J2 Specifications PN 11731512.pdf

PDF 6 MB Posted

Attached to
Building and Site Repairs at USCG SFO Fort Macon, NC
Solicitation number
70Z08321BPAC13100
Issued by

About this file

This invitation for bid outlines requirements for a construction project. The U.S. Coast Guard is seeking bids to provide building and site repairs at Coast Guard Sector Field Office Fort Macon in North Carolina, with work including replacing HVAC systems, exterior windows and doors, and repairing storm damage. The project value is estimated between $5-10 million. The solicitation is set aside for eligible 8(a) small businesses. Bids are due by March 2022. The successful bidder must meet all requirements in the specifications dated March 2021 and drawings listed in the IFB. Construction Wage Rate Requirements apply. The bid package must include a bid bond of 20% and be delivered to the specified contracting office by the stated deadline.

View the file

Other files

File Type Posted
21PAC131 Abstract of Offers Construction.pdf PDF
J13 Section 05 51 00 Metal Stairs.pdf PDF
J11 Section 31 31 16.13 Chemical Termite Control.pdf PDF
J12 Section 31 31 16.19 termite Control Barriers.pdf PDF
J10 Site Visit Sign In Sheet March 22 2022.pdf PDF
J15 C8601 D Pre alteration Hazardous Materials Survey Report REV.pdf PDF
Amend 3 Q A 21PAC131 pg 2 to 10.pdf PDF
J9 Site Visit Sign In Sheet March 15 2022.pdf PDF
J14 Section 05 52 00 Metal Railings.pdf PDF
Amend Three 21PAC131 SF30-16.pdf PDF
Amend Two 21PAC131 SF30-16 032822.pdf PDF
Amend One 21PAC131 SF30-16.pdf PDF
Amend One pg 2 to 4 031622.pdf PDF
J7 CEUC EQUIPMENT ENROLLMENT FORM.xlsx XLSX spreadsheet
J4 C7003 - Reference DWG 6.pdf PDF
J7 CEUC USCG APPROVED EQUIPMENT ENROLLMENT CATALOG.pdf PDF
J3 C8601-D Sheets 16-30 of 134.pdf PDF
J3 C8601-D Sheets 31-45 of 134.pdf PDF
J4 C8540 - Reference DWG 10.pdf PDF
J3 C8601-D Sheets 76-90 of 134.pdf PDF
J1 SF1442 21PAC131 022822.pdf PDF
J5 WD NC20220069 02252022.PDF PDF
J4 C7219 - Reference DWG 7.pdf PDF
J3 C8601-D Sheets 121-134 of 134.pdf PDF
J3 C8601-D Sheets 91-105 of 134.pdf PDF
J8 Contractor_Responsibility_Questionair_-_New.rtf RTF text file
J4 C8316 - Reference DWG 9.pdf PDF
J1 21PAC131 IFB pages 3 to 53.pdf PDF
J4 C8600-D - Reference DWG 11.pdf PDF
J3 C8601-D Sheet 106 of 134.pdf PDF
J3 C8601-D Sheets 107-120 of 134.pdf PDF
J3 C8601-D Sheets 1-15 of 134.pdf PDF
J4 C3840 - Reference DWG 2.pdf PDF
J4 C6646 - Reference DWG 3.pdf PDF
J3 C8601-D Sheets 46-60 of 134.pdf PDF
J4 C050385 - Reference 1.pdf PDF
J4 C7943 DWG SET Reference DWG 8.pdf PDF
J5 WD NC20220062 02252022.PDF PDF
J4 C6875 - Reference DWG 5.pdf PDF
J7 C8601-D CZMA Consistency Letter.pdf PDF
J3 C8601-D sheets 61-75 of 134.pdf PDF
J6 RFI 21PAC131.docx DOCX document
J4 C6827 - Reference DWG 4.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P/N 11731512

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

ENGINEERING SERVICES DIVISION

SPECIFICATIONS

FOR

BUILDING AND SITE REPAIRS AT

U.S. COAST GUARD SECTOR FIELD OFFICE

FORT MACON

ATLANTIC BEACH, NC

24 March, 2021

COMMANDING OFFICER

UNITED STATES COAST GUARD

CIVIL ENGINEERING UNIT, RM 2179

1240 EAST NINTH STREET

CLEVELAND, OHIO 44199-2060

Final Submission

3/26/2021

3/26/2021

TABLE OF CONTENTS

Division Section Title Page

1 GENERAL REQUIREMENTS

01 11 00 Scope of Work 6

01 11 16 Work by Others 9

01 14 00 Contractor Work Hours 9

01 14 13 Pre-bid Site Visits 9

01 14 14 Pre-Construction Site Conditions 10

01 14 16 Coordination 10

01 14 19 Field Adjustments 11

01 18 13 Utility Permits 11

01 18 14 Building Permits 11

01 18 17 Environmental Permits 11

01 26 13 Request for Information 12

01 31 19 Project Meetings 14

01 32 16 Construction Schedule, Schedule of Values and Progress Schedule

01 32 26 Construction Daily Reports 16

01 33 00 Submittal Procedures 16

01 35 29 Safety Program 19

01 51 00 Temporary Utilities 19

01 51 13 Equipment/Utility Lockout and Tagout

Requirements

01 51 16 Temporary Fire Protection 20

01 54 30 Confined Entry 21

01 55 00 Access Roads and Parking 21

01 55 29 Staging Areas and Access 21

01 56 00 Lights, Signs & Barricades 22

01 57 13 Erosion and Sediment Control 22

01 57 23 Pollution Control 23

01 65 00 Recovered Materials Notice 24

01 66 13 Hazardous Waste 24

01 66 16 Safety Data Sheets and Material Handling

Procedures

01 74 00 General Cleanup and Site Restoration of Work

Areas

TABLE OF CONTENTS (cont.)

