This solicitation requests bids for building and site repairs at the US Coast Guard Sector Field Office in Fort Macon, North Carolina. The contractor shall provide all labor, materials, equipment, tools and services to perform work in accordance with specifications and drawings. Construction Wage Rate Requirements apply. The requirement value is estimated between $5 million and $10 million. Bids are due by the specified date and time. A bid bond of 20% must be submitted with the bid. This is an 8(a) set-aside for eligible small businesses with a size standard of $39.5 million. The Department of Homeland Security Coast Guard is the contracting agency.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SFO Fort Macon Building and Site Repairs
P/N 11731512 SECTION 05 52 00 Page 1
SECTION 05 52 00
METAL RAILINGS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020; Errata 1 2021) Structural Welding Code -
Steel
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural
Steel
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A283/A283M (2013) Standard Specification for Low and
Intermediate Tensile Strength Carbon Steel Plates
ASTM A500/A500M (2021a) Standard Specification for Cold-Formed
Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
ASTM A575 (2020) Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades
NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS
(NAAMM)
NAAMM AMP 521 (2001; R 2012) Pipe Railing Systems Manual
1.2 ADMINISTRATIVE REQUIREMENTS
1.2.1 Preinstallation Meetings
Within 30 days of contract award, submit fabrication drawings to the Contracting Officer for the following items:
a. Steel railings and handrails
SECTION 05 52 00 Page 2
b. Aluminum railings and handrails
1.3 SUBMITTALS
Government approval is required for submittals with a “G” designation; submittals not having a “G” designation are for information only. When used, a designation following the “G” designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Fabrication Drawings; G
Iron and Steel Hardware; G
Steel Shapes, Plates, Bars and Strips; G
SD-03 Product Data
Structural-Steel Plates, Shapes, and Bars; G
Structural-Steel Tubing; G
Hot-Rolled Carbon Steel Bars; G
Protective Coating; G
Steel Railings and Handrails; G
SD-07 Certificates
Welding Procedures; G
Welder Qualification; G
SD-08 Manufacturer's Instructions
Installation Instructions
1.4 QUALITY CONTROL
1.4.1 Welding Procedures
Submit results of welding procedures testing in accordance with AWS D1.1/D1.1M made in the presence of the Contracting Officer and by an approved testing laboratory at the Contractor's expense.
1.4.2 Welder Qualification
Submit certified welder qualification by tests in accordance with AWS D1.1/D1.1M, or under an equivalent approved qualification test. In addition, perform tests on test pieces in positions and with clearances equivalent to those actually encountered. If a test weld fails to meet requirements, conduct an immediate retest of two test welds and ensure that each test weld passes. Failure in the immediate retest will require that the welder be retested after further practice or training and make a complete set of test welds.
SECTION 05 52 00 Page 3
PART 2 PRODUCTS
2.1 FABRICATION
Preassemble items in the shop to the greatest extent possible. Disassemble units only to the extent necessary for shipping and handling.
Clearly mark units for reassembly and coordinated installation.
For the fabrication of work exposed to view, use only materials that are smooth and free of surface blemishes, including pitting, seam marks, roller marks, rolled trade names, and roughness. Remove blemishes by grinding, or by welding and grinding, before cleaning, treating, and applying surface finishes, including zinc coatings.
Provide railing and handrail detail plans and elevations at not less than 1 inch to 1 foot. Provide details of sections and connections at not less than 3 inches to 1 foot.
Also detail setting drawings, diagrams, templates for installation of anchorages, including concrete inserts, anchor bolts, and miscellaneous metal items having integral anchors.
Use materials of size and thicknesses indicated or, if not indicated, of the size and thickness necessary to produce adequate strength and durability in the finished product for its intended use.
Work the materials to the dimensions indicated on approved detail drawings, using proven details of fabrication and support. Use the type of materials indicated or specified for the various components of work.
Form exposed work true to line and level, with accurate angles and surfaces and straight sharp edges. Ensure that all exposed edges are eased to a radius of approximately 1/32 inch. Bend metal corners to the smallest radius possible without causing grain separation or otherwise impairing the work.
Weld corners and seams continuously and in accordance with the recommendations of AWS D1.1/D1.1M. Grind exposed welds smooth and flush to match and blend with adjoining surfaces.
Form the exposed connections with hairline joints that are flush and smooth, using concealed fasteners wherever possible. Use exposed fasteners of the type indicated or, if not indicated, use countersunk Phillips flathead screws or bolts.
Provide anchorage of the type indicated and coordinated with the supporting structure. Fabricate anchoring devices and space as indicated and as required to provide adequate support for the intended use of the work.
