This document is an attachment to a Request for Proposal (RFP) for Utilities Privatization at Norfolk Naval Shipyard, specifically for the Electric Utility System. The document provides a detailed example of how to complete Price Data Sheets for a Fixed Price with Economic Price Adjustment (FP-EPA) type contract. It illustrates the methodology for calculating various charges, including Utility Services Charge, Renewals and Replacements (R&R), Initial System Deficiency Corrections, Purchase Price Credit, and Purchase Price Recovery.
The example involves a hypothetical 50-year contract for a wastewater collection system with a $500,000 purchase price. Key calculations include a monthly utility services charge of $10,000 (comprising $7,900 for Operations and Maintenance and $2,099.53 for Renewals and Replacements), an Initial System Deficiency Correction of $125,000 to remedy cross-connections, and a transition period charge of $50,000. The document emphasizes the importance of using consistent interest and discount rates in calculations to ensure proper cost recovery over the contract term. The example serves as a comprehensive guide for potential offerors on how to develop and present pricing information in their proposals.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP0600-25-R-0800 UTILITIES PRIVATIZATION
NORFOLK NAVAL SHIPYARD, VA ELECTRIC UTILITY SYSTEM
i
ATTACHMENT JA40
EXAMPLE FOR FP-EPA TYPE CONTRACTS -
COMPLETION OF PRICE DATA SHEETS
TABLE OF CONTENTS .................................................................................................. i
LIST OF TABLES AND EXHIBITS .............................................................................. ii
EXAMPLE FOR FP-EPA TYPE CONTRACT - COMPLETION OF PRICE DATA
SHEETS
JA40 EXAMPLE
JA40.1 Schedule B-2
JA40.2 Supporting Calculations
JA40.2.1 CLIN 0001 Utility Services Charge Supporting Calculations
JA40.2.1.1 Interest Rate and Discount Rate Should be the Same for R&R Charge Calculation
JA40.2.1.2 R&R Schedule Does Not Impact R&R Cash Balance
JA40.2.2 CLIN 0001 Monthly Credit as Payment for Purchase Price Supporting Calculations
JA40.2.3 CLINS 0002 and 0003 Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period
JA40.2.3.1 CLIN 0002 Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) Supporting Calculation
JA40.2.3.2 CLIN 0003 Transition Period
JA40.2.4 CLIN 0001 Recoverable Portion of the Purchase Price Supporting Calculation ii
LIST OF TABLES AND EXHIBITS
TABLE JA40-1: Wastewater System Inventory
TABLE JA40-2: Recognized System Deficiencies
TABLE JA40.1-1: Schedule B-2 Fixed Price Economic Price Adjustment
TABLE JA40.2.1-1: Part 1: Price Data Sheet 2, Renewals and Replacements – 50-Year Plan
TABLE JA40.2.1-1: Part 2: Price Data Sheet 2, Renewals and Replacements – 50-Year Plan
EXHIBIT JA40.2.1-1: Renewals and Replacements Investment by Year
TABLE JA40.2.1-2: Calculation of Annual / Monthly R&R
EXHIBIT JA40.2.1-2: Income and Cost Forecast by Year
TABLE JA40.2.1-3: Price Data Sheet 1, Utility Services Charge
EXHIBIT JA40.2.1.1-1: Cash Balance for Different Interest and Discount Rates
TABLE JA40.2.1.2-1: R&R Investment for Distributed, Front-end Loaded, and Back-end Loaded Schedules
EXHIBIT JA40.2.1.2-1: R&R Cash Balance for Distributed, Front-end Loaded, and Back-end Loaded R&R Schedules
TABLE JA40.2.2-1: Calculation of Annual / Monthly Purchase Price Credit
TABLE JA40.2.3.1-1: Calculation of Annual / Monthly ISDC Charge
TABLE JA40.2.3.2-1: Price Data Sheet 3, Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period
TABLE JA40.2.4-1: Calculation of Annual / Monthly Purchase Price Recovery Charge 19
TABLE JA40.2.4-2: Price Data Sheet 4, Recoverable Portion of Purchase Price
J40-1
ATTACHMENT JA40
EXAMPLE FOR FP-EPA TYPE CONTRACT -
COMPLETION OF PRICE DATA SHEETS
The objective of this document is to illustrate through examples how to complete the required Schedule B-2 and Price Data Sheets in the request for proposal (RFP) for Fixed Price with Economic Price Adjustment (FP-EPA) type contracts. These examples cover Schedule B-2, Fixed Price Economic Price Adjustment; Price Data Sheet 1, Utility Services Charge; Price Data Sheet 2, Renewals and Replacements – 50-Year Plan; Price Data Sheet 3, Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period;
and Price Data Sheet 4, Recoverable Portion of Purchase Price. Price Data Sheet 6, Proposal – 50-Year Charges to the Government, is also a required submittal in an FP-EPA proposal; it is not discussed in this document.
Offerors1 proposing a FP-EPA contract must prepare their Schedule B-2 and Price Data Sheets in accordance with the methodology set forth in this Section.