Division Section Title Page

1 GENERAL REQUIREMENTS (cont.)

01 78 00 As Built Drawings 26

01 80 00 Facility Preventative Maintenance Program

(FPMP)

List of Submittals 29

Contract Item Acceptance Request 51

1 GENERAL REQUIRMENTS – DESIGNER

ADDED

01 45 35 Special Inspections 52

2 EXISTING CONDITIONS

02 41 00 Demolition 87

02 84 16 Handling of Lighting Ballasts and Lamps

Containing PCBs and Mercury

3 CONCRETE

03 30 00 Cast-In-Place Concrete 100

4 MASONRY

04 20 00 Unit Masonry 141

5 METALS

05 12 00 Structural Steel 165

05 50 13 Miscellaneous Metal Fabrications 175

6 WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 183

06 20 00 Finish Carpentry 195

7 THERMAL AND MOISTURE PROTECTION

07 22 00 Roof and Deck Insulation 201

07 31 13 Asphalt Shingles 215

07 41 13 Metal Roof Panels 221 07 60 00 Flashing and Sheet Metal 243 07 92 00 Joint Sealants 261

8 OPENINGS

08 11 13 Steel Doors and Frames 271 08 36 13 Sectional Overhead Doors 277 08 41 13 Aluminum-Framed Entrances and Storefronts 283 08 51 13 Aluminum Windows 297 08 71 00 Door Hardware 309 08 81 00 Glazing 317 08 91 00 Metal Wall Louvers 325

9 FINISHES

09 29 00 Gypsum Board 329 09 51 00 Acoustical Ceilings 337 09 65 00 Resilient Flooring 341 09 90 00 Paints and Coatings 347

10 SPECIALTIES

10 22 13 Wire mesh Partitions 379

13 STANDARD CONSTRUCTION

13 34 19 Metal Building Systems 383

23 HEATING, VENTILATION, AIR CONDITIONNG

23 01 30.41 HVAC System Cleaning 417 23 03 00.00 20 Basic Mechanical Materials and Methods 427 23 05 93 Testing Adjusting and Balancing for HVAC 433 23 07 00 Thermal Insulation for Mechanical Systems 475 23 09 53 00.20 Space Temperature Control Systems 505 23 21 13.00 20 Low Temperature Water Heating System 521 23 23 00 Refrigerant Piping 529 23 30 00 HVAC Air Distribution 541 23 64 10 Water Chillers Vapor Compression Type 559 23 64 26 Chilled Chilled-Hot and Condenser Water

Piping Systems

23 74 33.00 40 Packaged Outdoor Heating and Cooling

Makeup Air-Conditioners

26 ELECTRICAL

26 05 00 Common Work Results for Electrical 605 26 05 26.00 40 Grounding and Bonding for Electrical Systems 625 26 32 00 Packaged Generator Assemblies 633 26 51 00 Interior Lighting 653

31 EARTHWORK

31 00 00 Earthwork 673 31 05 19 Geotextile 689 31 11 00 Clearing and Grubbing 695

32 EXTERIOR IMPROVEMENTS

32 01 19.61 Sealing of Joints in Rigid Pavement 697 32 11 23 Aggregate Base Courses 709 32 11 23.23 Drainage Layer 719 32 12 13 Prime Coat 729 32 12 16 Hot Mix Asphalt for Roads 735 32 13 13.06 Portland Cement Concrete Pavements for Roads and Site Facilities

32 17 23 Pavement Markings 775 32 31 13 Chain Link Fence 787 32 92 19 Seeding 797

32 92 23 Sodding 803

33 UTILITIES

33 32 15 Package Utility Pumping Stations 809 33 40 00 Storm Drainage 827 33 46 16 Subdrainage Piping 841 33 47 13 Pond Liners 847

DIVISION 1

(May 2019 Version)

SECTION 01 11 00

SCOPE OF WORK

1. WORK INCLUDED: Major items of work shall include the following:

1.1 RPUID 16754, OR1 - Racquetball Building:

Repair /replace metal duct elbow at top of outdoor stack. Provide PVC cover or coating to protect from corrosion and make watertight.

Repair / refinish rusted siding connections and miscellaneous flashings at building perimeter.

1.2 RPUID 16750, OM1 - Multi-Mission Building:

Replace 30-ton chiller, provide code compliant conditioned outside air throughout the entire building. Replace fan coil units and other HVAC systems as required. Maintain existing cooling capacity, and enhanced humidity control.

Replace cracked/damaged exterior widows & curtainwall system as noted. Reseal all door & window heads, sills and jambs to prevent water infiltration. Replace existing hollow metal doors.

Repair/replace existing metal louvers at building exterior envelope.

Repair/replace aluminum trim and soffits which were displaced as the result of storm damage.

Repair/replace damaged and missing ceiling tiles on building interior.

Provide cast-in-place concrete equipment pads as necessary for new equipment, where shown.

1.3 Lift Station #1 & RPUID 67647, OL8 – Lift Station 2:

Provide a portable generator connection for Lift Station #1 as shown on drawings.

Provide a portable diesel generator for use at either Lift Station.

1.4 RPUID 848995, B01 - HAZMAT Building:

Provide air conditioning and dehumidification for building to control high humidity and mitigate mold growth.

1.5 RPUID 16753, OO2 - ISD Office Building:

Temporarily raise the building to allow for the installation of a new building foundation system.

Relocate the existing condensing unit, as shown on drawings.

Install new stairs, ramps, and decks as shown on drawings.

1.6 RPUID 843052, OI2 - Engineering Facilities Building:

Repair/replace aluminum trim and soffits which were displaced as the result of storm damage. Repair water damaged GWB and refinish to match, as shown on drawings.

Reseal all door & window heads, sills and jambs to prevent water infiltration.

1.7 RPUID 16743, OE1 - Medical/Dental Building:

Repair/replace aluminum trim and soffits which were displaced as the result of storm damage. Reseal all door & window heads, sills and jambs to prevent water infiltration. Repair / replace missing siding as indicated on the drawings. Repair vertical and horizontal concrete surfaces in entry ramp.

Repair/replace refrigerant piping where noted on the drawings.

1.8 RPUID 16741,OA1 - ANT Fort Macon Building:

Replace overhead door, frame and mechanical systems. Replace lintels, windows and exterior doors. Repair interior flooring due to water damage. Repair masonry cracks as indicated on drawings.

1.9 RPUID 16740, O31 - Prevention Building:

Replace exterior doors, windows and frames.

