This document is a pricing sheet for the "Capitol Power Plant (CPP) Predictive Maintenance Services" contract opportunity, solicitation number AOCSSB24R0012, issued by the Architect of the Capitol (AOC). The pricing sheet details the Contract Line Item Numbers (CLINs) and associated pricing for the base period of 1 month (transition in period) and 11 months, as well as four 1-year option periods and a 6-month extension option. The pricing covers services such as annual vibration analysis, infrared thermography analysis, ultrasonic analysis, oil sampling/analysis, and program overview/training. The pricing is shown as $0.00 across all CLINs, indicating the actual unit prices will need to be provided by offerors. The overall contract period of performance, if all options are exercised, is 5 years from the date of award. The solicitation uses the negotiated acquisition procedures outlined in the AOC Contracting Manual.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sec-B Summary
| Architect of the Capitol |
| Independaent Government Cost Estimate (IGCE) |
| CAPITOL POWER PLANT (CPP) |
| AOCSSB23R0085 - Predictive Maintenance Services |
| Period of perfromance date | |||||
| Base Period (1- Month (Transition In Period) | $0.00 | Period of performance - Base (1-Month) : | 8/1/24 | - | 8/31/24 |
| Base Period (11-Month) | $0.00 | Period of performance - Base (11-Month) : | 9/1/24 | - | 7/31/25 |
| Option Period 1 | $0.00 | Period of performance - Option Period 1 : | 8/1/25 | - | 7/31/26 |
| Option Period 2 | $0.00 | Period of performance - Option Period 2 : | 8/1/26 | - | 7/31/27 |
| Option Period 3 | $0.00 | Period of performance - Option Period 3 : | 8/1/27 | - | 7/31/28 |
| Option Period 4 (11-Month) | $0.00 | Period of performance - Option Period 4: | 8/1/28 | - | 7/31/29 |
| Option Period 4 (1- Month (Transition Out Period) | $0.00 | Period of performance - Option Period 4: | 8/1/29 | - | 7/31/30 |
| Option Period 5 | $0.00 | Period of performance Option Period 5: (FAR 52.217-8) : | 8/1/29 | - | 1/28/30 |
| Base Period Total: | $0.00 | Base Period |
| All Option Periods Total: | $0.00 | ALL Option Periods |
(To include FAR 52.217-8) Base & Option Periods Total: $0.00 Base & ALL Option Periods
June 02, 2022
1 Mnth TIP Base Period Section B - Supplies or Services and Prices/Costs
(1) Month Tranistion in Period (TIP) - BASE PERIOD
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($) 001 Base Period: Program Setup Data Prep 1.00 Monthly $0.00 $0.00
Base Period $0.00
Base Period-11 Mnth Base Section B - Supplies or Services and Prices/Costs
11 MONTH BASE PERIOD
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
002 Base Period: Annual Vibration Analysis 11.00 Monthly $0.00 $0.00
003 Base Period: Annual Infrared Thermography Analysis Service (Optional ) 11.00 Monthly $0.00 $0.00
004 Base Period: Annual Ultrasonic Analysis Service (Optional ) 11.00 Monthly $0.00 $0.00
005 Base Period: Annual Oil Sampling/ Analysis Service 11.00 Monthly $0.00 $0.00
006 Base Period: Annual Program Overview / Training 11.00 Monthly $0.00 $0.00
Base Period $0.00
Option Period 1 Section B - Supplies or Services and Prices/Costs
OPTION PERIOD 1
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
101 Option Period 1 : Annual Vibration Analysis 12.00 Monthly $0.00 $0.00
102 Option Period 1 : Annual Infrared Thermography Analysis Service (Optional ) 1.00 Annually $0.00 $0.00
103 Option Period 1 : Annual Ultrasonic Analysis Service (Optional ) 12.00 Monthly $0.00 $0.00
104 Option Period 1 : Annual Oil Sampling/ Analysis Service 12.00 Monthly $0.00 $0.00
105 Option Period 1 :Annual Program Overview / Training 12.00 Monthly $0.00 $0.00
Option Period 1: $0.00
Option Period 2 Section B - Supplies or Services and Prices/Costs
OPTION PERIOD 2
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
201 Option Period 2 : Annual Vibration Analysis 12.00 Monthly $0.00 $0.00
202 Option Period 2 : Annual Infrared Thermography Analysis Service (Optional ) 1.00 Annually $0.00 $0.00
203 Option Period 2 : Annual Ultrasonic Analysis Service (Optional ) 12.00 Monthly $0.00 $0.00
204 Option Period 2 : Annual Oil Sampling/ Analysis Service 12.00 Monthly $0.00 $0.00
205 Option Period 2 :Annual Program Overview / Training 12.00 Monthly $0.00 $0.00
Option Period 2: $0.00
Option Year 3 Section B - Supplies or Services and Prices/Costs
OPTION YEAR 3
| Contract Line Item Number (CLIN) | Commodity Name | Quantity | Unit of Issue | Unit Price ($) | Total Cost ($, Inc. disc) |
| 301 | Option Year 3 - 6.2 General Requirements | 12.00 | MONTHLY | $0.00 | $0.00 |
| Labor rates table below shall be filled out for every option year. | |||||
| 302 | Option Year 3 - 6.3 Facility Management | 12.00 | MONTHLY | $0.00 | $0.00 |
303 Option Year 3 - 6.4 Operations and Maintenance 12.00 MONTHLY $0.00 $0.00
304 Option Year 3 - 6.5 Project Manager 12.00 MONTHLY $0.00 $0.00
305 Option Year 3 - 6.6 On-Site Supervisor 12.00 MONTHLY $0.00 $0.00
306 Option Year 3 - 6.7 Stationary Engineer 12.00 MONTHLY $0.00 $0.00
307 Option Year 3 - 6.8 Pipefitter 12.00 MONTHLY $0.00 $0.00
308 Option Year 3 - 6.9 Designated Entry Attendant 12.00 MONTHLY $0.00 $0.00
309 Option Year 3 - 6.10 CMMS Technician 12.00 MONTHLY $0.00 $0.00
310 Option Year 3 - 6.11 Independent Safety Officer 12.00 MONTHLY $0.00 $0.00
Option Year 3 $0.00
LABOR RATES (OPTION YEAR 3)
| List below all Labor Categories that will be used in the performance of the Time & Material portion of the services under this BPA. | |||||
| Labor Category (Technician, Plumber,Welder, etc) | Type of time worked: (Standard,Overtime,Holiday Overtime, Weekend Overime) | Quantity | Unit of Issue | Unit Price ($) | Discounted |
Unit Price ($)
