J-6-GFI-List.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
RFP Amendment - Undersea Warfare Training Range(USWTR) Increment II & III Federal contract opportunity
Solicitation number
N6134021R0006
Issued by
Department of the Navy Naval Air Systems Command

About this file

This document provides details on a federal solicitation for the redevelopment and modernization of six undersea warfare training ranges. The solicitation seeks to upgrade four existing deep water ranges at the Pacific Missile Range Facility in Hawaii and the Atlantic Undersea Test and Evaluation Center in the Bahamas. It will also add two new shallow water ranges near San Clemente Island in California. Services required include hydrographic data collection, installation and maintenance of hydrophone systems, and development of best practices for environmental mitigation. The response date for proposals is 1 June 2021. The award is expected to be made on the same date. The solicitation is designated for small businesses with fewer than 1,250 employees. The procuring agency is the Naval Air Systems Command Department of the Navy.

View the file

Other files for this federal contract opportunity

Other files attached to RFP Amendment - Undersea Warfare Training Range(USWTR) Increment II & III, newest first.
File Type Posted
USWTR Inc II III RFP Questions (Updated 12212020).xlsx XLSX spreadsheet
USWTR Inc II III RFP Questions (Updated 12152020).xlsx XLSX spreadsheet
L-4-Vol3-CE-Tables.xlsx XLSX spreadsheet
USWTR Inc II III RFP Questions.xlsx XLSX spreadsheet
J-6-GFI-List (Updated 12082020).xlsx XLSX spreadsheet
RFP Amendment - USWTR Inc. II & III.docx DOCX document
J-1-SOW (Updated 12082020).docx DOCX document
USWTR Inc. II & III RFP.pdf PDF
J-5-GFP.docx DOCX document
USWTR Inc. II&III Virtual Pre Sol Attendance 29 Sept 2020.pdf PDF
ExhibitA-DD1423.pdf PDF
DD1423_Addendum.docx DOCX document
J-4-DD_254.pdf PDF
L-5-Vol4-PrimeCostPrice.xlsx XLSX spreadsheet
J-1-SOW.docx DOCX document
L-2-Vol1-CA-Tables.xlsx XLSX spreadsheet
L-4-Vol3-CE-Tables.xlsx XLSX spreadsheet
L-B-DD2345.pdf PDF
USWTR Inc II III PSC Questions Final.pdf PDF
L-1-Vol1-SBPCD.docx DOCX document
L-6-Vol4-CPFF.xlsx XLSX spreadsheet
L-A-GFIandNDA.docx DOCX document
L-3-Vol2-CRM.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GFI

Number Title To be provided calendar days after contract award (DACA) SOW Reference Electronic Filename Available in Technical Library at time of issue of solicitation