1.10 RPUID 16742, OD1 - Exchange Building:

Replace exterior doors, windows and frames. Add vestibule to building entry.

Repair/replace refrigerant piping where noted on the drawings.

1.11 RPUID 16757, OU1 - Public Works Lawn Maintenance Shed #1; RPUID 16745, OL2 – Public Works Lawn Maintenance Shed #2; RPUID 843131, OV14 – Public

Works Equipment Shed; RPUID 852121, B004 – Master at Arms Shed:

Demolish existing sheds and replace with one new pre-engineered metal building as shown on the drawings.

1.12 RPUID 16759, OU5 - Dock Side Utility Building:

Demolish building in its entirety.

1.13 RPUID 71461, CB1 - Stormwater Retention:

Drain wet pond, clean out soil accumulated in bottom of wet pond, remove heavy over grown vegetation around wet and dry pond, repair areas of pond liner and rip rap outside of the demolition limits.

Re-grade and re-sod dry pond and emergency spillway as shown on the drawings.

Replace dual 18” RCP pipes that outlet into wet pond.

Construct new outfall weir structure to better stabilize outlet pipes and help with future pond maintenance.

Grade between existing parking lot and pond as shown on the drawings.

1.14 Infiltration Systems and other drainage related improvements:

Install under drain system along the fence line near the ISD Bldg as shown on the drawings

Install infiltration piping and small pump station underneath the ISD Bldg that will connect to the new under drain system described above.

Install new trench drain in the parking area behind the ISD and IPD Bldgs and connect to the existing Stormceptor as shown on the drawings.

Install check valve on the outlet pipe from the existing Stormceptor to prevent backflow.

Remove concrete pavement and repave the parking area behind the ISD and IPD

Bldgs sloping new pavement as shown on the drawings.

Replace existing drop inlets in back parking lot with deeper open bottom drop inlets connected with overflow piping conveyed to a new overflow control structure and eventually new overflow leach field as shown on the drawings.

Surface drainage inlet replacement and pipe cleanout as shown on the drawings.

1.15 Pebble Sheds 1, 2, 3 & 4

Demolish sheds as shown on drawings.

1.16 Pavilion

Remove existing pavilion in its entirety

Replace pavilion as shown on drawings.

1.2 Work associated with these items are described in the following specification sections and/or are shown on the contract drawings. Incidental work items not listed above and necessary for completing the project shall be included.

2. DRAWINGS: Drawings and the accompanying specifications are the property of the

Government and comprise legal documentation that pertains exclusively to this project.

Drawings will be made available in a format determined by the solicitation method. CEU

Cleveland will not provide hard copies of drawings.

2.1 Construction Drawings: CG DWG 8601-D, Sheets 1 thru 134.

2.2 Reference Drawings: C050385, Sheets 1 thru 110

C3840, Sheets 1 thru 3

C6646, Sheets 1 thru 21

C6827, Sheets 1 thru 4

C6875, Sheets 1 thru 3

C7003, Sheets 1 thru 10

C7219, Sheets 1 thru 7

C7943, Sheets 1 thru 12

C8316, Sheets 1 thru 8

C8540, Sheets 1 thru 10

C8600-D, Sheets 1 thru 34

2.3 Reference Documents: CEUC USCG Approved Equipment Enrollment Catalog.pdf

CEUC Equipment Enrollment Form.xlsx

C8601-D CZMA Consistency Letter.pdf

SECTION 01 11 16

WORK BY OTHERS

1. WORK NOT INCLUDED IN THE CONTRACT: Non-contractor personnel will accomplish the following work items necessary for completion of the project. However, the contractor must coordinate accomplishment of these work items with the appropriate parties noted below in accordance with Section 01 14 16, “Coordination”.

1.1 Work by other Contractors or Service Companies: Contractor personnel and equipment associated with another construction contract in progress may require access to the site during execution of this contract. The contractor shall coordinate work and ensure that work operations do not interfere with the contract currently in progress. The contractor shall allow service contract personnel access to the site for trash removal, snow removal, grounds maintenance or the performance of other related service contracts. The Coast Guard will advise the contractor of the trash removal, grounds maintenance or other recurring maintenance schedules.

SECTION 01 14 00

CONTRACTOR WORK HOURS

1. WORK HOURS: Accomplish work during normal unit operational hours of 7:30 a.m. to

4:30 p.m., Monday through Friday unless otherwise approved by the Coast Guard. Note any departures from these work hours on the Daily Reports.

2. SATURDAY, SUNDAY AND HOLIDAYS: The contractor shall provide the

Contracting Officer's Representative at least forty-eight hours advance notice prior to working on weekends or Federal holidays. The Government may reject any such request without impacting the completion time of the contract.

3. CONTRACT COMPLETION: The contractor shall complete work within the time frame indicated upon issuance of the Notice to Proceed. Limitations imposed by these work hours will not entitle the Contractor additional time to complete the project. Refer to FAR Clause 52.211-10

"Commencement, Prosecution and Completion of Work".

SECTION 01 14 13

PRE-BID SITE VISITS

1. GENERAL: Bidders are responsible for visiting the site to field verify existing conditions and determine actual dimensions and the nature of the work required. Failure to visit the site does not relinquish the bidder from determining the extent and scope of the work required and estimating the difficulty and cost to complete the project. Requests for equitable adjustments, in either time or money, arising from failing to field verify site conditions may be denied. Provisions regarding the site visit requirements are outlined in FAR Clause 52.236-3

“Site Investigation and Conditions Affecting the Work”.

2. SITE VISIT: Arrange pre-bid site visits to verify existing conditions with Guy Brunell, U.S. Coast Guard SFO Fort Macon at (252) 240-8494 Guy.M.Brunell@uscg.mil, or DCCS Chris

Schulte, (252) 240-8487, James.C.Schulte@uscg.mil. The Facility Engineer may limit hours of access or levy certain restrictions regarding visits to the site.

SECTION 01 14 14

PRE-CONSTRUCTION SITE CONDITIONS

1. SITE CONDITION VERIFICATION: The Contractor shall verify the conditions of the existing site, equipment and facilities potentially affected by the work under this contract and photograph and/or videotape the conditions in order to document their pre-construction condition. Copies of the photos and videos shall be submitted to the Contracting Officer prior to starting work.

