions
Scope of Construction – Near Detector Service Building Specialty Conditions
Conference Wrap-up
Procurement Closeout
Backup Slides
LBNF/DUNE-US Project DUNE Collaboration Management
Slide Number 85
Blank Page
Blank Page