Proposed Operations and Maintenance (O&M) and Renewals and Replacements (R&R) charges should be in first contract year dollars (real or constant dollars), and in the future years these prices will be adjusted for inflation based on the agreed-to EPA clause in the contract. The interest rate used to calculate the R&R prices should not include inflation; the prices will be adjusted for inflation based on the agreed-to EPA clause in the contract.
All proposals utilizing Schedule B-2 must develop a residual value (RV) as described herein and must remove that RV amount from the total amount used to calculate the proposed R&R annual / monthly prices.
The Contractor will fund all capital investments (R&R, Initial System Deficiency Corrections (ISDC), etc.). The capital investments are recovered from the Government through the proposed R&R and ISDC charges.
The ISDC charge(s), Connection charge(s), Transition charge, Purchase Price Recovery charge and Purchase Price credit are proposed in nominal dollars (current dollars, including inflation). These nominal dollar charges and credits are not adjusted through the EPA process. The monthly charges (Purchase Price Credit, Purchase Price Recovery, ISDC(s), and Service Charge for R&R) should be calculated utilizing the Contractor’s cost of capital rate (amortization interest rate). The ISDC charges may be proposed as a one-time charge or, if required by the solicitation/contract, amortized over a minimum amortization schedule. The interest rates used to calculate the ISDC charges should include inflation; ISDC charges will not be adjusted for inflation in the EPA process.
Each ISDC charge will be effective after its capital investment project is completed and placed into useful service.
1 The terms Offeror and Contractor are used somewhat interchangeably, but are intended to be the same entity, e.g., defined as the Offeror prior to contract award and as the Contractor after contract award.
J40-2
This J40 is intended to demonstrate to Offerors how to complete detailed assumptions and calculations and formulate a Schedule B-2 and applicable Price Data Sheets. Any proposal utilizing Schedule B-2 must include discussion of the following items in initial and final proposal revisions:
1. All assumptions used to develop a sufficient cash flow for both R&R and O&M.
2. Details of prices including profit level and mark-ups used in development of the O&M charges and capital investments (R&R, ISDC, etc.).
3. Offeror’s approach to correct Government-identified deficiencies (as an ISDC project, R&R project, and/or O&M task).
4. Details of proposed cost of capital rate development. Provide details of the mix of borrowing rate, expected equity (shares and bonds) rate, etc., that comprise the proposed cost of capital rate.
5. The Purchase Price Credit is expected to be equal to the Purchase Price Recovery Charge and offset each other. The Offeror should explain if they are different and do not offset each other.
The following example is for illustration purposes only and should not be taken as representative of any DoD utility system. Similarly, the values used, or assumptions presented herein are hypothetical and Offerors should not place any specific significance on them as part of the preparation of its actual proposal(s).
JA40 EXAMPLE
The Government is considering privatization of a wastewater collection system at one of its installations. It plans to complete the privatization procurement process in year 2022, resulting in a 50-year contract for utility services. The Government has issued an RFP that, among other things, requires Offerors submitting an FP-EPA proposal to complete Schedule B-2 presented in Section B. of the RFP and Price Data Sheets 1, 2, 3, and 4 and 6 presented in Section B of the RFP. The Government’s inventory of the wastewater system is shown in Table JA40-1.
J40-3
TABLE JA40-1: Wastewater System Inventory Utilities Privatization
Component / Item Size Quantity Unit Approximate Year of Installation
Concrete Pipe 4-in. 2,000 LF 1972
Concrete Pipe 12-in. 2,000 LF 1972
Concrete Pipe 24-in. 1,000 LF 1972
CI Pipe 4-in. 1,000 LF 1985
CI Pipe 12-in. 4,000 LF 1985
PVC Pipe 4-in. 3,000 LF 2000
PVC Pipe 12-in. 8,000 LF 2000
PVC Pipe 24-in. 4,000 LF 2000
PVC Pipe 4-in. 3,000 LF 2015
PVC Pipe 12-in. 8,000 LF 2015
PVC Pipe 24-in. 4,000 LF 2015
Manhole 20 EA 1975
Manhole 10 EA 1985
Manhole 30 EA 2000
Manhole 30 EA 2015
Lift Station #1 1 EA 1985
Lift Station #2 1 EA 2000
Lift Station #3 1 EA 2015
In addition to the inventory, the RFP lists the Government-recognized system deficiencies and may include the approach the Government would take to remedy them if the system is not privatized. Table JA40-2 is an example of the Government-recognized system deficiencies.
J40-4
TABLE JA40-2: Recognized System Deficiencies Utilities Privatization
System Component Recognized Deficiencies and the Government’s Approach to Remedy
Year to be Completed
Collection System The system has excessive infiltration and inflow (I&I) Within two years after contract start date
Lift Station #2 Lift Station #2 is prone to frequent overflows of sewage into the street; may be inappropriately sized
Within two years after contract start date
Table Notes: Deficiencies may be corrected by the Offeror as an ISDC project, R&R project, and/or O&M task.