2. UTILITIES: The contractor shall use proactive measures such as digging, metering, testing, underground utility location devices, and utility company location services to locate all underground utilities identified in the area of work at no additional expense to the Government.

Additional cost of unplanned outages and repair of damaged utilities, including emergency repairs by others, not properly identified by the Contractor shall be the Contractor’s responsibility.

SECTION 01 14 16

COORDINATION

1. INTERFERENCE WITH COAST GUARD OPERATIONS: Accomplish work in a manner that causes minimal impact on normal operations. The Contractor shall notify the

Contracting Officer’s Representative at least five working days in advance of any planned outages of water, electrical, telephone, or sanitary facilities. Notify the Contracting Officer’s

Representative at least one week prior to beginning construction.

2. MILITARY STATION REGULATIONS:

2.1 The Contractor, his employees, and subcontractors shall become familiar with and obey all station regulations. All personnel employed on the project shall keep within the limits of the work and avenues of ingress and egress, and shall not enter any other areas outside of the site of the work unless required to do so in the performance of their duties. The Contractor's equipment shall be conspicuously marked for identification.

2.2 There shall be NO SMOKING in any Coast Guard building.

2.3 Storage Areas: The Contracting Officer’s Representative will determine exact location and boundaries of staging areas. Under no circumstances shall materials be stored in areas that will interfere with aircraft operations.

mailto:Guy.M.Brunell@uscg.mil

2.4 Storm Protection: If a gale force wind warning or higher is issued, take precautions to minimize any danger to persons and protect the work and nearby Government property.

Precautions shall include, but not be limited to, closings, removing loose materials, tools and equipment, from exposed locations. Remove and secure scaffolding and temporary work. Close openings in the work area if storms of lessor intensity are imminent.

SECTION 01 14 19

FIELD ADJUSTMENTS

1. The Contracting Officer’s Representative may authorize field adjustments. Field adjustments are those alterations that do not affect time, price, or intent of the contract documents. All field adjustments shall be documented in the Daily Reports and on the As-Built

Drawings.

SECTION 01 18 13

UTILITY PERMITS

1. The Contractor is responsible for obtaining all permits required for connection to all public or private utility systems. This shall include all permit, inspection, administrative and accessory costs normally charged of customers by the utility.

1.1 All Tie-in and/or connection fees will be paid by the Contractor.

SECTION 01 18 14

BUILDING PERMITS

1. NO BUILDING PERMITS from state or local governments are required for work performed on federal property. Courtesy permits may be obtained at the Contractor's option. No payment will be made to the Contractor for any permit cost. Design changes to obtain courtesy permits, even at no cost, will not be allowed without written approval of the Contracting Officer.

SECTION 01 18 17

ENVIRONMENTAL PERMITS

1. Unless directed by other sections of this specification, the Contractor will not be responsible for obtaining environmental permits.

SECTION 01 26 13

REQUESTS FOR INFORMATION

1. SUMMARY:

A. Section Includes: Administrative requirements for requests for information.

2. DEFINITIONS:

A. Request for Information: A document submitted by the Contractor requesting clarification of a portion of the contract documents, hereinafter referred to as RFI (Request for

Information).

B. Proper RFIs: A properly prepared request for information shall include a detailed written statement that indicates the specific Drawings or Specification in need of clarification and the nature of the clarification requested.

1. RFIs shall be sequentially numbered.

2. Drawings shall be identified by drawing number and location on the drawing sheet.

3. Specifications shall be identified by Section number, page and paragraph.

C. Improper RFIs: RFIs that are not properly prepared.

1. Improperly prepared RFIs will not be processed by the Contracting Officer but will be returned unprocessed.

D. Frivolous RFIs: RFIs that request information that is clearly shown on the Contract

Documents.

1. Frivolous RFIs may be returned unprocessed.

3. CONTRACTOR’S REQUESTS FOR INFORMATION:

A. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Contracting Officer shall be requested to make a clarification of the indeterminate item.

1. Wherever possible after contract award, such clarification shall be requested at the next site visit by the Contracting Officer’s Representative (COR), with the response entered on the daily reports. When clarification at the COR’s site visit is not possible either because of the urgency of the need, or the complexity of the item, Contractor shall prepare and submit an

RFI to the Contracting Officer.

B. Contractor shall endeavor to minimize the number of RFIs. In the event that the process becomes unwieldy, in the opinion of the Contracting Officer because of the number and frequency of the RFIs submitted, the Contracting Officer may require the Contractor to abandon the process and submit future requests as either submittals, substitutions or requests for change.

C. RFIs shall be submitted on the form provided by the Contracting Officer. Forms completely filled in, and if prepared by hand, shall be fully legible after photocopying or fax transmission. Each page of the attachments to RFIs shall bear the RFI number in the upper right corner.

D. RFIs shall be originated by the Prime Contractor.

1. RFIs from subcontractors or material suppliers shall be submitted through, reviewed by, and signed by the Prime Contractor prior to submitting to the Contracting Officer.

2. The Contracting Officer will neither act on nor respond to RFIs received directly from subcontractors or suppliers.

E. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract

Documents will be deemed either Improper or Frivolous as defined above.

F. In cases where RFIs are issued to request clarification of coordination issues, for example, pipe and duct routing, clearances, specific locations of work shown diagrammatically, and similar items when feasible, Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale, and submit with the RFI.

G. RFIs shall not be used for the following purposes:

1. To request approval of submittals.

2. To request approval of substitutions.

3. To request changes which entail additional cost or credit.

4. To request different methods of performing work than those drawn and specified.

H. In the event the Contractor believes that a clarification by the Contracting Officer results in additional cost or time, the Contractor shall not proceed with the work indicated by the

RFI until a modification is prepared and approved. RFIs do not automatically justify a cost increase in the work or a change in the project schedule.

1. Answered RFIs shall not be construed as approval to perform extra work.

I. Contractor shall prepare and maintain a log of RFIs, and at any time requested by the

Contracting Officer, Contractor shall furnish copies of the log showing outstanding RFIs.

Contractor shall note unanswered RFIs in the log.