6.1GFI
6.1.1USWTR Inc III In_Water Subsystem Performance Specification0ALLJ-3-USWTR Inc III IWS SPEC with Errata 1 16 SEP 2020_signedyes
6.1.2Visitor policies at AUTEC30 calendar days prior to travelALL
6.1.3Visitor policies at PMRF30 calendar days prior to travelALL
6.1.4Visitor policies at SCTTR30 calendar days prior to travelALL
6.1.5USWTR System Engineering Plan04.2.1, 4.2.2, 4.2.13, 4.2.16
6.1.6Visitor policies at NUWCDIVNPT30 calendar days prior to travelALL
6.1.7BARSTUR Hydrophone positions04.3, 4.18USWTR Inc II_III and ASRP Node Locations Initial Releaseyes
6.1.8BSURE Hydrophone positions04.3USWTR Inc II_III and ASRP Node Locations Initial Releaseyes
6.1.9BARSTUR route position list04.3USWTR Inc II_III and ASRP Route Position Lists_Initial Releaseyes
6.1.10BSURE route position list04.3, 4.28USWTR Inc II_III and ASRP Route Position Lists_Initial Releaseyes
6.1.11USWTR Required States and Modes”, Naval Undersea Warfare Center, Division Newport, Newport RI,04.3, 4.5, 4.6, 4.33, 4.43
6.1.12PMRF facility salient characteristics1204.3
6.1.13BARSTUR and BSURE best management practices and environmental mitigation measuresInitial - 0; Final - 5 days after exercising CLINs 0301 and 03034.3, 4.18, 4.28USWTR Increment II_III BMPs and Environmental Mitigation Measures Initial Release_FINAL_JJyes
6.1.14BARSTUR BSURE hydrographic data1204.3, 4.18, 4.28
6.1.15AUTEC Hydrophone positions04.4USWTR Inc II_III and ASRP Node Locations Initial Releaseyes
6.1.16AUTEC route position list04.4USWTR Inc II_III and ASRP Route Position Lists_Initial Releaseyes
6.1.17AUTEC hydrographic data1204.4, 4.23
6.1.18AUTEC facility salient characteristics1204.4, 4.23
6.1.19Production Representative Display Processing and Control System Test Plan30 calendar days prior to test4.11, 4.13, 4.21, 4.42, 4.54, 4.34, 4.39, 4.41
6.1.20SOAR Hydrophone positions04.6USWTR Inc II_III and ASRP Node Locations Initial Releaseyes
6.1.21SOAR route position list04.6, 4.43, 4.57USWTR Inc II_III and ASRP Route Position Lists_Initial Releaseyes
6.1.22SOAR facility salient characteristics1204.6, 4.43, 4.33
6.1.23USWTR Model Management Plan54.2.1
6.1.24Visitor policies at NAVAIR PMA20530 calendar days prior to travelALL
6.1.25Requests for action2 calendar days after the event4.2.16, 4.2.19
6.1.26iPRR checklist10 calendar days prior to the event4.2.16, 4.2.19
6.1.27Marine Mammal Observation Training120 calendar days prior to packaging of IWS for shipment4.18, 4.23, 4.28, 4.57, 4.44, 4.52
6.1.28AUTEC best management practices and environmental mitigation measuresInitial - 0; Final - 5 days after exercising CLIN 03054.4, 4.10.2, 4.23ASRP BMPs and Environmental Mitigation Measures Initial Releaseyes
6.1.29SOAR hydrographic data1204.6, 4.43, 4.57
6.1.30SOAR best management practices and environmental mitigation measuresInitial - 0; Final - 5 days after exercising CLINs 0301 and 03054.6, 4.43, 4.57USWTR Increment II_III BMPs and Environmental Mitigation Measures Initial Release_FINAL_JJyes
6.1.31USWTR Increment II In_Water Subsystem Performance Specification0ALLJ-2-USWTR Inc II IWS SPEC_20200828_signedyes
6.1.32USWTR Increment I technical data package (only the drawing list is provided with the solicitation04.33, 4.3521501012E USWTR A00K-002 Rev Eyes
6.1.33WC_SWTR San Clemente Island Hydrophone positions04.33USWTR Inc II_III and ASRP Node Locations Initial Releaseyes
6.1.34WC_SWTR Tanner Bank Hydrophone positions04.33USWTR Inc II_III and ASRP Node Locations Initial Releaseyes`
6.1.35WC_SWTR trunk cable(s) route position list5 days after exercising CLIN 04034.33, 4.44, 4.52USWTR Inc II_III and ASRP Route Position Lists_Initial Releaseyes
6.1.36WC_SWTR hydrographic data5 days after exercising CLIN 04034.33, 4.44, 4.52
6.1.37WC_SWTR best management practices and environmental mitigation measuresInitial - 0; Final - 5 days after exercising CLINs 0702 and 08044.33, 4.44, 4.52USWTR Increment II_III BMPs and Environmental Mitigation Measures Initial Release_FINAL_JJyes
6.1.38Commercial Undersea Telecommunications Cable Minimum Requirements/Specifications04.3, 4.4, 4.6, 4.8, 4.10, 4.11, 4.47, 4.43Commercial Undersea Telecommunications Cable Minimum specificationsyes
6.1.39NAVAIRINST 5720.10 Public Release Authorization Requestas requested within 5 daysALL
6.1.40USWTR Inc II_III SES_ASP ICD Initial Release04.3, 4.5, 4.6, 4.33, 4.43USWTR Inc II_III SES_ASP ICD_Initial_Releaseyes
6.1.41USWTR Inc II_III SES_UCS ICD Initial Release04.3, 4.5, 4.6, 4.33, 4.43USWTR Inc II_III SES_UCS ICD_Initial_Releaseyes
6.1.42WC-SWTR Fishing HazardsInitial - 0; Final - 5 days after exercising CLIN 04034.33WC-SWTR Fishing Hazards Initial Releaseyes
6.1.43USWTR IWS Model (.mdzip file (Magic Draw file extension name))04.2.1

File details come from the government source that posted it. Updated .