This document is a Functional Requirements document for the Long-Baseline Neutrino Facility (LBNF) Liquid Argon (LAr) Condenser Pump Units for Cryostats 1 and 2. It outlines the current interface requirements, technical requirements, and modes of operation for the condenser pump units.
The key details are:
- The LAr condenser pump units will be located inside the North/South Detector Cavern envelopes, with 6 pumps divided into 1 pump per condenser.
- The pumps must be designed for internal vacuum and 10 bar pressure, with an adiabatic efficiency greater than 0.5.
- The pumps will be used for cryostat fill, normal operations, bearing replacement, and maintenance activities. Redundancy is required to ensure uninterrupted operations.
- Key design parameters include a maximum working pressure of 145 psig (10 bar) and a temperature range of 87K (-186°C) to 310K (37°C).
- The required flow rate is 66 lb/min (98 g/s) per condenser during cryostat fill, and 132 lb/min (996 g/s) during normal operations.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US
LBNF/DUNE-US
LAr Condenser Pump Units Functional Requirements
Document Number: EDMS 3048171 v.1
Liquid Argon Condenser Pumps 1 - Functional Requirements - Rev. 1
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page ii
Document Approvals
Signatures Required Signature & Date Approved
Originator:
Zachery West / Roza Doubnik Cryogenic Engineer
01.18.2024
Approver:
David Montanari, LBNF FDC Deputy Project Manager for Cryogenics
Approver:
Approver:
Approver:
Approver:
Revision History and Version Control
This version of the document may not be the current or approved revision. The current revision is maintained in the Engineering & Equipment Data Management Service (EDMS) where internal Project document approvals are managed. EDMS can be accessed through the web at https://edms.cern.ch. This document can be identified by the revision date as indicated in the Version Control Table below.
The currently approved version is always available at: https://edms.cern.ch/document/3048171/1
Author Revision Date Location EDMS Description of Changes
Zachery West / Roza Doubnik 01/18/2024 EDMS 3048171 v.1 Original Document https://edms.cern.ch/ https://edms.cern.ch/document/3048171/1
Functional Requirements
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page iii
Document Approvals .................................................................................................................................... ii
Revision History and Version Control ........................................................................................................... ii
List of Figures ............................................................................................................................................... iii
List of Tables ................................................................................................................................................ iii
1 Scope of Document ........................................................................................................................ 1-1
2 Condenser Pump Unit Current Interface Requirements ............................................................... 2-1
3 Condenser Pump Technical Requirements .................................................................................... 3-3
4 Modes of Operation for Condenser Pumps Units .......................................................................... 4-3
5 Appendix A – Design Parameters and Tables ................................................................................ 5-4
List of Figures
Figure 2-1: Current Condenser Pump Unit Skid Typical Configuration (To be checked) ........................... 2-1
List of Tables
Table 5-1: Design Parameters .................................................................................................................... 5-4 Table 5-2: Required Flow per Condenser .................................................................................................. 5-4 Table 5-3: Modes of Operations ................................................................................................................ 5-4
Functional Requirements List of Tables
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page 2-1
1 Scope of Document This document describes the functional requirements for the Long-Baseline Neutrino Facility (LBNF) Liquid Argon Condenser Pump Units for Cryostats 1 and 2.
2 Condenser Pump Unit Current Interface Requirements The LAr Condenser Pump units for the Cryostats shall be located inside spaces allocated in the North / South Detector Cavern envelopes where six (6) pumps are divided into one pump per condenser (see Figure 2-1).
Figure 2-1: Current Condenser Pump Unit Skid Typical Configuration (To be checked)
The current configuration is highlighted in Figure 2-2 below. The yellow highlighted section is the pumps themselves that show the 6 (six) condenser pumps that come off each condenser. The green highlighted sections are the upstream piping that is made of 2” vacuum jacketed piping coming from each condenser.
The blue highlighted sections are the downstream piping that is made of 1-1/2” vacuum jacketed piping that is utlized during LAr Purification where the gaseous argon boiloff is being sent back to condenser to be re-liquiefied. The pink highlighted section is the 1” vacuum jacketed manifold that is utlized during the cooldown of the cryostat where the liquid argon has been cooled and cleaned coming out of the condenser. The flow from this system merges with the flow from out of the circulation system common manifold. The combined flow goes to the CUC.
Figure 2-3 is a zoomed in version of the P&ID that better highlights the finer details per condenser pump.
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page 2-2
Figure 2-2: Current Condenser Pump Unit Skid Typical Configuration (To be checked)
Figure 2-3: Typical Pump Current Configuration (Zoomed In) (To be checked)
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page 4-3
3 Condenser Pump Technical Requirements
3.1 Each liquid argon condenser pumps shall be designed for internal vacuum and for a pressure of
10 bar at any temperature ranging from about 310 K to about 87 K (for the cool-down and warm-up processes).
3.2 The liquid argon condenser pumps shall each have an adiabatic efficiency higher than 0.5.
4 Modes of Operation for Condenser Pumps Units The Condenser Pumps units defined in this Functional Requirements document will be used for the following modes of operation:
1. Cryostat Fill
2. Normal Operations
3. Bearing Replacement
4. Maintenance
The current configuration uses 6 pumps in modular fashion. The functional parameters should dictate the optimal number of pumps and their characteristics as long as requirements are met. Redundancy shall be considered to ensure uninterrupted operations.
4.1 Cryostat Fill
When the system is clean and cold, the liquid argon is condensed in the Argon Condenser. The clean and cold liquid argon leaving the condenser valve box is sent to the condenser pump and sent to the cryostat for cooldown and fill operations.
4.2 Normal Operations
Liquid argon leaves the condenser from the bottom and into the pump where it circulates liquid argon back to the condenser through the Desuperheater.
4.3 Bearing Replacement
Based on liquid argon pump manuals, each pump needs to replace bearings approximately each 6000 working hours. Supply shall be able to replace bearings on each pump without interruption of circulation process.
4.4 Maintenance
Each pump units shall be capable of a controlled warm-up/cool-down for maintenance without interfering with the pump capacity. Any of the pump units shall be capable of being taken out of service for maintenance while any combination of the other units remains in operation.
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page 5-4
5 Appendix A – Design Parameters and Tables The main design parameters are listed below in Table 5-1.
Table 5-1: Design Parameters
Equipment
MAWP
psig/ bar Design Temperatures
Minimum/Maximum K (°C) Adiabatic Efficiency
Liquid Argon Condenser Pump Unit
145/10 87K (-186.15°C) / 310K (36.85°C) > 0.5
Table 5-2: Required Flow per Condenser
Supply Scope Max Flow per unit lb/min (g/s) Function
From each Condenser 66 (98) Transfer the LAr during Cryostat fill
Table 5-3: Modes of Operations
Operation Mode Flow lb/min (g/s)
Cryostat Fill Process 396 (2990)
Normal Operations 132 (996)
Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) - US Page 5-5
Figure 5-4: Flow Diagram for single Condenser and Pump System Typical
Figure 5-5: Flow Diagram for Condensers and Pumps System High Level
| Document Approvals |
| Revision History and Version Control |
| List of Figures |
| List of Tables |
| 1 Scope of Document |
| 2 Condenser Pump Unit Current Interface Requirements |
| 3 Condenser Pump Technical Requirements |
| 4 Modes of Operation for Condenser Pumps Units |
| 4.1 Cryostat Fill |
| 4.2 Normal Operations |
| 4.3 Bearing Replacement |
| 4.4 Maintenance |
5 Appendix A – Design Parameters and Tables