J. Contractor shall allow up to 14 days review and response time for RFIs, however, the

Contracting Officer will endeavor to respond in a timely fashion to RFIs.

K. The Government reserves the right to issue a change order to expedite the work per

FAR Clause 52.243-4, Changes.

4. CONTRACTING OFFICER’S RESPONSE TO RFIs:

A. Contracting Officer will respond to RFIs on one of the following forms:

1. Proper RFIs:

a. Change Order

b. Request for Proposal

2. Improper or Frivolous RFIs:

a. Unprocessed RFIs will be returned with a stamp or notation: Not

Reviewed.

3. Answers to properly prepared RFIs may be made directly upon the RFI form with supplementary instructions as necessary.

SECTION 01 31 19

PROJECT MEETINGS

1. LOCATION: Project meetings will be conducted either on-site or with a conference call.

The following meetings may be held:

1.1 Pre-Construction Conference: After award of a contract, the Coast Guard will arrange a conference with the contractor, and necessary Coast Guard personnel. The purpose of this conference is to orient the Contractor to Government procedures for wage rates, contractual and administrative matters, and to discuss specific issues regarding actual construction.

1.2 Progress and Technical Review Meetings: These meetings generally take place at the project site. Either party may request a meeting to review the progress of the project and/or review or clarify the technical requirements of the specifications.

SECTION 01 32 16

CONSTRUCTION SCHEDULE, SCHEDULE OF VALUES,

AND PROGRESS SCHEDULE

1. In accordance with the Notice to Proceed letter, the Contractor shall submit the following:

A. Construction Schedule-This schedule shall be prepared using a horizontal bar graph with time scale. It shall be in an industry accepted Project Management format and shall accurately display:

1. All major categories of work to be performed within the required contract completion date broken out in sufficient detail to track progress throughout the life of the contract. Major work categories should include but are not limited to mobilization, carpentry, plumbing, mechanical, electrical, roofing, concrete, site work, and demobilization. In addition to construction activities, procurement times for critical items, submittal turnaround time, mobilization, final inspection, punchlist work, and demobilization shall be shown on the schedule.

2. The duration of each work category.

3. Any concurrent work categories.

B. Schedule of Values-This schedule shall be prepared as a detailed cost breakdown of the contract price and be submitted with the Construction Schedule. This schedule shall include but not be limited to costs of materials, equipment, and labor for all major work categories shown on the Construction Schedule. The Contractor shall adhere to the following guidelines when developing the Schedule of Values.

1. Format - The line items in the Schedule of Values shall be the same as that of the Construction Schedule.

2. Bonds - Bonding costs will only be paid in a lump sum if they are broken out separately and included with the schedule of values. The Contractor shall provide evidence that he has furnished full payment to the surety.

3. Materials - To request progress payments for materials delivered to the construction or fabrication site, the particular category of work associated with the materials must be broken down into separate material and labor costs.

2. UPDATES: Each month and /or with each progress payment request, the Contractor shall submit the following:

A. Progress Schedule-This schedule shall be an update of the Construction Schedule. It shall show the current schedule of all work.

1. Modifications - If modifications are made to the contract, the work added shall be tracked separately from the original Construction Schedule and shall maintain its individuality on the Progress Schedule throughout the life of the contract. Progress Payment requests shall not lump modification costs into the original contract price.

SECTION 01 32 26

CONSTRUCTION DAILY REPORTS

1. GENERAL: The Contractor shall complete a Daily Report for each and every day after mobilization. The importance of an accurate, fully detailed Daily Report promptly delivered to the designated On-Site Representative cannot be overemphasized. The report shall provide an accurate cumulative summary of the history and performance of the work. The Daily

Report shall document weather; work hours; work in-place; inspections and tests conducted, and their results; dimensional checks; equipment and material checks; data on workers by classification; the mobilization and demobilization of construction equipment; materials delivered to the site; and any other pertinent noteworthy event; e.g., personnel injury, site visit by

Coast Guard personnel, etc.

2. RESPONSIBILITY: The Daily Reports play an important role in settling disputes and claims for both parties. For this reason, the On-Site Representative and the Contractor's

Superintendent, together, should review the report to ensure its completeness and accuracy. Each day's report shall be submitted to the On-Site Representative no later than 10:00 a.m. the following morning. The maximum allowable retainage will be enforced for late, sporadic or non-submission of Daily Reports. In the absence of an On-Site Representative the Contractor shall mail the Daily Reports directly to the Contracting Officer every Friday. Should the Daily

Report indicate an accident, environmental issue, OSHA violation or any crisis the On-Site

Representative deems important, the Report should be faxed immediately to the Contracting

Officer at (216) 902-6278.

3. DESIGNATED ON-SITE REPRESENTATIVE RESPONSIBILITY: After a Notice to

Proceed for site work has been issued the On-Site Representative shall complete a Daily Report for each day until the Contractor mobilizes. After the Contractor is at the site, the On-Site

Representative shall ensure that the Contractor completes the Daily Report in accordance with

Paragraphs 1 and 2 above. Any items of dispute or other notes the On-Site Representative feels appropriate shall be added to the Daily Report. The On-Site Representative is also responsible for informing the COR when the contractor fails to submit daily reports.

SECTION 01 33 00

SUBMITTAL PROCEDURES

1. GENERAL: The Contractor shall submit to the Contracting Officer (4) copies of submittals required by this specification and/or itemized on the "List of Submittals" found at the end of this division.

2. REQUEST: A "CONTRACT ITEM ACCEPTANCE REQUEST" shall accompany all submittals. All items shall be individually listed and clearly identified, referencing the applicable Section and Paragraph. A copy of this form is located at the end of this division and may be reproduced as needed.

2.1 Up to eight (8) items may be listed on an individual acceptance request. Number each

Contract Item Acceptance Request consecutively (Submittals # 1, 2, etc.) and re-submittals with letters (Submittal #1A is the first re-submittal of Submittal #1).