JA40.1 Schedule B-2 Schedule B-2 is prepared based on the amortized purchase price credit and the data presented in Price Data Sheet 1, Utility Services Charge, Price Data Sheet 2, Renewals and Replacements – 50-Year Schedule, and Price Data Sheet 4, Recoverable Portion of Purchase Price. Projects shown in Price Data Sheet 3, Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period, are not included in the totals shown in Schedule B-2 but are added to the monthly charge in accordance with the amortization schedule for each ISDC, upgrade, or connection project. The completed Schedule B-2 is presented in Table JA40.1-1.
J40-5
TABLE JA40.1-1: Schedule B-2 Fixed Price Economic Price Adjustment Utilities Privatization
Utility System a: ________________
CLIN Supplies/Services Qty Unit Unit Price Total
0001 Utility Services Charge 12 Months $10,000.00 $120,000.00
FPEPA
The unit price is the Utility Services Charge less the monthly credit as payment for the purchase price (PP) plus the recoverable portion of the purchase price.
Utility Services Charge b $ 10,000.00
Monthly Credit for PP c $ (3,476.29)
# of Months 180
Annual Interest Rate 3.16%
Recoverable Portion of PP c $ 3,476.29
# of Months 180
Annual Interest Rate 3.16%
Unit Price $ 10,000.00
0002 Initial System Deficiency Correction(s)/
Upgrade(s)/Connection Charge(s) d 60 Months $2,235.85 $134,150.90
FFP
0003 Transition Period d 1 Each $50,000.00 $50,000.00
FFP
a Utility system to be filled in by the Offeror. A Schedule B-2 must be completed for each utility system offered.
Utility systems are shown in paragraph B.1, Systems to be Privatized.
b The offeror should enter the Utility Services Charge, as computed in Price Data Sheet 1.
c The offeror should enter the Credit for PP, as computed utilizing JA40.2.2, and the Recoverable Portion of PP, as computed in Price Data Sheet 4.
d The offeror should enter the Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period, as computed in Price Data Sheet 3.
J40-6
JA40.2 Supporting Calculations The following sections describe the calculations used to determine the values for CLINs 0001, 0002, and 0003 in Schedule B-2.
JA40.2.1 CLIN 0001 Utility Services Charge Supporting Calculations The Utility Services Charge (CLIN 0001) is comprised of the Utility Services Charge (O&M and R&R), Monthly Credit for PP, and Recoverable Portion of PP. Based on the Offeror’s assessment of the requirements in the RFP, its evaluation of the system, and its experience with wastewater systems, the Offeror determines the utility services charge for O&M to be $7,900.2 This amount includes all costs for operations, maintenance, repair, and associated administration and general costs.
The utility services charge for R&R is developed starting with the example Price Data Sheet 2 developed by the Offeror shown in Table JA40.2.1-1: Part 1. R&R project costs are entered into Price Data Sheet 2 in first contract year dollars (constant 2022 $). The proposed service life is based on the Offeror’s experience regarding a component’s useful (design) life. The Offeror should calculate its present value using its proposed real discount rate (without inflation) and middle of the year discounting convention. The discount rate is the Offeror’s time value of money or cost of capital rate. The residual value is the unrecovered investment in the utility system remaining at the end of the contract term. It is calculated based on the remaining service life at the end of the contract term (% of Service Life remaining x R&R Project Cost). The present value of the cumulative residual value is subtracted from the cumulative present value of R&R project costs to determine the total present value of the R&R investment recovered during the current contract. The Government recognizes the residual value as a Government liability representing the Contractor’s unrecovered investment in the utility system. The residual value would be part of the subsequent contract term for utility services (after the 50-year term), or the Contractor would be duly compensated if the contract is not renewed.
Please note: The description of R&R must be specific enough to identify the exact component/item from the inventory listing. As shown in Table JA40.2.1-1: Part 1 and Part 2, the following must be clearly listed:
- The inventory item undergoing R&R, including component/item, size, quantity, and installation date.
- The type of replacement component/item if different from the original inventory item (e.g., if steel pipe is being replaced by PVC).
- The lifespan and expected replacement date(s) for the inventory line item and its replacement.
- The unit cost for the inventory item and its replacement if different.
2 Demonstrating how to develop the monthly charge for O&M is beyond the intent of this guidance document.
J40-7
- The impact of any Initial System Deficiency Correction(s) / Connection Charge(s) projects on the R&R schedule.
- The residual value for each inventory item (or respective replacement) at the end of the contract period. If a specific inventory item does not undergo R&R, there is no residual value for it.
COMPETITIVE RFP TEMPLATE UTILITIES PRIVATIZATION
J40-8
TABLE JA40.2.1-1: Part 1: Price Data Sheet 2, Renewals and Replacements – 50-Year Plan
A B C D E F G H I J K L M
Item Size Quant Unit Approx.
