J-8 Bid Schedule_101624.pdf

PDF 181 KB Posted

Attached to
B2621 Dorm Construction Renovations
Solicitation number
FA448425R0001
Issued by

About this file

This document is a Bid Schedule for the repair and renovation of Dormitory 2621 at Joint Base McGuire-Dix-Lakehurst (JB MDL) in New Jersey. The work includes renovating the sleeping rooms, bathrooms, common areas, mechanical, electrical, and telecom rooms, and installing a new HVAC system. The bid schedule provides a detailed breakdown of the base bid and option items, including quantities, unit prices, and total amounts for the various renovation activities. The allowance items include removal and disposal of slab-on-grade, asbestos-containing materials, and structural concrete. Pricing details require a breakdown of material, labor, equipment, subcontractor costs, and overhead. This bid schedule is part of a larger Request for Proposal (RFP) for the B2621 Dorm Construction Renovations project, which is a new construction requirement for the Department of the Air Force Air Mobility Command.

View the file

Other files

File Type Posted
J-16 Questions and Answers Version 2.pdf PDF
Solicitation Amendment FA448425R00010007 SF 30.pdf PDF
J-18 revised A-612_door hardware schedule.pdf PDF
Solicitation Amendment FA448425R00010006 SF 30.pdf PDF
J-17 Design Analysis.pdf PDF
J-8 Bid Schedule_011525 .pdf PDF
Solicitation Amendment FA448425R00010005 SF 30.pdf PDF
Solicitation Amendment FA448425R00010004 SF 30.pdf PDF
J-16 Questions and Answers Version 1.pdf PDF
Solicitation Amendment FA448425R00010003 SF 30.pdf PDF
Solicitation Amendment FA448425R00010002 SF 30.pdf PDF
J-15 Site Visit Sign in Sheet_112624.pdf PDF
J-14 Pre-Bid Addendum No 1_112624.pdf PDF
Solicitation Amendment FA448425R00010001 SF 30.pdf PDF
J-12 Section L_112724.pdf PDF
Solicitation - FA448425R0001.pdf PDF
C-1 Statement of Work_082224.pdf PDF
J-7 Specifications - Vol II_032224.pdf PDF
J-11 Past Performance Questionnaire_102824.pdf PDF
J-12 Section L_111324.pdf PDF
J-6 Specifications - Vol I_032224.pdf PDF
J-1 Materials Submittal_070324.pdf PDF
J-3 JBMDL AT Awareness Guide for Contractors_22APR24.pdf PDF
J-5 Medical Statement.docx DOCX document
J-9 Drawings_032224.pdf PDF
J-10 Wage Determination Burlington County_110124.pdf PDF
J-13 Section M_111224.pdf PDF
J-2 JBMDL Antiterrosim Awareness for Contractors (Trifold)_22APR 24.pdf PDF
J-4 SFS Appendix- Contractor Appendix_Sep 23.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART 1 - THE SCHEDULE

SECTION B (repair Dormitory 2621, PTFL 21-1010)

SUPPLIES OR SERVICE AND PRICES/COSTS

UNIT

ITEM SUPPLIES/SERVICES (Base Bid) QUANTITY UNIT PRICE AMOUNT

0001 Provide all labor, equipment, appliances, and materials, and furnish and perform all work in strict accordance with the specifications, schedules, and drawings forming parts thereof, subject to the terms and conditions of the contract to include selective demolition, renovation and reconfiguration of Dormitory 2621. It includes renovating the sleeping rooms, bathrooms, common 1 JOB $ $ areas include lobby, ABA public toilet, service areas include mechanical, electrical and telecom rooms along with a new mechanical system.

TOTAL (Base Bid) $

UNIT

ITEM SUPPLIES/SERVICES (Option Items) QUANTITY UNIT PRICE AMOUNT N/A N/A

1 LS $_N/A_ $_N/A_

TOTAL (Option Items) $_N/A_

ALLOWANCE

ITEM

SUPPLIES/SERVICES QUANTITY UNIT

Removal and disposal of slab-on-grade excluding

AMOUNT

loading and disposal. (350 SF). 1 LS $_$20,000

0003 Removal and disposal of additional asbestos-containing 1 LS $_$25,000 materials. (500 SF).

0004 Structural concrete, in place, Flowable fill (20 CY). 1 LS $_$20,000

TOTAL $

GRAND TOTAL (Line items 0001 through 0004) $

PRICING DETAILS:

For evaluation purposes, the offeror shall provide detailed proposals in response to this RFP. Pricing shall include a detailed breakdown of all the cost elements attributed to each line item in the bid schedule and the requirements of the SOW and specifications. Price breakdown shall include sufficient details to permit an analysis of profit, and all the costs: (i) Material (ii) Labor (iii) Equipment (iv) Subcontractor’s costs as applicable and (v) Overhead.

NOTE 1: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.

NOTE 2: If a modification to a bid based on unit prices is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro-rata basis to every unit price in the bid schedule.

NOTE 3: (Applicable to Items 0002 thru 0004) The amounts are an allowance. In no case shall the contractor change amounts shown on this bid schedule for these services.

NOTE 4: Failure to provide a bid on all items will render your bid non-responsive.