2.2 Submittals shall be forwarded to the Contracting Officer. The contractor shall allow 14 calendar days, excluding mailing time, for the review process in the Construction Schedule and all project planning. In instances where submittal review must be expedited, the Contractor may annotate the Contract Item Acceptance Request as "Urgent" and provide a FAX number for prompt return. The Coast Guard will make every effort to accelerate the review of each urgent submittal; however, the Contractor should not anticipate a reduced time schedule and shall plan project progress accordingly.

3. DEVIATIONS

3.1 Deviation from specification:

3.1.1 The Contracting Officer will consider requests for deviations/substitutions only if submitted within fifteen (15) calendar days after award.

3.1.2 Deviations may be considered when a product becomes unavailable through no fault of the Contractor.

3.1.3 The Contractor shall document each request with complete data substantiating compliance of proposed deviation with the Contract documents. Request for deviation shall not be submitted on a Request for Information (RFI) form.

3.1.4 A request constitutes a representation that the Contractor:

3.1.4.1 Has investigated proposed product and determined that it meets or exceeds quality level of specified product.

3.1.4.2 Will provide the same warranty for deviation as for specified product.

3.1.4.3 Will coordinate installation and make changes to other work which may be required for the work to be completed at no additional cost to the Government.

3.1.4.4 Waives claims for additional costs or time extension which may subsequently become apparent.

3.1.4.5 Will reimburse the Government for review or redesign services associated with re-approval by the Contracting Officer.

3.1.5 If the deviation has a lesser value than the product originally specified, the Contractor shall provide a credit to the Government.

3.1.6 Deviations will not be considered when they are indicated or implied on Shop Drawings or Product Data submittals, without a separate written request, or when acceptance will require revisions to the Contract documents.

3.2 Deviation submittal procedures:

3.2.1 The Contractor shall mark the “Deviation” block on the Contract Item Acceptance

Request (CIAR) form and provide the information stated in Paragraph 3.1.

3.2.2 The Contractor shall submit shop drawings, product data, and certified test results attesting to proposed product equivalence. Burden of proof is on the Contractor.

3.2.3 The Contracting Officer will then review the “deviation” request and either accept or reject the deviation. The Contracting Officer’s acceptance of the deviation signifies that the

Contractor has provided the information required in Paragraph 3.1. If a credit is due the government, the Contracting Officer will notify the Contract Specialist and the deviation will be processed utilizing the Change Request procedures for a modification to the contract/task order.

3.2.4 The Contracting Officer will notify the Contractor of acceptance/rejection of the deviation via an accepted or rejected CIAR. The Contracting Officer will notify the Contractor, in writing, if a modification to the contract is required.

3.2.5 If a request for deviation is received without the documentation stated above, the

Contracting Officer will return the submittal to the contractor for the required information.

4. ACCEPTANCE: Submittals will be stamped "Accepted," "Accepted with Comments," or "Resubmit". Acceptance, Acceptance with comments or Resubmit for each item will be indicated on the Contract Item Acceptance Request form and one copy returned to the

Contractor.

4.1 Prompt re-submittal of items is required. The Contractor shall furnish a new Contract

Item Acceptance Request numbered in accordance with the requirements of paragraph 2.1.

5. DEFECTIVE WORK: Acceptance of Submittals does not restrict the Government's right to reject departures from contract requirements, use of damaged or improperly installed items/materials, or latent defects, nor does it prejudice the Government's rights of rejecting any work found defective at Final Inspection and Acceptance.

5.1 Work started or completed prior to submittal acceptance is solely at Contractor's risk and may jeopardize contract performance.

SECTION 01 35 29

SAFETY PROGRAM

1. GENERAL: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. The Contractor shall provide appropriate safety barricades, signs, signal lights, etc. (see Section 01 56 00, “Lights, Signs & Barricades”) as well as complying with the requirements of all applicable

Federal, State and Local safety laws, rules and regulations.

2. COMPLIANCE: The Contractor is specifically required to comply with the requirements of the U. S. Army Corps of Engineers "Safety and Health Requirements Manual" (EM 385-1-1, latest version available) and the “Accident Prevention” clause (FAR 52.236-13). Once accepted, this safety plan shall become part of the contract requirements. Note: This review/acceptance does not in any way relinquish the Contractor from responsibility for work site safety nor the obligation to comply with the OSHA regulations found in 29 CFR 1910 & 1926 or any other

State or Local safety law, rule or regulation applicable to the contract work. The Coast Guard will cooperate fully with the Department of Labor (Occupational Safety and Health

Administration) in their enforcement of OSHA regulations.

3. SAFETY PLAN: The Contractor shall submit a written safety plan. At a minimum, this plan shall describe the Contractor's general safety program and identify specific safety provisions for hazards incidental to the contract work; e.g., elevated working surfaces, working over water, working from floating work platforms, overhead crane operations, etc.

SECTION 01 51 00

TEMPORARY UTILITIES

1. GENERAL: All temporary utility connections shall be compatible with existing materials and equipment to provide safe and efficient installation, operation and removal.

2. ELECTRICITY AND WATER: Electrical power and water are available on the site. The

Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded. The Contractor is responsible for installing and removing all connections to existing systems and shall ensure work and materials are in accordance with local codes. The use of the electricity shall be limited to tools that can be operated on 60 Hertz, single phase, 20 ampere, 120 volt circuits.

3. TELEPHONE: Telephone services will not be available for use by the Contractor.

4. WATER HOOKUP: All connections to the water system shall be equipped with back flow protection. Temporary potable water pipes and hoses shall be sterilized before being placed in operation and every time the system is opened to the atmosphere for repair or relocation.

5. SANITARY FACILITIES: It shall be the Contractor's responsibility to furnish and maintain approved portable toilet facilities for all Contractor personnel. The On-Site

Representative will designate the physical location for the facility and the Contractor shall maintain the toilet facility to the satisfaction of the Government. Contractor personnel are forbidden to use toilet facilities within existing buildings.

SECTION 01 51 13

EQUIPMENT/UTILITY LOCKOUT AND TAGOUT REQUIREMENTS

1. GENERAL: The Contractor shall comply with OSHA 29 CFR 1910.147, “The Control of Hazardous Energy” (Lockout/Tagout). The Contractor shall provide a Lockout/Tagout Plan to the Contracting Officer prior to starting any work affected by the energy in the equipment/utility system.

