J-1502000-02(DHA)-01_Above Ceiling Penetration Permit.pdf
PDF 804 KB Posted
- Solicitation number
- N6945022R0032
About this file
This document contains a federal solicitation notice and an above ceiling penetration permit template. The solicitation notice is for Base Operations Support (BOS) services at Naval Station Guantanamo Bay, Cuba under solicitation number N6945022R0032. The services required include family housing, facility management, facility investment, custodial services, pest control, integrated solid waste management, grounds maintenance and landscaping, utility management, electrical, wastewater, water, and base support vehicles and equipment. The contract type is an indefinite-delivery, indefinite-quantity contract with both fixed price and non-fixed price CLINs, as well as award fee provisions. The base period of performance is one year with seven one-year options, not to exceed eight total years. The permit template provides guidance on maintaining the integrity of fire barriers during above ceiling work, with requirements for location details, reasons for penetration, signatures, and inspections.
View the file
Other files
Show 40 more
Latest 50 of 78 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABOVE CEILING, FIRE AND SMOKE BARRIER PENETRATION PERMIT
Permit Number: ___________________________ Issue Date: ___________________
Approved by: Estimated Completion Date: ______________________
(Facilities Representative)
Permit Issued To:
(Department / Contractor Name) (Individual’s Name) (Phone Number)
Location of Corridor Wall(s) or Barrier(s) to be Penetrated: (building, floor, room number) (Attached Sketch if applicable) (Attached photos of existing condition of wall pentetrations if applicable)
Reasons for Penetration or Work to be Performed:
Final Inspection by Department/Contractor:
Sign: __________________________________________ Date: ______________________
Facilities Management:
Sign: __________________________________________ Date: ______________________
Instructions:
1. Maintain a copy of this permit at the work area at all times.
2. Promptly repair penetration in an approved (NFPA/MFG/CDC/etc…) manner. Contact the hospital’s Facilities
Management office, if there are any questions regarding the repairs.
3. Notify Facilities Management when repairs are complete to schedule a final inspection.
4. Contractors must fill all penetrations with a rated fire stopping product approved by the hospital.
5. Prior to performing related tasks within patient care, laboratory, surgery or other areas where the services rendered are directly impacting patient care; you will be required to obtain an Infection Control Permit.
6. All ceiling tile(s) will be reinstalled or replaced to the satisfaction of the final inspection.
7. Pictures will be taken of the fire and smoke barrier walls before the penetrations are made by department/contractor performing work. Pictures will be taken after the work has been completed by department/contractor performing work. Pictures will be sent to the Facilities Management office.
Pictures required for this permit? Yes No
NAVAL HOSPITAL, GUANTANAMO BAY, CUBA
POLICY AND PROCEDURE
SUBJECT: ABOVE THE CEILING INSTALLATION PERMIT PROGRAM
POLICY STATEMENT:
The above the ceiling permit program is designed to ensure the integrity of fire rated walls, doors and smoke compartments through the use of monitoring; inspecting and providing a permit to all outside contractors or subcontractors, and hospital personnel that may be creating penetrations.
PROCEDURE:
1. Each maintenance, telecommunications, I.T./MID, and contract employee shall submit a schedule of anticipated penetrations to Facilities Management Department (FMD) prior to the start of any construction project. All outside contractors and any Naval Hospital employee doing above ceiling work will be required to obtain a permit from the Facilities Management Department (FMD) before work begins.
2. The location of each penetration will be identified on a floor plan for the area under construction, and submitted to FMD.
3. Upon submission of all required documentation, an "Above Ceiling Installation Permit" will be issued to the contractor by FMD.
4. FMD will accompany the contractor to the construction site and will post the permit in a visibly prominent location, and the permit will remain posted for the duration of the project.
5. Upon completion of the permitted project, the contractor will notify the FMD that the project is complete and ready for inspection. Once inspected, FMD will sign off on the construction project.
6. No payment to any construction contractor will be allowed without documentation of a completed Above the Ceiling Installation Permit, signed by FMD and a completed Letter of Conformance signed by FMD.
LETTER OF CONFORMANCE
Project Name: _________________________________________________________________
Job Location: __________________________________________________________________
Brief Description of Job: __________________________________________________________
Firestop Manufacture Used: ______________________________________________________
I, _______________________ of _____________________, on this Date _______________, by completing and signing this letter certify that all firestop systems used on this project have been installed in accordance with Naval Hospital Guantanamo Bay, Cuba guidelines.
In addition, all firestop systems have been installed to system details and written instructions in accordance with UL 1479 / ASTM E 814 and/or UL 2079 / ASTM E 1966 test Standards.
The following supporting document s must be attached:
Approved UL or OPL systems used on the Job (may differ from initial permit)
Any Engineering Judgments provided for this project.
Signed, completed Above Ceiling Installation Permit (necessary for payment, if applicable)
Contractor Signature FMD Signature
Contractor Name (printed) FMD Representative (printed)
Date Date
| Permit Number: |
| Issue Date: |
| Estimated Completion Date: |
| Individuals Name: |
| Phone Number: |
| Date: |
| Date_2: |
| Department Contractor Name: |
| FM: |
| 2: |
| 3: |
| 4: |
| 5: |
| 6: |
| 7: |
| 8: |
| 9: |
| 10: |
| Text1: |
| 12: |
| 11: |
| Sketch 1: |
| Sketch 2: |
| Sketch 3: |
| Sketch 4: |
| Reasons 1: |
| Reasons 2: |
| Reasons 3: |
| Reasons 4: |
| CB1: Off |
| CB2: Off |
| CB3: Off |
File details come from the government source that posted it. Updated .