| Project Manager | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| On-Site Supervisor | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Stationary Engineer | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Pipefitter | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Designated Entry Attendant | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| CMMS Technician | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Independent Safety Officer | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Electrician | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Electrician Helper | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| HVAC Mechanic | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Maintennace Mechanic | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Welder | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Welding Inspector | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Plumber | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Pipe Insulator | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Laborer | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Welder | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Welding Inspector | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Plumber | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Pipe Insulator | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Laborer | Standard time (Monday through Friday from 6:00 a.m. through 2:30 p.m. ET) | 1 | HR | $0.00 | $0.00 |
| Project Manager | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| On-Site Supervisor | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Stationary Engineer | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Pipefitter | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Designated Entry Attendant | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| CMMS Technician | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Independent Safety Officer | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Electrician | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Electrician Helper | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| HVAC Mechanic | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Maintennace Mechanic | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Welder | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Welding Inspector | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Plumber | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Pipe Insulator | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Laborer | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Welder | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Welding Inspector | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Plumber | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Pipe Insulator | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Laborer | Overtime (Monday through Friday outside of standard time hours or any time on Saturday) | 1 | HR | $0.00 | $0.00 |
| Project Manager | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| On-Site Supervisor | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Stationary Engineer | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Pipefitter | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Designated Entry Attendant | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| CMMS Technician | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Independent Safety Officer | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Electrician | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Electrician Helper | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| HVAC Mechanic | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Maintennace Mechanic | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Welder | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Welding Inspector | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Plumber | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Pipe Insulator | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Laborer | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Welder | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Welding Inspector | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Plumber | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Pipe Insulator | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
| Laborer | Sunday Overtime (any time worked on a Sunday) | 1 | HR | $0.00 | $0.00 |
Option Period 3 Section B - Supplies or Services and Prices/Costs
OPTION PERIOD 3
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
301 Option Period 3 : Annual Vibration Analysis 12.00 Monthly $0.00 $0.00
302 Option Period 3 : Annual Infrared Thermography Analysis Service (Optional ) 1.00 Annually $0.00 $0.00
303 Option Period 3 : Annual Ultrasonic Analysis Service (Optional ) 12.00 Monthly $0.00 $0.00
304 Option Period 3 : Annual Oil Sampling/ Analysis Service 12.00 Monthly $0.00 $0.00
305 Option Period 3 :Annual Program Overview / Training 12.00 Monthly $0.00 $0.00
Option Period 3: $0.00
Option Period 4, 11 Mnth Option Section B - Supplies or Services and Prices/Costs
OPTION PERIOD 4 (11-Month)
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
401 Option Period 4 : Annual Vibration Analysis 11.00 Monthly $0.00 $0.00
402 Option Period 4 : Annual Infrared Thermography Analysis Service (Optional ) 11.00 Monthly $0.00 $0.00
403 Option Period 4 : Annual Ultrasonic Analysis Service (Optional ) 11.00 Monthly $0.00 $0.00
404 Option Period 4 : Annual Oil Sampling/ Analysis Service 11.00 Monthly $0.00 $0.00
405 Option Period 4 :Annual Program Overview / Training 11.00 Monthly $0.00 $0.00
Option Period 4: $0.00
Option Period 4, 1 Mnth TOP Section B - Supplies or Services and Prices/Costs
(1) Month Tranistion Out Period (TOP) OPTION PERIOD 4
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
401 Option Period 4 : Annual Vibration Analysis 1.00 Monthly $0.00 $0.00
402 Option Period 4 : Annual Infrared Thermography Analysis Service (Optional ) 1.00 Monthly $0.00 $0.00
403 Option Period 4 : Annual Ultrasonic Analysis Service (Optional ) 1.00 Monthly $0.00 $0.00
404 Option Period 4 : Annual Oil Sampling/ Analysis Service 1.00 Monthly $0.00 $0.00
405 Option Period 4 :Annual Program Overview / Training 1.00 Monthly $0.00 $0.00
Option Period 4: $0.00
Option Period 5 FAR 52.217-8 Section B - Supplies or Services and Prices/Costs
OPTION PERIOD 5 (PER FAR 52-217-8) 6 MONTH EXTENTION
Contract Line Item Number (CLIN) Commodity Name Quantity Unit of Issue Unit Price ($) Discounted Total Cost ($)
501 Option Period 5 : Annual Vibration Analysis 6.00 Monthly $0.00 $0.00
502 Option Period 5 : Annual Infrared Thermography Analysis Service (Optional ) 6.00 Monthly $0.00 $0.00
503 Option Period 5 : Annual Ultrasonic Analysis Service (Optional ) 6.00 Monthly $0.00 $0.00
504 Option Period 5 : Annual Oil Sampling/ Analysis Service 6.00 Monthly $0.00 $0.00
505 Option Period 5 :Annual Program Overview / Training 6.00 Monthly $0.00 $0.00
Option Period 5: $0.00