Year Installed
Existing Unit RCN
Existing Item
Service Life
First Expected Replace
Date
New Item
New Item
Service Life
New Unit Cost
RCN
New Item
RCN
Next Replace
Dates
Row 1 Concrete Pipe 4-in. 2,000 LF 1972 $15 50 2022 PVC 50 $10 $20,000 2072 Row 2 Concrete Pipe 12-in. 2,000 LF 1972 $20 50 2022 PVC 50 $20 $40,000 2072 Row 3 Concrete Pipe 24-in. 1,000 LF 1972 $60 50 2022 PVC 50 $50 $50,000 2072 Row 4 CI Pipe 4-in. 1,000 LF 1985 $25 50 2035 PVC 50 $10 $10,000 2085 Row 5 CI Pipe 12-in. 4,000 LF 1985 $100 50 2035 PVC 50 $20 $80,000 2085 Row 6 PVC Pipe 4-in. 3,000 LF 2000 $10 50 2050 same 50 $10 $30,000 2100 Row 7 PVC Pipe 12-in. 8,000 LF 2000 $20 50 2050 same 50 $20 $160,00
Row 8 PVC Pipe 24-in. 4,000 LF 2000 $50 50 2050 same 50 $50 $200,00
Row 9 PVC Pipe 4-in. 3,000 LF 2015 $10 50 2065 same 50 $10 $30,000 2115 Row 10 PVC Pipe 12-in. 8,000 LF 2015 $20 50 2065 same 50 $20 $160,00
Row 11 PVC Pipe 24-in. 4,000 LF 2015 $50 50 2065 same 50 $50 $200,00
Row 12 Manhole 20 EA 1975 $3,500 60 2035 same 60 $3,500 $70,000 2095 Row 13 Manhole 10 EA 1985 $3,500 60 2045 same 60 $3,500 $35,000 2105 Row 14 Manhole 30 EA 2000 $3,500 60 2060 same 60 $3,500 $105,00
Row 15 Manhole 30 EA 2015 $3,500 60 2075 same 60 $3,500 $105,00
Row 16 Lift Station #1 1 EA 1985 $25,000 50 2035 same 50 $25,000 $25,000 2085 Row 17 LS Controls #1 1 EA 1985 $50,000 20 2022 same 20 $50,000 $50,000 2042, 2062 Row 18 Lift Station #2 1 EA 2000 $25,000 50 2022* same 50 $25,000 $25,000 2072 Row 19 LS Controls #2 1 EA 2000 $50,000 20 2022 same 20 $50,000 $50,000 2042, 2062 Row 20 Lift Station #3 1 EA 2015 $25,000 50 2065 same 50 $25,000 $25,000 2115 Row 21 LS Controls #3 1 EA 2015 $50,000 20 2035 same 20 $50,000 $50,000 2055
This table represents a sample R&R plan. For display purposes, the R&R table is split into two parts. The first part shows the inventory items, the associated costs, and the respective replacement costs of the replacement items, if different from the original. The second part shown in Table JA40-3 Part 2, shows the annual cost breakouts. Impacts of Initial System Deficiency Correction(s) / Connection Charge(s) projects on inventory must be accounted for in the R&R plan.
• Columns A-E: Lists the original inventory description
• Columns F: Details the Replacement Cost New (RCN) unit cost at the component/item level
• Column G: Lists the service/design life of the existing component/item; number of years the item is expected to be in service
• Column H: Lists the first expected replacement date. Replacement Date = Approximate Year Installed + Service Life
• Column I-J: Describes the new replacement component/item and the new replacement component’s service life
• Columns K-L: Details the unit cost of the new replacement component/item and total RCN cost
• Column M: Lists the next expected R&R dates during the 50-years. Replacement Date = Replacement Date(s) + Service Life
• *Cell H18: Per Table JA40-2 Lift Station #2 is listed as a deficiency. Contractor chose to replace LS #2 via R&R in first year.