2. APPLICATION: The Contractor shall be responsible for locking out and tagging out of service, all equipment/utility systems involved in the work under this contract. After the

Contracting Officer’s Representative has approved an outage, Government personnel and the

Contractor shall independently secure the equipment/utility system and tag the respective system out of service. The Contractor shall provide their own locks and chains that are required to secure the equipment/utility systems, e.g., steam, water, air, and/or electricity.

SECTION 01 51 16

TEMPORARY FIRE PROTECTION

1. TEMPORARY FIRE PROTECTION: Install and maintain temporary fire-protection facilities to protect against predictable and controllable fire loss. Comply with NFPA 10

"Standard for Portable Fire Extinguishers" and NFPA 241 "Standard for Safeguarding

Construction, Alterations and Demolition Operations".

1.1 Locate fire extinguishers where convenient and effective for their intended purpose, but not less than one extinguisher at each floor stairwell and one at each building construction opening for personnel egress.

1.2 Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire-protection facilities, stairways, and other access routes for fighting fires.

1.3 Provide independent supervision of welding, flame cutting and other open flame work.

Provide each fire supervisor with an appropriate fire extinguisher.

1.4 Provide training for all personnel on-site in the proper operation of each type of fire extinguisher provided. Provide all personnel with the proper notification procedure to summon the local fire department or emergency medical service.

1.5 There shall be NO SMOKING or unsupervised open flame permitted inside any structure, temporary or permanent; nor within 25 feet of combustible material or within 50 feet of flammable liquids or compressed gasses.

SECTION 01 54 30

CONFINED ENTRY

1. COMPLIANCE: The Contractor shall comply with OSHA 29 CFR 1910.146, Permit-

Required Confined Space. The Contractor shall provide a Confined Space Entry Plan to the

Contracting Officer prior to entering, or starting any work, in a confined space. The Contractor shall provide all equipment and materials as required to comply with OSHA and complete the work under this contract.

SECTION 01 55 00

ACCESS ROADS AND PARKING

1. ACCESS: Access to the site is available from public roads. Any damage to these roads by the Contractor's vehicles shall be repaired without cost to the Government.

2. PARKING: Vehicular operations and parking shall comply with all applicable government orders and regulations. All driveways and entrances serving the Government shall be kept clear and available to emergency vehicles at all times.

3. VEHICLE AND VEHICLE OPERATION: All vehicles, owned by the Contractor or employees of the Contractor, and operators of these vehicles, shall meet all state regulations for safety, noise, loading and minimum liability insurance. All vehicle operators demonstrating reckless or careless operation in the opinion of the Government shall not be allowed to operate vehicles on government property for the duration of the contract.

4. VISITORS: No visiting vehicles will be permitted on government property unless the operator is employed by a subcontractor or supplier.

SECTION 01 55 29

STAGING AREAS AND ACCESS

1. LOCATION: The Contractor shall store materials and operate equipment within the confines of the staging area identified by the Government. Storage of materials outside of the staging area will not be permitted.

2. COORDINATION: Two weeks prior to construction, the Contractor shall contact Guy

Brunell, U.S. Coast Guard SFO Fort Macon (252) 240-8494 Guy.M.Brunell@uscg.mil, or DCCS

Chris Schulte (252) 240-8487, James.C.Schulte@uscg.mil to verify the condition of the staging area.

3. ADJACENT AREAS: The Contractor shall ensure that all land and vegetation adjacent to the staging area and access drive remain undisturbed and undamaged; all damages shall be repaired at no cost to the Government.

SECTION 01 56 00

LIGHTS, SIGNS & BARRICADES

1. GENERAL: The contractor shall provide and maintain all warning lights, sign, and barriers to ensure the safety of pedestrians or vehicles traveling near or through any hazardous area caused by the execution of the Contract work.

2. LIGHTING: All lighting requirements shall meet table 7-1 in the US Army Corps of

Engineers Safety and Health Requirements Manual (EM 385-1-1).

3. BARRICADES: Hard barricades or flexible barriers shall completely encompass all exterior work areas. Flexible barriers shall consist of 1/2 inch steel bars or 2" X 2" wood stakes driven 12 inches minimum into hard packed soil. Space stakes on a maximum 10 feet interval and with two rows of yellow or orange 1/4 inch diameter rope (wire and plastic tape are not acceptable) at 24 inches and 36 inches each above ground.

SECTION 01 57 13

EROSION AND SEDIMENT CONTROL

1. GENERAL: The Contractor shall plan and execute all earthwork to minimize the duration of exposure of unprotected soils. Temporary protection shall be provided on side and back slopes as soon as rough grading is completed or when sufficient soil is exposed to require protection to prevent erosion. All earthwork brought to final grade shall be finished immediately.

2. METHODS: The Contractor shall prevent erosion, control sedimentation, and prevent waterborne soil from entering surface waters, ditches, and storm drain inlets by use of any or all of the following methods.

2.1 Mechanical Control: Divert runoff by constructing ditches or berms. Filter runoff using straw bale dikes, filter fabric dams or other methods.

2.2 Sediment Basins: Trap sediment in temporary basins sized to accommodate the runoff of mailto:Guy.M.Brunell@uscg.mil mailto:James.C.Schulte@uscg.mil a local 25-year storm. Pump basins dry and remove accumulated sediment after each storm. Use a paved weir or vertical overflow pipe for overflow. Establish effluent quality monitoring programs as required by federal, state, and local regulations.

2.3 Vegetation and Mulch: Protect slopes by accelerated growth of vegetation, mulching, or netting. Stabilize slopes by hydroseeding, sodding, anchoring mulch or netting in place.

2.4 Geotextiles: Protect and stabilize slopes by anchoring geotextile fabric or matting. The

Contractor shall use a geotextile designed and sized for the particular application.

3. OTHER METHODS: Other erosion and sediment control methods may be used, as authorized by the Contracting Officer.

SECTION 01 57 23

POLLUTION CONTROL

1. VOLATILE ORGANIC COMPOUND (VOC) REGULATIONS: Contractors are required to comply with local, state and federal VOC compliance laws and regulations in the foregoing order of precedence. In order to comply with the provisions of the Clean Air Act, each state must have a State Implementation Plan. Some contractors may be required to abide by the provisions of a Title V Permit. Some contractors may be required by state or local law to operate under the terms of a Compliance Plan to reduce VOC Emissions.

