About this file

This addendum to Invitation to Bid (ITB) #PWD/260378 issued by the City of Ocala, Florida, provides clarifications and modifications to the Grounds Maintenance Mowing - Northwest solicitation. The addendum, dated February 5, 2026, establishes specific mowing frequency schedules for contractor performance, defining how one, two, or three monthly mowing cycles shall be distributed throughout each month based on the contract line items selected. Contractors must follow the mowing schedule sequentially beginning with the first line item or coordinate an alternative schedule with the City Project Manager, though the City reserves the right to adjust the schedule as needed. The addendum indicates that a revised Exhibit B - Price Proposal has been uploaded to the solicitation documents, which removes Tree Haven locations from the original scope, adds at least one new location, and incorporates median mowing responsibilities at certain properties. The original solicitation maintains a non-mandatory pre-bid meeting on February 5, 2026, at 11:00 AM EST, with bids due February 25, 2026, and a contract term running from March 1, 2026, through March 1, 2028, with two optional one-year renewals available.

All medians within the scope of work or designated line items become the contractor's maintenance responsibility under this addendum. The solicitation requires contractors to possess a minimum of five years of grounds maintenance experience with verifiable references, a current Florida Department of Transportation Temporary Traffic Control Certification, and a valid Florida Department of Agriculture Pesticide Applicator License, with copies of both certifications submitted at bid time. Contractors must perform 100 percent of work with their own workforce with no subcontracting permitted. The award will be granted to the lowest responsive bidder based on the grand total price proposal on a unit price basis, with pricing remaining firm and fixed during the initial two-year term and any renewal adjustments capped at the lesser of Consumer Price Index increase or three percent annually. Contractors must maintain commercial general liability insurance of $1,000,000 per occurrence and $2,000,000 aggregate, commercial automotive liability of $1,000,000 combined limit, and workers' compensation insurance per Florida statutory requirements throughout the contract term.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum # 1

Date: February 5, 2026

To: All bidders

From: Caley Conard, Buyer

Solicitation Number: ITB# PWD/260378

Solicitation Title: Ground Maintenance Mowing - Northwest

SECTION 1. QUESTIONS AND ANSWERS

N/A

SECTION 2. SOLICITATION ADDITIONS, CLARIFICATIONS AND CORRECTIONS

2.1 The following wording is added to the scope of work:

• One (1) mowing per month shall be scheduled anytime during that month

• Two (2) mowing per shall be scheduled from the 1st of the month through the 15th and the 16th of each month to the end of the month 30th/31st of each month.

• Three (3) mowings per month shall be scheduled from the 1st of the month to the 10th, from the

11th of the month to the 20th, and from the 21st of the month to the end of the month 30th/31st.

• The Contractor shall follow the mowing cycle in sequent, starting with the first line item, or schedule the mowing cycle with the City Project Manager. The City of Ocala reserves the right to change the schedule as needed.

2.2 A REVISED EXHIBIT B – PRICE PROPOSAL has been uploaded to Documents. The revised Exhibit B – Price Proposal removes the Tree Haven locations, adds a location, and adds median mowing to some locations.

2.3 All medians within the scope of the contract or line item shall be the contractor's responsibility to maintain