COMPETITIVE RFP TEMPLATE UTILITIES PRIVATIZATION
J40-9
TABLE JA40.2.1-1: Part 2: Price Data Sheet 2, Renewals and Replacements – 50-Year Plan
A B N O P Q R S T U V W X
Item Size
Planned Renewals & Replacement: Year 1, Year XX, Year 50 Cumulative
Total
Residual Value in Year 50
(Const $)
Const $ Year 1
Const $ Year 14
Const $ Year 21
Const $ Year 24
Const $ Year 29
Const $ Year 34
Const $ Year 39
Const $ Year 41
Const $ Year 44
Row 1 Concrete Pipe 4-in. $20,000 $20,000 $400 Row 2 Concrete Pipe 12-in. $40,000 $40,000 $800 Row 3 Concrete Pipe 24-in. $50,000 $50,000 $1,000 Row 4 CI Pipe 4-in. $10,000 $10,000 $2,800 Row 5 CI Pipe 12-in. $80,000 $80,000 $22,400 Row 6 PVC Pipe 4-in. $30,000 $30,000 $17,400 Row 7 PVC Pipe 12-in. $160,000 $160,000 $92,800 Row 8 PVC Pipe 24-in. $200,000 $200,000 $116,000 Row 9 PVC Pipe 4-in. $30,000 $30,000 $26,400
Row 10 PVC Pipe 12-in. $160,000 $160,000 $140,800 Row 11 PVC Pipe 24-in. $200,000 $200,000 $176,000 Row 12 Manhole $70,000 $70,000 $28,000 Row 13 Manhole $35,000 $35,000 $19,833 Row 14 Manhole $105,000 $105,000 $85,750 Row 15 Manhole $0 $0 Row 16 Lift Station #1 $25,000 $25,000 $7,000 Row 17 LS Controls #1 $50,000 $50,000 $50,000 $150,000 $27,500 Row 18 Lift Station #2* $25,000 $25,000 $500 Row 19 LS Controls #2 $50,000 $50,000 $50,000 $150,000 $27,500 Row 20 Lift Station #3 $25,000 $25,000 $22,000 Row 21 LS Controls #3 $50,000 $50,000 $100,000 $10,000 Row A Total Const $ $235,000 $235,000 $100,000 $35,000 $390,000 $50,000 $105,000 $100,000 $415,000 $1,665,000 $824,883 Row B Present Values $230,992 $147,697 $49,400 $15,594 $146,307 $15,793 $27,925 $24,827 $92,927 $751,462 $150,261
This is the second part of the R&R plan. It shows the annual R&R totals for each inventory line item.
• Columns A-B: Lists original inventory as described in Part 1
• Columns N-V: Corresponds to the year that R&R occurs, and R&R Investment (RRI) in Rows 1-21. RRI amounts are in constant year dollars based on the expected price levels during the first year (2022) of the utilities privatization service contract
• Column W: Totals of R&R Investment amounts of Columns N-V
• Column X: The Residual Value (RV) is the value of the investment, in constant year dollars, at the end of the contract term. RV = The last scheduled RRI (before end of contract) x (Contract Year (CY) of last replacement + Design Life – Contract length) / Design Life.
• Row A: Lists the RRI totals in Constant 2022$ per column (each year)
J40-10
• Row B (shown for example calculations): Present Value of Row A, where Present Value (PV) = RRI x Discount Factor (DF); DF = [ 1 / (1 + I)^(N-0.5) ]. I = the Offeror’s Real (without inflation) Discount or Interest Rate. N is the year of the contract (i.e., 2022 is year one; therefore, (N – 0.5) = (1 – 0.5) = 0.5, in 2023, (N – 0.5) = (2 – 0.5) = 1.5 and so on for middle of the year discounting).
• *Row 18: Per Table JA40-2 Lift Station #2 is listed as a deficiency. Contractor chose to replace LS #2 via R&R in first year.
• Service / Design Life = The number of years the item is expected to be in service
• Contract length = A value of 50 years needs to be used
• Example: Calculation of residual value at contract start based on Row 17 LS Controls
Recent RRI is $50,000, Contract Year of last replacement is year 41, Design life is 20 years, and Contract length is 50 years.
RV = RRI x (Contract Year of last replacement + Design Life – Contract length) / Design Life RV = $50,000 x (41 + 20 – 50) / 20 = $27,500
J40-11
Exhibit JA40.2.1-1 shows the projected R&R investments by year (Row A of Table JA40.2.1- 1(Part 2)). This chart shows a distribution of investments (costs) roughly over the entire 50-year term of the contract.
EXHIBIT JA40.2.1-1: Renewals and Replacements Investment by Year
Calculation of Annual / Monthly R&R: The Offeror must develop a utility services charge for R&R to pay for the investments proposed in Price Data Sheet 2. The Offeror proposes to spend $1,665,000 (in constant year 2022$) on planned R&R over the 50-year contract term, as shown in Table JA40.2.1-1(Part 2). The cumulative present value of R&R investments is $751,462, using the 3.5 percent Real Discount Rate and middle of the year discounting convention. In this example, it is assumed the long-term cost of capital (I) for the Offeror is
3.5 percent. The cumulative residual value at the end of the contract term is $824,883. The present value of the cumulative residual value is $150,261. Therefore, the present value of the Offeror’s total investment in R&R during the contract term is $601,201 ($751,462 - $150,261).
The utility services charge is calculated by amortizing the Present Value of Total Investment in R&R ($601,201) over 600 months, using an interest rate that results in a monthly charge sufficient for the Offeror to recover all its R&R investment costs. It is important that the interest rate (I), used in amortization is the Offeror’s cost of capital, and the Discount Rate (DR), used in calculation of the Discount Factor (DF) for the present value (PV) calculations, must be exactly the same (DR = I) (see Table JA40.2.1-2 for calculation details). If different rates are used, the utility services charge for R&R will be under- or over-collected during the 50-year contract period (see JA40.2.1.1). The timing of R&R investments during the 50 years does not affect the calculated utility services charge for R&R because the PV of R&R investments are used in the charge calculation (see JA40.2.1.2).