1.1 In accordance with the Notice to Proceed Letter, the contractor will submit copies of any local, state or federal implementation plans, permits or compliance plans required/applicable to the use/application of VOCs at contractor's facility or offsite workplaces.

1.2 If no local, state or federal implementation plans, permits or compliance plans are required/applicable to the use/application of VOCs, then the contractor shall submit to the designated Contracting Officer a letter, notarized under oath, that such documents are not required.

1.3 If the use of paint is required the contractor shall submit to the Contracting Officer and in accordance with the Notice to Proceed Letter, certificates, specifications or manufacturing data verifying the VOC rating.

2. SPILL RESPONSE PLAN: The Contractor shall submit a Spill Response Plan covering all regulated materials brought to the site for execution of work and all wastes generated as a result of the work to the Contracting Officer. The plan shall include, at a minimum, the following: types and quantity of all substances covered under this plan; the reportable quantity

(RQ) for each substance; the on site storage location of each substance; the Contractor's spill response equipment, if applicable; procedures to be followed for responding to a spill, including initial responses to be taken; procedures to be followed in reporting a spill, including the names and telephone numbers for all federal, state, and local agencies/authorities to be notified; and the name, address, and telephone number (work, home, cell and pager) of all Contractor response and media relations personnel.

2.1 In the event of a spill or release, the Contractor shall be responsible for immediate implementation of the spill response plan and restoration of the site to pre-spill condition at no cost to the Government. The Contractor shall also immediately notify the Contracting Officer to coordinate further notifications.

SECTION 01 65 00

RECOVERED MATERIALS NOTICE

1. GENERAL: It is the intent of CEU Cleveland to comply with the requirements of

Section 6002 of the Solid Waste Disposal Act as amended by the Resource Conservation and

Recovery Act (RCRA or the Act) as amended, 42 U.S.C. 6962 and Executive Order 12873 as they apply to the procurement of the materials designated in paragraph 2.

2. DESIGNATED RECOVERED MATERIALS: It is the purpose of this section to designate items that are or can be made with recovered materials. These designated items can be found at https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program#products.

3. CONTRACTOR RESPONSBILITY: The contractor should provide recycled materials to the extent practical, provided the materials meet all other requirements of the applicable specification section.

SECTION 01 66 13

HAZARDOUS WASTE

1. GENERAL: The Contractor shall comply with all federal, state, and local environmental regulations dealing with the generation, management, storage, and disposal of solid, toxic, and hazardous wastes. The Contractor shall ensure that all wastes are properly containerized, labeled and placarded, managed, tested, stored, documented/manifested, transported and disposed of in accordance with all applicable regulations.

2. USED ELECTRIC LAMPS: 40 CFR 273 requires that electric lamps, including incandescent, fluorescent, neon and high intensity discharge (mercury vapor, high/low pressure sodium, metal halide) lamps that are no longer of use be recycled or treated as hazardous waste.

The Contractor shall not dispose of any used electric lamps as solid waste. The Contractor shall recycle all waste electric lamps generated as a result of this work only at a licensed recycling facility.

3. METALS: Unless noted otherwise, scrap metal shall not be landfilled or treated as hazardous waste. Recycle all scrap metal by smelting or any other acceptable recycling process.

http://www.epa.gov/epaoswer/non-hw/procure/products.htm http://www.epa.gov/epaoswer/non-hw/procure/products.htm

Scrap metal includes ductwork, light fixture housings, pipe, mechanical and electrical equipment, doors and frames, etc.

4. SUBMITTALS: The Contractor shall provide the Contracting Officer with signed and fully executed originals of all hazardous waste profiles, test results, hazardous waste manifests and/or other shipping papers, electric lamp disposal documents and all other required documentation. Maximum payment retention shall be withheld until this documentation is received.

SECTION 01 66 16

SAFETY DATA SHEETS AND MATERIAL HANDLING PROCEDURES

1. DATA SHEETS: Submit a Safety Data Sheet (SDS) for all materials containing hazardous substances required for contract execution. Information provided in SDS’s shall meet the requirements of 29 CFR 1910.1200. SDS’s require Contracting Officer review and acceptance prior to bringing these materials on site.

2. MATERIAL STORAGE: Limit the quantity of these materials stored on site to the amount needed for execution of work. Storage of excess materials will not be permitted. Assure that the storage of these materials comply with all applicable federal, state, and local laws and regulations and provide additional storage facilities (paint lockers, etc.) as required for the storage of such materials. Coordinate the physical location of storage areas with the On-site

Representative prior to bringing these materials on site.

3. PROTECTIVE MEASURES: The contractor shall take all protective measures outlined on the SDS’s and as required by federal, state, and local regulations to protect all personnel in the vicinity of the work area from exposure to these materials. The Contractor shall //submit a separate plan outlining the measures required. //include any required protective measures in the

Safety Plan (See Section 01 35 29, “Safety Program”)//. The Contracting Officer's Representative shall review protective measures prior to allowing use of these materials.

4. DISPOSAL OF EXCESS MATERIAL: The Contractor shall dispose of all excess hazardous materials as required by the SDS and all applicable federal, state, and local laws and regulations.

SECTION 01 74 00

GENERAL CLEANUP & SITE RESTORATION OF WORK AREAS

1. GENERAL: The Contractor shall remove and properly dispose of all trash and debris incidental to the contract work from the limits of government property, as well as all adjacent affected areas. The Contracting Officer shall determine the extent and interval of these cleanups.

2. WORK AREA CLEANUP: At the end of each day the entire work area and all adjacent affected areas shall be thoroughly cleaned by removing all trash, debris, dust, etc. caused by the contract work. Any floor, wall or ceiling surfaces that may have been stained or soiled by the contract work shall be restored to pre-construction condition.

3. SITE RESTORATION: If at any time while performing the contract the Contractor causes damage or destruction to any portion of any Government facility or grounds; e.g., bulkheads, pavement, lawns, shrubbery, etc., it shall be the Contractor's responsibility to…