Use hot-rolled steel bars for work fabricated from bar stock unless work is indicated or specified to be fabricated from cold-finished or cold-rolled stock.
SECTION 05 52 00 Page 4
2.1.1 Steel Handrails
Fabricate joint posts, rail, and corners by one of the following methods:
a. Flush-type rail fittings of commercial standard, welded and ground smooth, with railing splice locks secured with 3/8 inch hexagonal-recessed-head setscrews.
b. Mitered and welded joints made by fitting post to top rail and intermediate rail to post, mitering corners, groove-welding joints, and grinding smooth. Butt railing splices and reinforce them by a tight-fitting interior sleeve not less than 6 inches long.
c. Railings may be bent at corners in lieu of jointing, provided that bends are made in suitable jigs and the pipe is not crushed.
Provide removable sections as indicated.
2.1.2 Protective Coating
Shop-prime the steelwork as indicated in accordance with Section 09 90 00 PAINTS AND COATINGS except the following:
a. steel surfaces encased in concrete
b. steel surfaces for welding
c. high-strength bolt-connected contact surfaces
2.2 COMPONENTS
2.2.1 Structural Steel Plates, Shapes And Bars
Provide structural-size shapes and plates, except plates to be bent or cold-formed, conforming to ASTM A36/A36M, unless otherwise noted.
Provide steel plates, to be bent or cold-formed, conforming to ASTM A283/A283M, Grade C.
Provide steel bars and bar-size shapes conforming to ASTM A36/A36M, unless otherwise noted.
2.2.2 Structural-Steel Tubing
Provide structural-steel tubing, hot-formed, welded or seamless, conforming to ASTM A500/A500M, Grade B, unless otherwise noted.
2.2.3 Hot-Rolled Carbon Steel Bars
Provide bars and bar-size shapes conforming to ASTM A575, grade as selected by the fabricator.
SECTION 05 52 00 Page 5
2.2.4 Steel Pipe
Provide pipe conforming to ASTM A53/A53M, type as selected, Grade B; primed finish, unless galvanizing is required; standard weight (Schedule 40).
2.2.5 Steel Railings And Handrails
Design handrails to resist a concentrated load of 200 lb in any direction at any point of the top of the rail or 50 lb per foot applied horizontally to the top of the rail, whichever is more severe.
NAAMM AMP 521, provide the same size rail and post. Provide pipe collars of the same material and finish as the handrail and posts.
PART 3 EXECUTION
3.1 PREPARATION
Adjust stair railings and handrails before securing in place in order to ensure proper matching at butting joints and correct alignment throughout their length. Space posts not more than 8 feet on center. Plumb posts in each direction. Secure posts and rail ends to building construction as follows:
a. Anchor posts to steel with oval steel flanges, angle type or floor type as required by conditions, welded to posts and bolted to the steel supporting members.
b. Anchor rail ends to steel with oval or round steel flanges welded to tail ends and bolted to the structural-steel members.
Secure handrails to walls by means of wall brackets and wall return fitting at handrail ends.
Provide brackets of malleable iron castings, with not less than 3 inch projection from the finished wall surface to the center of the pipe, drilled to receive one 3/8 inch bolt. Locate brackets not more than 60 inches on center. Provide wall return fittings of cast iron castings, flush type, with the same projection as that specified for wall brackets. Secure wall brackets and wall return fittings to building construction as follows:
Install toe boards and brackets where indicated. Make splices, where required, at expansion joints. Install removable sections as indicated.
3.2 INSTALLATION
Submit manufacturer's installation instructions for the following products to be used in the fabrication of steel stair railing and hand rail work:
a. Structural-steel plates, shapes, and bars
b. Structural-steel tubing
c. Steel railings and handrails
SECTION 05 52 00 Page 6
d. Anchorage and fastening systems
Provide complete, detailed fabrication and installation drawings for all iron and steel hardware, and for all steel shapes, plates, bars, and strips used in accordance with the design specifications cited in this section.
3.2.1 Steel Handrail
Install handrail by means of base plates bolted to stringers or structural-steel frame work. Secure rail ends by steel pipe flanges through-bolted to a back plate or by 1/4 inch lag bolts to studs or solid backing.
3.2.2 Touchup Painting
Immediately after installation, clean field welds, bolted connections, abraded areas of the shop paint, and exposed areas painted with the paint used for shop painting. Apply paint by brush or spray to provide a minimum dry-film thickness of 2 mils.
3.3 FIELD QUALITY CONTROL
3.3.1 Field Welding
Ensure that procedures of manual shielded metal arc welding, appearance and quality of welds made, and methods used in correcting welding work comply with AWS D1.1/D1.1M.
-- End of Section --