J40-12
TABLE JA40.2.1-2: Calculation of Annual / Monthly R&R Utilities Privatization
Calculation Result
Present Value of Proposed R&R Cost (from Price Data Sheet 2) => $751,462
Cumulative Residual Value due to R&R Investments (from Price Data Sheet 2) => $150,261
(PV) Present Value of Total Investment in R&R = 751,462 – 150,201 => $601,201
(N) # Years to Recover R&R Cost => 50
(I) Annual Interest Rate => 3.50%
(A) Annual R&R Charge a => $25,194
(a) Monthly R&R Charge A / 12 => $2,099.53
Table Notes: an Annual R&R Charge calculated as uniform series of 50 annual payments and middle of the year discounting for the first year. A = { PV x [ I x (1 + I) 50 ] / [ (1 + I) 50 – 1 ] } x (1 / (1 + I) (1-0.5))
Exhibit JA40.2.1-2 shows the projected income and cost based on the Offeror’s utility services charge for R&R and Price Data Sheet 2, respectively. The cash balance is the year-to-year cumulative sum of the income (R&R charge) and expense (R&R investment). The chart below shows negative cash balance where costs exceed income and positive cash balance during the few years where income exceeds costs. At the end of the contract the cash balance becomes zero (including the cumulative residual value added to the income), indicating complete recovery of R&R investments with interest.
EXHIBIT JA40.2.1-2: Income and Cost Forecast by Year
J40-13
The Total Utility Services Charge (CLIN 0001) proposed by the Offeror is calculated as demonstrated in the example Price Data Sheet 1 shown in Table JA40.2.1-3.
TABLE JA40.2.1-3: Price Data Sheet 1, Utility Services Charge Utilities Privatization
Component Monthly Charge
1. Operations and Maintenance (O&M) $7,900.47
2. Renewals and Replacements (R&R) $2,099.53
Total Utility Services Charge (to be entered into CLIN 0001 for Schedule B-2)
$10,000.00
JA40.2.1.1 Interest Rate and Discount Rate Should be the Same for R&R Charge Calculation The annual interest rate should be the same as the annual discount rate, and both should be equal to the Offeror’s cost of capital and time value of money rate. If they are different the cash balance will not be zero, indicating the Offeror is under-collecting or over-collecting its R&R investments.
Exhibit JA40.2.1.1-1 illustrates the financial management benefit when the annual discount rate matches the annual interest rate. The following graph shows the cash balances for three different annual interest rates (I = 2.5%, 3.5% and 4.5%; used in amortization) and the annual discount rate (D= 3.5%, used in the calculation of the discount factor (DF) used for present value (PV) calculations). When different interest and discount rates are used for the R&R charge calculation, the contract ending balance is not zero. The Offeror will be under-collecting (blue line), or over-collecting (red line) the R&R charges compared to the R&R investment, and the cash balance will not be zero at the end of the 50-year term.
EXHIBIT JA40.2.1.1-1: Cash Balance for Different Interest and Discount Rates
J40-14
JA40.2.1.2 R&R Schedule Does Not Impact R&R Cash Balance The following illustrates the R&R investment timing during the 50-year contract term does not result in R&R cash imbalance when the annual interest rate is exactly the same as the annual discount rate. Table JA40.2.1.2-1 shows R&R investments scheduled under three scenarios: distributed, front-end loaded, and back-end loaded. Under the distributed scenario, the R&R projects are roughly distributed throughout the 50 years. In the front-end loaded scenario, the majority of the R&R projects are completed in the first half. Under the back-end loaded scenario, the majority of the R&R projects are completed in the second half of the 50-year contract.
TABLE JA40.2.1.2-1: R&R Investment for Distributed, Front-end Loaded, and Back-end Loaded Schedules Utilities Privatization
Year R&R Investments Year R&R Investments Distributed Front-end
Loaded Back-end Loaded Distributed Front-end
Loaded Back-end Loaded
1 $235,000 $700,000 $75,000 26 $0 $0 $0
2 $0 $0 $0 27 $0 $0 $0
3 $0 $0 $0 28 $0 $0 $0
4 $0 $0 $0 29 $0 $0 $0
5 $0 $0 $0 30 $390,000 $30,000 $390,000
6 $0 $0 $0 31 $0 $0 $0
7 $0 $0 $0 32 $0 $0 $0
8 $0 $0 $0 33 $0 $0 $0
9 $0 $0 $0 34 $0 $0 $0
10 $0 $0 $0 35 $50,000 $50,000 $50,000
11 $0 $0 $0 36 $0 $0 $0
12 $0 $0 $0 37 $0 $0 $0
13 $0 $0 $0 38 $0 $0 $0
14 $235,000 $425,000 $75,000 39 $0 $0 $0
15 $0 $0 $0 40 $105,000 $0 $155,000
16 $0 $0 $0 41 $0 $0 $0
17 $0 $0 $0 42 $100,000 $100,000 $50,000
18 $0 $0 $0 43 $0 $0 $0
19 $0 $0 $50,000 44 $0 $0 $0
20 $0 $0 $0 45 $415,000 $225,000 $720,000
21 $100,000 $100,000 $50,000 46 $0 $0 $0
22 $0 $0 $0 47 $0 $0 $0
23 $0 $0 $0 48 $0 $0 $0
24 $35,000 $35,000 $0 49 $0 $0 $0
25 $0 $0 $0 50 $0 $0 $0
J40-15
Exhibit JA40.2.1.2-1 shows the ending cash balance is not affected irrespective of the R&R schedule. Cash balances (R&R Charge (income) + R&R Expense (investment)) are shown for distributed (blue line), front-end loaded (red line), and back-end loaded (green line).
EXHIBIT JA40.2.1.2-1: R&R Cash Balance for Distributed, Front-end Loaded, and Back-end Loaded R&R Schedules
The ending cash balance for the three scenarios is zero, illustrating full recovery of the Contractor’s R&R investments with interest (cost of capital).
JA40.2.2 CLIN 0001 Monthly Credit as Payment for Purchase Price Supporting Calculations The Monthly Credit as Payment for Purchase Price (CLIN 0001) is calculated by amortizing the purchase price over the number of contract periods (months) the Offeror proposes to credit the purchase price.
• The Offeror proposes to purchase the wastewater system for $500,000.
• The $3,476.29 monthly credit is calculated by amortizing the $500,000 Purchase Price over 15 years (180 months) at a 3.16 percent annual interest rate (see Table JA40.2.2-1 for calculation details). The interest rate is the Offeror’s cost of capital for the amortization period.
J40-16
TABLE JA40.2.2-1: Calculation of Annual / Monthly Purchase Price Credit Utilities Privatization
Calculation Results
(PP) Proposed Purchase Price => $500,000
(N) # Years to Amortize Purchase Price => 15
(I) Annual Interest Rate => 3.16%
CLIN 0001, (A) Annual Credit for Purchase Price a => $41,716
Monthly Credit for Purchase Price = (A) / 12 => $3,476.29
Table Notes: an Annual Credit as Payment for Purchase Price is calculated based on uniform series of payments and middle of the year discounting for the first year. A = { PP x [ I x (1 + I) 15 ] / [ (1 + I) 15 – 1 ] } x (1 / ( 1+I) (1-0.5))
JA40.2.3 CLINS 0002 and 0003 Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period
JA40.2.3.1 CLIN 0002 Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) Supporting Calculation Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) are documented in Price Data Sheet 3. Transition costs are also included in Price Data Sheet 3;
however, these costs are addressed in CLIN 0003 (see section JA40.2.5). In this example, based on its assessment of the utility system, the Offeror identified three deficiencies in the wastewater system.
• All of the 1970s-era collection system piping needs to be replaced because it has reached the end of its service life, it requires excessive maintenance, and has unacceptable infiltration and inflow (I&I). The cost to replace the collection piping was determined to be $110,000. The replacement is to be done in CY 1 of the contract term as planned renewal and replacement (R&R) costs. Even though this project may be a deficiency, the Offeror determined that it was actually the result of the system reaching the end of its service life and therefore addressed it as an R&R project by including it in Price Data Sheet 2.
• Cross connections between the Installation’s wastewater system and stormwater system were determined to be the cause of the I&I problem. The cost to remedy the cross connections was determined to be $125,000. The Offeror included an Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) project in Price Data Sheet 3 to address this deficiency. The project is amortized over 15 years at a 2.90 percent annual interest rate (assumed cost of capital for the Offeror for the amortization period). The Offeror also determines a program to periodically televise and test the system for I&I needs to be implemented. The Offeror determines the annual cost for this program will be $2,000 per year, which is included in the $7,900 monthly operating cost.
J40-17
• The lift station prone to overflowing was evaluated and determined to be in good condition, but inappropriately sized for the facilities served. The cost to replace the lift station was determined to be $25,000 and was incorporated into the first year of performance as a planned R&R cost. Even though this project may be a deficiency, the Offeror accounted for it under R&R because it is a replacement and impacts the overall schedule of replacements.
Two of the deficiencies, replacing the 1980s-era pipes and lift station #2, were included in the first year of planned R&R. A portion of the other deficiency was accounted for in the O&M component of the utility services charge. Remedying the cross-connections in the system was not included as R&R and it must be included in the Initial System Deficiency Corrections in Price Data Sheet 3.
• The Offeror proposes a $125,000 Initial System Deficiency Correction to remedy the cross connections in the system. This project is scheduled to be completed in the 12th month of performance and amortized over the next 5 years (months 13 through 72) at a
2.90 percent annual interest rate (assumed Offeror’s cost of capital for the amortization period (see Table JA40.2.3.1-1 for calculation details).
TABLE JA40.2.3.1-1: Calculation of Annual / Monthly ISDC Charge Utilities Privatization
Calculation Result
(PV) Project Cost => $125,000
(N) # Years to Amortize Project Cost => 5
(I) Annual Interest Rate => 2.90%
(A) Annual Charge a => $26,830
Monthly Charge = (A) / 12 => $2,235.85
Table Notes: a Annual Charge calculated based on uniform series of payments and middle of the year discounting for the first year. A = { PV x [ I x (1 + I) 5 ] / [ (1 + I) 5 – 1 ] } x (1 / ( 1+I) (1-0.5))
JA40.2.3.2 CLIN 0003 Transition Period The Transition Period charge (CLIN 0003) comes directly from Price Data Sheet 3 (Table JA40.2.3.2-1). If the Contractor chooses to amortize the transition period payments, the same methodology that is used to calculate the Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) must be used. Refer to CLIN 0002 Supporting Calculations.
The example Price Data Sheet 3 developed for Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s)/ Transition Period (CLINS 0002 and 0003) is shown in Table JA40.2.3.2-1.
J40-18
TABLE JA40.2.3.2-1: Price Data Sheet 3, Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period Utilities Privatization
Project Name Interest Rate
Project Cost (Constant $)
Project Start Date
First Full Month Project will be in Service
Amortization Period
(Months) Monthly Charge
Project 1 - Remedy Cross Connections 2.90% $125,000 12 60 $2,235.85
Transition 0.00% $50,000 0 1 $50,000.00
JA40.2.4 CLIN 0001 Recoverable Portion of the Purchase Price Supporting Calculation The Monthly Charge for the Recoverable Portion of the Purchase Price (CLIN 0001) is calculated by amortizing the recoverable amount of the purchase price over the number of contract periods (months) the Offeror proposes to recover the purchase price (see Table
JA40.2.4-2).3
• The Offeror proposes to purchase the wastewater system for $500,000.
• The Offeror proposes to recover the full amount of the purchase price. If there is any extra capacity in the system that can used by another entity with the permission of the Government, the Offeror can propose to serve and charge that entity and credit those charges to the Government (i.e., O&M, R&R, ISDC, and purchase price recovery).
• The $3,476.29 monthly charge is calculated by amortizing the $500,000 Recoverable Portion of the Purchase Price over 15 years (180 months) at a 3.16 percent annual interest rate (assumed Offeror’s cost of capital for that time period (see Table JA40.2.4-1 for calculation details)). Generally, the interest rate is the Offeror’s cost of capital used in the calculation of the Purchase Price Credit; if it is different, it should be explained in the proposal.
3 The Recoverable amount cannot exceed the Purchase Price. Additionally, recovery terms (interest rate, number of periods) should be the same as used when calculating the monthly credit for the Purchase Price (CLIN 0001).
J40-19
TABLE JA40.2.4-1: Calculation of Annual / Monthly Purchase Price Recovery Charge Utilities Privatization
Calculation Results
(PP) Proposed Recoverable Portion of Purchase Price => $500,000
(N) # Years to Amortize Recovery => 15
Annual Interest Rate => 3.16%
CLIN 0001, (A) Annual Purchase Price Recovery Charge a => $41,716
Monthly Purchase Price Recovery Charge = (A) / 12 => $3,476.29
Table Notes: a Annual Purchase Price Recovery Charge is calculated based on uniform series of payments and middle of the year discounting for the first year. A = { PP x [ I x (1 + I) 15 ] / [ (1 + I) 15 – 1 ] } x (1 / ( 1+I) (1-0.5))
TABLE JA40.2.4-2: Price Data Sheet 4, Recoverable Portion of Purchase Price Utilities Privatization
Item Interest Rate Amount Amortization
Period (Months) Monthly Charge
Recoverable Portion of Purchase Price 3.16% $500,000 180 $3,476.29
| EXAMPLE FOR FP-EPA TYPE CONTRACTS - COMPLETION OF PRICE DATA SHEETS |
| EXAMPLE FOR FP-EPA TYPE CONTRACT - COMPLETION OF PRICE DATA SHEETS |
| JA40 EXAMPLE |
| JA40.1 Schedule B-2 |
| JA40.2 Supporting Calculations |
| JA40.2.1 CLIN 0001 Utility Services Charge Supporting Calculations |
| JA40.2.1.1 Interest Rate and Discount Rate Should be the Same for R&R Charge Calculation |
| JA40.2.1.2 R&R Schedule Does Not Impact R&R Cash Balance |
| JA40.2.2 CLIN 0001 Monthly Credit as Payment for Purchase Price Supporting Calculations |
| JA40.2.3 CLINS 0002 and 0003 Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) / Transition Period |
| JA40.2.3.1 CLIN 0002 Initial System Deficiency Correction(s) / Upgrade(s) / Connection Charge(s) Supporting Calculation |
| JA40.2.3.2 CLIN 0003 Transition Period |
JA40.2.4 CLIN 0001 Recoverable Portion of the Purchase Price Supporting Calculation